The Change Management Body of Knowledge
The Change Management Body of Knowledge
The Change Management Body of Knowledge
Body of Knowledge
Capturing the Maximum Value
Possible from Projects
and Programs
ii
Version 11.0 September 2013
Table of Contents
Table of Figures vi
Introduction 1
1 Understand the purpose of the change 4
1.1 The steps of project value realization 4
1.2 Understand the project’s “value proposition” 4
2 Analyze Change Impact 5
2.1 Identify areas of change 5
2.2 Visualize the “change hot spots” by using a change point matrix 6
2.3 Determine if change management is needed 6
2.4 Identify any barrier or enablers associated with key stakeholders 7
2.5 Identify and prioritize risks inherent to the change 7
3 Determine the Organization's Change Enablers and Barriers 8
3.1 Review historical enablers and barriers to change 8
3.2 Assess the organization's current change capacity 8
3.3 Assess the availability and quality of change sponsors and champions 9
3.4 Assess the capacity of individuals to manage change 9
3.5 Create a prioritized list of the major change barriers and change enablers 11
4 Develop the Organizational Change Management Plan 12
4.1 Plan the change management activities (WBS) 12
4.2 Clarify that responsibility for all change management results are clear 18
4.3 Confirm due dates for all change management milestones (for all 4.1 activities) 18
4.4 Analyze project plans for compliance risks 18
4.5 Review and approve the change plan 19
5 Create a transition plan to help people successfully deal with change 20
5.1 William Bridges Three Questions 20
5.2 Dealing with endings 23
5.3 The “Transition Zone” 26
5.4 New Beginnings 26
6 Conduct a risk analysis for the change management plan 29
6.1 Identify risks to the change plan 29
6.2 Prioritize the change management plan's risks 30
6.3 Develop mitigation and contingency plans for the top risks 30
iii
Version 11.0 September 2013
7 Execute the Change Management Plan 31
7.1 Monitor change milestone delivery and key performance indicators 31
7.2 Coordinate change project communications 32
7.3 Coordinate the execution of organizational design activities 33
7.4 Coordinate training 33
8 Ensure Knowledge Management Integrity 34
8.1 Update all business processes, desktop procedures and job aids 34
8.2 Conduct a post-project business impact analysis 34
8.3 Identify future business transformation opportunities 35
9 Conduct a change management retrospective after the project 36
9.1 Analyze change management milestone and KPI performance 36
9.2 Conduct a change management retrospective 37
9.3 Review Change project effectiveness in key areas 38
9.4 Rate the effectiveness of the transition management efforts with the stakeholders 38
9.6 Communicate lessons learned and changes made 39
Tools, Templates and Reference Materials 40
Appendix A - Reference Materials and Additional Reading 40
Appendix B – Change Impact Questionnaire Example 41
Appendix C - Change Readiness Assessment 43
Appendix D – Simple Individual Change Resilience Assessment 48
Appendix E - The Professional Life Stress Test 50
Appendix F - Transition Management Planning Checklist 54
Appendix G -Change sponsor and Champion Planning Checklist 55
Appendix H - Planning Major Change Announcements Template 56
Appendix I– Ongoing or Periodic Communications Planning Checklist 57
Appendix J - Planning Outbound Communications Template 58
Appendix K- Feedback Planning Checklist 59
Appendix L - Engaging and Involving Staff during Transition 60
Appendix M – Planning Major Change Announcements 62
Appendix N - Ensure Knowledge Management Integrity 64
Appendix O - Retrospective Review Meeting Agenda 66
Appendix P - Transition Management Effectiveness Rating Sheet 68
iv
Version 11.0 September 2013
v
Version 11.0 September 2013
Table of Figures
Figure 1 Managed Change vs. Unmanaged Change Curves ............................................................ 4
Figure 2 Change Impact Questionnaire ........................................................................................... 5
Figure 3 Change Point Matrix .......................................................................................................... 6
Figure 4 Risk Planning Table ............................................................................................................ 7
Figure 5 Barriers and Enablers Lists................................................................................................. 8
Figure 6 Change Readiness Assessment ......................................................................................... 8
Figure 7 Individual change resilience assessment ......................................................................... 10
Figure 8 Professional Life Stress Test ............................................................................................ 11
Figure 9 Change Barriers and Enablers List ................................................................................... 11
Figure 10 Change Map or Change WBS ........................................................................................ 12
Figure 11 Change Work Breakdown Structure Planning Matrix .................................................. 13
Figure 13 Engaging and Involving Staff during Transitions ........................................................... 14
Figure 14 Skills Gap Inventory ...................................................................................................... 15
Figure 15 Major Change Announcement Planning Template ....................................................... 16
Figure 16 Outbound Communications Checklist ........................................................................... 16
Figure 17 Planning Ongoing or Periodic Outbound Communications Template .......................... 17
Figure 18 On-going Feedback Checklist......................................................................................... 17
Figure 19 Responsibility and Assignment Matrix .......................................................................... 18
Figure 20 Change Management Project Schedule ........................................................................ 18
Figure 12 Transition Management Planning Checklist ................................................................. 20
Figure 21 Risk Planning Table ........................................................................................................ 29
Figure 22 Milestone Schedule Performance ................................................................................ 31
Figure 23 Key Performance Indicator Dashboard ........................................................................ 31
Figure 24 Communications Dashboard ......................................................................................... 32
Figure 25 Training Dashboard ....................................................................................................... 33
Figure 26 Job Aid ........................................................................................................................... 34
Figure 27 KPI Form ........................................................................................................................ 36
Figure 28 Milestone Schedule Performance ................................................................................ 36
Figure 29 Retrospective Meeting Agenda ..................................................................................... 37
Figure 30 Transition Management Effectiveness Rating Sheet..................................................... 39
Figure 31 Job Aid .......................................................................................................................... 64
vi
Version 11.0 September 2013
Introduction
The goal of change management is “value
realization”. Projects are originally proposed by
Optimal Value
Effective
leadership to deliver a specific business outcome. Realization from
Communications
Projects
Change management’s main responsibility is to see that that value is delivered to the greatest
degree possible and as soon as possible.
To this end the change management office is tasked with delivering three major goals:
• Optimal value realization from projects - Minimal productivity disruptions and a higher
level of adoption
• Effective communications – to provide timely and accurate organization-wide
information
• Procedures optimized and documented – to keep the business manageable
1
Version 11.0 September 2013
To accomplish these goals, the Change Management Office provides the following functions and
services:
This body of knowledge reviews each of these goals; however the focus is organizational
development which minimizes productivity disruptions.
There are three parts to every successful effort to control productivity losses during a period of
change:
Any change management effort must have as its foundation strong employee/manager
relationships. This guide outlines the change methodology that the Change Management
Organization (CMO) uses here at Lender Business Process Services (LBPS), and is intended to
accelerate the change process by engaging people to the greatest degree possible. To do this it
is important to emphasize the following three factors:
2
Version 11.0 September 2013
In the laboratory, a catalyst is a substance that heightens or accelerates a reaction. In the
workplace the definition is similar: someone who sparks action in others. Being a catalyst is not
just another role. It requires a shift in thinking. It multiplies effectiveness. It requires
consistency. When effective, the work of the change manager is often behind the scenes and
not readily apparent to people outside the scope of the change project.
When people interact, they generally have two kinds of needs: practical needs (to reach a
productive outcome), and personal needs (to be understood and involved). Addressing both
kinds of needs helps ensure successful interactions. When left on the sidelines during change,
people turn to speculation. Morale drops and trust declines. The solution is to get people
involved and give them ownership in creating solutions.
The glue that holds everything together during times of uncertainty is good communications. It
is inevitable that issues will arise, people will face confusion and everyone will need to be
refocused and reenergized. Times of change require extraordinary skill at communications.
The following chapters outline the methodology in the order that it usually flows, however, you
will find that you will often have to pick and choose the particular tools and processes that are
relevant to each unique change situation.
3
Version 11.0 September 2013
1 Understand the purpose of the change
Projects will come to the Office of change management through the Investment and
Management board. Projects of sufficient complexity, magnitude or importance will be
assigned a change manager to help optimize value realization.
The foundation of change management is to understand the purpose of a project from the
organization’s viewpoint. A project proposal is in effect a “value proposition.” It states a
business case, defines a value to be delivered and estimates a cost to realize that value.
The first step in the organizational change management process is for the change manager to
interview the business leaders and managers and to thoroughly understand and document what
led the organization to initiate these changes:
• The business purpose of the project
• How the business will measure value
The whole change management plan will be focused on
maximizing the realization of this value to the business.
Once the purpose of the change is thoroughly understood
a plan can be designed to:
1. Reduce the productivity dips during times of
change
2. See that the new systems and procedures deliver
value as early as possible
3. Ensure that the new system is thoroughly adopted Figure 1 Managed Change vs. Unmanaged
Change Curves
and utilized to deliver maximum value
4
Version 11.0 September 2013
2 Analyze Change Impact
2.1 Identify areas of change
It is important to understand exactly what will be changing. If stakeholders are confused or have
differing visions of the change, you can guarantee that the change will either grow in magnitude,
creating undue anxiety, or the change will be minimized causing surprises down the line. The
following checklist is designed to help identify exactly where change will occur.
This questionnaire is used during planning meetings to stimulate thinking about the magnitude
of change imbedded within a project. It is to be used by a planning team to determine
additional work that will need to be addressed within the project.
The change impact questionnaire seeks to pinpoint the places in the organization that will be
experiencing the greatest changes.
1. Working relationships
2. Work content
3. Skills and competencies
4. Work environment
FigureFigure
2 Change Impact
1 Change Questionnaire
Impact Questionnaire
The change impact questionnaire will work with a large percentage of changes you will
encounter, but can be customized for change projects that have change impacts not covered.
5
Version 11.0 September 2013
Identify which of the stakeholder or stakeholder groups should be interviewed either
individually or in focus groups to better understand the impact of the change project.
Once the stakeholders are identified the change manager should arrange individual interviews,
facilitate focus groups, email or an online survey service to administer the questionnaire.
2.2 Visualize the “change hot spots” by using a change point matrix
Identify specific points of high change where the changes will be impacting the organization.
Transfer the change impact questionnaire scores from the groups impacted by the changes into
the change point matrix and sort the matrix. The change point matrix creates a “heat map” that
identifies points within the organizations structure that will be subjected to the most change.
The change point matrix can be sorted so that the areas that can benefit the most from a
change management effort are in the upper left of the matrix. The organizations that are the
most impacted by the change are at the top of the list and the types of change that will cause
the greatest impacts are now on the left.
If there are a large percentage of scores rated high, a change manager should be assigned to the
project. If the scores tend to be rated medium, a change manager should act as a consultant to
the project, sharing any applicable change management work breakdown structure modules. A
low score means that the change has such a low impact that change management is not
necessary.
6
Version 11.0 September 2013
2.4 Identify any barrier or enablers associated with key stakeholders
After analyzing all key stakeholders, it will be important to develop mitigation strategies to
influence stakeholders that are negative or lacking knowledge about the change. This is done in
section 4 – Develop the Change Management Plan
Identify specific risks to achieving the desired end-state of the project and maintaining
productivity during the period
of change.
7
Version 11.0 September 2013
3 Determine the Organization's Change Enablers and Barriers
3.1 Review historical enablers and barriers to change
Select the three or four top scoring enabling forces and opposing forces and add them to the list
of “change enablers and barriers.”
8
Version 11.0 September 2013
3.2.2 Prioritize the change enablers and barriers stemming from the organization’s capacity
to handle change
Continue to build the list of organizational enablers and barriers for the coming change that can
be added to the change WBS matrix in section 4 – Develop the Change Management Plan.
Again, you can use the force field analysis tool to capture barriers and enablers of this particular
change and its current perceived status within the organization.
3.3 Assess the availability and quality of change sponsors and champions
Add to the list of change enablers and change barriers items that come from the availability and
quality of the change sponsors and champions. The change management plan will be developed
out of the final list of change enablers and barriers. Change sponsors and change champions
play an important part in determining whether a change will be adopted or resisted. People take
clues from management as to whether they should take a change seriously or not. If “the right”
managers don’t seem to think the change is important, people will be more likely to ignore the
change or make it a second priority. Managers with influence, who visibly support a change, can
speed the rate of adoption. Managers need to be prepared and willing to give compelling
reasons why the change is important to the business.
Draft a complete list of potential change sponsors and champions. Validate that they:
The stakeholder analysis matrix created in section 2.3 looks at the first three of these factors.
The change manager should assess the individuals that will be impacted by the change and add
to the list significant change enablers and change barriers that can be added to the change WBS
matrix.
According to Dr. Bridges there are two main drivers of behavior during times of change:
1. Fear of losses
2. Lack of information
Both can cause serious losses of productivity and extend the time it takes for people to adopt
the changes. Our capacity to handle more change is known as “change resilience.” Resilience is
defined as: the ability to recover from or adjust easily to misfortune or change.
9
Version 11.0 September 2013
William Bridges says change is what happens to our work procedures and work environment.
The organization can change in an instant; people on the other hand react to change slower and
in different ways. People go through a transition period where they adjust to the change. Some
people go through their transition quickly and ultimately align with the change. Other people
will resist, ignore or deny the change. People’s capacity to handle any given change is highly
personal. Individual reactions to change can depend on factors such as:
Some of the things people can be afraid of losing due to the change are:
Some people will have lots of capacity to absorb more change; others
will have little or no capacity to deal with more change. The state of an
individuals and a groups collective “change resilience” can often be a
major determining factor in whether the change will be adopted or not.
The degree of change resilience can also impact the productivity losses
associated with the change. As people focus on their losses and resist
change productivity dips lower and the dip lasts longer.
10
Version 11.0 September 2013
The change readiness assessment will measure how much change is coming. An individual
change resiliency assessment will determine how much capacity
people will have to deal with the change.
11
Version 11.0 September 2013
4 Develop the Organizational Change Management Plan
4.1 Plan the change management activities (WBS)
The purpose of this activity is to develop a plan to return the organization to a productive, stable
with compliant business systems as rapidly as possible by insuring that:
Customize the standard change management WBS project modules to fit the specifics of the
change project.
12
Version 11.0 September 2013
4.1.1 Review the business purpose of the project and the change management goals
Make sure there is a clear understanding of the business purpose of the project plus the
conditions that are desired during and following toward which change management can make a
contribution.
If there is not a clear understanding of the goals for the change management efforts, work with
the change sponsor and key stakeholders to determine the complete range of their change
management goals and priorities. Part of this discussion will be to clarify: the scope of the
change based upon information gathered in the assessment phase.
Select activities from the generic change plan, WBS that will:
• Keep productivity as high as possible during the period of change
13
Version 11.0 September 2013
• Shorten the time between introducing the change and full adoption
• Deliver all of the elements of the desired “end-state”
• Address the “hot spots” in the change point matrix
• Leverage the “enablers” to change
• Overcome the “barriers” to change
Determine the level of change awareness in the sponsor/champion group. Make an assessment
of the following:
14
Version 11.0 September 2013
• Knowledge of the stages of transition and the actions required
• Understanding of the need to effectively communicate
• Understanding of how the change may be viewed by the end-users
• Understanding of how involving
end-users in the process lowers
resistance
Work with the training department to make sure that any necessary end-user skills training is
identified and included in the overall change plan:
Figure 12 Checklist Change Sponsor Planning
• Create skills gap map (heat chart)
• Determine specific training
solution to be used
• Develop desktop aids and online
references
Figure 13 Skills Gap Inventory
4.1.7 Plan communications
15
Version 11.0 September 2013
The communication about the specifics of
any change initiative is a key to the success
of the project. There are many types and
levels of communications that become
appropriate based upon the change project
complexity and the number of people
impacted by the change. In general, a
change initiative involves the following
three steps:
16
Version 11.0 September 2013
See Appendix J - Planning
Outbound Communications
Template
Figure 16 Planning
Ongoing or Periodic
Outbound
Communications
Template
If the change plan will involve changes to the organization’s structure (roles, tasks, reporting
level, performance metrics, etc.), determine the activities that need to occur to put these
changes in place:
17
Version 11.0 September 2013
Determine any work arounds or temporary working arrangements that need to be put in place
to support impacted stakeholder groups while the change is being rolled out.
4.2 Clarify that responsibility for all change management results are clear
The purpose of this is to ensure that there is no confusion about who is doing what.
4.3 Confirm due dates for all change management milestones (for all 4.1
activities)
Working to guarantee that the team is in agreement on when milestones will be finished is
important for the success of the project.
Coordinate with the Project Manager to plan the appropriate timing of the WBS change
modules, to minimize
organizational impact,
and resolve any
conflicts. Refine the
Gantt chart of the WBS
change activities, as
appropriate.
Insure that there are no unacceptable risks to compliance, legal, business impact, operations
imbedded in the change management plan.
• Pass the completed change management plan to the Operations Risk Analyst
• The operations risk analysis will review the project as designed for legal and compliance issues
18
Version 11.0 September 2013
• Correct any compliance related issues
Review the change plan with the project owner, project manager, and any key stakeholders that
stand in a decision-making capacity on the project. The purpose of this step is to gain a common
understanding of the change plan, make any necessary modifications, and to secure final
approval for the change activities. This step can be done electronically, but for a large change
project, this review should be in person. For a significant change projects it is advisable to have
an approval sign-off page for the change plan with a line for each key stakeholder.
19
Version 11.0 September 2013
5 Create a transition plan to help people successfully deal
with change
To accelerate the speed of change adoption by directly addressing the issues that slows the
psychological acceptance of change. See
Appendix F - Transition Management Planning
Checklist.
The reason for the potential problems is that while organizations can be changed with the
stroke of a pen, people change more slowly and go through a period of adjustment and
“transition”. Transitions involve three distinct stages:
• A period of endings
• A chaotic middle ground
• Creating and adjusting to new beginnings.
A common mistake is to avoid the first two stages and attempt to go directly to the new
beginnings. In the literature this is called an “unmanaged transition.” An unmanaged transition
typically takes longer, experiences greater productivity losses and results in unnecessary losses of
key staff.
Getting ready to talk to the executive director of a large non-profit organization the other day, I
found myself jotting down three questions that I wanted to ask her. I realized that I had been
1
Taken from Organizations in Transition, Vol 13, #2
20
Version 11.0 September 2013
using these questions with clients, in one form or another, for some time now but had never
written them out and reflected upon why I was using them. When I did so, I realized how central
they are to my practice. Here they are:
• What is changing?
• What will actually be different because of the change?
• Who's going to lose what?
• Here is why I think that they are so important:
It surprising how often organizations undertake changes that no one can describe very clearly.
Unclear descriptions of change: "We're changing the whole way we manufacture our
product." Or, "We're developing a world-class HR infrastructure." Or, "We've come to
believe that it is time to rethink the way that we go to market competitively and
differentiate ourselves from the other niche players in our industry.
The trouble with these announcements is that they convey a very unclear picture of the change
to those who have to make it work.
In fairness, it is often true that at an early stage in the process they themselves have only a
vague idea of what, specifically, is going to have to change. The planners know only that there
needs to be change in response to some threatening presence or some great opportunity "out
there."
But until that vagueness can be cooked out of the undertaking and until the leaders of the
change can not only explain it clearly, but do so in a statement lasting no longer than one
minute, there is no way that they are going to be able to get other people to buy into the
change. Longer explanations and justifications will also have to be made, of course, but it is the
one-minute statement that will be the core of people's understanding.
Don't get me wrong. I am not urging you to do a Readers Digest version of all your strategic
plans. I'm only saying that the successful leader is a person who can take a complex change and
reduce it to statements that are readily comprehensible to the people who are going to have to
make the changes work. The Communications Department may offer editorial help, but the
statement itself needs to express the understanding and intention of the leader.
So the first thing to check is whether there is, in fact, a short statement describing and justifying
the intended change, one that doesn't use jargon. (What is a "world class HR infrastructure,"
anyway?)
And be sure that the statement ties the change to whatever situation it is that makes the change
important. The way we often say that to our clients is, "Sell the problem before you try to sell
the solution." In other words, don't try to make a change to meet a challenge, solve a problem,
or seize an opportunity unless you have already established the challenge, the problem, or the
opportunity in people's minds.
21
Version 11.0 September 2013
5.1.2 What will actually be different because of the change?
Explaining the what and why of the change is essential, but it is not enough. I go into
organizations where a change initiative is well underway, and I ask what will be different when
the change is done—and no one can answer the question. One of my students arrived to run a
transition management seminar at a large oil company and asked, in all innocence, what was
going to be different because of the change. "We thought that you were going to tell us,"
replied the room full of managers.
Many change projects are designed and launched at such a high level in the organization that all
the planning is unrelated to the everyday, operational details that make up the lives of most
workers. In such cases, the decision-makers often have no idea how changes will actually make
anyone's life or job, or even the function of a whole department, different. Yet that is all that
people need to know before they can embrace and support a change.
Leaders find this frustrating. "The workers can't even see the crisis the organization is facing!"
they growl. True. But who is responsible for that fact? Leaders are paid to understand the
organization's larger problems, but at most companies the people under them are paid to do
their jobs. When we tell the leaders that they ought to share the state of the business, in all its
financial detail, with their followers, they say, "That'll just worry them. Besides, they don't need
to know that stuff to do their jobs."
A change may seem very important and very real to the leader, but to the people who have to
make it work it seems quite abstract and vague until actual differences that it will make begin to
become clear. Some of those differences will be behavioral (answering customer complaints
within 24 hours, for instance), while others will be structural (realigning sales teams by product
rather than region or reducing the layers between CEO and line workers from twelve to five).
The drive to get those differences clear should be an important priority on the planners' list of
things to do. If the differences simply cannot be spelled out at this time, then tell people how
they will be established (by whom, using what criteria?) and when the differences will be
explained. If you miss that date, by some mischance, explain why you missed it and give a new
date. The thing to remember: Say what you'll do and do what you say.
The previous two questions, as important as they are, concern the change--the shift in the
situation. The transition--the psychological reorientation that the people must go through to
make the change work—does not start with a new situation. It starts when the affected people
let go of their old situation. Endings come first. You can't do something new until you have let go
of what you are currently doing. Even the transitions that come from "good" changes begin with
losses of some sort, for letting go of the old way is experienced by the people who were used to
it as a loss.
For that reason, we often say in training programs that you don't cross the line separating
change management from transition management until you have asked "Who will lose [or has
lost] what?" Some of our clients resist asking that question. "That's negative," they say. "We
22
Version 11.0 September 2013
want to be positive about this change." Or they argue, "Let's don't talk about what is ending.
What we want them to understand is the new things that are beginning." Or they rationalize: "It
isn't as though they were going to lose their jobs. It's just a reorganization, for heaven's sake"--
as if leaving the team or the boss you've worked with for a year weren't a loss. Sometimes they
argue, "If we talk about losses, we'll just trigger off a lot of bitching and moaning," or that "I
don't think that loss-stuff has even occurred to them. We don't want to be putting ideas into
their heads."
There must be a hundred other versions of this objection to dealing with endings and losses, but
they are all variations on a single theme: the mistaken idea that the best way to get people
through a transition is to deny that they are even in a transition. In fact many communications
projects are based on this central misconception that you can (and should) talk people out of
their reactions to the change.
Transition management is based on another idea: that the best way to get people through
transition is to affirm their experience and to help them to deal with it. It is not a question of
agreeing with people or being nice to them. It is simply a question of understanding how the
world looks to them and using that as the starting point in your dealings with them.
When you do that, you bring issues out on the table, build trust and understanding, and give
people the tools they need to move forward through a difficult time. When you speak to where
people actually are in the transition process rather than telling them that they ought to be
somewhere else, you are bringing people along with you.
If, on the other hand, you deny endings and losses and act as though they did not need to let go
of anything, you are sowing the seeds of mistrust and talking in a way that simply convinces
people that you don't know or care anything about them. That is not your intent, of course. But
that is why "Who is going to lose what?" is such an important question.
For it is by asking that question, that you open the door to the transitions that people will have
to make if the change is to work. It is that question that helps them to let go of the old way, so
that the new way can be established and work.
More than half of "communication" is the result of listening rather than speaking. That is why
three questions are so important in a time of change:
What is changing?
They not only create a climate of listening which reassures people and defuses opposition. They
also generate information that you may not, yourself, know yet. And, hey, you're in transition
too.
23
Version 11.0 September 2013
People cannot adopt the new way of doing things until they have released the old ways. Those
planning organizational changes need to also plan to assist their staff in accepting what has
ended.
The first step to restoring any morale and productivity losses is to accept what specific things
have ended and need to be grieved and then given up. It is usually not sufficient to only
emphasis the positive gains within the change. A quicker transition to productivity can be made
if the leadership team insures that everyone goes through a process of identifying and dealing
with losses.
Behavior that signals that people are grieving for real and perceived losses:
Anger Sadness
Bargaining Disorientation
Anxiety Depression
Identify what was good and is now lost in the new order of things. Organizations lose such
things as:
• Structure – a way that the organization functioned that was clearly understood
• Meaning – commonly understood values and interpretation of outcomes
• Vision/Mission/Values – the old comfortable vision may have shifted…even a small shift
will be perceived as a loss
Publicly acknowledge and honor these losses – don’t try to hide them or gloss over them.
• Talk about what was good about the “old” way before talking about the new…do not
make the old way totally wrong
• Talk or get people to talk about what is being lost and what that feels like to them
• In these initial meetings hold the future vision and plan out there, but allow a set period
of time (e.g. a month) to mainly focus on endings.
For difficult losses create ways of marking the endings. Acknowledging and marking endings is
the first step in moving beyond strongly felt losses and starting the journey towards a new
beginning.
If people are losing their position, provide outplacement assistance and keep those remaining
apprised and celebrate when the person finds a new position so people don’t feel like the
person has “disappeared”…a fate which they may share someday.
24
Version 11.0 September 2013
When a company or part of a company loses a highly regarded manager, hold a good- bye event
and allow people to say goodbye and put forward their good wishes. If at all possible have the
manager who is leaving introduce the new manager…even if he/she needs to come back to do
so. This lends legitimacy to the new manager and provides continuity in the transition.
Case Example:
When one organization was forced to lay off employees, they set up a special area for
outplacement training and services. The company kept a special bulletin board with pictures
in the cafeteria to let people know when someone had landed on their feet. People
understood the business reasons for the lay-off but felt that people were being humanely
treated, which kept the morale from plummeting.
Train all staff members to identify and acknowledge what they personally will be losing due to
the changes. People lose such things as:
Recognize the broad range of things that people can perceive of as losses
Create safe formats for them to express and grieve for what they’re losing. For example:
• Hold small focus groups to listen to peoples concerns without judgment. At the end of
the session, let people begin to image what the new way will be like.
• Set aside several hours a week for appointments just to address peoples concerns and
questions about the change. Keep them to 15 minutes (face-to-face or on the phone),
• Set aside a section of the team meeting for the team to surface questions, issues or
concerns…seed these discussions with your own issues and what you are doing about
them.
Assist them in creating a formal ending for these losses. The formal ending marks a place in time
where people can begin to move toward their new beginnings.
25
Version 11.0 September 2013
• If people are moving into new positions, hold a luncheon to honor them for their past
service.
• Hold a funeral. This works particularly well when it is an old “system” that is changing.
Have people write down the thing they liked the most about the old system and fold it
up adding it to a “coffin” which can later be disposed of in a way the group sees fit. It is
good to do this close to the go-live of a new system.
People don’t recover immediately from their real and perceived losses. It is common for them to
enter a chaotic middle ground called the neutral zone. This period can be identified by people
alternately focusing on moving forward into the new beginnings and then returning to worrying,
grieving or complaining about what has been lost. This vacillating is normal behavior for people
transitioning through a change with strong perceived losses.
There are a few key things that leaders and managers can do to shorten unproductive time in
the neutral zone. Allow people a space and time for erratic neutral zone behavior.
Resist saying:
• “Get over it and get back to work!” Something more like, “I know this change is hard to
adjust to, what things in particular are causing problems for you?”
• “If you can just hang on a little longer, I think you will feel better about some of these
changes as we work out the kinks.”
• “I think what you are doing to cope with this change is creative, would you mind sharing
that at our next team meeting?”
• The CMO can help design and facilitate change related meetings, retreats and
brainstorming or problem-solving workshops to design and improve things.
• Use the CMO to provide training in creative problem solving techniques.
• Encourage experimentation.
• Don’t block people’s creativity by making the temporary systems too rigid.
26
Version 11.0 September 2013
It is important to get the sequencing correct with new beginnings. There is a temptation to
begin a change with a “new beginning” celebration or announcement. The “new beginnings”
we are talking about here are not the announcement of the change. The “new beginnings” here
is the recognition that the change has happened and the adjustments required have largely
been successfully made. It acknowledges that the losses associated with the change have been
adjusted to and we are entering a new phase of productivity and focus. Having the new
beginning too early may lengthen the time people spend in the low productivity “neutral zone.”
A good analogy would be the transition someone goes through when change
takes the form of losing a loved one.
• Endings – the memorial service acknowledging the loss
• Neutral zone - a period of grieving
• New beginning – becoming engaged and active again
New beginnings refers to the planned and orchestrated process of moving people away from
endings, out of the chaos of the neutral zone and focusing on the new state of increasing
productivity.
Techniques:
1. Create powerful symbols, stories and analogies for the new identity. For example:
When Jack Welch was trying to transform an old-fashioned manufacturing company into
a more entrepreneurial company, he created the values of “Speed, Simplicity and
Boundarylessness,” and spent a year defining those values and telling stories of people
within the company who exemplified them.
8. Carefully design and sequence each new start.
9. Have an executable plan for each new beginning
10. The timing of each new beginning is critical.
11. Don’t overwhelm employees.
12. Change one thing at a time.
13. Clearly explains the purpose of the changes
14. Give each individual an important part to play.
15. Give people specific information they can act on about the new state of things.
16. Provide people with the knowledge and skills to excel. People often start out associating
the learning of a new skill with a loss of reputation or expertise. Make sure they have
the resources they need to quickly gain competence in the new skill:
17. Have a development plan in place
18. When you tell employees the new things that will be required of them, be able to tell
them when they will be trained and for how
19. Carefully orchestrate and celebrate a continuing series of “wins.” For example, when the
team solves a difficult customer service problem using the new methods or tools:
20. Get communications resources involved to coordinate
27
Version 11.0 September 2013
21. Give people kudos and put the story in a newsletter and on the website with
pictures…be sure it is seen with the organization and within the company.
22. Acknowledge the beginning in meetings
23. Acknowledge the beginning in emails
28
Version 11.0 September 2013
6 Conduct a risk analysis for the change management plan
It is important that the change manager anticipate what can go wrong with the change
management plan and take steps to mitigate those possibilities.
Look at change activities in the context of other major activities competing for attention during
the same time period. Take into account all change readiness data collected previously as well
as the complexity of internal and external work product handoffs and the change history of the
end-users impacted by the change. For a small change this analysis will be short or nonexistent.
However, for larger change efforts, the analysis may surface many potential issues.
Using the risk possibilities list, express all the potential risks to the change effort, with everything
that is known about each issue
Rank each of the risk for impact and probability on a scale of 1 to 5. Multiply those two
numbers together to obtain a “risk severity” rating. Sort the list of risk by order of “severity” to
identify the top risks to which you should pay the most attention.
6.3 Develop mitigation and contingency plans for the top risks
Using the Risk Planning Table, add mitigation and contingency plans that can be adopted if the
risk should occur.
30
Version 11.0 September 2013
7 Execute the Change Management Plan
7.1 Monitor change milestone delivery and key performance indicators
Activities:
31
Version 11.0 September 2013
7.2 Coordinate change project communications
When information is lacking, people invent worse case answers, when coordinating the change
project communications we combat misinformation and reduce the time lost speculating about
the unknown. The rumor mill will spread the misinformation throughout the organization. The
communications portion of the change management plan is of the most important and effective
tools available to reduce lost time and reduce unnecessary anxiety and stress.
Communications activities:
• Select optimal communications channels based upon the purpose, numbers of people
impacted, level of complexity, etc.
• Craft consistent messages for all communication channels.
• Communicate a clear and consistent business case for change, based upon the direction
set by the leadership team.
• Communicate clearly about restructuring, staffing changes, etc.
• Test the effectiveness of the communications by asking random people or groups of
people (usually by attending normally scheduled meetings) what they heard and
understand about the communications.
• Maintain a communications dash board to evaluate the effectiveness of the
communications
32
Version 11.0 September 2013
7.3 Coordinate the execution of organizational design activities
These activities are completed to insure that any changes to the organization’s structure
dictated by the changes will be thoughtfully planned and deployed to minimize work
disruptions.
Activities:
• Coordinate the deployment of facilities and infrastructure requirements caused by the change.
• Coordinate the execution of any staffing requirements change plans.
• Coordinate any staff redeployments, hiring’s or outplacements with impacted management
• Facilitate the deployment of any optimal organizational structures planned
• Coordinate the execution of any strategies to move the organization towards an optimal
and supportive organizational culture planned for areas impacted by the change.
Coordinate with all the people, departments and vendors involved in training the end users to
minimize delays and insure people are prepared to be productive when the change rolls out.
In this step all planned training is deployed. The change and resilience training is supported by
the CMO, while the skills-based training is supported by HR training with the change manager in
a coordination role.
33
Version 11.0 September 2013
8 Ensure Knowledge Management Integrity
8.1 Update all business processes, desktop procedures and job aids
It is required that all projects with new or updated processes be documented by the originating areas to
demonstrate compliance and to make the procedure
available to the client upon demand.
• Desktop procedure
• A system reference document for a
fully automated process
• Or a copy of the applicable form in use
for notices handled by third parties
While the project prioritization project analyst is responsible for monitoring their assigned
projects from start through completion, the project closing analyst is responsible for managing
projects while they are in the desktop procedure collection and review stage.
• Referring projects to operational risk analyst and internal controls for review
• Review business case and KPIs for the project to actual measurements for the project.
• Analyze post-project KPI performance against goals by comparing actual amounts to
estimate and any
• Make recommendations to close any gaps
8.3.1 Analyze business KPI performance and ROI when projects are finished
Transformation projects are approved based on the potential for a substantial ROI. In the
weeks and months following the project the KPIs are tracked to establish a new baseline of
performance and confirm the realization of the expected ROI.
“Ideal state” business process flowcharts and performance KPIs are created and maintained
to function as a business model against which future transformation opportunities can be
measured.
The market place environment and businesses do not remain static. Once an improvement
has been realized the search begins again for opportunities to perform better.
Following business transformation analysis a proposal is made to initiate a project to secure the
potential gains and savings that have been identified. Project proposals are made for high return
of investment (ROI) process transformation opportunities.
35
Version 11.0 September 2013
Once a project is proposed and accepted a detailed project plan is created. A project manager,
business analysts and a change manager are assigned to create and execute the transformation
plan.
Use the retrospective review to capture the key change milestones and KPIs of from the completed
change project in preparation for the retrospective review meetings.
The change manager will compile statistics about the project, including the projected baseline vs. actual
for the following items:
36
Version 11.0 September 2013
This document should also contain the following information, for comparison and sharing purposes with
future projects:
• Scope changes for the change management project that occurred during the project
• Risks to change management that manifested and those that didn’t
• Risk mitigation measures for change management that were effective and those that were not
• Estimates of major change management tasks that were correct and those that varied widely
from actual time spent.
9.2 Conduct a change management retrospective
Who: The project manager is accountable for calling the meeting to review successes and lessons
learned. All full-time and part-time members should be invited, as well as major stakeholders. It is often
outsiders who are best able to see objectively what has occurred.
Goals:
• Recognize processes that worked, so that they
can be repeated in future projects.
• Learn from mistakes and publish these
learnings to avoid repetition on future projects.
• Prepare and distribute retrospective review
document
Consider using a third-party facilitator to conduct the
meeting. Change management performance issues are
to be discussed and a consensus reached, if possible. If
a consensus cannot be reached, the differing opinions
should be documented.
Figure 29 Retrospective Meeting Agenda
See
37
Version 11.0 September 2013
Appendix O - Retrospective Review Meeting Agenda.”
The tables from this form could be drawn on a white board or projected on a screen to help facilitate
the retrospective discussion.
Evaluate the following areas for what was effective; what could be done differently next time and
process or Communications issue:
• Change planning
• Change Scheduling
• Change resource availability
• Change communications
• Change risk assessment
• Change Risk management
• Change scope control
• Other change control
• Change Issues resolution
• Change documentation
• Change approach
• Change management related decision making
9.4 Rate the effectiveness of the transition management efforts with the
stakeholders
38
Version 11.0 September 2013
Figure 30 Transition Management Effectiveness Rating Sheet
Integrate any changes based upon lessons learned into the change process and update desk top
procedures.
Email retrospective meeting minutes and a list of subsequent changes to key stakeholders.
39
Version 11.0 September 2013
Tools, Templates and Reference Materials
Beer, Michael and Nohria, Nitin, Cracking the Code of Change, Harvard Business Review 133 (May June
2000)
Bridges, William, Managing Transitions: Making the Most of Change (2nd Edition), Da Capo Press. 2003
Collins, James, Turning Goals into Results: the Power of Catalytic Mechanisms, Harvard Business Review
71, at 82 (July August 1999) (quoting from Walden)
Duarte, Deborah and Snyder, Nancy, Mastering Virtual Teams, Jossey-Bass, Inc., 2000.
Goleman, Daniel, Leadership That Gets Results, Harvard Business Review 78, at 82 (March-April 2000)
Henry, Jane and Hartzler, Meg, Tools for Virtual Teams, ASQ Quality Press, 1998.
Jude-York, Deborah, Davis, Lauren, Wise, Susan, Virtual Teaming: Breaking the Boundaries of Time and
Place, Crisp Publications, 2000.
Kimball, Lisa, Noble, Stu and Kennedy, Jon, Virtual Team Tool Kit, Group Jazz Publishing, 2002.
Lipnack, Jessica and Stamps, Jeffrey, Virtual Teams: Reaching Across Space, Time and Organizations with
Technology, John Wiley & Sons, 1997.
40
Version 11.0 September 2013
Appendix B – Change Impact Questionnaire Example
The Change Impact Questionnaire Example
Please select your organization (Insert actual unit names)
Org Unit 1 Org Unit 2 Org Unit 3 Org Unit 4 Org Unit 5
80%+
Med
Zero
Zero
20%
50%
1 Working Relationships
Lo
Hi
1.1 Tasks shifting to a new person, role or location
41
Version 11.0 September 2013
4 Work Environment
42
Version 11.0 September 2013
Appendix C - Change Readiness Assessment
Introduction
The goal of this change management assessment is to help us prepare for the coming changes in the
most thoughtful way possible and with the least impact on productivity and effectiveness. This will be
accomplished by:
• Giving individuals’ knowledge, skills and information that will allow them to manage their own
transitions through change.
• Giving managers the understanding of tools, techniques and processes that will keep
productivity and moral high during the changes associated with the acquisition.
• Building a communication program that gives people a map to the goals and progress reports
along to help people focus on creating a compelling future together.
• Engaging people early as contributors to the process of change.
• Building the capacity for on-going change.
Anonymity
Personal identities will be at all times protected. Every effort will be made to insure that while results
will be communicated throughout the organization there will be no way to link results to a particular
individual. Results will be grouped by large enough sections of the organization that anonymity will be
preserved.
43
Version 11.0 September 2013
Change Readiness Assessment
Please select your organization (Insert actual unit names)
Org Unit 1 Org Unit 2 Org Unit 3 Org Unit 4 Org Unit 5
1.2 Given the situation, this change represents the best way forward
The organization's top leaders have shown that they are committed
1.3 to the change.
1.4 Middle managers are committed to the change
1.5 Supervisors and front-line managers are committed to the change
I am more committed to my work since the change has been
1.6 announced.
Strongly Disagree Strongly Agree
2 My capacity to manage change
2.1 I have significant reserve capacity to handle more change.
2.2 I know how to easily let stress go when I have to.
2.3 Excited about my future role in the new organization.
2.4 I have great outlets and support when things are chaotic or confusing.
2.5 My work environment is very productive.
2.6 Comfortable continuing my employment here into the foreseeable
future.
2.7
I am handling all the changes in the organization well.
2.8
Minimal personal impact associated with this change.
2.9
There are safe outlets for expressing frustrations and/or anger.
44
Version 11.0 September 2013
Strongly Disagree Strongly Agree
4 The organization’s capacity to manage change
4.1
The organization has a history of handling change pretty well.
4.2
We have the capacity to successfully execute this magnitude and
scope of change.
4.3
As an organization, we have a clear track record of learning from
previous change experiences.
4.4
We have a successful track record helping people negotiate change.
The organization makes allowances for productivity dips during
4.5
times of change.
4.6 We have an effective way of dealing with rumors.
4.7
I am an important part of this organization.
I can actively participate in identifying things that need to change in
4.8
order to reach our goals.
4.9
Good support is provided when taking on new roles or tasks.
4.10
It is safe to take an "intelligent" risk in this organization.
The organization resolves things on a timely basis and doesn’t let
4.11
them become long-term issues
We are encouraged to speak candidly about the organization's
4.12
problems.
Strongly Disagree Strongly Agree
5 Leadership's capacity to manage change
5.1 Our leader's have a history of acting on their commitments.
5.2 Decisions are generally made in a timely fashion.
5.3 I understand why certain decisions were made.
5.4
Leadership generally shows an awareness and concern for how
change will affect the rest of us.
45
Version 11.0 September 2013
Strongly Disagree Strongly Agree
6 Communication Practices
In the past, important information was well communicated (i.e.
6.1
accurate and timely).
6.2
There are effective ways for employees to voice their concerns and
questions about the change.
Don’t Prefer Strongly Prefer
The way I prefer to get information about things that will
7 affect my work life
7.1 Face-to-face interaction with my direct supervisor
7.2 Personal e-mail announcing the changes.
7.3 General announcement by e-mail from Corporate Executive.
7.4 Group or town hall meetings.
7.5 Newsletter or corporate web-site.
8.2 Personal e-mail announcing the changes.
8.3 General announcement by e-mail from Corporate Executive.
8.4 Group or town hall meetings.
8.5 Newsletter or corporate web-site.
Don’t Prefer Strongly Prefer
The way I prefer to get information that effect day to day
9 issues
9.1 Face-to-face interaction with my direct supervisor
46
Version 11.0 September 2013
47
Version 11.0 September 2013
Appendix D – Simple Individual Change Resilience Assessment
I see difficulties as temporary and expect to overcome them.
Never
Rarely
Sometimes
Almost always
Always
Never
Rarely
Sometimes
Almost always
Always
Never
Rarely
Sometimes
Almost always
Always
Never
Rarely
Sometimes
Almost always
Always
Never
Rarely
Sometimes
Almost always
Always
48
Version 11.0 September 2013
Never
Rarely
Sometimes
Almost always
Always
Never
Rarely
Sometimes
Almost always
Always
49
Version 11.0 September 2013
Appendix E - The Professional Life Stress Test
The following stress scale must be treated as a useful guide rather than as a precise instrument.
Compete it quickly, and don't think too hard before responding to each question. Your first
response is often the most accurate one. As with any stress scale, it isn't difficult to spot what is
the 'low stress' answer to each question. Don't be tempted to give this answer if it isn't the
accurate one. Nothing is at stake. You are as stressed as you are. Your score on the scale doesn't
change that, one way or the other. The purpose of the scale is simply to help you clarify some of
your thinking about your own life.
1. Two people who know you well are discussing you. Which of the following statements
would they be most likely to use?
a. 'X is very together. Nothing much seems to bother him/her.'
b. 'X is great. But you have to be careful what you say to him/her at times.'
c. 'Something always seems to be going wrong with X's life.'
d. 'I find X very moody and unpredictable.'
e. 'The less I see of X the better!'
2. Are any of the following common features of your life?
a. Feeling you can seldom do anything right
b. Feelings of being hounded, trapped, or cornered
c. Indigestion
d. Poor appetite
e. Difficulty in getting to sleep at night
f. Dizzy spells or palpitations
g. Sweating without exertion or high air temperature
h. Panic feelings when in crowds or in confined spaces
i. Tiredness and lack of energy
j. Feelings of hopelessness ('what's the use of anything?')
k. Faintness or nausea sensations without any physical cause
l. Extreme irritation over small things
m. Inability to unwind in the evenings
n. Waking regularly at night or early in the mornings
o. Difficulty in making decisions
p. Inability to stop thinking about problems or the day's events
q. Tearfulness
r. Convictions that you just can't cope
s. Lack of enthusiasm even for cherished interests
t. Reluctance to meet new people and attempt new experiences
u. Inability to say 'no' when asked to do something
v. Having more responsibility than you can handle
50
Version 11.0 September 2013
3. Are you more or less optimistic than you used to be (or about the same)?
a. more
b. about the same
c. less
4. Do you enjoy watching sports?
a. yes
b. no
5. Can you get up late on weekends if you want to without feeling guilty?
a. yes
b. no
6. Within reasonable professional and personal limits, can you speak your mind to your
boss?
a. yes
b. no
7. Can you speak your mind to your colleagues?
a. yes
b. no
8. Can you speak your mind to members of your family?
a. yes
b. no
9. Who usually seems to be responsible for making the important decisions in your life?
a. yourself
b. someone else
10. When criticized by superiors at work, are you usually:
a. Very upset?
b. Moderately upset?
c. Mildly upset?
11. Do you finish the working day feeling satisfied with what you have achieved?
a. often
b. sometimes
c. only occasionally
12. Do you feel most of the time that you have unsettled conflicts with colleagues?
a. yes
b. no
13. Does the amount of work you have to do exceed the amount of time available?
a. habitually
b. sometimes
c. only very occasionally
14. Do you have a clear picture of what is expected of you professionally?
a. mostly
b. sometimes
c. hardly ever
15. Would you say that generally you have enough time to spend on yourself?
a. yes
b. no
16. If you want to discuss your problems with someone, can you usually find a sympathetic
ear?
51
Version 11.0 September 2013
a. yes
b. no
17. Are you reasonably on course towards achieving your major objectives in life?
a. yes
b. no
18. Are you bored at work?
a. often
b. sometimes
c. very rarely
19. Do you look forward to going into work?
a. most days
b. some days
c. hardly ever
20. Do you feel adequately valued for your abilities and commitment at work?
a. yes
b. no
21. Do you feel adequately rewarded in terms of status and promotion for your abilities and
commitment at work?
a. yes
b. no
22. Do you feel your superiors actively hinder you in your work? Or do they actively help you
in your work?
a. hinder
b. help
23. If ten years ago you had been able to see yourself professionally as you are now, how
would you have seen yourself?
a. exceeding your expectations
b. fulfilling your expectations
c. falling short of your expectations
24. If you had to rate how much you like yourself on a scale from 1 (least like) to 5 (most
like), what would your rating be?
a. 1
b. 2
c. 3
d. 4
e. 5
52
Version 11.0 September 2013
5. Score 0 for a. 'yes', 1 for b. 'no'
6. Score 0 for a. 'yes', 1 for b. 'no'
7. Score 0 for a. 'yes', 1 for b. 'no'
8. Score 0 for a. 'yes', 1 for b. 'no'
9. Score 0 for a. 'yourself', 1 for b. 'someone else'
10. Score 2 for a. 'very upset', 1 for b. 'moderately upset', 0 for c. 'mildly upset'
11. Score 0 for a. 'often', 1 for b. 'sometimes', 2 for c. 'only occasionally'
12. Score 0 for a. 'no', 1 for b. 'yes'
13. Score 2 for a. 'habitually', 1 for b. 'sometimes', 0 for c. 'only very occasionally'
14. Score 0 for a. 'mostly', 1 for b. 'sometimes', 2 for c. 'hardly ever'
15. Score 0 for a. 'yes', 1 for b. 'no'
16. Score 0 for a. 'yes', 1 for b. 'no'
17. Score 0 for a. 'yes', 1 for b. 'no'
18. Score 2 for a. 'often', 1 for b. 'sometimes', 0 for c. 'very rarely'
19. Score 0 for a. 'most days', 1 for b. 'some days', 2 for c. 'hardly ever'
20. Score 0 for a. 'yes', 1 for b. 'no'
21. Score 0 for a. 'yes', 1 for b. 'no'
22. Score 1 for a. 'hinder', 0 for b. 'help'
23. Score 0 for a. 'exceeding your expectations', 1 for b. 'fulfilling your expectations', 2 for c.
'falling short of your expectations'
24. Score 4 for a. '1', 3 for b. '2', 2 for c. '3', 1 for d. '4', and 0 for e. '5'
Keep in mind that scores on stress scales must be interpreted cautiously. There are so many
variables which lie outside the scope of these scales but which influence the way in which we
perceive and handle our stress, that two people with the same scores may experience themselves
as under quite different levels of stress. Nevertheless, taken as no more than a guide, these scales
can give us some useful information.
Score = 15. Stress isn't a problem in your life. This doesn't mean that you have insufficient stress
to keep yourself occupied and fulfilled. The scale is only designed to assess undesirable
responses to stress.
Score = 16-30. This is a moderate range of stress for a busy professional person. It's nevertheless
well worth looking at how it can reasonably be reduced.
Score = 31-45. Stress is clearly a problem, and the need for remedial action is apparent. The
longer you work under this level of stress, the harder it often is to do something about it. There
is a strong case for looking carefully at your professional life.
Score = 45-60. At these levels, stress is a major problem, and something must be done without
delay. You may be nearing the stage of exhaustion in the general adaptability syndrome. The
pressure must be eased
53
Version 11.0 September 2013
Appendix F - Transition Management Planning Checklist
Once the magnitude of the changes is known it is possible to begin planning for people’s transitions
through endings, through the neutral zone and into new beginnings.
This checklist is designed for teams as a reminder of the basic techniques available to them to manage
transitions. The greater the magnitude of the change, the more necessary it will be to use a higher
percentage of these techniques. The largest change projects will use almost all the techniques in the
checklist.
1 Marking Endings
1.1 Acknowledge and honor what has truly ended
1.2 Acknowledge personal endings as well as organizational endings
1.3 Allow people to take as much of the past with them as practical
1.4 Where needed create ceremonies and events to mark and honor endings
2 During the Neutral Zone
2.1 Provide safe outlets for frustrations, anger and rumors
2.2 Create scaffolding structures to temporarily stabilize critical areas
2.3 Involve people in identifying and improving processes and procedures
3 Creating New Beginnings
Ensure that the scope of change does not exceed the capacity of the organization to
3.1
successfully execute
Provide deployment plans with sufficient details to identify all substantive work
3.2
including dates and responsibilities
3.3 Insure that staff are participants not spectators or victims of the changes
4 Communications
4.1 Create a proactive communications plan. Don’t leave communications to chance
4.2 Make communications two-way – involve staff and customers
54
Version 11.0 September 2013
Appendix G -Change sponsor and Champion Planning Checklist
3 Sponsor/champion training
4 Retrospective
Schedule a time to go over what worked and what should be improved specific to the
4.1
role of sponsor/champion
4.2 Communicate lessons learned and improvement actions that will be taken
55
Version 11.0 September 2013
Appendix H - Planning Major Change Announcements Template
The Headline (The essential message: Crisp, clear, and well crafted):
Attitudes that could be modeled How it can be modeled Who will model Where and when
Virtual team skills that could be How it can be modeled Who will model Where and when
modeled
Demonstrations of compassion, How it can be modeled Who will model Where and when
justice, respect, excellence and
stewardship
56
Version 11.0 September 2013
Appendix I– Ongoing or Periodic Communications Planning Checklist
1.1 Agree on what you want people to know and or do as a result of the communication
1.2 Be sure content is provided and checked by the appropriate person or people
1.3 Check for “unintended messages”
1.4 Select the appropriate person to send the message
57
Version 11.0 September 2013
Appendix J - Planning Outbound Communications Template
Target Communications
Message Content Frequency Feedback Methods
Audience Channel
Recipient
Group 1
Recipient
Group 2
Recipient
Group 3
Recipient
Group 4
Recipient
Group 5
Version Date
Revision Author Summary of Major Changes Made
Number Updated
1.0 <Date> <Author> Initial document created.
<Next
<Date> <Author> <Description of major changes>
number>
58
Version 11.0 September 2013
Appendix K- Feedback Planning Checklist
Often you will want feedback from key stakeholders to validate what they are hearing and
understanding. This checklist helps you determine the feedback that you want.
1.3 Consider whether you want or can expect different information from different
populations
1.4 Give people multiple ways to contribute their information (e.g. face-to-face, mail-in,
email)
2 The Right Venue and Frequency
2.1 Use multiple channels for (e.g. email, team meetings, district meetings)
2.2 Do not confuse frequency with effectiveness of communication when using email
2.3 Send a reminder two days before information is due
4.1 Make compiled data available in a common space, asking for validation and feedback
In common space, solicit discussion to surface questions and help make meaning of
data
59
Version 11.0 September 2013
Appendix L - Engaging and Involving Staff during Transition
“Most change efforts fail not because of flawed strategy, but because they fail to reach out broadly
enough—and deeply enough—to frontline employees.”
Principle 1: Look for leadership from lower levels of your company instead of issuing all directives from
the executive suite.
Principle 2: Overhaul the way you communicate with frontline employees, who are your company’s
most important agents of change.
Principle 3: Make sure that your change initiative addresses the often hidden psychological and social
issues that define the unwritten rules workers have with their employers.
It is well understood that there are large benefits for organizations that drive participation in decision-
making as close to the frontlines as possible.
Factors to consider when determining who should be involved in an improvement or problem solving
effort:
60
Version 11.0 September 2013
Major improvement initiatives are larger in scope, take longer and are more
radical in nature. For such initiatives a rigorous methodology is required such as
Business Process Improvement (BPI).
Major improvement priorities are set by management
Make a decision is made as to whether this is an opportunity to involve staff in
creating solutions
Pick an improvement process that matches the scope and nature of the change
initiative
Enlist the help of an appropriate mix and number of managers, staff, customer
and experts
Execute by following the procedures of the selected process (Work-Out, CAP or
Service Design)
Celebrate both achievements and lessons learned
61
Version 11.0 September 2013
Appendix M – Planning Major Change Announcements
Often what starts as a simple message ends up being misinterpreted and triggers unexpected
reactions…
What various employees “hear”: “They are replacing the old manager because she was
too lenient with us. Or…I heard that this manager has been hired to reduce head count”
Limit rumors by giving people complete and accurate information; communicate through the most
effective channel; provide people with a way to give feedback and get more information.
Process:
• Carefully craft a “headline” for clarity. It is the essential message: Crisp, clear,
and well crafted
• Determine the best method, time and place to disseminate the message
• Assemble detailed information that people may find helpful
Plan in advance how you will:
• Gather feedback and validate what people heard
• Clear up any misconceptions and address unanswered questions
• Manage people’s transitions to the new reality
• Communicate the headline
• Simultaneously distribute or make available the detailed information.
At the same time, tell people where and how they can:
• Give feedback.
• Participate in a dialogue to clarify the message and its implications.
62
Version 11.0 September 2013
Validating what people heard
The validation can be very brief or somewhat extended depending on the complexity and severity of
impact. The purpose of validation is to expose unintended conclusions being derived from the message.
• Create a safe and open forum for people to state their understanding of the
message
• Don’t delay. Discover rumors and misconceptions quickly
• Answer all questions. Both the question and answers should be disseminated to
everyone
• Promptly clarify any misunderstandings
Clarification can be the most important step in communications. In the clarification phase the manager
should:
• Be genuine, listen more than talk
• Be empathetic of impacts on a person’s professional or personal life
• Give space for expressions of doubt, anger, or sadness
Before executing any communication, as the manger you should ask yourself a series of questions:
• What do I expect people to do differently as a result of this communication? Are
there new behaviors expected? Are there new procedures to be followed?
• What attitudes would be desirable in the light of this communication?
• Is this a time to use a desirable virtual team skill like, empathetic listening,
creativity, group problem solving, etc.
• How could we express compassion, justice, respect, excellence and stewardship?
o Invent a way to model the behavior you want to see in others.
o Publicly demonstrate the desired attitude or behavior.
“You must be the change you wish to see in the world” Ghandi
63
Version 11.0 September 2013
Appendix N - Ensure Knowledge Management Integrity
Update all business processes, desktop procedures and job aids
All projects require that any new or updated processes in use by the organization are documented by
the originating areas to demonstrate compliance when
applicable and ultimately to make the procedure available
on demand for the client. The documentation is
primarily in the form of a desktop procedure,
but may also be in the form of a system
reference document for a fully automated
process or a copy of the applicable form in use
for notices handled by third parties. All
documentation for projects must be approved
by a direct report of the VP of Mortgage
Servicing for that respective business area
before submitting it to Project Closing Analyst
for review
Procedure for Managing Projects in the Desktop Procedure Collection and Review Stage
While the Project Prioritization Project Analyst is responsible for monitoring their assigned projects from
start through completion, the Project Closing Analyst is responsible for managing projects while they are
in the Desktop Procedure Collection and Review Stage by following the process below:
1. Review project summary, legislative compliance, action items and other additional
information available to gain an understanding of the purpose and the requirements of
the project.
2. Review action items opened in the Change Management database to determine which
business areas are required to submit documentation.
3. Monitor action items for appropriate updates and comments regarding delays in
completing the documentation.
4. Once documentation is received from the business liaisons via email, review for the
following:
5. Is it clear why the desktop procedure is necessary?
64
Version 11.0 September 2013
6. Is it clear what is being done by the department?
7. Is it clear when the task needs to be completed?
8. Is it clear who is involved in the process?
9. Are there reports that are part of the process and is it clear who generates them and
how they are used?
10. Is it clear when the procedure was created, changed or certified?
11. Is it clear who performs each part of the process?
12. If the procedures meet the above guidelines, review to ensure that the procedure
clearly demonstrates compliance with the requirements and objective of the project.
13. If any of the above is missing or unclear, the procedures with documented questions or
comments are sent back to the liaison for updates. An additional action item will be
assigned in the database to update the procedures with the additional information
needed and a new target due date will be set. General guidelines for establishing target
due dates for the turnaround of updated procedures is less than one week, however
this may vary.
14. Once updated documentation from the business liaison is received, they are reviewed
again to ensure that the requested changes are appropriately captured. Steps 2 through
7 may be repeated as many times as necessary to capture all required documentation.
65
Version 11.0 September 2013
Appendix O - Retrospective Review Meeting Agenda
Project Summary
Retrospective review meeting attendees
Project manager
Original target completion date
Actual completion date
Original budget
Actual budget
Targeted KPI measures May refer to a separate document.
Actual KPI results May refer to a separate document.
66
Version 11.0 September 2013
Change Management Process or
What we would do
What we did well Communications
Element differently next time
issue (P/C)
Change planning
Change Scheduling
Change Resource
availability
Change Communications
Change documentation
Change approach
Other issues addressed during the meeting with stakeholders & the change team
67
Version 11.0 September 2013
Appendix P - Transition Management Effectiveness Rating Sheet
This document has been designed to help determine how well transitions are being planned and
managed. It can be used:
Marking Endings 1 2 3 4 5
1
1.1 What has truly ended is acknowledge and honored 1 2 3 4 5
2.1 There are safe outlets for frustrations, anger and rumors 1 2 3 4 5
During times of change critical areas are temporarily stabilized to
1 2 3 4 5
2.2 minimize disruptions
Everyone is involved in identifying and improving processes and
1 2 3 4 5
2.3 procedures
4 Communications
During changes a communications plan is created to avoid leaving
1 2 3 4 5
4.1 communications to chance
68
Version 11.0 September 2013
Index
69
Version 11.0 September 2013
ROI, 25 Transition Management Planning Checklist, 53
Skills / Competencies, 33 transition through the change, 14
Skills Inventory, 16 Transitions, three stages, 14
skills training, 16 Validating, message effectiveness, 62
Staff, engaging and involving, 15, 59 value realization, 1
Survey, change readiness, 35 WBS, 13
Survey, change readiness of the organization, WBS matrix, 8, 9, 11
35 William Bridges’ Managing Transitions, 39
Surveys, 8 Work Content, 33
temporary support structures, 18 Work Environment, 34
The Neutral Zone, transition management, 44 Working Relationships, 33
training, change sponsors and champions, 15 Worries surrounding the change, assessment,
training, coordination, 23 36
Transition Management Effectiveness, rating
sheet, 30, 67
70
Version 11.0 September 2013