Schedule Performance
Schedule Performance
COST AND SCHEDULE PERFORMANCE Earned workhours or $ to date represent what was done.
This is called budgeted cost for work performed
The concepts discussed thus far provide a system for deter- (BCWP).
mining the percent complete of single work tasks or combi-
nations of tasks. The next challenge is to analyze the results Actual workhours or $ to date represent the cost incurred.
and to determine how well things are proceeding according This is called actual cost of work performed (ACWP).
A variation of this approach uses equivalent units for each subtask. In the example above, each subtask item would be given a unit
of measure that is an equivalent ton. For example, each beam would have an equivalent ton value determined as follows:
beam equivalent ton = (0.11 allowed credit) (520 tons) = 0.666 tons/beam
(859 beams)
14.3