Lecture Notes-2 Contract Costing
Lecture Notes-2 Contract Costing
Value of work certified = proportion of work done and certified x contract price
OR
=
(b) Work uncertified: This is that part of WIP which has not been
approved by the architect or engineer. It is valued at cost and does
not include an element of profit. It appears on the CREDIT side of
the contract account and also on the assets side of the balance
Cost of work uncertified = Ratio of work done but not yet certified to total
work done x cost incurred to date
The amount of WIP includes the value of work certified and un-certified
appearing in the contract account. WIP may be calculated using the following formulas
WIP = value of work certified x
Add: cost of work uncertified x
xx
Less; Amount received from contractee (x)
Less; Reserves for unrealized profit (x)
Xx
OR
WIP = Uncertified work – unrealized profit
Estimated profit x
OR
Estimated profit x
OR
Estimated profit x
OR
Estimated profit x
Where estimated profit represents the excess of the contract price over the estimated
total cost of the contract and computed as follows:
Contract price x
Estimated profit xx
(x) Loss on uncompleted contracts –
In the event of a loss on un-completed contracts, this should be transferred in FULL to
the profit and loss account, whatever is the stage of completion of the contract, however,
the practice may vary from firm to firm, but whatever method is adopted, it should be
applied consistently from year-to-year so as not to disturb the trend of profits.
(xi) Extra work
Sometimes, the contractor is required to do some extra work like additions or alterations
in the work originally done as per agreement. The contractor will charge extra money for
such extra work. The cost of such extra work is DEBITED to the contract account and extra
price realized is credited to the contract account.
(xii) Expenses before the commencement of a contract
Cost incurred by the contractor before a contract is secured are usually treated as period cost
and expensed in that period. However, if costs attributable to securing the contract can be
separately identified and there is a clear indication that the contract will be secured, the cost
may be deferred and DEBITED to the contract when secured.
(xiii) Payments by the Contractee
This should be DEBITED to Bank if the money is paid into the bank and credited to the
contractee’s personal account.
(5) Other important considerations in contract costing
(i) Retention money and cash ratio- It is a usual practice not to pay the full
amount of work certified. The contractee may pay a fixed percentage, e.g.,
80% of the work certified, depending on the terms of the contract. This is
known as cash ratio. The balance amount not paid is known as retention
money, for example, if cash ratio is 75%, the retention money will be the
remaining 25%. This retention money is a type of security for any defective
work which may be found in the contract later on. This also works as a
deterrent for the contractor to leave the contract incomplete.
(ii) Escalation & De-escalation clause – This clause is often provided in
contracts to cover any likely changes in the price or utilization of materials
and labour. Thus, a contractor is entitled to suitably enhance the contract price
if the cost rises beyond a given percentage. The object of this clause is to
safeguard the interest of the contractor against unfavourable changes in cost.
The escalation clause is of particular importance where prices of materials and
labour are anticipated to increase or where quantity of material and/or labour
time cannot be accurately estimated.
Just as an escalation clause safeguards the interest of the contractor by upward
revision of the contract price, a de-escalation clause may be inserted to look
after the interest of the contractee by providing for downward revision of the
contract price in the event of cost goings down beyond an agreed level.
Escalation claim may be calculated thus:
For material = standard quantity x (Actual price – standard price)
For labour = standard hours x (Actual rate – standard rate)
(iii) Cost – plus contracts – This is a type of contract in which the contract price
is not fixed at the time of entering into the contract. The contract price is
determined by adding a specified amount or percentage of profit to the costs
allowed in the contract. The contractee compensates the contractor for all
allowable costs actually incurred by him and a percentage of cost as profit.
The items of cost to be included for the purpose of determining contract price
are broadly agreed upon in advance. The accounts of the contractor are
usually subject to audit by the contractee.
(iv) Target-price contracts – In this type of contract, the contractor receives an
agreed sum of profit over his pre-determined costs. In addition, a figure is
agreed as the target figure and if actual costs are below this target the
contractor is eligible for bonus for the savings.
(v) Mobilization fees – It is usual for contractors to collect mobilization fees
from the contractee before commencement of the construction work. A
mobilization fee is an advance payment made to the contractor to enable him
buy the equipment, initial materials and provide working capital for the take-
off of the construction. Mobilization fees received should be credited to a
special account and transferred to the contractee’s account at the end of the
contract.
(6) Contract costing format
Contractee’s Account
Value of work certified x Cash received x
Contract Account
N N
Material consumed x cost of work done c/d x
Wages incurred x material returned to store/other
contract
sale of material at site
material stolen/destroyed by fire
Direct expenses x
Depreciation on P &M x
xx xx
xx xx
Practice Questions
Example 1: The following are the particulars relating to a contract carried out by
Accounting – for show- contractors Ltd, which begun on 1st January, 2004.
N
Contract price 500,000
Machinery 30,000
Materials 170,600
Wages 148,750
Direct expenses 6,330
Outstanding wages 5,380
Uncertified work 9,000
Overheads 8,240
Material returned 1,600
Materials on hand - 31/12/04 3,700
Machinery on hand – 31/12/04 22,000
Value of work certified 390,000
Cash received 351,000
Required
You are required to prepare the contract account for the year 2004 showing the amount of
profit that may be taken to the credit of profit and loss account of the year.
Example 2: Part-2-Accounting Consultants Ltd. secured a contract to build a
swimming pool and sports centre at the OAU, sports complex at a price of
N550,000,000. Work commenced on 1st July, 2008 and the contract was due for
completion in 18months from that date. By December 2009, most of the preliminary
excavation had been completed and the expenditure relating to the contract was as
follows:
Value of plant at site 250,000,000
Stores from Depot 640,000
Materials purchased – cement 9,200,000
- Re-inforced rod 18,400,000
- Sand 5,400,000
Fuel for bulldozer 5,940,000
Wages paid 27,320,000
Wages accrued 1,040,000
Sub-contractor charge 3,600,000
Insurance 800,000
Miscellaneous Expenses 60,400,000
The last certificate for work done was dated 15th December, 2010 and the total
amount certified under the contract to that date was N160,000,000. The cost of work
from that date to the end of the year was estimated at N14,000,000.
Payment for the certificate was subject to 10% retention and all money due had
been received. At 31st December 2010, the value put upon the plant was N212, 000,000
and the materials at site amounted to N3,500,000.
Required
You are required to show the :
(a) Contract Account
(b) Contractee’s Account