Boundary Wall After Correction
Boundary Wall After Correction
Boundary Wall After Correction
5 Centering and shuttering including strutting propping etc. and Sqm 316.2 251.3 79458 5.9.5
removal or form for Lintels,Beams, Plinth beams, girders,
bressumers and cantilevers
6 Reinforcement for RCC work including straightening, cutting, Kg 2901.7 70.4 204282 5.22.1B
bending, placing in position and binding and complete. Cold
twisted bar
Total (In Rs.) 414159
Brick Work
7 Brick work with bricks of class designation 100A in foundations 6.1A
and plinth in :
Cement mortar 1:6 (1 cement : 6 coarse sand) Cum 124.7 3992.9 497887 6.1.14A
8 Brick work with F.P.S. bricks of class designation 100A in
superstructure above plinth level up to floor V level in all shapes
and sizes in :
Cement mortar 1:6 (1 cement : 6 coarse sand) Cum 59.0 4427.5 261400 6.3A
Total (In Rs.) 759287
Steel Work
9 Providing and fixing hand rail of approved size by welding etc. to 10.33.1
steel ladder railing, balcony railing and staircase railing including
applying a priming coat of approved steel primer. M.S. tube.
13 Forming groove of uniform size in the top layer of washed stone 13.113
grit plaster as per approved pattern using wooden battens, nailed
to the under layer including removal of wooden battens, repair to
the edges of panels and finishing the groove complete as per
specifications and direction of the Engineer-in-charge :
20mm wide and 15mm deep grove RM 282.0 18.5 5217 13.113.2
Sub Total (In Rs.) 200957
Total (In Rs.) 1910400
After Escalation 20 % 2292480
Say 22.92 Lakhs