Final Project FINAL
Final Project FINAL
BY
A project report submitted in partial fulfilment of the requirements for the award of the Post
Graduate diploma in Construction Project Management of the College of Engineering,
Design, Art & Technology of Makerere University.
August, 2018
DECLARATION
I, MBYEMEIRE AMBROSE declare that the content of this report is my original work
with the exception of acknowledged citations and that it has never been submitted to any
institution by any other person for any purpose.
Signature...................................
MBYEMEIRE AMBROSE
2017/HD08/1185U
Date.....................................
Signature.................................
Dr. Godfrey Mwesige
Supervisor
Date........................................
First, I would like to thank the Almighty God for this opportunity to further my education.
I would like acknowledge my supervisor, Dr. Godfrey Mwesige for having the time to direct
us in the course of this program.
Finally yet importantly, I would like to thank my family and friends for the encouragement
and support.
This project report presents the technical findings and aspects of construction management
practice exercised by George and Company Limited while working as one of the Contractors
for improvement of water supply and sanitation services of the Urban Poor in Kampala
through National Water and Sewerage Corporation (NWSC). It provides in-sight on project
appreciation, contract documentation and administration, and application of project
management knowledge in the process of contract implementation.
The Government of Uganda, as part of its poverty eradication and preventive health strategic
programmes, made a pledge to improve water supply and sanitation services of the Urban
Poor in Kampala. As such, the Kawempe Sanitation Improvement Project (KSIP) was borne
as a follow-up of the Public Stand Pipes Project, which was implemented in the FY
2005/2006 through National Water and Sewerage Corporation.
The KSIP had public toilet facilities that range from three stances to six stances and each
facility had provisions for shower rooms. The KSIP entailed two phases. The first phase,
completed in 2012, comprised of 56 public toilet facilities. The second phase that comprised
of 44 public toilet facilities effectively commenced construction works in March 2015 and
was substantially completed by January 2016.
The KSIP is in line with earlier studies undertaken by NWSC, which offered a platform for
improving water and sanitation (WATSAN) services for Kampala's urban poor particularly in
informal settlements.
The KSIP Phase 2 was handed-over to the designated caretakers in user communities upon
completion. The caretakers were to be responsible for the management and operation of these
sanitation facilities, provide security, toilet usage materials and ensure cleanliness.
The project was implemented through stakeholder engagement and social marketing
approach. Specifically, NWSC worked closely with Kampala Capital City Authority
(KCCA), the local leaders and Councillors to identify the areas with critical need of sanitation
facilities. The community provided the land, at no cost or free of charge, since these facilities
serve them including the landlords.
Each toilet facility has squatting pans, flushing cisterns, showers finished with ceramic wall
The superstructure walls are 150mm thick brickwork, bonded with cement mortar including
25mm thick plaster and rendering internally and externally. The roof is gauge 28 pre-painted,
galvanised corrugated iron roofing sheets.
In terms of finishing, the external walls were finished with cement roughcast and interior
walls painted with vinyl silk paint
The author’s practical professional involvement on this project started with the Construction
stage as the Contractor’s Site Engineer for the 22 toilet units.
The tasks executed during the course of works were specific to contract implementation and
interpretation:-
The above project tasks and activities are detailed in chapter two.
2.0 Introduction
The Success of a project was greatly attributed to the site management practices used by the
contractor. The supervising team from NWSC constantly reviewed and advised on any
arising contradictions and community concerns accordingly. This was done to ensure that the
project is carried out within the stipulated time, cost and as specified in the contract.
This chapter entails the major construction activities undertaken from commencement of
works to completion of the project.
The contractor was issued a commencement order effective 15th February 2015 with a
duration of 6months; therefore, the intended completion date was 15th August 2015 (see
appendix). The contract specified that updated work programs were to be submitted not more
than 7 days from the start date.
After site hand over, the contractor preliminary works kicked off in preparation for execution
of the project. These preliminary works entailed mobilization of the technical team/ personnel
and the necessary plant and equipment.
The technical team comprised of the - site engineer, site agent, site quantity surveyor, and site
supervisor. During mobilization, works such as site clearance, construction of temporary
structures such as site offices & toilets, selection of possible sources of materials and testing
of materials.
This was followed by construction of the intended ground breaking site, which was situation
in Bwaise Opposite Total. This site was treated as special since it was to be used as a
demonstration and it was constructed with a septic tank and toilet house detached.
The construction contract between M/S George & Co. Ltd and NWSC was duly signed on
23rd December 2014 (See appendix). The contract was admeasurement with no sectional
completion and price adjustments clauses. The following documents were deemed to form
and were part of the contract;
Reference was made to the above documents to harmonise the instructions from the project
manager.
Any entrance on site was registered in the diary that was maintained by the contractor. The
diary was also used to keep evidence of any activities that took place on site as well
anomalies that arose during project run time such as rainfall events and all those that could be
used as evidence for extra payments.
All instruction during the execution of the project, all communications and instruction were
through electronic mails and in hardcopy. Copy of various correspondences are attached for
reference.
The project did not have measurement forms. The works were executed as per the drawing
and valuation was carried out jointly at the time of certification. This allowed the contractor
and the employer to have consensus on the works executed.
All the materials used on the project were subject to approval from the project management
team before use in the project. Common materials such as bricks and sand was approved as a
stockpile and later recommended for use. A mix design for concrete was carried out and
submitted to the project manager and it was accepted and used for grade 20 with a working
ratio of 1:2:4. A copy of the design mix is attached for reference.
The initial intended completion date was 15th August 2015, but according to the contract,
forces of nature were allowed if proven to cause an extension. During execution of the project
some difficulties and obstacles were encountered which led to time extension. In line with
clause 28 of the General Conditions of Contract (GCC), the contractor gave an early warning
and requested for non-cost time extension of two months on the following grounds;
Difficulty in accessing some sites. This led to taking long hours to ferry construction
materials
The project manager after review of the request found the reasons justifiable and requested
NWSC contracts committee through the Manager procurement to consider extending the
project for two months. The contracts committee approved it and project completion date
revised to 15th October 2015
Upon site selection, setting out the extents of the building boundaries was carried out using
the 345 method. The tools used included pegs, nails, a hammer and profile boards. Setting out
was done concurrently for the architectural and structural drawings.
Excavation of pits was done to a depth as specified in the drawings from the reduced level;
this was done manually using pick axes, hoes and spades marked by the building lines on the
profile boards but in some sections, mechanical methods were used.
Construction of the substructures commenced with well-burnt clay bricks to a height of 1.5m
with a partition wall and a beam (200x200) was constructed to improve the rigidity to
collapsing. The brickworks was continued after the beam to the slab level where a second
beam to receive the deck was constructed.
Shuttering and formwork was done using local timber boards known as “kirudu” forming the
design sizes and shapes of the all the elements of work to receive concrete. Concrete grade 25
was used for the sub-structure concrete works. Curing was done for a minimum of 7 days to
ensure good strength for other work to continue.
The substructure consisted mainly of 200mm thick block work, bonded with cement mortar
in substructure including a 25mm thick rendering with a steel float cement-screen finish on
the inner face
Figure 1: Substructure/ Septic tank pit construction and top slab reinforcement
2.3.2.1 Beams
The dividing beams divided the height of the septic tank in the ration 1:1, and enabled the
two sections to be fixed together and prevent any likely failures during the vertical loads.
They were made of concrete and reinforced steel to provide the tensile strength that
brickwork lacks. They further gave structures supreme stability, where they would otherwise
be rather unstable. Although a ring beam also helped to support the roof of the supers
structure (Toilet house), it was vital to make sure it would be able to do so, and it was not
necessary to overload the beam with more than it can take.
When casting the concrete shuttering (plywood formwork) was placed around the steel to
form a box shaped mould ready to cast the concrete around the steel. This was placed to make
sure that the walls are 200mm thick and, when the concrete is poured, that there should be a
good thick layer of concrete on both sides of the steel mesh to stop the steel rusting.
The concrete was correctly mixed and, during pouring, the concrete was vibrated with a
vibrator to make sure it is properly compacted with no cavities or air holes. The aggregates
were small enough to fit easily between the steel and the plywood.
2.3.2.2 Slab
The slab was designed to act as the foundation for the superstructure. It consisted of High
Yield square twisted bars to BS4449 and of 10mm high yield steel bars in suspended pit slab
and lintels. The formwork was class S1 finish to suspended slabs and lintels and concrete
Grade C20, designed mix to BS 5328, cement to BS 12, with 20mm aggregate to BS 882.
The reinforcement was spaced at 150mm center to center with 25mm concrete cover.
Figure 2: Septic tank beam after casting of concrete and materials for the superstructure
The construction of the toilet house depended on the number of stances. These were, 4
stances+2 bathrooms, 3 stances +1 bathroom.
After the septic tank beam had properly set, it formed the foundation for the superstructure. It
consisted of;
100mm thick burnt clay pompey grill brick work, bonded with cement mortar
150mm thick hollow block work bonded with cement mortar in super structure
including 25mm thick plaster and rendering internally and externally
Urinal walls finish with ceramic wall tiles, 150mmx150mm up to 1.5 height
The roof system of the superstructure was composed of the following elements;
50mmx100mm purlins/rafters
The plumbing works executed on the project involved installation of rainwater gutters,
internal and external pipe fitting, connections to the tank, soak pits and urinals. The major
components and plumbing materials included the following;
20mm HDPE, PN 10 pipe complete with spigot and socket joints from tank to cisterns
to BS4660
75 mm nominal bore soil drains complete with spigot, socket joints and 20mm water
seal in UPVC pipes to BS 4514
Urinal/floor trap with domical removable cast iron grating
Three (3) litre flushing cistern tanks in liaison with the engineer
Dito butt squatting pans as per detail
A hand washing facility complete with wash hand basin, tap and soakpit as per details
furnished by the engineer
1500mm top/bottom diameter x 2.0m deep soakpit including filling with hard core,
covering with 2 layers of gauge 100 polyethylene sheet complete including
connecting to gulley traps with 75mm diameter UPVC drain pipes
UPVC SIMBA Rainwater Gutter system complete with UPVC fascia and barge
boards or equivalent (4'' size)
500 litre plastic water tank as manufactured by M/S Crest tank or other approved ,
complete with all associated plumbing fittings installed onto steel tower (contractor to
liaise with Engineer to furnish fabrication details)
25mm diameter GI pipe toilet grab rails for the disabled complete with fittings and
ancillaries including anchoring into the floor and wall to the engineer’s approval and
details.
2.3.5.2 Plastering
Plastering was carried out aimed at covering rough walls and uneven surfaces that resulted
from the construction of the superstructure, which was a mixture of cement concrete and sand
along with the required quantity of water. This plaster removed imperfections from both inner
and outer walls of the construction. The following ratio between cement and sand were used
to maintain the following applications.
The volume of plaster was calculated by multiplying the area of the plaster and the thickness
of the plastering (in this case – 25mm)
Kept all the mortar joints of wall rough, to give a good bonding to hold plaster.
Cleaned all the joints and surfaces of the wall with a wire brush, there was no oil or
grease etc. left on wall surface.
Where the surface was smooth, the mortar joint was raked out to a depth of at least 25
mm to give a better bonding to the plaster.
Where the projection on the wall surface was more than 25mm, it was knocked off, to
obtain a uniform surface of wall. This reduced the consumption of plaster
Where cavities existed or holes on the surface, it was filled in advance with
appropriate material.
Roughened the entire wall to be plastered. Wash the mortar joints and entire wall to
be plastered, and kept it wet for at least 6 hours before applying cement plaster.
In order to get uniform thickness of plastering throughout the wall surface, dots on the
wall were first placed. A dot means patch of plaster of size 15 mm * 15 mm and
having thickness of about 10 mm.
Dots were fixed on the wall first horizontally and then vertically at a distance of about
2 meters covering the entire wall surface.
Checked the verticality of dots, one over the other, by means of plumb bob.
The ratio of cement and sand for first coat plaster was 1:3
Applied the first coat of plaster between the spaces formed by the screeds on the wall
surface. This was done by means of trowel.
Levelled the surface by means of flat wooden floats and wooden straight edges.
After levelling, left the first coat to set but not to dry and then roughened it with a
scratching tool to form a key to the second coat of plaster.
2.3.5.3 Doors
750mmx2000mmx50mm framed, ledged and braced door with 3 No. 100mm steel
butt hinges, 1No 100mm tower bolt, 1No 200mm stainless steel barrow padlock
complete with a 63x125mm rebated door frame
Well painted grilled mild steel fabricated door overall dimensions 2100mmx900mm
One coat of aluminium based wood primer then super gloss to fascia/verge board
One coat of aluminium based wood primer then super gloss to door and frame
One coat of alkali resisting primer then vinyl silk to interior and weather guard to
exterior walling
3.1 Introduction
The Project Management Book of Knowledge (PMBOK) defines a project as a “temporary
endeavour undertaken to create a unique product or service”. Furthermore, projects can be
said to be performed by people, constrained by limited resources and are planned, executed
and controlled. Chudley & Greeno, (2006) who described a construction site as a temporary
factory employing the necessary resources to successfully fulfil a contract broke down this
concept. The resource requirements mainly utilized are;
a) Man power-In form of managerial, supervisory staff and in form of artisans and
general site operatives.
b) Materials -for temporary works, access positions, security and final structure.
c) Plant and Equipment - from the simple hand held tools to large items like tower
cranes.
d) Money–a building contractor who uses his money to buy materials, buy or hire plant
and hire labour to enable the project to be realized.
The PMBOK Guide (2004) further defines project management as “the application of
knowledge, skills, tools and techniques to project activities in order to meet or exceed
stakeholder needs and expectations from a project”. Project management also involves
project planning, monitoring and control.
This chapter entails the author’s contribution during the implementation of this project in
terms of project management. As the Contractor’s site engineer, the author’s major role was
to carry out project management, supervision and in particular cost control management.
3.2.3 Variations
A variation (sometimes referred to as a variation instruction, variation order or change order)
is an alteration to the scope of works in a construction contract in the form of an addition,
substitution or omission from the original scope of works. Variations are an inevitable
occurrence on construction projects. Variations are also a major cause of disruption, delay,
disputes, escalated project cost, extended construction time, and compromised quality.
Causes of variations
Amiruddin Ismail, Towhid, Amir and Majid identified common causes, which were grouped
under four categories.
Others variations - originate from other sources other than the Client and contractor
Differing site conditions
Safety consideration/emergency field condition
Weather condition
A major factor necessitating variations is attributable to preference or taste for enhanced
finished product different from the initially agreed quality by the Client in a particular
contractual agreement. In addition, there might be modifications to an initial design by
consultant due to weather conditions and differing site conditions (Hsieh et al., 2004).
3.4.2.2 Materials
The materials used on this project had to be approved by the supervising team appointed by
NWSC, which comprised of Performance and Monitoring team from Head Office and a team
from urban poor branch- Kampala Water, before use. For materials like sand and aggregates,
the source had to be verified by the NWSC in case of deliveries in their absence. Materials
such as reinforcement bars had to be procured from approved hardware and concrete test
tubes had to be tested and their results submitted to the Project Manager. Finishes like wall
tiles; these had to be approved by the client before placement. Bricks and cement was
visually approved before use to avoid usage of inferior material.
• A significant number of the sites for the facilities have been located in low-lying areas
with very high water tables and this presented difficulties in construction of the sub-
structures.
• Lack of payment for water bills that have accrued from the use of the toilet facilities
delivered under Phase 1. This lack of payment of water bills is partly premised on the
decisions of who should pay for the accruing water bills
4.4 Conclusion
Construction projects involve a diversity of skills that comes from the diversity of
professions, specialists and suppliers that are involved in the process from inception to end.
Successful implementation of a project can only be achieved with good project management
practices in place. Failure of to have proper project management monitoring and control
systems can easily result in poor relationships, disputes and cost overruns on a project.
Efficient contract administration is achieved when the project manager and key stakeholders
are fully aware of their contractual obligations and follow the right procedures during project
implementation. This is where effective application of project management techniques comes
The project was successfully completed since the end objective was attained. The sanitation
were built up and functional. Furthermore, this project experienced no time and cost overrun.