Introduction
Introduction
Prepare by:
INTRODUCTION TO MANAGEMENT Megha Desai,
Civil Eng. Dept.
TECHNIQUES CHARUSAT
MANAGEMENT TECHNIQUES
• Bar Charts
• Critical Path Method (AON/AOA)
• Precedence Diagrams
• PERT (Programme Evaluation and Review Technique)
• GERT (Graphical Evaluation and review techniques)
• Line of Balance (LOB) Diagrams
1
09-Aug-18
BAR CHART
2
09-Aug-18
3
09-Aug-18
4
09-Aug-18
CRITICAL PATH
Critical Path of a Network
The critical path is the path through the project network in which none of the activities
have float (total float is zero).
It is the longest path on the network. The duration of project is fixed by the time taken
to complete the path through the network with the greatest total duration.
This path is known as critical path & activities on it are known as critical activities.
A delay in the critical path delays the project. Similarly, to accelerate the project it is
necessary to reduce the total time required for the activities in the critical path.
Dummy activity may be there in the critical path.
5
09-Aug-18
6
09-Aug-18
7
09-Aug-18
8
09-Aug-18