Refrigeration Piping

Download as pdf or txt
Download as pdf or txt
You are on page 1of 43

Refrigeration Piping & Charging

Residential AirConditioning R-22

Roger D. Holder, CM, MSME

Refrigeration is the process of moving heat from


one location to another by the use of refrigerant
in a closed cycle. The piping and tubing system
must be designed, installed and maintained to
provide proper flow of refrigerant in both liquid
and gaseous states.
2

2
3

Piping & Tubing

Refrigeration Piping

Refrigeration is the process of moving heat from one location to another by the use of
refrigerant in a closed cycle. The piping and tubing system must be designed, installed and
maintained to provide proper flow of refrigerant in both liquid and gaseous states. A
successful refrigeration system depends on a good piping design and an understanding of the
required accessories. The first skill that any refrigeration apprentice mechanic learns is to
make a soldered joint. Running pipe is so common a task that its critical importance in system
performance is often overlooked.

Tubing Inspection & Leak Check

The object of a good visual inspection of system tubing design is to note obvious oil traps.
Also look for long vertical suction lengths without p traps and inadequate OD tubing size If the
system is known to be leaking or if oil is present around mechanical fittings, solder joints,
gaskets or seals, recover the refrigerant and repair the leaks. Pressurize the system with a
residual amount of refrigerant and dry nitrogen using the recommended test pressure on data
plate. Maximum test pressures should be approximately 150 psi for high-pressure AC/R
systems. In chiller applications, controlled hot water or heater blankets will raise pressure
adequately for a leak check, which should never exceed 10 psi for low pressure chillers. After
a thorough inspection with a good leak detector, apply a deep vacuum to 500 microns. A good
triple evacuation, with dry nitrogen and then deep vacuum is the preferred method.

Piping Basic Principles

Refrigeration piping involves extremely complex relationships in the flow of refrigerant and oil.
Fluid flow is the study of the flow of a gas or a liquid, and the inter-relationship of velocity,
pressure, friction, density and the work required to cause the flow. The design of a
refrigeration piping system is a continuous series of compromises. It is desirable to have
3
4

maximum capacity at minimum cost, as well as proper oil return. Since oil must pass through
the compressor cylinders to provide lubrication, a small amount of oil is always circulating
with the refrigerant. Oil and refrigerant vapor, however, do not mix readily, and the oil can be
properly circulated through the system only if the mass velocity of the refrigerant vapor is
great enough to sweep the oil along. To ensure oil circulation adequate velocities of
refrigerant must be maintained in the suction and discharge lines, and in the evaporator.

The design of refrigerant piping systems should:


• Ensure proper refrigerant feed to evaporators.
• Provide practical refrigerant line sizes without excessive pressure drop.
• Prevent excessive amounts of lubricating oil from being trapped in any part of the system.
• Protect the compressor at all times from loss of lubricating oil.
• Prevent liquid refrigerant or oil slugs from entering the compressor during operating and
idle time.
• Maintaining a clean and dry system.

Refrigerant Line Velocities


Economics, pressure drop, noise, and oil entrapment require establishing feasible design
velocities in refrigerant lines.
• Suction line 700 to 4000 fpm
• Discharge line 500 to 3500 fpm
• Condenser drain line 100 fpm or less
• Liquid line 125 to 450 fpm

Higher gas velocities are sometimes found in relatively short suction lines, on comfort air
conditioning or other applications where the operating time is only 2000 to 4000 hours per
year and where low initial cost of the system may be more significant than low operating cost.
In the Industrial refrigeration applications where equipment runs continuously, should be
designed with low refrigerant velocities for most efficient compressor performance and low
equipment operating cost. Care must be taken that the velocities is not to low that oil is taped
in the refrigeration lines.

Liquid line from condenser to receivers should be sized for 100 fpm or less to ensure positive

4
5

gravity flow without incurring backup of liquid flow. Liquid lines from receivers to evaporator
should be sized to maintain velocities below 300 fpm, thus minimizing or preventing liquid
hammer when solenoids or other electrically operated valves are used.

Refrigerant Line Sizing

In sizing refrigerant lines, cost considerations favor keeping line size as small as possible.
However, suction and discharge line pressure drops cause loss of compressor capacity and
increased power use. Excessive liquid line pressure drops can cause the liquid refrigerant to
flash, resulting in faulty expansion valve operation. Refrigeration systems are designed so that
friction pressure losses do not exceed a pressure differential equivalent to a corresponding
change in the saturation boiling temperature. The primary measure for determining pressure
drop is a change in saturation temperature. Pressure drop in refrigerant lines causes a
reduction in system efficiency. Correct sizing must be based on minimizing cost and
maximizing efficiency. Pressure drop calculations are determined as normal pressure loss
associated with a change in saturation temperature of the refrigerant. Typically, the
refrigeration system will be sized for pressure losses of 2ºF or less for each segment of the
discharge, suction, and liquid lines. An HFC refrigerant liquid line is sized for pressure losses
of 1ºF or less.

Discharge lines should be designed to:


• Avoid trapping oil at part-load operation.
• Prevent condensed refrigerant and oil from draining back to the head of the compressor.
• Have carefully selected connections from a common line to multiple compressors.
• Avoid developing excessive noise or vibration from hot-gas pulsation, compressor
vibration, or both.

When sizing discharge lines, considerations similar to those applied to the suction line are
observed. Pressure loss in discharge lines increases the required compressor power per unit
of refrigeration and decreases the compressor capacity by increasing the compression ratio.
While the discharge line pressure drop is not as critical as that of the suction line, the
accepted maximum values are 4 psi for R-12 and 6 psi for R-22. The same minimum gas
velocities of 500 feet per minute in horizontal runs and 1000 feet per minute in vertical runs
with upward gas flow are observed. The maximum acceptable gas velocity, based on noise
considerations, is 4000 feet per minute.

5
6

Condenser Drain Line

The line between a condenser (not providing liquid subcooling) and a liquid receiver, when
such an arrangement is used, must be carefully sized. While it is almost impossible to oversize
such a line, under sizing is to be avoided. An undersized line can restrict the flow of refrigerant
to the extent that some of it is held in the condenser. If some of the condenser surface is
flooded, the capacity is reduced. These causes the head pressure to rise and decrease the
overall system capacity. At the same time, the power to drive the compressor rises.

There are a few points that the piping designer should keep in mind.
• Condenser drain line velocity should be 100 fpm or less.
• The distance from the condenser to receiver should be as short as possible.
• The condenser must be located above the receiver.
• If the system is equipped with an air-cooled condenser and a liquid receiver, it is good
practice to locate the receiver within the building. Some means should be provided to isolate
the receiver from the condenser during cold weather shutdown, such as a combination check
and relief valve.

Receiver

Refrigerant receivers are vessels used to store excess refrigerant while still allowing
circulation throughout the system. Receivers perform the following functions:

• Provide pumpdown storage capacity when another part of the system must be serviced or
the system must be shut down for an extended time. In some water-cooled condenser
systems, the condenser also serves as a receiver if the total refrigerant charge does not
exceed its storage capacity.
• Handle the excess refrigerant charge that occurs with air-cooled condensers using the
flooding type condensing pressure control.
• Accommodate a fluctuating charge in the low side.
• Drain the condenser of liquid.
• Maintain an adequate affective condensing surface on system where the operating charge in
the evaporator and or condenser varies for different loading conditions. When an evaporator is
fed with a thermal expansion valve, hand expansion valve, or low-pressure float, the operating
charge in the evaporator varies considerably depending on the loading. During low load, the
evaporator requires a larger charge since the boiling is not as intense. When the load

6
7

increases, the operating charge in the evaporator decreases, and the receiver must store
excess refrigerant.
• Hold the full charge of the idle circuit on systems with multicircuit evaporators that shut off
the liquid supply to one or more circuits during reduced load.

Receiver Design Considerations

• Receiver should be close to the condenser.


• If there is any doubt about the line size, use the larger of the sizes.
• Always adhere to the minimum vertical dimension required to overcome friction.
• Install a pressure relief device on top of each receiver and on condenser.
• The surge receiver pressure relief device is piped together with condensers.
• Size the receiver to hold 40 to 125% of refrigerant charge depending on system load
variance.

When a through type receiver is used, the liquid must always flow from the condenser to the
receiver. The piping must provide free flow of liquid from the condenser to the receiver by
equalizing the pressure between the two. If a vent is not used, the piping between condenser
and receiver is sized so that liquid flows in one direction and gas flows in the opposite
direction. Sizing the condensate drain line for 100 fpm liquid velocity is usually adequate to
attain this flow. Piping should slop at least 0.25 in/ft and eliminate any natural liquid traps. The
condensate drain line should be sized so that the velocity does not exceed 100 fpm.

Please consult the manufacturer’s literature for making receiver capacity comparisons when
changing refrigerants.

Liquid Lines

Pressure drop should not be so large as to cause gas formation in the liquid line or insufficient
liquid pressure at the liquid feed device. Systems are normally designed so that the pressure
drop in the liquid line, due to friction, is not greater than that corresponding to about a 1º to
2ºF change in saturation temperature.

Pressure drop (in psig) for a change of 1ºF saturation at 100ºF condensing
pressure: (R-508B is at 10ºF):
7
8

Liquid subcooling is the only method of overcoming the liquid line pressure losses in
order to guarantee liquid at the expansion device in the evaporator. If the subcooling is
insufficient, flashing will occur within the liquid line and degrade the efficiency of the
system. Friction pressure drops in the liquid line are caused by accessories such as
solenoid valves, filter driers, and hand valves, as well as by the piping and fittings
between the receiver outlet and the refrigerant feed device at the evaporator. Liquid
line risers are also a source of pressure loss. The loss due to a riser is approximately
0.556 psi per foot of liquid lift. The total loss is the sum of all friction losses plus the
pressure loss from liquid risers. Refrigeration systems that have no liquid risers and
have the evaporator below the condenser and/or receiver benefit from a gain in
pressure due to liquid weight. They can thus tolerate larger friction losses without
flashing. When flashing occurs, the overall efficiency is reduced and the system may
malfunction. The only way to reduce the effect of pressure loses and friction is by
subcooling the refrigerant.

Suction Lines

Suction lines are more critical than liquid and discharge line from a design and
construction standpoint. They should be designed to:
• Provide a minimum pressure drop at full load.
• Return oil from the evaporator to the compressor under minimum load conditions.
• Prevent oil from draining from an active evaporator into an idle one.

A pressure drop in the suction line reduces a system’s capacity by forcing the
compressor to operate at a lower suction pressure, in order to maintain a desired
evaporating temperature in the coil. As the suction pressure is decreased, each pound
of refrigerant returning to the compressor occupies a greater volume, and the weight
of the refrigerant pumped by the compressor decreases. For example, a typical low

8
9

temperature R-502 compressor at -40ºF evaporating temperature will lose almost 6% of


its rated capacity for each 1 psi suction line pressure drop. Normally accepted design
practice is to use a suction line pressure drop equivalent to a 2ºF change in saturation
temperature.

Of equal importance in sizing the suction line is the necessity of maintaining adequate
velocities to properly return oil to the compressor. Studies have shown that oil is most
viscous in a system after the suction vapor has warmed up a few degrees from the
evaporating temperature, so that the oil is no longer saturated with the refrigerant.
This condition occurs in the suction line after the refrigerant vapor has left the

9
10

evaporator.
Movement of the oil through suction lines is dependent on both the mass and velocity
of the suction vapor. As the mass or density decreases, higher velocities are required
to force the oil along.

Nominal minimum velocities of 700 fpm in horizontal suction lines and 1500 fpm in
vertical suction lines have been recommended and used successfully for many years
as suction line sizing design standards. Use of the one nominal velocity provided a
simple and convenient means of checking velocities. However, tests have shown that
in vertical risers the oil tends to crawl up the inner surface of the tubing, and the larger
the tubing, the greater velocity required in the center of the tubing to maintain tube
surface velocities that will carry the oil. The exact velocity required in the vertical line
is dependent on both the evaporating temperature and the line size, and under varying
conditions, the specific velocity required might be either greater or less than 1500 fpm.
An HFC refrigerant, however, is designed for 1500 fpm or greater.

Always pitch vapor lines in the direction of flow, 1/2 inch per ten-foot of suction line.
“P” traps for uphill oil return should be used after the first 6- foot and every 12-foot
thereafter. It is good practice to use an inverted trap just before entering the
compressor.

Double Risers
On systems equipped with capacity control compressors, or where tandem or multiple
compressors are used with one or more compressor cycled off for capacity control, a
single suction line riser may result in either unacceptably high or low gas velocities. A
line properly sized for light load conditions may have too high a pressure drop at
maximum load, and if the line is sized based on full load condition, then velocities may
not be adequate conditions to move oil through the tubing at light load. On air
conditioning applications where somewhat higher pressure drops at maximum load
conditions can be tolerated without any major penalty in overall system performance,
it is usually preferable to accept the additional pressure drop imposed by a single
vertical riser. However, on medium or low temperature applications where pressure
10
11

drop is more critical and where separate risers from individual evaporators are not
possible, a double riser may be necessary to avoid an excessive loss of capacity.

A typical double riser has a small and large riser. The two should be sized so that the
total cross-sectional area is equivalent to the cross-section area of a single riser that
would have both satisfactory gas velocity and acceptable pressure drop at maximum
load conditions. The larger is trapped and the smaller line must be sized to provide
adequate velocities and acceptable pressure drop when the entire minimum load is
carried in the smaller riser.

Another method of suction oil return is the use of a double riser, as shown
in Figure 1. Oil return is accomplished with this method at minimum loads. In addition,
excessive pressure drop at full load is avoided. The small riser “A” is sized to return
oil under minimum capacity conditions. Riser “B” which, may be larger, is sized so
pressure drop through both risers during full load conditions is adequate. Traps with
minimum oil holding capacity are recommended.

11
12

Suction Line Double Risers Sizing

Single Riser Size Double Riser Sizes 2/3, 1/3


1 1/8 = .83 7/8 and 3/4 = .83
1 3/8 = 1.26 1 1/8 and 7/8 = 1.31
1 5/8 = 1.78 1 3/8 and 7/8 = 1.74
2 1/8 = 3.10 1 5/8 and 1 3/8 = 3.04
2 5/8 = 4.77 2 1/8 and 1 5/8 = 4.88
3 1/8 = 6.81 2 5/8 and 1 5/8 = 6.55

Defrost Gas Supply Lines

Sizing refrigeration lines to supply defrost gas to one or more evaporator is an


estimate at best. The parameters associated with sizing the defrost gas lines are
related to allowable pressure drop and refrigerant flow rate during defrost. Design
professionals typically use approximately two times the evaporator load for effective
refrigerant flow rate to determine line-sizing requirements. The pressure drop is not as
critical during the defrost cycle, and many engineers have used velocity as criterion
for determining line size. The effective condensing temperature and average
temperature of the gas must be determined. The velocity determined at saturated
conditions will give a conservative line size. It is recommended that initial sizing be
based on twice the evaporator flow rate and that velocities from 1000 to 2000 fpm be
used for determining the defrost gas supply line size.

Refrigerant Line Capacity Tables & Equivalent Lengths Of Valves & Fittings
Refrigerant line capacity tables are based on unit pressure drop per 100 ft length of
straight pipe or per combination of straight pipe, fitting, and valves with friction drop
equivalent to a 100 ft length of straight pipe. Generally, pressure drop through valves
and fittings is determined by establishing the equivalent straight length of pipe of the
same size with the same friction drop. Alternately, one rule of thumb is to add 50% to
the calculated pipe length to account for pressure drops from fittings and valves.

12
13

Expansion & Contraction


Temperature change will expand and contract all refrigeration piping material.
Techniques must allow for expansion and contraction changes to prevent stresses
that may buckle, bend or rupture the refrigerant piping. he two common methods of
taking care of expansion and contraction in copper piping are the “expansion loops”
or “pipe offsets”. During the installation of the line, care must be taken that the line
maintains a perfect alignment.

On average, copper’s coefficient of expansion is 0.0000104 inch per inch per degree
Fahrenheit. Thus, expansion of copper is 1.25 inch per 100 feet per 100ºF change. For
example, a copper compressor discharge line of 75 feet long at 225ºF could have a
temperature change of 150ºF in a 70ºF room. Therefore, 1.25 X 1.55 (temperature
change per 100ºF) X .75 (length per 100 feet) will equal 1.453 inches of expansion. The
75 foot long line would now be approximately 75 feet, 1-1/2 inches long.

Location & Arrangement of Piping


Refrigerant lines should be as short and direct as possible to minimize tubing and
refrigerant requirements and pressure drops. Plan piping for a minimum number of
joints, using as few elbows and other fitting as possible, but provide sufficient
flexibility to absorb compressor vibration and stresses due to thermal expansion and
contraction.

13
14

Arrange refrigerant piping so that normal inspection and servicing of the compressor
and other equipment is not hindered. Do not obstruct the view of the oil level sight
glass, or run piping so that it interferes with the removal of compressor cylinder head,
end bells, access plates, or any internal parts. Suction line piping to the compressor
should be arranged so that it will not interfere with removal of the compressor for
servicing.

You must provide adequate clearance for insulation installation between the piping,
wall, and hangers. Use sleeves that are sized to permit installation of both pipe and
insulation through floor, walls, or ceilings. Set the sleeves prior to pouring of concrete
or erection of brickwork. Piping must not interfere with passages or obstruct
headroom, windows, or doors. Refer to ASHRAE Standard 15, Safety Code for
Mechanical Refrigeration, and other governing local codes for restrictions that may
apply.

Protection Against Damage To Piping


Protection against damage is necessary, particularly for small lines, which have a false
appearance of strength. Where traffic is heavy, provide protection against impact from
pedestrian and motorized traffic.

Piping Insulation
All piping joints and fittings should be thoroughly leak tested before insulation is
sealed. Suction lines should be insulated to prevent sweating and heat gain. Insulation
covering lines on which moisture can condense or lines subjected to outside
conditions must be vapor sealed to prevent any moisture travel through the insulation,
or condensation in the insulation. Although the liquid line ordinarily does not require
insulation, the suction and liquid lines can be insulated together. The liquid line should
be insulated to minimize heat gain if it passes through an area of higher temperature.
Hot gas discharge lines usually are not insulated, however, they should be insulated if
the heat dissipated is objectionable or if necessary to prevent injury from high
temperature surfaces.

14
15

Vibration & Noise in Piping


Two undesirable effects of vibration of refrigerant piping are: 1) physical damage to
the piping, which may result in the breaking of brazed joints and consequent loss of
charge; and 2) transmission of noise through the piping itself and through building
construction with which the piping may come into direct physical contact. Both can be
eliminated or minimized by proper piping design and installation.

Using Manufacturer’s Pressure Drop & Velocity Charts

Always size for pressure drop first, then velocity. On the top right of the pressure drop
chart in Figure 8-3, you will find tons of refrigeration or cooling capacity calibrated in
Btu per hour up to 1 ton, and in tons of cooling from 1 ton to 100 tons. You start the
sizing procedure by drawing a straight line from your system’s designated capacity
through the diagonal lines on the right side of the chart.

The diagonal lines represent:


• The “evaporator temperature”, used to size the suction line.
• The “discharge line” temperature, used to size the hot gas discharge.
• The “liquid lines” diagonal line, used to size the liquid line.

15
16

The diagonal lines on the left of the chart represent the actual tubing sizes that will be
derived by your calculation. Starting at the bottom line, representing 3/8" OD Type L
copper tubing and increasing in size up through 6-1/8. Draw a horizontal line from each
intersection of tonnage and each of the three diagonal lines, horizontally across
through the tubing sizes.

On the bottom left of the chart you will find the “pressure drop graph.” The three
horizontal lines represent condenser coil temperature applications. The curved
diagonal lines are pressure drop in psi per 100 ft. When you have determined
necessary condenser coil temperature follow the horizontal line to the required
pressure drop. Draw a line straight up until it intersects with the horizontal line used to
determine tubing size. If it falls in between two sizes then your size is the tubing size
up and to the left. For example, let’s size for a 6-ton R-134a medium temperature walk-
in refrigerator using the chart in your book:

16
17

• First, find 6 tons on the top right of your chart and draw a vertical line straight down
through all of the diagonal lines.

Medium temperature requires a 20°F evaporator so draw a line from the diagonal line
designated 20°F horizontally all the way across the chart.

• Do the same from the diagonal line labeled “Discharge Line.”


• And again from the diagonal line labeled “Liquid Line.”

The suction line pressure drop maximum for medium temperature is 1-1/2 psi so the
suction line size will be 1-5/8". We require a 3psi pressure drop for our liquid line so
the line size is 5/8". The hot gas discharge line is a bit more forgiving, 10 psi or less,
so 1-1/8" will work adequately. The velocity chart is very similar to the pressure drop
chart and is used in the same way. The idea is to confirm the sizes you found on the
pressure chart by cross checking with the applicable velocities on the velocity chart. If
you plot the same temperature variables on the velocity chart, you’ll find the sizes
chosen will fall between minimum and maximum velocities recommended for each
refrigeration line. There are exceptions and sometimes economical compromises on
many close-coupled and field fabricated systems. It is these exceptions that may need
careful consideration before retrofit.

17
18

18
19

19
20

20
21

21
22

22
23

23
24

24
25

25
26

404A

26
27

27
28

402A

28
29

29
30

30
31

31
32

32
33

Charging Residential Air Conditioning R-22

Different types of metering devices have different ways of charging. A Thermostatic


Expansion Valve (TXV) is charged to the subcooling of the liquid line leaving the
condenser. A fixed orifice is charged to the superheat of the suction line leaving the
evaporator. To under stand why this is, it requires an understanding of the physical
properties of the refrigeration cycle. The four main components of the refrigeration
cycle include:
• Compressor
• Condenser
• Metering Devices
• Evaporator
These four components are divided into sections and explained in depth as follows.

Compressor

The Compressor compresses a low-pressure superheated gas into a high-pressure


superheated gas. If the suction gas is not superheated, the compressor can be
damaged. The compressor pulls the refrigerant out of the evaporator and pushes it
though a condenser. The act of compression is performed by any one of the following
six types of compressors: a reciprocating piston, rotary, scroll, screw, centrifugal, and
sonic compressors. Of the six, the reciprocating and scroll compressors are the two
most frequently found in a residential air conditioning system.

The mass flow rate produced by a compressor is equal to the mass of the suction gas
pulled in by the compressor. The compressor’s out put is equally only to its intake
because the mass flow must be equal. The process of compression, through mass
flow, raises the temperature and pressure of the refrigerant. The result of the
temperature increase is superheat. Pressure and temperature of the refrigerant must
be higher than the condensing temperature. The refrigerant temperature must be
33
34

higher so heat can flow into the condensing medium. This process explains the
necessary relationship between the increased pressure and the rise in temperature. If
the pressure and temperature is not increased through compression, there is no heat
transferred from the refrigerant to the condensing medium. The compressor has a
maximum inlet temperature of about 70° degrees and outlet of about 225° degrees.
Inlet refrigerant gas cools the compressor motor.

Desuperheating (heat leaving the refrigerant gas) of refrigerant begins as it is


discharged. From a compressor and pushed into a condenser.

Condenser
The condenser removes heat and changes a high-pressure vapor into a high-pressure
liquid. As the superheated (high-pressure) gas is pushed into the condenser, it is
desuperheated, that is the temperature is reduced to saturated pressure-temperature.

The refrigerant does not start to change state until the temperature reaches saturated
pressure-temperature. The only variable that can change the temperature is a
pressure change. (See table 1) At saturation pressure-temperature point, the change
of state becomes latent heat (invisible or hidden heat). Latent heat is a lack of rise or
fall of temperature during a change of state (saturation). When the temperature does
not rise or fall it is at saturation and the change of state process begins. Refrigerant
continues to change state at one pressure-temperature. The only variable that can
change a temperature is a pressure change. If a temperature change occurs a
pressure change occurs. If a pressure change occurs a temperature change occurs.
At the change of state the refrigerant liquid and vapor are at the same temperature.
This is defined as equilibrium contact. The temperatures of the liquid and vapors will
stay the same until the temperature of the refrigerant starts to drop. Temperature of
the refrigerant start to drop once 98% to 99% of the refrigerant becomes a liquid. This
is called subcooling. Subcooling is a temperature below saturated pressure-
temperature. (See table 1) Subcooling is a measurement of how much liquid is in the
condenser. In air conditioning, it is important to measure subcooling because the
longer the liquid stays in the condenser, the greater the sensible (visible) heat loss.

34
35

Low subcooling means that a condenser is empty. High subcooling means that a
condenser is full. Over filling a system increases, pressure due to the liquid filling of a
condenser that shows up as high subcooling. To move the refrigerant from
condenser to the liquid line, it must be pushed down the liquid line to a metering
device. If a pressure drop occurs in the liquid line and the refrigerant has no
subcooling, the refrigerant will start to re-vaporize (change state from a liquid to a
vapor) before reaching the metering devise.

Refrigerant –22

Liquid line

Saturated temperate - Temperature = subcooling

200 psig = 101 degrees - 96 degrees = 5 degrees

210 psig = 105 degrees - 90 degrees = 15 degrees

240 psig = 114 degrees - 98 degrees = 16 degrees

(Table 1)

Metering Devices
A metering device is a pressure drop point, which has two jobs:
1. Holds refrigerant back in a condense; and
2. Feeds refrigerant into the evaporator.

When high-pressure liquid enters a metering device, pressure starts to drop, as the
temperature remains the same until it reaches saturation pressure-temperature. At
this time both the pressure and temperature continues to drop to evaporator pressure-
temperature. (See table 2) Low-pressure liquid that is leaving the metering device is
boiling at saturated pressure-temperature. The process of a refrigerant changing its
state (from a liquid to a vapor) in the metering device is called flash gas. Flash gas is
what cools the refrigerant liquid in the metering device. A system with no subcooling

35
36

has more gas that is flashed and less capacity.

Evaporators
The refrigerant enters the evaporator as a boiling low-pressure liquid at saturated
pressure-temperature. It continues to boil at one temperature as long as the pressure
remains the same. If there is not a pressure change in the evaporator, there will not be
a temperature change in the refrigerant changing state. At saturation, refrigerant
absorbs latent heat, which is a change of state heat. The refrigerant changes state at
one temperature (for any one pressure) from the beginning of the evaporator until the
entire liquid refrigerant has become a vapor. The only variable that can change a
temperature is a pressure change. If a temperature change occurs a pressure change
occurs. In latent heat, the liquid and vapor are at the same temperature due to
equilibrium contact. When heat is added to the gas, past saturation pressure-
temperature, it is called superheat. (See Table 2) Superheat is an indication of how full
the evaporator is of liquid refrigerant. High superheat means the evaporator is empty.
Low superheat means the evaporator is full. There have been reports that liquid
refrigerant can still be boiling with 2° degrees of superheat. Superheat should never
be observed below 4° degrees or a compressor failure may occur. The superheat gas
is pulled into the compressor were it starts the cycle again.

Refrigerant –22

suction line

Saturated temperate - Temperature = superheat

58 psig = 32 degrees - 44 degrees = 12 degrees

64 psig = 37 degrees - 47 degrees = 10 degrees

70 psig = 41 degrees - 50 degrees = 9 degrees

(Table 2)

36
37

Charging Methods
Before charging of a residential air conditioning system, two temperatures must be
recorded:
1. Condensing air inlet dry bulb temperature.
2. Evaporator air inlet wet bulb temperature. Wet bulb temperature is a measurement
of the heat contained within air. Air may have many different wet bulb temperatures
for one dry bulb temperature, depending on relative humidity of the air.

Different types of metering devices have different ways of charging.

Thermostatic Expansion Valve R-22


A/C with a Thermostatic Expansion Valve (TXV) is charged to the subcooling of the
liquid line leaving the condenser because the superheat is fixed. The superheat is
fixed at 8 to 12 degrees in most residential air conditioning systems. Subcooling is the
amount of liquid held back in the condenser. This allows the liquid to give up more
heat, below saturated pressure- temperature. For every one degree of subcooling at
the same condensing pressure, capacity will increase .5 percent. Increasing
subcooling with an increase of discharge pressure and compression ratio, decrease
capacity. Add 5 degrees of subcooling for every 30 feet of liquid line lift.

To measure subcooling:
1. Obtain refrigerant saturation pressure-temperature. Take a pressure reading of the
liquid line leaving the condenser. Refrigerant saturation temperature is the pressure-
temperature when the refrigerant is turning from a high-pressure vapor into a high-
pressure liquid (giving up heat). At saturation pressure-temperature, both liquid and
vapor are at the same temperature.
2. Convert pressure to temperature with a pressure temperature chart.
3. Take a temperature reading at the leaving liquid line of the condenser.
4. Compare both, the saturated temperature and leaving liquid line temperature.
Subtracting one from the other, the difference is the amount the refrigerant has cooled
past saturated temperature. This is subcooling. (See table 1)

This four-step procedure is known as subcooling. Manufacturers should be able to


37
38

identify the amounts of subcooling they have designed into a system. A low charge
will give a low subcooling. An overcharge will give a high subcooling along with a
high compression ratio. Do not worry about a few bubbles in the sight glass. Sight
glasses will not always be clear with a full charge. The zeotropes refrigerant group is
known for their fractionation. It is possible to never have a clear sight glass. To
determine what the subcooling should be in a system (see table 3).

Subcooling for A/C with TXV R-22


Evaporator Inlet Air Temperature Fahrenheit Wet Bulb
57 59 61 63 65 67 69 71 73
Outside Air
Temperature DB
75 25 24 23 22 21 20 19 18 17
80 24 23 22 21 20 19 18 17 15
85 23 22 21 20 19 18 17 16 14
90 22 21 20 19 18 16 15 14 12
95 21 20 19 18 17 15 13 12 10
100 20 19 18 17 15 13 12 10 8
105 19 18 17 16 14 12 10 8 6
110 17 16 15 13 12 10 8 6 4
115 15 14 13 12 10 8 6 4 2
(Table 3) + --2 degrees

Fixed Orifice R-22


A/C with a fixed orifice is charged to the superheat of the suction line leaving the
evaporator. Superheat is the gas temperature above the saturated temperature.
Superheat can be split into two types of heat:
1. Superheat of the evaporators; and
2. Total superheat entering the compressor.

The evaporators superheat must be figured at the evaporator outlet not at the
compressor inlet. Total superheat is figured at the compressor inlet.

To measure evaporator superheat:


1. Take a pressure reading of the suction line-leaving evaporator to get refrigerant
saturation pressure-temperature. Refrigerant saturation temperature is the pressure-
38
39

temperature when the refrigerant is turning from a low-pressure liquid to a low-


pressure vapor (absorbing heat). At saturation pressure-temperature, both liquid and
vapor are at the same temperature.
2. Convert pressure to temperature with a pressure temperature chart. If reading is
obtained at the compressor, not at the evaporator leaving line, you may have to add a
few pounds of pressure due to pressure drop in the suction line.
3. Take a temperature reading at the leaving suction line of the evaporator.
4. Compare both, the saturated temperature and the leaving suction line temperature.
Subtracting one from the other, the difference is the amount the refrigerant gas has
heated past saturated temperature. This is superheat. (See table 2)

This four-step procedure is known as superheat. Manufacturers should be able to


identify the amounts of superheat they have designed into a system. A low charge will
give a high superheat. An overcharge will give a low superheat along with a higher
compression ratio. To determine what superheat in a system should be, see (table 4).

Superheat for A/C with fixed Orifice R-22


Evaporator Inlet Air Temperature Fahrenheit Wet Bulb

54 56 58 60 62 64 66 68 70 72 74
Outside Air
Temperature DB
60 13 17 18 20 24 26 28 30 33 36 39
65 11 13 15 17 18 22 25 28 30 33 36
70 8 11 12 14 16 18 22 25 28 30 33
75 5 7 10 12 14 16 18 23 26 28 30
80 4 6 8 12 14 16 18 23 27 28
85 4 6 8 12 14 17 20 25 27
90 4 6 9 12 15 18 22 25
95 4 7 11 13 16 20 23
100 5 8 11 14 18 20
105 4 6 8 12 15 19
110 5 7 11 14 18
115 5 8 13 16

(Table 4) +-- 2 degrees

39
40

Total Superheat Method

Some residential air-conditioning system with fixed orifice may be charged by the total
superheat method. Various equipment manufacturers furnish charts with their units
that explain the proper procedures to the installing or servicing technician.

This method, similar to evaporator superheat method, is effective only when the indoor
conditions are within 2F° of desired indoor comfort conditions and the suction
pressure and temperature is stabilized.

To measure total superheat:


1. Read and record the outdoor ambient air-dry bulb temperature entering the
condenser.

2. Read and record suction line pressure and temperature at the suction service valve
or service port at compressor.

3. From Table 5, the reading at the intersection of vapor pressure and outdoor ambient
temperature should coincide with the actual vapor line temperature.

4. If the vapor line temperature is not the same, adjust the refrigerant charge. Adding
R-22 will raise suction pressure and lower suction line temperature. Removing R-22
will lower suction pressure and raise suction line temperature.

Caution: If adding R-22 increases both suction pressure and temperature, the unit is
overcharged.

This method is very useful when performing preventive maintenance or corrective


40
41

service on residential air conditioning. Remember to always refer to the


manufacturer’s recommendations whenever possible.

Vapor pressure at service valve

52 54 56 58 60 62 64 66 68 70 72 74 76 78 80 82 84

Outdoor T°⏐Vapor line T° at compressor F°

100+ ⏐ 43 45 46 47 49 50 51 53 54 55

100 44 45 47 48 49 51 52 53 55 56 57

95 45 47 48 50 51 52 54 55 56 58 59 60

90 49 51 52 54 55 56 58 59 60 62

85 52 53 55 56 58 59 61 62 63

80 53 55 56 58 59 61 62 63 65

75 55 56 58 59 61 62 64 65 66

70 55 57 58 60 61 63 64 66 67

65 57 58 60 61 63 64 66 67 69

Refrigeration
The use of sight glass for charging is common in refrigeration. It is better to charge a
system first by measuring the operating condition (discharge and suction pressures,
suction line temperature, compressor amps, super heat, subcooling and coils
temperature deferential) before using the liquid line sight glass. If the sight glass is
close to the exit of the condenser or if there is very little subcooling at the sight glass,
bubbles may be present even when the system is properly charged. If a system is
charged to full sight glass, overcharging may be the result, decreasing efficiency.

Note: Follow the manufacturer recommendation for superheat and subcooling.


41
42

A Thermostatic Expansion Valve (TXV) is designed to maintain a constant superheat.


Over charging a TXV will rise subcooling, increases system pressures, and decreases
system efficiency. Under charging a TXV will decrease subcooling, increases
superheat, decrease system capacity, and lower refrigerant velocity leaving oil in the
evaporator. An Automatic Expansion Valve (AXV) is a constant evaporator pressure
valve and not normally used in A/C. A fixed orifices is the simplest metering devise
made and the most critical to charge. Over charging fixed orifices will lower
superheat, increases pressures, decrease efficiency, and flood the compressor with
liquid refrigerant. Under charge, the fixed orifices will raise superheat, lower pressure,
lower capacity, and lower refrigerant velocity leaving oil in the evaporator. Always
refer to the manufacturer recommendations on charging fixed orifices.

The process of charging to superheat and subcooling improves an air conditioning


system’s efficiency, capacity and lessens equipment failures. Always let system
stabilize (10 to 20 minutes) after adjusting the charge, this takes time but improves
efficiency and capacity.

Remember when changing refrigerants all superheat and subcooling adjustments have
to be checked and recorded. The procedure of recording adjustments is called
Baselining. This procedure not only saves time, money, and aggravation but it is a
sign of a professional.

Roger D. Holder, CM, BSME, Is the owner of R D Holder Eng in Bakersfield CA, 661-
665-8893, He also is a Refrigeration and Air Conditioning specialist at National
Technical Transfer Inc., P. O. Box 4558 Englewood, CO 80155 (800) 922-2820

42
43

43

You might also like