1.1 Overview
1.1 Overview
1 Overview
The first pipeline was built in the United States in 1859 to transport crude oil (Wolbert,
1952). Through the one-and-a-half century of pipeline operating practice, the petroleum
industry has proven that pipelines are by far the most economical means of large scale
overland transportation for crude oil, natural gas, and their products, clearly superior to
rail and truck transportation over competing routes, given large quantities to be moved on
a regular basis. Transporting petroleum fluids with pipelines is a continuous and reliable
operation. Pipelines have demonstrated an ability to adapt to a wide variety of environments
including remote areas and hostile environments. Because of their superior flexibility
to the alternatives, with very minor exceptions, largely due to local peculiarities, most
refineries are served by one or more pipelines.
Man’s inexorable demand for petroleum products intensified the search for oil in the
offshore regions of the world as early as 1897, when the offshore oil exploration and
production started from the Summerland, California (Leffler et al., 2003). The first
offshore pipeline was born in the Summerland, an idyllic-sounding spot just southeast
of Santa Barbara. Since then the offshore pipeline has become the unique means of
efficiently transporting offshore fluids, i.e., oil, gas, and water.
Offshore pipelines can be classified as follows (Figure 1.1):
. Flowlines transporting oil and/or gas from satellite subsea wells to subsea manifolds;
. Flowlines transporting oil and/or gas from subsea manifolds to production facility
platforms;
. Infield flowlines transporting oil and/or gas between production facility platforms;
. Export pipelines transporting oil and/or gas from production facility platforms to shore;
and
. Flowlines transporting water or chemicals from production facility platforms, through
subsea injection manifolds, to injection wellheads.
The further downstream from the subsea wellhead, as more streams commingle, the
larger the diameter of the pipelines. Of course, the pipelines are sized to handle the
expected pressure and fluid flow. To ensure desired flow rate of product, pipeline size varies
significantly from project to project. To contain the pressures, wall thicknesses of the
pipelines range from 3/8 inch to 11⁄2 inch.
1.2 Pipeline Design
Design of offshore pipelines is usually carried out in three stages: conceptual engineering,
preliminary engineering, and detail engineering. During the conceptual engineering stage,
issues of technical feasibility and constraints on the system design and construction
are addressed. Potential difficulties are revealed and non-viable options are eliminated.
Required information for the forthcoming design and construction are identified. The
outcome of the conceptual engineering allows for scheduling of development and a rough
estimate of associated cost. The preliminary engineering defines system concept (pipeline
size and grade), prepares authority applications, and provides design details sufficient to
order pipeline. In the detail engineering phase, the design is completed in sufficient detail
to define the technical input for all procurement and construction tendering. The
materials covered in this book fit mostly into the preliminary engineering.
A complete pipeline design includes pipeline sizing (diameter and wall thickness) and
material grade selection based on analyses of stress, hydrodynamic stability, span, thermal
insulation, corrosion and stability coating, and riser specification. The following data
establish design basis:
Reservoir performance
. Fluid and water compositions
. Fluid PVT properties
. Sand concentration
. Sand particle distribution
. Geotechnical survey data
. Meteorological and oceanographic data
Table 1.1 shows sizes of some pipelines. This table also gives order of magnitude of typical
diameter/wall thickness ratios (D/t). Smaller diameter pipes are often flowlines with high
design pressure leading to D/t between 15 and 20. For deepwater, transmission lines with
D/t of 25 to 30 are more common. Depending upon types, some pipelines are bundled and
others are thermal- or concrete-coated steel pipes to reduce heat loss and increase stability.
Pipeline Installation
Once design is finalized, pipeline is ordered for pipe construction and coating and/or
insulation fabrication. Upon shipping to the site, pipeline can be installed. There are
several methods for pipeline installation including S-lay, J-lay, reel barge, and tow-in
methods. As depicted in Figure 1.2, the S-lay requires a laying barge to have on its
Pipeline Operations
Pipeline operation starts with pipeline testing and commissioning. Operations to be
carried out include flooding, cleaning, gauging, hydrostatic pressure testing, leak testing,
and commissioning procedures. Daily operations include flow assurance and pigging
operations to maintain the pipeline under good conditions.
Flow assurance is defined as an operation that generates a reliable flow of fluids from the
reservoir to the sales point. The operation deals with formation and depositions of gas
hydrates, paraffin, asphaltenes, and scales that can reduce flow efficiency of oil and gas
pipelines. Because of technical challenges involved, this operation requires the combined
efforts of a multidisciplinary team consisting of scientists, engineers, and field personnel.
Technical challenges in the flow assurance operation include prevention and control of
depositions of gas hydrates, paraffin (wax), asphaltenes, and scales in the oil and gas
production systems. Usually one or two of these problems dominate in a given oil/gas
field.
Natural gas hydrate is formed when methane molecules—the primary component of
natural gas—are trapped in a microscopic cage of water molecules under certain pressure
and temperature conditions (Katz and Lee, 1990). As a rough rule of thumb, methane
hydrate will form in a natural gas system if free water is available at a temperature as high
as 408F and a pressure as low as 170 psig. Decreasing temperature and increasing pressure
are favorable for hydrate formation (Guo et al., 1992). Hydrate forming conditions are
predictable with computer programs. Natural gas hydrate can form within gas pipelines as
a solid or semi-solid mass that can slow or completely block gas flow. Clearing hydrateplugged
pipelines is an expensive and time-consuming task that can take as long as several
weeks. There are five methods for preventing hydrate formation (Makogon, 1997):