Scaffold Safety Procedure

Download as pdf or txt
Download as pdf or txt
You are on page 1of 24
At a glance
Powered by AI
The key takeaways from this document are that it outlines mandatory requirements and safe practices for scaffold erection, modification, dismantling, use and storage to help achieve safe scaffolding. It applies to all Tata Power Group company sites.

The objective of this scaffold safety procedure is to provide mandatory requirements and safe practices required for scaffold erection, modification, dismantling, use and storage. It should be used in conjunction with local regulations and consensus standards.

Accountability for scaffold safety lies with division heads and asset custodians. Responsibility lies with concerned engineers. Competent persons must be knowledgeable, capable of identifying hazards, and have authority to take prompt corrective actions.

Document Title:

The Tata Power Company Ltd Scaffold Safety Procedure


Document Ref No.
Date of Issue: 01/01/2016
TPSMS/CSP/SCAF/007 Rev 01

Scaffold Safety Procedure

Rev No. Reason for Revision Prepared By Checked By Approval by

Rev 00 First release R&P Sub committee D Kamath Vijay Chourey

Rev 01 Standardization of procedure Uday Jha (Head -


Navendra Singh Vijay Chourey
Contracts & Materials
(Group Head – P & (Chief – Corp Safety)
Jojobera)
CB; Corp Safety.)

Note: Uncontrolled once printed Page 1 of 24


Document Title:
The Tata Power Company Ltd Scaffold Safety Procedure
Document Ref No.
Date of Issue: 01/01/2016
TPSMS/CSP/SCAF/007 Rev 01

Contents

Section Description Page No.


1.0 OBJECTIVE 3
2.0 SCOPE 3
3.0 EXPECTED RESULTS 3
4.0 ACCOUNTABILITY & RESPONSIBILTIY 3
5.0 GLOSSARY/ DEFINITIONS 3
6.0 PROCEDURES 7
7.0 RECORDS 12
8.0 TRAINING & COMMUNICATION 12
9.0 VERIFICATION 12
10.0 EXCEPTION 12
11.0 REFERENCES 12
12.0 REVIEW 12
13.0 ATTACHMENTS/APPENDIX 13
- Annexure-1: Scaffold erection, use and removal process 14
flow Chart
- Annexure-2: Scaffolding request, inspection, certificate and 15
Weekly re-certificate - TPSMS/CSP/SCAF/007/FORM/001
- Pat-1: Requesting for Scaffolding
- Part-2: Inspection Check List for Scaffolding
- Part-3: Certificate of Fitness of Scaffolding
- Part-4: Weekly Re-Certification for Fitness of
Scaffolding
- Annexure-3: Safety Boards. 20
- Annexure-4: Scaffolding Audit Check List - 21
TPSMS/CSP/SCAF/007/FORM/002
- Annexure-5: Scaffold pipe, Ladder, Plank/Jali, Clamps, 23
Base Plate Check-list - TPSMS/CSP/SCAF/007/FORM/003
- Annexure 6: Do’s and Don’ts for Scaffold Safety 24

Note: Uncontrolled once printed Page 2 of 24


Document Title:
The Tata Power Company Ltd Scaffold Safety Procedure
Document Ref No.
Date of Issue: 01/01/2016
TPSMS/CSP/SCAF/007 Rev 01

1. OBJECTIVE:
Objective of this procedure is to provide the mandatory requirements and safe practices
required for scaffold erection, modification, dismantling, use and storage. This Procedure
should be used in conjunction with local regulations, consensus standards which help to
achieve safe scaffold erection and use.

2. SCOPE:
This procedure applies to all operating and project sites of Tata Power Group companies.

3. EXPECTED RESULTS:
3.1. Manage scaffold erection, use and dismantling job safely.
3.2. Control of incidents related to scaffold erection, use and dismantling work.
3.3. Compliance to Regulatory requirements related to Scaffolds.
3.4. To provide safe scaffolding platform for jobs to be done at height.

4. ACCOUNTABILITY & RESPONSIBILITY:


4.1. ACCOUNTABILITY: Concerned Division’s Heads/Assets Custodian.
4.2. RESPONSIBILITY: Concerned Engineer

5. GLOSSARY/ DEFINITIONS:
Brace: A member fixed diagonally across two or more members in a scaffold to afford
stability.
Bracing: Bracing is a system of braces or ties that prevent distortion of a scaffold.
Base Plate: It is a Mild Steel (MS) square plate of 100 mm x 100 mm x 6 mm thick with 38
mm diameter and 75 mm long spigot supporting at bottom to the standard at ground.
Competent person: one who through training and/or experience a) is knowledgeable of
applicable scaffolding regulations; b) is capable of identifying existing and predictable
hazards related to the erection, alteration, dismantlement, storage, and inspection of
scaffolding; and c) has the authority to take prompt corrective actions to eliminate such
hazards.
Fabricated-frame scaffold: A scaffold consisting of a platform(s) supported on fabricated
end frames with integral posts, horizontal bearers, and intermediate members (also known
as welded-frame scaffold and sectional scaffold).
Guard rail: A horizontal rail secured to standards and erected along the exposed edges
of scaffolds to prevent workmen from falling.
HIRA: Hazard Identification and Risk Assessment
Hazard Identification & Risk Assessment: Hazard Identification & Risk Assessment is to
identify and evaluate the hazards, Risk and put controls measures for safe execution of
activities.

Note: Uncontrolled once printed Page 3 of 24


Document Title:
The Tata Power Company Ltd Scaffold Safety Procedure
Document Ref No.
Date of Issue: 01/01/2016
TPSMS/CSP/SCAF/007 Rev 01

Hazard: Source or situation with potential for harm, something that can cause body injury /
occupational illness, damage company property.
IDLH: Immediate Danger to Life and Health
Job: A piece of physical work defined by time or other limits and that has a clear start and
end point.
Job Safety Analysis: Job safety analysis (JSA) is a procedure which helps integrate
accepted safety and health principles and practices into a particular task or job. In a JSA,
for each basic step of the job, it is to identify potential hazards and to recommend the
safest way to do the job.
Job: A piece of physical work defined by time or other limits and that has a clear start and
end point
Kicker Lift: The vertical distance measured from ground to the center of first ledger,
normally this distance is 150 mm from ground and provided when scaffold is more than
6.0M height or scaffold carrying heavy load.
Ledger: A horizontal member which ties the standard at right angles and which may
support putlogs and transoms.
Lift Height: The vertical distance measured between center of two ledgers. Normal lift
height is 2.2 M.
Mobile (rolling) scaffold: A castor-mounted sections of tubular metal scaffolds and are
used for work on street lighting, plant etc.
Non Routine Job / Task: Where an SOP / SMP is not available or the conditions of the
SOP / SMP have changed
PPE: Personal Protective Equipment
PTW: Permit to Work
Putlog: A scaffold member spanning from ledger to ledger or from ledger/standard to a
building and upon which platform rests.
Racker: An inclined load bearing tube that braces the scaffold against ground.
Risk: The likelihood (probability) which can lead to potential negative consequences.
Risk Assessment: A systematic and structured process whereby hazards present in a
workplace, or arising from workplace activity, are identified, risks assessed / evaluated,
and decisions prioritized in order to reduce risks to acceptable levels.
SHE: Safety, Health and Environment
Sole Plate: It is a Mild Steel plate of 300 mm x 300 mm x 6 mm thick, provided below the
base plate in unpaved area.
Severity: The level of consequence / harm of an event that could occur due to exposure
to the hazard present
Shall: Mandatory requirement
Should: Optional requirement

Note: Uncontrolled once printed Page 4 of 24


Document Title:
The Tata Power Company Ltd Scaffold Safety Procedure
Document Ref No.
Date of Issue: 01/01/2016
TPSMS/CSP/SCAF/007 Rev 01

Scaffolding Supervisor: A competent person who through training and/or experience a)


is knowledgeable of applicable scaffolding regulations; b) is capable of identifying existing
and predictable hazards related to the erection, alteration, use, dismantling, storage, and
inspection of scaffolding; and c) has the authority to take prompt corrective actions to
eliminate such hazards.
Scaffolder: A person who through training and/or experience is capable of erecting,
moving, modifying and dismantling scaffold
Scaffold: Any temporary elevated platform (suspended or supported) and its supporting
structure (including points of anchorage) used for supporting man, material or both.
Supported scaffold: One or more platforms supported by outrigger beams, brackets,
poles, legs, uprights, posts, frames, casters, or similar rigid support. Examples include
fabricated-frame scaffold, system scaffold, tube-and-coupler scaffold, and manually
propelled mobile scaffold.
Suspension (suspended) scaffold: One or more platforms suspended by ropes or other
non rigid means from an overhead structure(s).
System scaffold: A scaffold consisting of posts with fixed connection points that accept
runners, bearers, and diagonals that can be interconnected at predetermined levels.
Standard: A vertical or near vertical member used in the construction of scaffold for
transmitting the load to the foundation.
Tube-and-coupler scaffold: A supported or suspended scaffold consisting of a
platform(s) supported by tubing, erected with coupling devices connecting uprights,
braces, bearers, and runners (also known as tube-and-clamp scaffold).
Transom: A member spanning across ledgers/standards to tie a scaffold transversely and
which may also support a working platform.
Toe Board: A barrier placed along the edge of scaffold platform and secured there to
guard against the falling of material and equipment.
Task / Activity: A sequence of steps taken to conduct a job. A task is a sub element of a
Job.

Note: Some of the common definitions, used in conjunction with scaffold, are illustrated
in the diagram (as depicted) for the ease of understanding.

Note: Uncontrolled once printed Page 5 of 24


Document Title:
The Tata Power Company Ltd Scaffold Safety Procedure
Document Ref No.
Date of Issue: 01/01/2016
TPSMS/CSP/SCAF/007 Rev 01

Illustrative Diagram – Scaffold Terminology

Note: Uncontrolled once printed Page 6 of 24


Document Title:
The Tata Power Company Ltd Scaffold Safety Procedure
Document Ref No.
Date of Issue: 01/01/2016
TPSMS/CSP/SCAF/007 Rev 01

6. PROCEDURES:
6.1 General Information
6.1.1 Erection, dismantlement, movement, and modification
Approved Permit-To-Work and Job Safety Analysis (JSA) shall be made available before
erecting, dismantling, moving, or modifying scaffolding. Examples of hazards to consider
include, but not limited to the following:
 Working from heights
 The presence of nearby electrical lines or process equipment
 Hazardous area classification
 The condition of working surfaces
 The presence and activity of other people in the vicinity of the work
 The weather (Heavy rain, high wind velocity-more than 36 Km/Hr, etc)
6.1.2 Scaffolding shall be erected, dismantled, moved, and modified only under the
direction of a competent person and by employees who have received appropriate
and specific training for the work they are to perform. Determination and
designation of competent persons for scaffold work are the responsibility of the site
except where local regulations set other criteria.
6.1.3 Categories and Classification:
Most scaffolds fall into one of the four primary categories:
 Tube and coupler scaffold/Coup lock scaffold
 Suspended scaffold
 Mobile scaffold
 System scaffold
 Supported scaffold
 Scaffolds are classified according to their intended use as:
 Light duty
 Medium duty
 Heavy duty

Load duty Light Medium Heavy/Special


Maximum Safe load in Kg/M² 75 150 225 300 450 600

Maximum bay length in meter 2.7 2.2 1.8 1.4 1.0 0.8

Note: Uncontrolled once printed Page 7 of 24


Document Title:
The Tata Power Company Ltd Scaffold Safety Procedure
Document Ref No.
Date of Issue: 01/01/2016
TPSMS/CSP/SCAF/007 Rev 01

6.1.4 Specifications of Scaffolds applicable to all Scaffolds:


6.1.4.1 All elevated structures/ working platform areas shall be guarded on all sides.
6.1.4.2 Railings and toe boards shall be provided on the platform.
6.1.4.3 Scaffolds shall be designed to support at least 4 times the anticipated weight of
Men and material.
6.1.4.4 Make certain that all scaffolds are in plumb and level at all times.
6.1.4.5 Scaffolds shall be secured from tipping when the scaffold height exceeds four
times its minimum base dimension.
6.1.4.6 Scaffolds shall be constructed at least 2 planks wide unless location makes this
physically impossible.
6.1.4.7 The scaffolding width is determined by the width of the boards, the minimum width
allowed for two boards is 600 mm but a more typical four-board scaffold would be
870 mm wide from standard to standard. More heavy-duty scaffolding can require
5, 6 or even up to 8 boards width
6.1.4.8 Landing platform shall be provided at every 9 meter of height.
6.1.4.9 The members of scaffolds shall overhang not less than 6" on either ends but not
more than 12". They shall be fastened on both ends and laid tight by scaffolds
and clamps.
6.1.5 Specifications of Scaffolds applicable to Tube-and-Coupler Scaffold:
6.1.5.1 Minimum height of first horizontal member (Ledger) of scaffolds from the
Ground/Kicker lift member shall be 2.2 meters. When scaffold is more than 6
meter height or carrying heavy load, kicker lift should be provided.
6.1.5.2 The mid rail and Top rail shall be at height 600 mm and 1200 mm respectively
and toe boards (150mm) shall be securely attached to the platform.
6.1.5.3 Wall scaffoldings shall be secured between structure and scaffolding, at least
every 10 meters of length and 8 meters of height.
6.1.5.4 Minimum overlap of vertical members (standards) and/ or horizontal members
(Ledgers) shall be 600 mm with at least two couplers.
6.1.5.5 Base plate 100 x 100 x 3 mm shall be used to support all vertical pipes of
Scaffolds.
6.1.5.6 Sole plate of 300 x 300 x 6 mm shall be used at all unpaved area to support base
plate.
6.1.6 Precautions applicable to Mobile Scaffold:
6.1.6.1 Attach castors with plain stems to the panel or adjustment screw by pins or other
suitable means. Mid rail and Top rail shall be at height 600mm and 1200 mm
respectively.
6.1.6.2 Apply castor brakes at all times when a scaffold is not being moved.
6.1.6.3 Do not ride rolling scaffoldings.
6.1.6.4 Remove all material and equipment from platform before moving scaffolding.

Note: Uncontrolled once printed Page 8 of 24


Document Title:
The Tata Power Company Ltd Scaffold Safety Procedure
Document Ref No.
Date of Issue: 01/01/2016
TPSMS/CSP/SCAF/007 Rev 01

6.1.6.5 Do not try to move rolling scaffolding without sufficient help. Watch out for holes
in the floor and for overhead obstructions.
6.1.6.6 Do not use brackets on rolling scaffoldings without first considering the
overturning effect.
6.1.6.7 Mobile Scaffolds shall be designed to restrict maximum height verses length to
4:1.
6.1.7 Safety Requirements
6.1.7.1 Appropriate barricades shall be installed to protect people in the vicinity during
scaffold erection, use, modification and dismantling. As far as practicable,
barricades shall be provided by keeping a clear distance of 1.0 meter from
scaffold structure.
6.1.7.2 Fall protection when erecting, dismantling, and modifying scaffolds shall be under
the direction of a competent person (Scaffold Supervisor).
6.1.7.3 Scaffold erectors (Scaffolders) shall use personal fall-arrest systems that provide
continuous fall protection while erecting, dismantling or modifying scaffolds unless
the determination is made by a competent person that fall protection is not
feasible or it creates a greater hazard.
6.1.7.4 Fall protection can be accomplished through the use of adequate anchorages that
are independent of the scaffold or by using scaffold systems and components that
are approved by the manufacturer as adequate anchorages.
6.1.7.5 Employees shall use appropriate fall-arrest equipment in accordance with
Engineering Standard on “Full body Harness and fall protection system”.
6.1.7.6 The footing for supported scaffolds shall be sound, rigid, and capable of
supporting the maximum intended load, including the weight of the scaffold.
6.1.7.7 Manufacturer’s guidelines for proprietary scaffolds (e.g. Cup & lock, H frame,
Insulating modular scaffolds) shall be followed with applicable regulations.
6.1.7.8 There shall be firm foundation for all scaffoldings. All scaffolding shall be made of
sound (free from deformation, cracks, corrosion) material.
6.1.7.9 Scaffolding material shall be inspected and used, only if found in good condition.
Avoid using equipment whose strength is not known.
6.1.7.10 Provide adequate sills for scaffolding posts. Metal base plate is used under all
upright or standard scaffoldings. Correct type of couplers shall be used for all
connections.
6.1.7.11 Plumb and level scaffoldings as erection proceeds, so that braces will fit without
forcing. Fasten all braces securely.
6.1.7.12 Where scaffoldings are erected above walkways or work areas, the space
between toe board and railing should be covered with net / screens.
6.1.7.13 Whenever work is being done above the scaffolding under erection, overhead
protection should be provided to the scarfolders.
6.1.7.14 A safe and convenient means of access shall be provided to the platform level.
Means of access may be a portable ladder, fixed ladder, ramp or runway or

Note: Uncontrolled once printed Page 9 of 24


Document Title:
The Tata Power Company Ltd Scaffold Safety Procedure
Document Ref No.
Date of Issue: 01/01/2016
TPSMS/CSP/SCAF/007 Rev 01

stairway. The ladder shall be so installed that there supporting member (pipe) is
just below ladder rung. This is to avoid tripping hazard, especially while using the
ladder.
6.1.7.15 During erection, the ladder shall be installed as early as practicable, but not later
than first two horizontal members (Ledgers). This is to facilitate Scaffolder while
erecting the scaffold.
6.1.7.16 Ladder should be provided with tie rods/studs at top and bottom rungs.
6.1.7.17 Do not cantilever or extend putlogs / trusses as side brackets, without thoroughly
considering the loads to be applied.
6.1.7.18 Do not climb cross braces.
6.1.7.19 Do not use ladders or makeshift devices on top of scaffoldings to increase the
height.
6.1.7.20 Have at least 12” overlap and 6” extension beyond centerline of support or cleat
both ends to prevent sliding.
6.1.7.21 Do not allow unsupported ends of planking to extend an unsafe distance beyond
supports.
6.1.7.22 Planks shall be non-greasy and free from defects.
6.1.7.23 Access to working platform shall be suitably protected against inadvertent fall by
providing swing members/ swing gate or chains.
6.1.7.24 When scaffolding is no longer required, request for dismantling of scaffold shall
be sent to scaffolding supervisor through work permit.
6.1.7.25 Scaffold shall be removed from top bracings. Ties, ledgers etc. should not be
removed from section lower than the one which is being dismantled.
6.1.7.26 Do not throw or allow falling to ground any scaffold member, board or fittings.
6.1.7.27 Dismantled scaffold material shall be neatly stacked, away from the site until
whole of scaffold has been dismantled.
6.1.7.28 During the erection stage of a scaffold, warning notices with the wording “scaffold
incomplete, Do not use” (Annexure - 3) shall be fixed to the scaffold at all access
points. This warning will be in the form of a painted board. It is a good practice to
have the authorized (competent) person(s) sign the boards.
6.1.7.29 In NO circumstances, incomplete scaffolding shall be allowed to carry out any
job.
6.1.7.30 The status board with the wording “Scaffold Complete, Safe for Use" (Annexure -
3) shall be displayed when the scaffolding is ready for use.
6.1.7.31 After erection, but before first use of a scaffold, the erected scaffolding shall be
inspected (Using scaffold check list as per Part 2 in Annexure-2) and approved
by the competent person. The certification of the scaffolding shall be as per Part
3 in Annexure-2.
6.1.7.32 Once erected the scaffolding shall be inspected “Every Week” and recorded in
Part 4 in Annexure-2. Scaffold after due date of inspections shall not be
permitted for Use without Re-inspection by the Competent person.

Note: Uncontrolled once printed Page 10 of 24


Document Title:
The Tata Power Company Ltd Scaffold Safety Procedure
Document Ref No.
Date of Issue: 01/01/2016
TPSMS/CSP/SCAF/007 Rev 01

6.1.7.33 When the completed scaffold is handed over for use, it is the responsibility of
user to ensure its correct and safe use.

6.1.7.34 In the event of any doubt concerning the integrity of a particular scaffold,
“Scaffold Incomplete – Do not Use” (Annexure-3) boards shall be displayed.
These boards will be put up after removing "Scaffold Complete- Ready for Use"
boards.
6.1.7.35 If any changes or alternation to the original scaffold are found, inform the
scaffolding supervisor and prevents others from using the scaffold by do not use
boards until it is re-inspected by the scaffolding supervisor.
6.1.7.36 Removal of scaffold shall be done through Permit-To-Work.
6.1.8 Use of scaffold:
6.1.8.1 Person who use scaffolds shall be trained. The scope of the training shall include
the appropriate safe working practices for the work to be performed and
guidance on assessing hazards and selecting the proper protective measures.
6.1.8.2 Personnel working below and passersby shall be protected from overhead
hazards.
6.1.8.3 Safe access shall be provided for scaffold users. Cross-bracing shall not be used
for access. End frames shall not be used for access unless they were designed
for use as access.
6.1.8.4 Person who use scaffolds shall assess the hazards posed by working on them
and take appropriate precautions to mitigate the hazards.
6.1.8.5 No scaffold shall be loaded beyond the working load for which it is intended.
6.1.8.6 Person shall use appropriate fall-arrest equipment in accordance with Standard
on “Full body harness and fall protection system” on scaffolds not equipped with
standard top rail, mid rail, toe guard and complete decking.
6.1.9 Storage and inspection of Scaffold materials
6.1.9.1 All scaffolding material shall be stored at designated location to protect them
from adverse environment conditions such as corrosion, weather according the
manufacturer’s recommendations and /or as per instructions of scaffolding
supervisor.
6.1.9.2 Storage racks/ Locations/ areas shall be clearly identified. Long term storage of
scaffolding material may be at a single location.
6.1.9.3 From designated storage, the requisite material should be moved to the location,
as transit storage, for immediate use for erection of scaffolding.
6.1.9.4 The dismantled scaffolding material should not be allowed to pile up in the plant
area. Storage facility of scaffold material shall be properly constructed for its
stability and load bearing capability.
6.1.9.5 Scaffolding material such as tubular, planks, clamps etc. shall be inspected
annually by the user department as per Annexure 5 to ensure they are free from
defects. The visual inspection shall cover 100% scaffold materials. The inspected

Note: Uncontrolled once printed Page 11 of 24


Document Title:
The Tata Power Company Ltd Scaffold Safety Procedure
Document Ref No.
Date of Issue: 01/01/2016
TPSMS/CSP/SCAF/007 Rev 01

lot of material should be suitably painted, clearly indicating due date for the next
inspection.
6.1.9.6 Information on inspecting scaffold components and testing scaffolds planking can
be found in the manufacturer’s literature.
7. Records:

Following records shall be retained in compliance with the Corporate Records.


7.1. Scaffolding request, inspection, certificate and Weekly re-certificate
(TPSMS/CSP/SCAF/007/FORM/001) – Retention -12 months
7.2. Scaffolding Audit check list (TPSMS/CSP/SCAF/007/FORM/002) - Retention –Three
Years
7.3. Scaffold pipe, Ladder, Plank/Jali, Clamps, Base Plate Check-list
(TPSMS/CSP/SCAF/007/FORM/003)- Retention –Three Years
8. Training & Communication:
8.1. Training on Scaffold Safety Procedure shall be carried out to cover for following-
a. Competent Person,
b. Scaffolding Supervisor,
c. Scaffolder
8.2. Initial Communication to be done through Corporate Communication, Email and
subsequently shall be made available at safety portal at Sangam.
9. VERIFICATION
9.1. Verification of implementation shall be done during Scaffold Safety procedure audit,
field safety visit and site inspections.
10. REFERENCES
 Indian Factory Act 1948 and State Factory Rules
 Tata Power Permit-To-Work Procedure(TPSMS/CSP/PTW/008)
 Tata Power Job Safety Analysis (JSA) Procedure (TPSMS/CSP/JSA/009)
 Tata Power Hazard Identification & Risk Assessment (HIRA) Procedure
(TPSMS/GSP/HIRA/005)
 Tata Power Working at Height Procedure (TPSMS/CSP/WAH/004)
Other references
IS : 3696 ( Part 1 ) – 1987 (Scaffolds) Safety code of scaffolds and ladders
IS : 3696 ( Part 2 ) – 1987 (Ladders) Safety code of scaffolds and ladders
IS : 4014 – 1967 Code of practice for steel tubular scaffoldings
IS : 3521 – 1999 Industrial safety belts and harnesses
 Provision on scaffold under the building and other construction workers.
(Regulation on employment and conditions of service) central rules, 1998.

11. Exceptions: Any Exception to this procedure shall only be done as per Document Control
.Procedure (TPSMS/GSP/DC/014).

Note: Uncontrolled once printed Page 12 of 24


Document Title:
The Tata Power Company Ltd Scaffold Safety Procedure
Document Ref No.
Date of Issue: 01/01/2016
TPSMS/CSP/SCAF/007 Rev 01

12. Review: Review of this procedure shall be done as and when but not later than once in
every three (03) years. Typical Factors like Changes in legislation, Review of Incident
Reports, Inspection & Audit findings, Feedback from users, Recommendations in Incident
investigation reports may be inputs for the review and revision of the procedure.

13. ATTACHMENTS/APPENDIX :
Refer Sample formats as Annexures attached in next page of this document:
13.1 Annexure-1: Scaffold erection, use and removal process flow Chart
13.2 Annexure-2: Scaffolding request, inspection, certificate and Weekly re-certificate
(TPSMS/CSP/SCAF/007/FORM/001)
Pat-1: Requesting for Scaffolding
Part-2: Inspection Check List for Scaffolding
Part-3: Certificate of Fitness of Scaffolding
Part-4: Weekly Re-Certification for Fitness of Scaffolding
13.3 Annexure-3: Safety Boards.
13.4 Annexure-4: Scaffolding Audit check list (TPSMS/CSP/SCAF/007/FORM/002)
13.5 Annexure-5: Scaffold pipe, Ladder, Plank/Jali, Clamps, Base Plate Check-list
(TPSMS/CSP/SCAF/007/FORM/003)
13.6 Annexure 6: Do’s and Don’ts for Scaffold Safety

Note: Uncontrolled once printed Page 13 of 24


Document Title:
The Tata Power Company Ltd Scaffold Safety Procedure
Document Ref No.
Date of Issue: 01/01/2016
TPSMS/CSP/SCAF/007 Rev 01

Annexure - 1
Scaffold erection, use and removal process flow Chart

Annexure 6: Scaffold erection, use and removal process flow chart


Pre erection stage Scaffold erection (Do not use Board) Scaffold use (Ready for use Board) Scaffold removal (Do not use Board)

Accept Work
User

Requirement of Permit, If scaffold requires


Needs review
scaffold execute the more than 7 days since
work last certified
NO
Operation
Engineer

Issue Work

No
Close Work Close Work Permit
Site review and Permit with Issue Work Permit
Permit for Issue Work Permit for work for Removal of
Decision for Issuing YES site specific with site specific
Erection of on scaffold scaffold
Work Permit Risk Risk assessment
scaffold

Yes
assessment

OK
Maintenance

Permit Request Accept Work Check & Certify the Requires


Engineer

Scaffold Request
for Scaffold Permit and scaffold for use rectification Permit Request for Accept Work Permit and
Part 1
Erection/ A Check & certify
(Annexure 2)
Modification
Communicate
Contractor
Part 2 & 3
( Annexure 2)
A scaffold Part 2 & 4 Scaffold Removal Communicate Contractor
(Annexure 2)
Remove “Ready
for Use board
Contractor

Erect scaffold as per scaffold


Site review and Check scaffold Dismantle scaffold and
request and defined in work
understand Part 2 & 4 move scaffold materials
permit under supervision
requirement (Annexure 2) at designated storage
Part 2 & 3 (Annexure 2)
Auditor

Annexure 2 (Scaffolding request, inspection,


The scaffold material is auditable as per The activity under scaffold use is
certificate and weekly re-certificate) documents to
annexure 4. auditable as per Annexure 3.
be retained as per self safety audit check records.

Note: Uncontrolled once printed Page 14 of 24


Document Title:
The Tata Power Company Ltd Scaffold Safety Procedure
Document Ref No.
Date of Issue: 01/01/2016
TPSMS/CSP/SCAF/007 Rev 01

Annexure - 2
TPSMS/CSP/SCAF/007/FORM/001 (Part: 1 of 4)
Part 1

Scaffolding request, Inspection, Certificate and Weekly re-certificate

REQUEST FOR SCAFFOLDING


I hereby request that the scaffolding for purpose of …………………….. be erected for
the duty (select from load table as given below) and height……….. Meter.

Load duty Light Medium Heavy/Special


Maximum Safe load in Kg/ M² 75 150 225 300 450 600
Maximum bay length in Meter 2.7 2.2 1.8 1.4 1.0 0.8
Width in Meter*

*Note: The scaffolding width is determined by the width of the boards, the minimum width
allowed for two boards is 600 mm but a more typical four-board scaffold would be 870 mm
wide from standard to standard. More heavy-duty scaffolding can require 5, 6 or even up to 8
boards width

Remarks (If any) :

(Name & Signature of Maintenance Engineer)

M/s ________________ Date:


(Scaffolding Contractor)

Note: Uncontrolled once printed Page 15 of 24


Document Title:
The Tata Power Company Ltd Scaffold Safety Procedure
Document Ref No.
Date of Issue: 01/01/2016
TPSMS/CSP/SCAF/007 Rev 01

Annexure - 2
TPSMS/CSP/SCAF/007/FORM/001 (Part: 2 of 4)
Part 2

INSPECTION CHECK LIST - SCAFFOLDING

S. Yes/ No/
Checks Points Remarks
No NA

1. Are the scaffoldings erected as per the load duty


requested?
2. Is every work platform fitted with handrail (top rail 1200
mm and mid rail at 600 mm high) and a toe board (150
mm) secured to the platform sides?
3. Are the scaffolding in plumb and level?
4. Are the planks/gratings placed in order without undue
gaps and anchored?
5. Are the footing / anchorage for scaffolds sound and the
bay lengths maintained as per the maximum Intended
load (duty)?
6. Are the poles, legs or uprights of scaffolding are securely
braced to prevent swaying / displacement?
7. Are the base plates (100 x 100 x 3 mm) provided for
scaffolding posts?
8. Are the base plates are supported by sole plate
(300 x 300 x 6 mm) at unpaved area?
9. Is kicker lift (at distance 150 mm from ground/base)
provided for scaffold of height more than 6.0 meter?
10. If the scaffolding is erected above walkways or work
areas, are the space between toe boards and railings
screened?
11. If work is done over men who are working on scaffolding,
is overhead protection provided?
12. Has the scaffolding area suitably barricaded during
erection / usage / dismantling? As far as practicable,
barricades shall be provided by keeping a clear distance
of 1.0 meter from scaffold structure.
13. Is free standing scaffolding tower protected from tipping
by guying or other means?

Note: Uncontrolled once printed Page 16 of 24


Document Title:
The Tata Power Company Ltd Scaffold Safety Procedure
Document Ref No.
Date of Issue: 01/01/2016
TPSMS/CSP/SCAF/007 Rev 01

S. Yes/ No/
Checks Points Remarks
No NA

14. Is there a safe and convenient means of access? If a


ladder is used, is it rising at least 1050mm above the
platform?
15. Are relevant status boards (tags) attached to the
scaffolding completed / under erection as applicable?
16. Is safe access to equipment or emergency egress
restricted by scaffolds?
17. Are wall scaffolding anchored every 10 m of length and 8
m of height?
18. Are landing platforms provided for access ladders more
than 9 meters height?
19. If two pipes are connected, are they overlapped at least
600 mm and at least two clamps used?

Checked by (Scaffolding Inspector/Supervisor):

Note: Uncontrolled once printed Page 17 of 24


Document Title:
The Tata Power Company Ltd Scaffold Safety Procedure
Document Ref No.
Date of Issue: 01/01/2016
TPSMS/CSP/SCAF/007 Rev 01

Annexure - 2
TPSMS/CSP/SCAF/007/FORM/001 (Part: 3 of 4)
Part 3

CERTIFICATES OF FITNESS OF SCAFFOLDING

I hereby certify that the scaffolding erected for work permit no. ------------------- is ready and fit
for use. I further certify that it is intended for light duty/ General purpose (Medium duty)/
Heavy duty or special duty (tick whatever applicable) service and fit for a load of ……………..
Kg and should not be overloaded.

Name and signature of Name and signature of


Competent Person Scaffolding Supervisor

(Dept……………..) M/s _________________


(Scaffolding Contractor)

Date: ____________

Note: Uncontrolled once printed Page 18 of 24


Document Title:
The Tata Power Company Ltd Scaffold Safety Procedure
Document Ref No.
Date of Issue: 01/01/2016
TPSMS/CSP/SCAF/007 Rev 01

Annexure - 2
TPSMS/CSP/SCAF/007/FORM/001 (Part: 4 of 4)
Part 4

WEEKLY RE-CERTIFICATION FOR FITNESS OF SCAFFOLDING

Scaffolding is
Scaffolding Name and
inspected as per Name & sign
Certification is safe for sign of
Date part 2 of Competent
for use scaffolding
(any new Person
( Yes/ No) supervisor
observation)
2nd week

3rd week
4th week
5th week

6th week

7th week
8th week
9th week

10th week

Note: Uncontrolled once printed Page 19 of 24


Document Title:
The Tata Power Company Ltd Scaffold Safety Procedure
Document Ref No.
Date of Issue: 01/01/2016
TPSMS/CSP/SCAF/007 Rev 01

Annexure - 3

Safety Boards

Scaffold No:_________

SCAFFOLDING
INCOMPLETE
DO NOT USE
Name of Contractor :

Scaffold No:__________

SCAFFOLDING
COMPLETE
READY FOR USE
Name of Contractor :
Date of Inspection :
Name of Scaffold Inspector:

Note: Uncontrolled once printed Page 20 of 24


Document Title:
The Tata Power Company Ltd Scaffold Safety Procedure
Document Ref No.
Date of Issue: 01/01/2016
TPSMS/CSP/SCAF/007 Rev 01

Annexure – 4
TPSMS/CSP/SCAF/007/FORM/002 Page: 1 of 2
Scaffolding Audit Check List

S. Yes/ NO/
Checks Points Remarks
No NA
1. Has the request for scaffolding been signed by authorized person?
2. Has the 'certificate of fitness of scaffolding' been signed by a
scaffolding supervisor and maintenance engineer?
3. Are the scaffoldings erected as per the load duty requested?
4. Is every work platform fitted with handrail (top rail 1200mm and mid
rail at 600 mm high) and a toe board (150mm) secured to the
platform sides?
5. Are the scaffolding in plumb and level?
6. Are the gratings placed in order without undue gaps and
anchored?
7. Are the footing / anchorage for scaffolds sound and the bay lengths
maintained as per the maximum intended load?
8. Are the poles, legs or uprights of scaffolding are securely braced to
prevent swaying / displacement?
9. Are the base plates (100 x 100 x 3 mm) provided for scaffolding
posts?
10. Are the base plates are supported by sole plate
(300 x 300 x 6 mm) at unpaved area?
11. Is kicker lift (at distance 150mm from ground/base) provided for
scaffold of height more than 6.0 meter?
12. If the scaffolding is erected above walkways or work areas, are the
space between toe boards and railings screened?
13. If work is done over men who are working on scaffolding, is
overhead protection provided?
14. Has the scaffolding area suitably barricaded during erection /
usage / dismantling? As far as practicable, barricades shall be
provided by keeping a clear distance of 1.0 meter from scaffold
structure.
15. Is free standing scaffolding tower protected from tipping by guying
or other means?
16. Is there a safe and convenient means of access? If a ladder is
used, is it rising at least 1050mm above the platform
17. Are relevant status boards (tags) attached to the scaffolding
completed / under erection as applicable?

Note: Uncontrolled once printed Page 21 of 24


Document Title:
The Tata Power Company Ltd Scaffold Safety Procedure
Document Ref No.
Date of Issue: 01/01/2016
TPSMS/CSP/SCAF/007 Rev 01

Annexure – 4
TPSMS/CSP/SCAF/007/FORM/002 Page: 2 of 2

S. Yes/ NO/
Checks Points Remarks
No NA
18. Is safe access to equipment or emergency egress restricted by
scaffolds?
19. Are wall scaffolding anchored every 10 m of length and 8 m of
height?
20. Are landing platforms provided for access ladders more than 9
meters height?
21. If two pipes are connected, Are they overlapped at least 600 mm
and at least two clamps are used?

Remarks (If any) :

Inspected By (Name & Signature of Scaffolding inspector/supervisor) :

Reviewed By (Name & Signature) :

Note: Uncontrolled once printed Page 22 of 24


Document Title:
The Tata Power Company Ltd Scaffold Safety Procedure
Document Ref No.
Date of Issue: 01/01/2016
TPSMS/CSP/SCAF/007 Rev 01

Annexure – 5
TPSMS/CSP/SCAF/007/FORM/003

Scaffold pipe, Ladder, Plank/Jali, Clamps, Base Plate - Check-list

Material Check List Observation


- Rust Free Pipes
Pipes - No Bends, Cuts, Holes
- No Sharp edge, pipe end condition
- Pipe thickness minimum 2 mm
- Painted / galvanized pipes
- Any other(Specify)
- Rail Damaged (cracks, deformation etc.)
Ladder - Rust free & Properly Painted Ladder.
- No Cut, Hole or any Physical damage.
- Equal spacing between rungs (max 30 cm).
- Ladder width greater than = 30 cm.
- No Bent, Broken, loose Rungs.
- No Sharp edge.
- No Oil, Grease and other slippery items
- Bottom non-skid pad damaged/missing
- Top and bottom rung tie rod provided
- Any other(Specify)
- Jalli spacing maximum 1.5” to 2”.
Plank/Jalli - Plank all 4 hooks not damaged.
- No Cut or any other Physical damage.
- Not depressed beyond 15 mm.
- Rust free and properly painted.
- Flat Thickness 3mm internal and 5mm outer boundary.
- Any other(Specify)
- Rust free and properly painted.
Clamps - No cut/cracks or physical damage.
- No lubrication.
- No Eyebolts bent.
- Thread condition/Nut condition.
- No welding / local repair
- Any other(Specify)
Base Plate - Rust free and properly painted.
& - No bend.
Sole plate - No Cut, Hole or physical damage.
- Flat Bottom portion.
- Any other(Specify)

Inspected By: Name: _______Designation:_____ Sign: ______Date:_____

Reviewed By: Name: _______Designation:_____ Sign: ______Date:_____

Note: Uncontrolled once printed Page 23 of 24


Document Title:
The Tata Power Company Ltd Scaffold Safety Procedure
Document Ref No.
Date of Issue: 01/01/2016
TPSMS/CSP/SCAF/007 Rev 01

Annexure – 6

Do’s and Don’ts for Scaffold Safety

Do’s
- Use only certified scaffolding, tagged with “Scaffolding Complete, Ready for Use”
- Maintain three-point-contact while climbing up or down the ladder.
- Use rope or container or other suitable means for carrying material from or to ground.
- Maintain good housekeeping, especially at elevated working platform and near the
access.
- Do take special precautions while working in vicinity of mobile cranes or electrical
overhead lines.
- Wear full body safety harness with double lanyard/ personal fall arrest system or other
equally effective means while ascending or descending the ladder or scaffolding
working platform is not fully guarded.
- Do check for emergency approach/ evacuation, especially adequacy means of egress.
- Use safe material handling ways while shifting the material.
- Do report “At-risk conditions” e.g. missing ladder, incomplete decking, improper
guarding, no landing platform, loosely clamped ladder, etc. to your supervisor.
- Do check weekly certification of scaffold at random

Don’ts
- Do not use any part of operational line or pressurized piping as a support, or tie point
for scaffolds or staging.
Do not permit mixing of scaffold types in any one structure (e.g., steel/aluminum
couplers, wooden boards/metal grid boards).
- During the possibility of a thunderstorm, no work shall be executed at a height where a
person can be exposed to lightning.
- Never keep loose tools, materials etc at height in a way it may roll off and fall from
height.
- Do not use cross-bracing or end-frame (unless specially designed) for access.
- Avoid overloading and impact loading
- Never alter or modify or dismantle any part of the scaffold without permission from
scaffolding supervisor or Tata Power personnel.
- Do not throw tools or scaffolding materials from height.
- Do not use “Incomplete Scaffold”.

Note: Uncontrolled once printed Page 24 of 24

You might also like