DP/IRL/CMS/1
LIQUID PENETRANT DATE 8-Aug-18
L&T DEFENCE EXAMINATION REPORT
PAGE No. 1
Project No. : 60541A Vendor Name : SCHLIM ENGINEERS
Part / Description : CHANNEL & GUSSETS Vendor P.O. No. : 06L011643
Part No. : 1&2 Quantity as per P.O. : 6 NOS
Drawing No. : DE-4541-1 Rev. :R 1 Code / Spec. : ASME SECTION Vlll DIV 1 APP 8
Overall final Visual Inspection carried out prior to LPT and found Satisfactory Yes No
Cleaner Batch No, Make & Expiry date 6748 , SEP 2019 (PRADEEP MAKE)
Penetrant Batch No, Make & Expiry date 6579 , MAR 2019 (PRADEEP MAKE)
Developer Batch No, Make & Expiry date 6457, SEP 2018 (PRADEEP MAKE)
Material Type & Thk. IS 2062 GR A & GR B. 10mmTHK & 6mm THK
Ground As Welded
Surface Condition
Machined Bend section
Observation :-
No recordable, relevant indications were observed. PT acceptable in
accordance with the procedure.
NOTES :-
Place of Test :- SCHLIM ENGINEERS, RABALE
Performed by Witnessed by Witnessed / Reviewed by
Examination Stage : AFTER WELDING (ROOT DP) Procedure No. : HE/NDE/LPE/001 Rev.:0
Overall final Visual Inspection carried out prior to LPT and found Satisfactory Yes No
Cleaner Batch No, Make & Expiry date 6748 , SEP 2019 (PRADEEP MAKE)
Penetrant Batch No, Make & Expiry date 6579 , MAR 2019 (PRADEEP MAKE)
Developer Batch No, Make & Expiry date 6457, SEP 2018 (PRADEEP MAKE)
Material Type & Thk. CHANNEL. 6 mm THK
Ground As Welded
Surface Condition
Machined Bend section
Observation :-
No recordable, relevant indications were observed. PT acceptable in
accordance with the procedure.
NOTES :-
Place of Test :- SCHLIM ENGINEERS, RABALE
Performed by Witnessed by Witnessed / Reviewed by
Overall final Visual Inspection carried out prior to LPT and found Satisfactory Yes No
Cleaner Batch No, Make & Expiry date 6748 , SEP 2019 (PRADEEP MAKE)
Penetrant Batch No, Make & Expiry date 6579 , MAR 2019 (PRADEEP MAKE)
Developer Batch No, Make & Expiry date 6457, SEP 2018 (PRADEEP MAKE)
Material Type & Thk. IS 2062 GR A & GR B. 10mmTHK & 6mm THK
Ground As Welded
Surface Condition
Machined Bend section
Observation :-
No recordable, relevant indications were observed. PT acceptable in
accordance with the procedure.
NOTES :-
Place of Test :- SCHLIM ENGINEERS, RABALE
Performed by Witnessed by Witnessed / Reviewed by
Examination Stage : AFTER WELDING (ROOT DP) Procedure No. : HE/NDE/LPE/001 Rev.:0
Overall final Visual Inspection carried out prior to LPT and found Satisfactory Yes No
Cleaner Batch No, Make & Expiry date 6748 , SEP 2019 (PRADEEP MAKE)
Penetrant Batch No, Make & Expiry date 6579 , MAR 2019 (PRADEEP MAKE)
Developer Batch No, Make & Expiry date 6457, SEP 2018 (PRADEEP MAKE)
Material Type & Thk. CHANNEL. 6 mm THK
Ground As Welded
Surface Condition
Machined Bend section
Observation :-
No recordable, relevant indications were observed. PT acceptable in
accordance with the procedure.
NOTES :-
Place of Test :- SCHLIM ENGINEERS, RABALE
Performed by Witnessed by Witnessed / Reviewed by
Overall final Visual Inspection carried out prior to LPT and found Satisfactory Yes No
Cleaner Batch No, Make & Expiry date 6748 , SEP 2019 (PRADEEP MAKE)
Penetrant Batch No, Make & Expiry date 6579 , MAR 2019 (PRADEEP MAKE)
Developer Batch No, Make & Expiry date 6457, SEP 2018 (PRADEEP MAKE)
Material Type & Thk. IS 2062 GR A & GR B. 10mmTHK & 6mm THK
Ground As Welded
Surface Condition
Machined Bend section
Observation :-
No recordable, relevant indications were observed. PT acceptable in
accordance with the procedure.
NOTES :-
Place of Test :- SCHLIM ENGINEERS, RABALE
Performed by Witnessed by Witnessed / Reviewed by
Examination Stage : AFTER WELDING (ROOT DP) Procedure No. : HE/NDE/LPE/001 Rev.:0
Overall final Visual Inspection carried out prior to LPT and found Satisfactory Yes No
Cleaner Batch No, Make & Expiry date 6748 , SEP 2019 (PRADEEP MAKE)
Penetrant Batch No, Make & Expiry date 6579 , MAR 2019 (PRADEEP MAKE)
Developer Batch No, Make & Expiry date 6457, SEP 2018 (PRADEEP MAKE)
Material Type & Thk. CHANNEL. 6 mm THK
Ground As Welded
Surface Condition
Machined Bend section
Observation :-
No recordable, relevant indications were observed. PT acceptable in
accordance with the procedure.
NOTES :-
Place of Test :- SCHLIM ENGINEERS, RABALE
Performed by Witnessed by Witnessed / Reviewed by