2017 08 02 18 44 33 Pprpii Fin Esc PW5 (1) - 87
2017 08 02 18 44 33 Pprpii Fin Esc PW5 (1) - 87
2017 08 02 18 44 33 Pprpii Fin Esc PW5 (1) - 87
Format for Invitation for Tender (IFT) attached at the back of this Document is for
information only
TENDER DOCUMENT
FOR PROCUREMENT OF WORKS (INTERNATIONAL)
[enter here the nature of the works and physical services to be procured]
Table of Contents
CPTU-IMED PW5-OTM (International) iv
Section 1. Instructions to Tenderers...............................................................1
A. General ......................................................................................................... 1
1.Scope of Tender ............................................................................................... 1
2.Interpretation .................................................................................................... 1
3.Source of Funds ............................................................................................... 1
4.Corrupt, Fraudulent, Collusive or Coercive Practices ........................................ 2
5.Eligible Tenderers ............................................................................................. 2
6.Eligible Materials, Equipment and Associated Services .................................... 3
7.Site Visit ........................................................................................................... 3
B. Tender Document ........................................................................................ 3
8. Tender Document: General............................................................................. 3
9. Clarification of Tender Document .................................................................... 4
10.Pre-Tender Meeting ....................................................................................... 4
11.Addendum to Tender Document ..................................................................... 4
C. Qualification Criteria ........................................................................................... 5
12.Qualification .................................................................................................... 5
13.Joint Venture, Consortium or Association (JVCA) ........................................... 5
14.Subcontractor(s) ............................................................................................. 6
15.Domestic Preference ...................................................................................... 6
D. Tender Preparation ...................................................................................... 7
16.Only One Tender ............................................................................................ 7
17.Cost of Tendering ........................................................................................... 7
18.Issuance and Sale of Tender Document ......................................................... 7
19.Language of Tender ....................................................................................... 8
20.Contents of Tender ......................................................................................... 8
21.Tender Submission Letter and Bill of Quantities.............................................. 9
22.Alternatives ..................................................................................................... 9
23.Tender Prices, Discounts and Price Adjustment ............................................. 9
24.Tender Currency and Payments ................................................................... 11
25.Documents Establishing Eligibility of the Tenderer........................................ 11
26.Documents Establishing the Eligibility and Conformity of Materials, Equipment
and Services .............................................................................................. 11
27.Documents Establishing Technical Proposal ................................................ 11
28.Documents Establishing the Tenderer’s Qualification ................................... 11
29.Validity Period of Tender............................................................................... 11
30.Extension of Tender Validity and Tender Security ..................................... 12
31.Tender Security ............................................................................................ 12
32.Form of Tender Security ............................................................................... 13
33.Authenticity of Tender Security ..................................................................... 13
34.Return of Tender Security ............................................................................. 13
35.Forfeiture of Tender Security ........................................................................ 13
36.Format and Signing of Tender ...................................................................... 14
E. Tender Submission.................................................................................... 14
37.Sealing, Marking and Submission of Tender ................................................. 15
38.Deadline for Submission of Tender ............................................................... 15
39.Late Tender .................................................................................................. 16
40.Modification, Substitution or Withdrawal of Tender ....................................... 16
41.Tender Modification ...................................................................................... 16
42.Tender Substitution ....................................................................................... 16
43.Withdrawal of Tender .................................................................................... 16
F. Tender Opening and Evaluation ............................................................... 16
A. General
1.Scope of 1.1 The Employer, as indicated in the Tender Data Sheet (TDS) issues
Tender this Tender Document for the procurement of Works and associated
Services incidental thereto as specified in the TDS and as detailed
in Section 6: Bill of Quantities. The name of the Tender and the
number and identification of its constituent lot(s) are stated in the
TDS.
1.2 The successful Tenderer shall be required to execute the works and
physical services as specified in the General Conditions of Contract
3.Source of 3.1 The Employer has been allocated ‘public funds’ as indicated in
Funds the TDS and intends to apply a portion of the funds to eligible
payments under the Contract for which this Tender Document is
issued.
3.2 For the purpose of this provision, “public funds” means any
funds allocated to the Employer under Government budget, or
loan, grants and credits placed at the disposal of the Employer
through the Government by the Development Partners or foreign
states or organisations.
Document1 1
4.Corrupt, 4.1 The Government requires that Employer, as well as Tenderers and
Fraudulent, Contractors shall observe the highest standard of ethics during
Collusive or implementation of procurement proceedings and the execution of
Coercive Contracts under public funds.
Practices
4.2 The Government requires that Employer, as well as Tenderers and
Contractors shall, during the Procurement proceedings and the
execution of Contracts under public funds, ensure-
(a) strict compliance with the provisions of Section 64 of the
Public Procurement Act, 2006;
(b) abiding by the code of ethics as mentioned in the Rule127
of the Public Procurement Rules, 2008;
(c) that neither it’s any officer nor any staff nor any other
agents nor intermediaries working on its behalf engages in
any such practice as detailed in ITT Sub Clause 4.2(b).
4.3 Should any corrupt, fraudulent, collusive or coercive practice of any
kind come to the knowledge of the Employer, it will, in the first place,
allow the Tenderer to provide an explanation and shall, take actions
only when a satisfactory explanation is not received. Such decision
and the reasons thereof, shall be recorded in the record of the
procurement proceedings and promptly communicated to the
Tenderer concerned. Any communications between the Tenderers
and the Employer related to matters of alleged fraud or corruption
shall be in writing.
4.4 If corrupt, fraudulent, collusive or coercive practices of any kind
is determined by the Employer against any Tenderer alleged to
have carried out such practices, the Employer shall :
(a) exclude the concerned Tenderer from further participation
in the particular Procurement proceeding; or
(b) reject any recommendation for award that had been
proposed for that concerned Tenderer; or
(c) declare, at its discretion, the concerned Tenderer to be
ineligible to participate in further Procurement proceedings,
either indefinitely or for a specific period of time.
4.5 Tenderers shall be aware of the provisions on corruption,
fraudulence, collusion and coercion in Section 64 of the Public
Procurement Act, 2006 and Rule 127 of the Public Procurement
Rules, 2008.
5.Eligible 5.1 This Invitation for Tenders is open only to the pre-qualified
Tenderers Tenderers for this particular procurement proceeding.
5.2 To establish that the Tenderer continues to meet the criteria used at
the time of pre-qualification, the Tenderer shall provide updated
information on any assessed aspects including litigation history in
Tender Submission Letter (PW5-1) that changed from the time the
Tenderer was pre-qualified for this particular procurement
proceeding.
B. Tender Document
8.Tender 8.1 The Sections comprising the Tender Document are listed below,
Document: and should be read in conjunction with any Addendum issued
General under ITT Clause 11.
Section 1 Instructions to Tenderers (ITT)
Section 2 Tender Data Sheet (TDS)
Section 3 General Conditions of Contract (GCC)
Section 4 Particular Conditions of Contract (PCC)
Section 5 Tender and Contract Forms
Section 6 Bill of Quantities (BOQ)
Section 7 General Specifications
Section 8 Particular Specifications
Section 9 Drawings
Document1 3
8.2 The Employer will not take into consideration any Tender if the
Tender Document was not directly purchased from or issued by,
the Employer, or through its agent(s) as stated in the TDS.
9. Clarification 9.1 Tenderers requiring any clarification of the Tender Document shall
of Tender contact the Employer in writing at the Employer’s address indicated
Document in the TDS before two-third of the time allowed for preparation and
submission of Tender elapses.
9.3 The Employer shall respond in writing within five (5) working days
of receipt of any such request for clarification received under ITT
Sub Clause 9.1.
9.4 The Employer shall forward copies of its response to all those who
have purchased or have been issued with the Tender Document,
including a description of the enquiry but without identifying its source.
9.5 Should the Employer deem it necessary to revise the Tender
Document as a result of a clarification, it will do so following the
procedure under ITT Clause 11 and ITT Sub Clause 38.2.
10.Pre-Tender 10.1 To clarify issues and to answer questions on any matter arising in the
Meeting Tender Document, the Employer may, if stated in the TDS, hold a pre-
Tender Meeting at the place, date and time as specified in the TDS.
All pre-qualified Tenderers are encouraged and invited to attend the
meeting, if it is held.
10.2 Minutes of the pre-Tender meeting, including the text of the
questions raised and the responses given, together with any
responses prepared after the meeting, will be transmitted within
seven (7) days of holding the meeting to all those who purchased
or obtained the Tender Document and, to even those who did not
attend the meeting. Any revision to the Tender Document listed in
ITT Sub-Clause 8.1 that may become necessary as a result of the
pre-Tender meeting will be made by the Employer exclusively
through the issue of an Addendum pursuant to ITT Sub Clause 11
and not through the minutes of the Pre-Tender meeting.
10.3 Non-attendance at the Pre-Tender meeting will not be a cause for
disqualification of a Tenderer.
11.Addendum 11.1 At any time prior to the deadline for submission of Tenders, the
to Tender Employer, on its own initiative or in response to an inquiry in writing
Document from a Tenderer, having purchased the Tender Document, or as a
result of a Pre-Tender meeting may revise the Tender Document by
issuing an Addendum.
11.4 The Employer shall also ensure posting of the relevant Addenda with
the reference number and date on their websites including notice
boards, where the Employer had originally posted the IFTs.
11.5 Tenderers who have purchased or been issued with the Tender
Documents and, have not received any Addenda issued under ITT
Sub Clause 11.1 shall inform the Employer of the fact by fax, mail or
e-mail, before two- third of the time allowed for the submission of
Tender has elapsed.
C. Qualification Criteria
12.Qualificatio 12.1 Tenderers shall be able to abide by the professional and ethical
n standards set out in Section 64 of the Public Procurement Act,
2006 and Rule 127 of the Public Procurement Rules, 2008.
12.2 To establish that the Tenderer continues to meet the criteria used
at the time of pre-qualification, the Tenderer shall provide updated
information on any assessed aspects including litigation history
in Tenderer Information (PW5-2), JV Partner Information (PW5-3),
as applicable, Subcontractor Information (PW5-4), as applicable,
Personnel Information (PW5-5) and the Schedule of Equipments
that changed from the time the Tenderer was pre-qualified for this
particular procurement proceeding.
13.Joint 13.1 Tenderers may participate in the procurement proceedings in a Joint
Venture, Venture, Consortium or Associations (JVCA) as formed, or
Consortium alternately with an agreement supported by a Letter of Intent as
or intended; whichever assessed earlier at the time of pre-qualification.
Association
(JVCA) 13.2 Tenderers shall submit along with the Tender the copies of the JV
agreement or the Letter of Intent and the proposed JV agreement,
assessed at the time of pre-qualification.
Document1 5
13.3 Each partner of the JV shall be jointly and severally liable for the
execution of the Contract, all liabilities and ethical and legal
obligations in accordance with the Contract terms.
13.4 The JV shall nominate a Representative (partner-in-charge) who
shall have the authority to conduct all business for and on behalf of
any and all the partners of the JV during the tendering process and,
in the event the JV is awarded the Contract, during contract execution
including the receipt of payments for and on behalf of the JV.
13.5 The composition or the constitution of a JV formed, assessed, and
pre-qualified, shall not be allowed to be altered prior to signing of the
Contract.
13.6 Alteration of partners to the composition or constitution at a date later
than the signing of the Contract during execution shall be allowed by
the Employer only when any of such partners is found to be
incompetent or has serious difficulties which may impact the overall
implementation of the proposed Works, where the incoming partner
shall require to have qualifications higher than that of the outgoing
partner.
13.7 Each partner of the JV shall complete the JV Partner Information
(Form PW5-3) for submission with the Tender.
14.Subcontract 14.1 Tenderers may intend to subcontract an activity or part of the Works
or(s) to a Specialist Subcontractor, in which case such elements and the
proposed Subcontractor shall be clearly identified and its
qualifications supported by documents.
14.2 A Specialist Subcontractor may participate in more than one Tender,
but only in that capacity.
15. Domestic 15.1 If so specified in the TDS, a national Tenderer including Joint
Preference Venture comprising only national partners shall qualify for a
percentage margin of ‘domestic preference’ provided the
conditions set out in ITT Sub Clause 15.2 are fully met.
15.2 The requirements of a national Tenderer to qualify for ‘domestic
preference’ shall be :
(a) for an individual firm
D. Tender Preparation
16.Only One 16.1 Tenderers shall submit only one (1) Tender for each lot, either
Tender individually or as a JV. The Tenderer who submits or participates in
more than one (1) Tender in one (1) lot will cause all the Tenders of
that particular Tenderer to be considered non-responsive.
17.Cost of 17.1 Tenderers shall bear all costs associated with the preparation and
Tendering submission of its Tender, and the Employer shall not be responsible
or liable for those costs, regardless of the conduct or outcome of the
Tendering process.
18.Issuance and 18.1 The Employer shall make Tender Documents available immediately
Sale of to the pre-qualified Tenderers, requesting to obtain and willing to
Tender purchase at the corresponding price by the date the advertisement
Document has been published in the newspaper.
18.2 Full contact details, with mailing address, telephone and facsimile
numbers and electronic mail address, as applicable, of those to
whom the Tender Documents have been issued shall be
recorded with a reference number by the Employer or its agents.
18.3 There shall not be any pre-conditions whatsoever, for sale or
issuance of Tender Documents and, the sale or issuance of such
Document shall be permitted up to the day prior to the day of
deadline for the submission of Tender.
18.4 Tender Document posted in the designated website may also be
used by the Tenderer for submission of Tenders, if so permitted by
the Employer and specified in the TDS.
Document1 7
19.Language of 19.1 The Tender shall be written in the English language.
Tender Correspondences and documents relating to the Tender may be
written in English. Supporting documents and printed literature
furnished by the Tenderer that are part of the Tender may be in
another language, provided they are accompanied by an accurate
translation of the relevant passages in English, in which case, for
purposes of interpretation of the Tender, such translation shall
govern.
19.2 Tenderers shall bear all costs of translation to the governing
language and all risks of the accuracy of such translation.
20.Contents of 20.1 The Tender prepared by the Tenderers shall comprise the following:
Tender (a) the Tender Submission Letter (Form PW5-1) and Appendix
to Tender;
(b) Tenderer Information (Form PW5-2), as stated under ITT Sub
Clause 12.2;
(c) the priced Bill of Quantities and the completed Schedules for
each lot in accordance with ITT Clauses 21,23 and 24;
(d) Tender Security, as stated under ITT Clauses 31, 32 and 33.
(e) alternatives, if permissible, as stated under ITT Clause 22;
(f) written confirmation authorizing the signatory of the Tender to
commit the Tenderer, as stated under ITT Sub Clause 36.3;
(g) documentary evidence, establishing the origin of all Materials,
Equipment and services to be supplied under the Contract,
as stated under ITT Clause 26;
(h) documentary evidence, establishing that the Tenderer is
pre-qualified for this particular procurement proceeding, as
stated under ITT Sub Clause 5.1;
(i) documentary evidence, establishing the Tenderer’s
continued eligible and qualified status, as stated under ITT
Sub Clause 5 and 12;
(j) Technical Proposal describing work plan & method,
personnel, equipment and schedules, as stated under ITT
Clause 27; and
(k) any other document as specified in the TDS.
20.2 In addition to the requirements stated under ITT Sub Clause 20.1,
Tenders submitted by a JV or proposing a Specialised
Subcontractor shall include updates, if any, on :
(a) Joint Venture Agreement legally entered into in the Tenderer’s
Leading Partner’s country of origin, by all partners, as stated
under ITT Sub Clause 13.1;
or
(b) Letter of Intent along with the proposed agreement duly signed
by all partners of the intended JV and authenticated by an
authority of the Tenderer’s Leading Partner’s country of origin
with the declaration that it will execute the Joint Venture
Agreement in the event the Tenderer is successful, as stated
under ITT Sub Clause 13.1;
(c) the JV Partner Information (Form PW5-3), as stated under
ITT Sub Clause 12.2;
(d) the Specialist Subcontractor Information (Form PW5-4), as
stated under ITT Sub Clause 12.2.
23.3 The items quantified in the BOQ for which no unit rates or prices
have been quoted by the Tenderer will not be paid for, by the
Employer when executed and shall be deemed covered by the
amounts of other rates or prices in the BOQ and, it shall not be a
reason to change the Tender price.
23.4 The Employer may, if necessary, require the Tenderer to submit the
detail breakdown of the unit rates or prices quoted by the Tenderer
for the facilitation of the Tender proceedings.
Document1 9
23.5 The Tender price shall be calculated on the basis defined in the ITT
which is the unit rates or prices applied to Works proposed in the
priced BOQ of this Tender Document.
23.6 The price to be quoted in the Tender Submission Letter, as stated
under ITT Sub Clause 21.1, shall be the total price of the Tender,
excluding any discounts offered, only in case of being awarded
more than one lot, by the Tenderer.
23.7 Tenderers shall quote any unconditional discounts for being
awarded more than one lot if so specified in the TDS and the
methodology for application of discount in the Tender Submission
Letter as stated under ITT Sub Clause 21.1.
23.8 If so indicated under ITT Sub Clause 23.7, Tenders are being invited
for individual lots or for any combination of lots. Tenderers wishing
to offer any price reduction for the award of more than one lot shall
specify in their Tender the price reductions applicable to each lot, or
alternatively, to any combination of lots within the package. Price
reductions or discounts will be submitted as stated under ITT Sub
Clause 23.1, provided the Tenders for all lots are submitted and
opened together.
23.9 All kinds of applicable taxes ,customs duties, fees, levies, VAT and
other charges payable by the Contractor under the Contract, or for
any other causes, as of the date twenty-eight (28) days prior to the
deadline for submission of Tenders, shall be included in the unit
rates and prices and the total Tender price submitted by the
Tenderer.
23.10 Unless otherwise provided in the TDS and the PCC, the price of a
Contract shall be fixed in which case the unit rates or prices may not
be modified in response to changes in economic or commercial
conditions.
23.11 If so indicated under ITT Sub Clause 23.10, Tenders are being
invited with a provision for price adjustments. The unit rates or prices
quoted by the Tenderer are subject to adjustment during the
performance of the Contract in accordance with the provisions of
GCC Clause 74 and, in such case the Employer shall provide the
indexes and weightings or coefficients in Appendix to the Tender
for the price adjustment formulae specified in the PCC.
23.12 The Employer may require the Tenderer to justify its proposed
indexes, if any of those as stated under ITT Sub Clause 23.11 are
instructed to be quoted by the Tenderer in Appendix to the Tender.
23.13 The formulas, indexes, coefficients and procedures to be followed
as referred to in the PCC shall be used to determine whether
economic or commercial conditions have changed during
performance of the Contract to significant degree to justify a price
adjustment and to identify the amount of increase and the frequency
with which price adjustments shall be implemented.
23.14 The price adjustment stated under ITT Sub Clause 23.11 shall be
dealt with in accordance with the provisions set out in this Tender
Document.
24.1 The currency of the Tender shall be either in USD or GBP or EUR
or JPY and/or Bangladesh Taka as specified in the TDS.
26.Documents 26.1 Tenderers shall submit documentary evidence to establish the origin
Establishing of all Materials, Equipment and services to be supplied under the
the Eligibility Contract as stated under ITT Clause 6.
and 26.2 To establish the conformity of the Materials, Equipment and services
Conformity of to be supplied under the Contract, the Tenderer shall furnish, as part
Materials, of its Tender, the documentary evidence (which may be in the form
Equipment of literature, specifications and brochures, drawings or data) that
and Services these conform to the technical specifications and standards
specified in Section 7, General Specifications and Section 8,
Particular Specifications.
27.Documents 27.1 Tenderers shall furnish a Technical Proposal including a statement
Establishing of work methods, equipment, personnel, schedule and any other
Technical information as stipulated in TDS, in sufficient detail to demonstrate
Proposal the adequacy of the Tenderer’s proposal to meet the work
requirements and the completion time.
28.Documents 28.1 To establish that the Tenderer continues to meet the criteria used
Establishing at the time of pre-qualification, the Tenderer shall provide
the updated information on any assessed aspects in Tenderer
Tenderer’s Information (PW5-2), JV Partner Information (PW5-3), as
Qualification applicable, Subcontractor Information (PW5-4), as applicable,
Personnel Information (PW5-5) and the Schedule of Equipments
that changed from the time the Tenderer was pre-qualified for this
particular procurement proceeding.
28.2 If ‘domestic preference’ applies as stated under ITT Sub Clause
15.1, the national Tenderers, individually or in Joint Ventures,
applying for eligibility for ‘domestic preference’ shall provide all
information required to satisfy the criteria for eligibility as stated
under ITT Sub Clause 15.2.
29.Validity 29.1 Tender Validities shall be determined on the basis of the complexity
Period of of the Tender and the time needed for its examination, evaluation,
Tender approval of the Tender and issuance of the Notification of Award.
Document1 11
29.2 Tenders shall remain valid for the period specified in the TDS after
the date of Tender submission deadline prescribed by the Employer,
as stated under ITT Sub Clause 29.1. A Tender valid for a period
shorter than that specified will be considered non-responsive by the
Employer.
30.2 The request for extension of Tender Validity period shall state the
new date of the validity of the Tender.
30.3 The request from the Employer and the responses from the
Tenderers will be made in writing.
30.6 If the Tenderers are not consenting in writing to the request made
by the Employer as stated under ITT Sub Clause 30.2, its Tender
shall not be considered in the subsequent evaluation.
31.Tender 31.1 Tender Securities and its amounts shall be determined sufficient to
Security discourage the submission of frivolous and irresponsible Tenders
shall be rounded fixed amount and, shall not be stated as a precise
percentage of the estimated total Contract price.
31.3 If the Tender is a Joint Venture, the Tenderer shall furnish as part of
its Tender, in favour of the Employer or as otherwise directed on
account of the title of the existing or intended JV or any of the
partners of that JV, a Tender Security in original form and in
currency of the amount as stated under ITT Sub Clause 31.2.
Document1 13
(a) withdraws its Tender after opening of Tenders but within the
validity of the Tender as stated under ITT Clause 29 and 30;
or
(b) refuses to accept a Notification of Award as stated under ITT
Sub Clause 60.3 ;
or
(c) fails to furnish Performance Security as stated under ITT Sub
Clause 61.2 and 61.3 ;
or
(d) refuses to sign the Contract as stated under ITT Sub Clause
65.2;
or
(e) does not accept the correction of the Tender price following
the correction of the arithmetic errors as stated under ITT
Clause 51.
36.Format and 36.1 The Tenderer shall prepare one (1) original of the documents
Signing of comprising the Tender as described in ITT Clause 20 and clearly
Tender mark it “ORIGINAL.” In addition, the Tenderer shall prepare the
number of copies of the Tender, as specified in the TDS and clearly
mark each of them “COPY.” In the event of any discrepancy
between the original and the copies, the ORIGINAL shall prevail.
36.2 Alternatives, if permitted in accordance with ITT Clause 22, shall be
clearly marked “Alternative”.
36.3 The original and each copy of the Tender shall be typed or written
in indelible ink and shall be signed by the Person duly authorized to
sign on behalf of the Tenderer. This authorization shall consist of a
written authorization and shall be attached to the Tender
Submission Letter (Form PW5-1). The name and position held by
each Person(s) signing the authorization must be typed or printed
below the signature. All pages of the original and of each copy of the
Tender, except for un-amended printed literature, shall be
numbered sequentially and signed or initialled by the person signing
the Tender.
36.4 In case of JV, the application of the provisions as stated under ITT
Sub Clause 36.3 shall extend up to each partner of that existing or
intended JV.
36.5 Any interlineations, erasures, or overwriting will be valid only if they
are signed or initialled by the Person(s) signing the Tender.
36.6 Person(s) signing the Tender shall describe his or her name,
address, position along with his or her national Identification
Number, if any.
E. Tender Submission
38.Deadline for 38.1 Tenders shall be delivered to the Employer at the address
Submission of specified in the TDS and no later than the date and time specified
Tender in the TDS.
Document1 15
38.4 The Employer shall ensure that the Tenders received at the
secondary place(s) are hand-delivered at the primary place as
stated under ITT Sub Clause 38.1 before the time specified in the
TDS; but in no case later than THREE (3) HOURS after the
deadline for submission of Tenders at the secondary place(s) in
case of MULTIPLE DROPPING.
39. Late Tender 39.1 Any Tender received by the Employer after the deadline for
submission of Tenders as stated under ITT Sub Clause 38.1 shall
be declared LATE, excluded, and returned unopened to the
Tenderer.
40.Modification, 40.1 Tenderers may modify, substitute or withdraw its Tender after it
Substitution or has been submitted by sending a written notice duly signed by the
Withdrawal of authorized signatory and properly sealed, and shall include a copy
Tender of the authorization confirmed by an affidavit authenticated by an
authority of the Tenderer’s Leading Partner’s country of origin;
provided that such written notice including the affidavit is received
by the Employer prior to the deadline for submission of Tenders
as stated under ITT Clause 38.
41.Tender 41.1 Tenderers shall not be allowed to retrieve its original Tender, but
Modification shall be allowed to submit corresponding modification to its
original Tender marked as “MODIFIFICATION”.
42.Tender 42.1 Tenderers shall not be allowed to retrieve its original Tender, but
Substitution shall be allowed to submit another Tender marked as
“SUBSTITUTION”.
43.Withdrawal of 43.1 Tenderers shall be allowed to withdraw its Tender by a Letter of
Tender Withdrawal marked as “WITHDRAWAL”.
44.3 Persons not associated with the Tender may not be allowed to
attend the public opening of Tenders.
44.7 Ensuring that only the correct (M), (S), (A), (O) envelopes are
opened, details of each Tender will be dealt with as follows:
(a) the Chairperson of the Tender Opening Committee will
read aloud each Tender and record in the Tender Opening
Sheet (TOS) :
Document1 17
(i) the name and address of the Tenderer;
(ii) state if it is a withdrawn, modified, substituted or
original Tender;
(iii) the Tender price;
(iv) the number of initialled corrections;
(v) any discounts;
(vi) any alternatives;
(vii) the presence or absence of any requisite Tender
Security; and
(viii) such other details as the Employer, at its discretion,
may consider appropriate.
(b) only discounts and alternatives read aloud at the Tender
opening will be considered in evaluation.
(c) all pages of the original version of the Tender, except for
un-amended printed literature, will be initialled by members
of the Tender Opening Committee.
45.Evaluation of 45.1 Tenders shall be examined and evaluated only on the basis of the
Tenders criteria specified in the Tender Document.
46.Evaluation 46.1 The TEC may consider a Tender as responsive in the Evaluation,
Process only if it is submitted in compliance with the mandatory
requirements set out in the Tender Document. The evaluation
process should begin immediately after tender opening following
four broad steps:
Document1 19
authentic, if the Tender is “WITHDRAWN”
“SUBSTITUTION” or “MODIFICATION’, in accordance with
ITT Clause 40;
(m) verification of the status of claims, arbitration and other
litigation cases of the Tenderer as stated under ITT Clause
5 and ITT Clause 25;
(n) verification of the validity and authenticity of the Tender
Security in the form of Bank Guarantee using the standard
format (Form PW5-6) furnished in Section 5: Tender and
Contract Forms, issued by an internationally reputable
Bank which has a correspondent Bank located in
Bangladesh as attached with the Tender Submission Letter
(Form PW5-1), in order to check the compliance of the
instructions as stated under ITT Clauses 30,31,32 and 33;
48.Technical 48.1 Secondly, the TEC will examine the adequacy and authenticity of
Examination the documentary evidence which may follow the order below.
and 48.2 The TEC will evaluate the technical aspects of the Tender
Responsivenes submitted as stated under ITT Clauses 25, 26 and 27, to confirm
s that all mandatory requirements have been met.
48.3 The TEC will further examine the terms and conditions specified
in Section 7: General Specifications and Section 8: Particular
Specifications of the Tender Document have been met without
any material deviation or reservation.
48.4 The TEC’s determination of a Tender’s responsiveness is to be
based on the documentary evidence as stated under ITT Clause
20 without recourse to extrinsic evidence.
48.5 Information contained in a Tender submission that was not
requested in the Tender Document shall not be considered in
evaluation of the Tender.
48.6 A Tender shall be considered responsive in the evaluation, only
when it is submitted in compliance with the mandatory
requirements set out in the Tender Document without material
deviation or reservation.
48.7 If, after the examination of the terms and conditions and the
technical aspects of the Tender, the TEC determines that the
Tender is not responsive in accordance with ITT Clause 20, it
shall consider the Tender non-responsive.
48.8 If a Tender is not responsive to the mandatory requirements set
out in the Tender Document, it shall be considered non-
responsive by the TEC and will not subsequently be made
responsive by correction of the material deviation or reservation.
48.9 A material deviation or reservation is one that:
(a) affects in any substantial way the scope, quality, or
performance of the Works; or
(b) limits in any substantial way, or is inconsistent with the
Tender Document, the Employer’s rights or the Tenderer’s
obligations under the Contract; or
(c) if rectified would unfairly affect the competitive position of
other Tenderers presenting responsive Tenders.
49.Clarification on 49.1 The TEC may ask Tenderers for clarification of their Tenders,
Tender including breakdowns of unit rates or prices, in order to facilitate
the examination and evaluation of Tenders. The request for
clarification by the TEC and the response from the Tenderer shall
be in writing, and Tender clarifications which may lead to a change
in the substance of the Tender or in any of the key elements of the
Tender pursuant to ITT Sub Clause 48.9, will neither be sought nor
be permitted.
49.2 Changes in the Tender price shall also not be sought or permitted,
except to confirm the correction of arithmetical errors discovered
by the TEC in the evaluation of the Tenders, as stated under ITT
Sub Clause 51.1.
49.3 Any request for clarifications by the TEC shall not be directed
towards making an apparently non-responsive Tender
responsive and reciprocally the response from the concerned
Tenderer shall not be articulated towards any addition,
alteration or modification to its Tender.
Document1 21
50.Restrictions on 50.2 Tenderers shall not seek to influence in anyway, the
Disclosure of examination and evaluation of the Tenders.
Information
Relating to 50.3 Any effort by a Tenderer to influence a Employer in its decision
Procurement concerning the evaluation of Tenders, Contract awards may
Process result in the consideration its Tender non-responsive as well as
further action in accordance with Section 64 (5) of the Public
Procurement Act, 2006.
50.4 All clarification requests shall remind Tenderers of the need for
confidentiality and that any breach of confidentiality on the part
of the Tenderer may result in their Tender being disqualified.
51.Correction of 51.1 Provided that the Tender is responsive, the TEC shall correct
Arithmetical arithmetical errors on the following basis:
Errors
(a) if there is a discrepancy between the unit price and the
line item total price that is obtained by multiplying the unit
price and quantity, the unit price will prevail and the line
item total price shall be corrected, unless in the opinion of
the TEC there is an obvious misplacement of the decimal
point in the unit price, in which case the total price as
quoted will govern and the unit price will be corrected; and
(b) if there is an error in a total corresponding to the addition
or subtraction of subtotals, the subtotals shall prevail and
the total shall be corrected; and
(c) if there is a discrepancy between words and figures, the
amount in words shall prevail, unless the amount
expressed in words is related to an arithmetic error, in
which case the amount in figures shall prevail subject to
(a) and (b) above.
52. Conversion to 52.1 For evaluation and comparison purposes, the currency of the
Single Currency Tender shall be converted into Bangladesh Taka currency.
52.2 The exchange rate for conversion, as stated under ITT Sub
Clause 52.1, to be used in arriving at the Bangladesh Taka
currency equivalent shall be the selling rate quoted by the
source being Bangladesh Bank on the date of opening of the
Tenders.
53.Financial 53.1 Thirdly the TEC will evaluate each Tender that has been
Evaluation determined, up to this stage of the evaluation, to be responsive to
the mandatory requirements set out in the Tender Document.
53.5 If so indicated in the ITT Sub Clause 23.7 the Employer may
award one or multiple lots to one Tenderer following the
methodology specified in ITT Sub Clause 53.6.
Document1 23
53.7 If the lowest Evaluated Tender is significantly below the official
estimated cost or unbalanced as a result of front loading in the
opinion of the TEC, the TEC may require the Tenderer to produce
detailed breakdown of unit price or rates for any or all items of the
BOQ, to demonstrate the internal consistency of those prices with
the construction methods and schedule proposed. After
evaluation of the breakdown of the unit price or rates, taking into
consideration the schedule of estimated Contract payments, the
Employer may require that the amount of the Performance
Security set forth in ITT Sub Clause 61.2 be increased at the
expenses of the Tenderer to a level as stated under ITT Sub
Clause 61.3 sufficient to protect the Employer against financial
loss in the event of default by such Tenderer during Contract
implementation, if awarded the Contract.
54.Price 54.1 The TEC will compare all responsive Tenders to determine the
Comparison lowest-evaluated Tender, in accordance with ITT Clause 53.
54.2 The TEC shall apply percent margin of preference for national
Tenderer, if applicable, as stated under ITT Sub Clause 15.3; only
for ranking.
54.3 For the purpose of comparison of the Tenders only, the margin
of ‘domestic preference’ shall be applied following the
procedures as stated under ITT Sub Clause 54.4, 54.5 and 54.6.
54.7 In the extremely unlikely event that there is a tie for the lowest
evaluated price, the Tenderer with the superior past performance
with the Employer shall be selected, whereby factors such as
delivery period, quality of Works delivered, complaints history
and performance indicators could be taken into consideration.
54.8 In the event that there is a tie for the lowest price and none of the
Tenderers has the record of past performance with the Employer
as stated under ITT Sub Clause 54.7, then the Tenderer shall be
CPTU-IMED PW5-OTM (International) 24
selected, subject to firm confirmation through the Post-
qualification process, after consideration as to whether the
Tenderer has demonstrated in its Tender superior past
performance with the other Procuring Entities or a more efficient
work programme and work methodology.
54.9 The successful Tenderer as stated under ITT Sub Clauses 54.1,
54.7 and 54.8 shall not be selected through lottery under any
circumstances.
55. Negotiations 55.1 No negotiations shall be held during the Tender evaluation or
award with the lowest or any other Tenderer.
55.2 The Employer through the TEC may, however, negotiate with
the lowest evaluated Tenderer with the objective to reduce the
Contract price by reducing the scope of works or a reallocation
of risks and responsibilities, only when it is found that the
lowest evaluated Tender is significantly higher than the official
estimated cost; the reasons for such higher price being duly
investigated.
56.2 The TEC shall contact the references given by Tenderers about
their previous working experience to verify, if necessary,
statements made by them in their Tender and to obtain the most
up-to-date information available concerning the Tenderers.
56.3 The TEC may visit the premises of the Tenderer as a part of the
qualification process, if practical and appropriate, to verify
information contained in its Tender particularly when evaluating
Tenders in respect of high value or complex Works projects.
56.4 The objective of any visit under IITT Sub Clause 56.3 shall be
limited to a general and visual inspection of the Tenderer’s
facilities and its plant and equipment, and there shall be no
discussion concerning the Tender or its evaluation with the
Tenderer during such visit(s).
Document1 25
56.5 In the event that the Tenderer with lowest evaluated Tender price
fails the post-qualification, the TEC shall make a similar
determination for the Tenderer offering the next lowest evaluated
Tender price and so on from the remaining responsive Tenders,
provided that,
(a) such action shall only be taken if the evaluated costs of the
Tenders under consideration are acceptable to the
Employer;
(b) when the point is reached whereby the evaluated costs of
the remaining responsive Tenders are significantly higher
than that of the official estimate, or the market price, the
Employer proceed for re-Tendering, using a revised Tender
Document, where necessary, designed to achieve a more
successful result.
57. Rejection of 57.1 The Employer may, in the circumstances as stated under ITT Sub
All Tenders Clause 57.2 , reject all Tenders following recommendations from
the Tender Evaluation Committee (TEC) only after the approval
of such recommendations by the Head of the Procuring Entity.
58.Informing 58.1 Notice of the rejection will be given promptly within seven (7) days
Reasons for of decision taken by the Employer to all Tenderers and, the
Rejection Employer will, upon receipt of a written request, communicate to
any Tenderer the reason(s) for its rejection but is not required to
justify those reason(s).
G. Contract Award
59. Award Criteria 59.1 The Employer shall award the Contract to the Tenderer whose
offer is responsive to all the requirements of the Tender
Document and that has been determined to be the lowest
evaluated Tender, provided further that the Tenderer is
determined to be Post-qualified in accordance with ITT Clouse
56.
60.Notification of 60.1 Prior to the expiry of the Tender Validity period and within
Award seven (7) working days of receipt of the approval of the award
by the Approving Authority, the Employer shall issue the
Notification of Award (NOA) to the successful Tenderer.
Document1 27
60.5 The Notification of Award establishes a Contract between the
Employer and the successful Tenderer and the existence of a
Contract is confirmed through the signature of the Contract
Document that includes all agreements between the Employer
and the successful Tenderer.
62.Form and 62.1 The Performance Security, as stated under ITT Clause 61,
Time Limit for shall be in the form of an irrevocable Bank Guarantee issued
Furnishing of by an internationally reputable Bank which has a correspondent
Performance Bank located in Bangladesh, in the format (Form PW5-9),
Security acceptable to the Employer.
65.Contract 65.1 At the same time as the Employer issues the Notification of
Signing Award (NOA), the Employer will send the draft Contract
Agreement and all documents forming the Contract to the
successful Tenderer.
68.Right to 68.1 Any Tenderer has the right to complain if it has suffered or likely
Complain to suffer loss or damage due to a failure of a duty imposed on
the Employer to fulfil its obligations in accordance with Section
29 of the Public Procurement Act 2006 and Part 12 of Chapter
Three of the Public Procurement Rules, 2008.
Document1 29
68.3 The pre-qualified Tenderer shall submit his or her complaint in
writing within seven (7) calendar days of becoming aware of the
circumstances giving rise to the complaint.
68.4 In the first instance, the pre-qualified Tenderer shall submit his
or her complaint to the Employer who issued the Tender
Document.
68.5 The place and address for the first stage in the submission of
complaints to the administrative authority is provided in the TDS.
ITT Amendments of, and Supplements to, Clauses in the Instructions to Tenderers
Clause
A. General
ITT 1.1 The Employer is [state name of Employer] represented by [state name of representative]
Tender Ref:
Lot No(s):
[if there is more than one(1) lot, individual lots are to be identified in conformity with Section 6: Bill of Quantities]
ITT 6.1 Materials, Equipments and associated services from the following countries are not
eligible:
B. Tender Document
ITT 8.2 The following are authorised agents of the Employer for the purpose of issuing the Tender
Document:
Agent’s Name:
Address:
Telephone No.:
Fax No.:
e-mail address:
[if not applicable, please specify “None”. If there is more than one (1) Agent, then list all Agent’s names and contact
details]
Document1 31
ITT 9.1 For clarification of Tender Document purposes only, the Employer’s address is:
Attention:
Address:
Telephone:
Fax No.:
e-mail address:
ITT 10.1 A Pre-Tender meeting shall not be held
or
A Pre- Tender meeting shall be held at
Address:
Time & Date:
C. Qualification Criteria
ITT 14.4 The Nominated Subcontractor(s) named [insert name(s)] shall execute the following specific
components of the proposed Works:
[state the components of the proposed works ; if not applicable state ‘none’]
ITT 15.1 Domestic Preference [shall/shall not] be applicable for eligible national Tenderers
[delete as appropriate]
[Domestic Preference shall not be mandatory and again any relaxation will require recommendation of the CCEA]
D. Tender Preparation
ITT The Tenderer shall submit with its Tender the following additional documents:
20.1(k)
[in case of purchase of capital equipment by the Contractor as part of the overall Contract, a Performance Statement
of the capital equipment in Bangladesh may be necessary and may be requested. if no other documents are required
then specify “none”]
[if alternatives are permitted then outline the method and evaluation criteria for such alternatives ]
[delete as appropriate]
ITT 23.7 Tenders are being invited for an individual lot.
OR
Tenders are being invited for a combination of lots.
[mention the Lot Numbers above for Tenders that anticipate the award of more than one Contract and state that
Tenderers can submit Tender(s) for one or more lots in the package. Tenderers will indicate in their Tender any
discounts which they offer ONLY for the award of more than one Contract]
ITT The prices quoted by the Tenderer shall be fixed for the duration of the Contract.
23.10 OR
The prices quoted by the Tenderer shall be adjustable applying the following formulae and
the weightings or coefficients:
[ delete as appropriate. if prices shall be adjustable, the methodology for adjustment including the formulae to be
applicable should be specified]
Example:
ITT 24.1 The currency of the Tender shall be USD/GBP/EU R/JPY and/or
BangladeshTaka
deleteif not appropriate
delete not appropriat e
[denominate currency, as appropriate, for those inputs to the Works clearly identified and specified in the Bill of
Quantities that a Tenderer is expected to supply from outside Bangladesh. The Employer may refer to Guidance Notes
for customizing the BoQ]
ITT 24.4 The currency of the payments shall be USD/GBP/EU R/JPY and/or
BangladeshTaka
deleteif not appropriate
delete not appropriat e
ITT 27.1 The required Technical Proposal shall include the following additional information:
ITT 29.2 The Tender Validity period shall be [state number] days.
Document1 33
ITT 31.2 The amount of the Tender Security shall be USD/GBP/EU R/JPY [insert amount] and/or
delete not appropriat e
BangladeshTaka
[insert amount]
deleteif not appropriate
[for more than one lot in a package, the Tender Security for each lot should be mentioned separately. The
amount of Tender Security should be expressed as a fixed amount not exceeding three(3) percent of the
official estimated cost for each lot in all cases]
In addition to the original of the Tender, [state number] copies shall be submitted.
ITT 36.1 [usually only two copies are needed, ask for more only if they are essential]
E. Tender Submission
ITT The inner and outer envelopes shall bear the following additional identification marks:
37.2(e)
[indicate any markings that are required on inner and outer envelopes ]
ITT 38.1 For Tender submission purposes only, the Employer’s address is:
Attention:
Address:
ITT 38.3 For Tender submission purposes only, the Employer’s address is:
in case of MULTIPLE DROPPING state below the addresses of the PRIMARY PLACE and SECONDARY PLACES
with Time and Date]
Attention:
Address (PRIMARY PLACE ):
[ the deadline for submission of Tenders at the Secondary Places shall be fixed as such that the Tenders received
at the Secondary Places can be hand-delivered to Primary Place within three (3) hours but essentially before the
deadline for submission at the Primary Place]
The deadline for the hand-delivering of the Tenders at the PRIMARY PLACE is:
Time & Date:
ITT 38.4
[must be within three(3) hours after the deadline for submission of Tenders at the SECONDARY PLACES but
essentially before the deadline for submission at the Primary Place]
Address:
Time & Date:
G. Contract Award
ITT 61.2 The amount of Performance Security shall be [insert percentage] percent of the Contract
BangladeshTaka
price in the currency of USD/GBP/EU R/JPY and/or .
deleteif not appropriate
delete not appropriat e
[ten (10) percent of the Contract price if advance payment is made, and the total percentage of Retention and
Performance Security may not exceed ten (10) percent , if no advance payment has been effected. Maximum twenty
five (25) percent of the total Contract price in case the Tender is significantly below the official estimated cost or
unbalanced as a result of front loading]
ITT 68.5 The name and address of the office where complaints to the Employer under Rule 57 are
to be submitted is:
Name:
Address:
Fax No.:
e-mail address:
Document1 35
Section 3. General Conditions of Contract
A. General
1. Definitions 1.1 In the Conditions of Contract, which include Particular Conditions
and these General Conditions, the following words and
expressions shall have the meaning hereby assigned to them.
Boldface type is used to identify the defined terms:
(a) Approving Authority means the authority which, in
accordance with the Delegation of Financial powers,
approves the award of Contract for the Procurement of
Goods, Works and Services.
(b) Act means The Public Procurement Act, 2006 (Act 24 of
2006).
(c) Adjudicator is the expert appointed jointly by the Employer
and the Contractor to resolve disputes in the first instance,
as provided for in GCC Sub Clause 100.2.
(d) Bill of Quantities (BOQ) means the priced and completed
Bill of Quantities forming part of the Contract defined in GCC
Clause 63.
(e) Compensation Events are those defined in GCC Clause
72.
(f) Competent Authority means the authority that gives
decision on specific issues as per delegation of
administrative and/or financial powers.
(g) Completion Certificate means the Certificate issued by the
Engineer as evidence that the Contractor has executed the
Works and Physical services in all respects as per design,
drawing, specifications and Conditions of Contract.
(h) Completion Date is the actual date of completion of the
Works and Physical services certified by the Engineer, in
accordance with GCC Clause 83.
(i) Contract means the Contract Agreement, the Notification
of Award, Tender Submission Letter, these Conditions, the
Specification, the Drawings, the Schedules, the Priced Bill
of Quantities, and the further Documents (if any ) which are
listed in the Contract Agreement or in the Notification of
Award.
(j) Contract Agreement means the Agreement entered into
between the Employer and the Contractor, together with the
Contract Documents referred to therein, including all
attachments, appendices, and all documents incorporated
by reference therein to execute, complete, and maintain the
Works.
(k) Contract Documents means the documents listed in GCC
Clause 6, including any amendments thereto.
Document1 37
care on the part of the Contractor; such events may include,
but not be limited to, acts of the Government in its sovereign
capacity, wars or revolutions, fires, floods, epidemics,
quarantine restrictions, and freight embargoes or more as
included in GCC Clause 88.;
(z) GCC means the General Conditions of Contract.
(aa) Government means the Government of the People’s
Republic of Bangladesh.
(bb) Goods mean the Contractor’s Equipment, Materials, Plant
and Temporary Works, or any of them as appropriate.
(cc) "Head of the Procuring Entity" means the Secretary of a
Ministry or a Division, the Head of a Government
Department or Directorate; or the Chief Executive, by
whatever designation called, of a local Government agency,
an autonomous or semi-autonomous body or a corporation,
or a corporate body established under the Companies Act;
(dd) Intended Completion Date is the date calculated from the
Commencement Date as specified in the PCC, on which it
is intended that the Contractor shall complete the Works
and Physical services as specified in the Contract and may
be revised only by the Engineer by issuing an extension of
time or an acceleration order.
(ee) Materials means things of all kinds other than Plant
intended to form or forming part of the Permanent Works,
including the supply-only materials, if any, to be supplied by
the Contractor under the Contract.
(ff) Month means calendar month.
(gg) Original Contract Price is the Contract Price stated in the
Employer’s Notification of Award and further clearly
determined in the PCC.
(hh) Permanent works means the permanent works to be
executed by the Contractor under the Contract.
(ii) PCC means the Particular Conditions of Contract.
(jj) Plant means the apparatus, machinery and other
equipment intended to form or forming part of the
Permanent Works, including vehicles purchased for the
Employer and relating to the construction of the Works and
Physical services.
(kk) Provisional Sums means amounts of money specified by
the Employer in the Bill of Quantities which shall be used, at
its discretion, for payments to Nominated Subcontractor(s)
and for meeting other essential expenditures under the
Contract pursuant to GCC Sub Clause 80.
(ll) Retention Money means the accumulated retention
moneys which the Employer retains under GCC Clause 75.
(mm) Schedules means the document(s) entitled schedules,
completed by the Contractor and submitted with the Tender
Submission Letter, as included in the Contract. Such
2. Interpretation 2.1 In interpreting the GCC, singular also means plural, male also
means female or neuter, and the other way around. Headings in
the GCC shall not be deemed part thereof or be taken into
consideration in the interpretation or construance of the Contract.
Words have their normal meaning under the language of the
Contract unless specifically defined.
Document1 39
2.2 Entire Agreement
The Contract constitutes the entire agreement between the
Employer and the Contractor and supersedes all
communications, negotiations and agreements (whether written
or verbal) of parties with respect thereto made prior to the date of
Contract Agreement; except those stated under GCC Sub Clause
6.1(j).
2.4 Severability
If any provision or condition of the Contract is prohibited or
rendered invalid or unenforceable, such prohibition, invalidity or
unenforceability shall not affect the validity or enforceability of any
other provisions and conditions of the Contract.
3.3 A Party may change its address for notice hereunder by giving the
other Party notice of such change to the address.
4. Governing Law 4.1 The Contract shall be governed by and interpreted in accordance
with the laws of the People’s Republic of Bangladesh.
5.2 The Contractor shall bear all costs of translation to the governing
language and all risks of the accuracy of such translation.
6. Documents 6.1 The following documents forming the Contract shall be interpreted
Forming the in the following order of priority:
Contract and
(a) the signed Contract Agreement (Form PW5-8);
Priority of
Documents (b) the Notification of Award (PW5-7);
(c) the completed Tender and the Appendix to the Tender;
(d) the Particular Conditions of Contract;
(e) the General Conditions of Contract;
(f) the Technical Specifications;
(g) the General Specifications;
(h) the Drawings;
(i) the priced Bill of Quantities and the Schedules; and
(j) any other document listed in the PCC forming part of the
Contract.
7. Contract 7.1 The parties shall enter into a Contract Agreement within twenty
Agreement eight (28) days from the date of issuance of the Notification of
Award (NOA). The costs of stamp duties and similar charges, if
any, designated by the applicable law in connection with entry into
the Contract Agreement, shall be borne by the Employer.
8. Assignment 8.1 Neither the Contractor nor the Employer shall assign, in whole or
in part, its obligations under the Contract; except with the
Employer’s prior written approval.
9. Eligibility 9.1 The Contractor and its Subcontractor(s) shall have the nationality
of a country other than that specified in the PCC.
Document1 41
11. Confidential 11.1 The Employer and the Contractor shall keep confidential and shall
Details not, without the written consent of the other party hereto, divulge
to any third party any documents, data, or other information
furnished directly or indirectly by the other party hereto in
connection with the Contract, whether such information has been
furnished prior to, during or following completion or termination of
the Contract. Notwithstanding the above, the Contractor may
furnish to its Subcontractor such documents, data, and other
information it receives from the Employer to the extent required
for the Subcontractor to perform its work under the Contract, in
which event the Contractor shall obtain from such Subcontractor
an undertaking of confidentiality similar to that imposed on the
Contractor under GCC Clause 11.
11.2 The Employer shall not use such documents, data, and other
information received from the Contractor for any purposes
unrelated to the Contract. Similarly, the Contractor shall not use
such documents, data, and other information received from the
Employer for any purpose other than the design, construction, or
other work and services required for the performance of the
Contract.
11.3 The obligations of a party under GCC Sub Clauses 11.1 and 11.2
above, however, shall not apply to information that: the Employer
or Contractor needs to share with institutions participating in the
financing of the Contract; now or hereafter enters the public
domain through no fault of that party; can be proven to have been
possessed by that party at the time of disclosure and which was
not previously obtained, directly or indirectly, from the other party;
or otherwise lawfully becomes available to that party from a third
party that has no obligation of confidentiality.
11.4 The above provisions of GCC Clause 11 shall not in any way
modify any undertaking of confidentiality given by either of the
parties hereto prior to the date of the Contract in respect of the
Works or any part thereof.
12. Joint Venture, 12.1 If the Contractor is a Joint Venture, Consortium, or Association
Consortium or (JVCA ),
Association
(a) each partner of the JV shall be jointly and severally liable for
(JVCA)
all liabilities and ethical or legal obligations to the Employer
for the performance of the Contract;
(b) the JV partners shall nominate a representative who shall
have the authority to conduct all business including the
receipt of payments for and on behalf of all partners of the
JV;
(c) in the event of a dispute that results in legal action against all
partners of the JV, if they are available and if only one
partner is available, then that partner alone shall answer on
behalf of all partners and, if the complaint lodged is proven,
Document1 43
16.4 The Engineer’s approval shall not alter the Contractor’s
responsibility for design of the Temporary Works.
16.5 The Contractor shall obtain approval of third parties to the design
of the Temporary Works, where required.
17. Contractor’s 17.1 The Contractor shall execute and complete the Works and
Responsibilitie remedy any defects therein in conformity in all respects with the
s provisions of the Contract Agreement.
18. Taxes and 18.1 The Contractor shall be entirely responsible for all kinds of taxes,
Duties duties, fees, levies, and such other charges to be paid under the
Applicable Law imposed inside and outside Bangladesh.
19. Contractor’s 19.1 The Contractor shall employ the key personnel named in the
Personnel Schedule of Key Personnel, as referred to in the PCC, to carry
out the functions stated in the Schedule or other personnel
approved by the Engineer.
19.2 The Engineer will approve any proposed replacement of key
personnel only if their relevant qualifications and abilities are
equal to or higher than those of the personnel named in the
Schedule.
19.3 If the Engineer asks the Contractor to remove a particular person
who is a member of the Contractor’s staff or work force from the
Site, he or she shall state the reasons, and the Contractor shall
ensure that the person leaves the Site within three (3) days and
has no further connection with the work in the Contract.
20. Subcontracting 20.1 Subcontracting the whole of the Works by the Contractor shall
not be permissible. The Contractor shall be responsible for the
acts or defaults of any Subcontractor, his or her agents or
employees, as if they were the acts or defaults of the Contractor.
20.2 The Contractor shall not be required to obtain consent from the
Engineer, for suppliers solely of Materials or to a subcontract for
which the Specialist Subcontractor(s) is already named in the
Contract.
20.3 The prior consent, in writing, of the Engineer shall however be
obtained for other proposed Subcontractor(s).
21. Nominated 21.1 Nominated Subcontractor named in the Contract shall be entitled
Subcontractor to execute the specific components of the Works stated in the
PCC.
21.2 The Contractor shall not be under obligations to employ a
Nominated Subcontractor against whom the Contractor raises
reasonable objection by notice to the Engineer as soon as
practicable, with supporting particulars while there are reasons
to believe that the Subcontractor does not have sufficient
competence, resources or financial strength, or does not accept
to indemnify the Contractor against and from any negligence or
misuse of Goods by the nominated Subcontractor, or does not
accept to enter into a subcontract which specifies that, for the
subcontracted work including design, if any, the Nominated
Subcontractor shall undertake to the Contractor such obligations
24. Delegation 24.1 The Engineer may delegate any of his duties and
responsibilities to his representative, after notifying the
Contractor, and may cancel any delegation, without
retroactivity, after notifying the Contractor.
Document1 45
29. Welfare of 29.1 The Contractor shall comply with all the relevant labour Laws
Laborers applicable to the Contractor’s personnel relating to their
employment, health, safety, welfare, immigration and shall
allow them all their legal rights.
29.2 The Contractor, in particular, shall provide proper
accommodation to his or her labourers and arrange proper
water supply, conservancy and sanitation arrangements at the
site for all necessary hygienic requirements and for the
prevention of epidemics in accordance with relevant
regulations, rules and orders of the government.
29.3 The Contractor, further in particular, shall pay reasonable
wages to his or her labourers, and pay them in time. In the event
of delay in payment the Employer may effect payments to the
labourers and recover the cost from the Contractor.
29.4 The Contractor shall appoint an accident prevention officer at
the Site, responsible for maintaining safety and protection
against accidents. This person shall be qualified for this
responsibility, and shall have the authority to issue instructions
and take appropriate protective measures to prevent accidents
that could result in injury. Throughout the execution of the
Works, the Contractor shall provide whatever is required by this
person to exercise this responsibility and authority.
30. Child Labor 30.1 The Contractor shall not employ any child to perform any work
that is economically exploitative, or is likely to be hazardous to,
or to interfere with, the child's education, or to be harmful to the
child's health or physical, mental, spiritual, moral, or social
development in compliance with the applicable laws and other
relevant treaties ratified by the government.
31. Fossils 31.1 All fossils, coins, articles of value or antiquity, and structures
and other remains or items of geological or archaeological
interest found on the Site shall be placed under the care and
authority of the Employer. The Contractor shall take reasonable
precautions to prevent Contractor’s Personnel or other persons
from removing or damaging any of these findings.
32. Employer’s 32.1 The Employer carries the risks that the Contract states are
and Employer’s risks and the Contractor carries the risks that the
Contract states are Contractor’s risks.
33. Employer’s 33.1 From the Start Date until the Defects Correction Certificate has
Risks been issued, the following are Employer’s risks:
(a) the risk of personal injury, death, or loss of or damage to
property (excluding the Works, Plant, Materials, and
Equipment), which are due to
i. use or occupation of the Site by the Works or for the
purpose of the Works, which is the unavoidable
result of the Works or
ii. negligence, breach of statutory duty, or interference
with any legal right by the Employer or by any person
employed by or Contracted to him except the
Contractor.
(b) the risk of damage to the Works, Plant, Materials, and
Equipment to the extent that it is due to a fault of the
Employer or in the Employer’s design, or due to war or
radioactive contamination directly affecting the country
where the Works are to be executed.
34. Contractor’s 34.1 From the Start Date until the Defects Correction Certificate has
Risks been issued the risks of personal injury, death, and loss of or
damage to property including without limitation, the Works,
Plant, Materials, and Equipment, which are not Employer’s
risks are Contractor’s risks.
35. Copyright 35.1 The copyright in all drawings, documents, and other materials
containing data and information furnished to the Employer by
the Contractor herein shall remain vested in the Contractor, or,
if they are furnished to the Employer directly or through the
Contractor by any third party, including Suppliers of materials,
the copyright in such materials shall remain vested in such third
party.
35.2 The Contractor shall not, except for the purposes of performing
the obligations under the Contract, without the written
permission of the Employer disclose or make use of any
specification, plan, design and drawing, pattern, sample or
information furnished by or on behalf of the Employer.
Document1 47
36. Limitation of 36.1 Except in cases of criminal negligence or wilful misconduct:
Liability
(a) the Contractor shall not be liable to the Employer,
whether in Contract, tort, or otherwise, for any indirect or
consequential loss or damage, loss of use, loss of
production, or loss of profits or interest costs, provided
that this exclusion shall not apply to any obligation of the
Contractor to pay liquidated damages to the Employer;
and
(b) the aggregate liability of the Contractor to the Employer,
whether under the Contract, in tort or otherwise, shall not
exceed the total Contract Price, provided that this
limitation shall not apply to the cost of repairing or
replacing defective Works, or to any obligation of the
Contractor to indemnify the Employer with respect to
patent infringement.
37. Insurance 37.1 The Contractor shall provide, in the joint names of the Employer
and the Contractor, insurance cover from the Start Date to the
end of the Defects Liability Period, in the amounts and
deductibles specified in the PCC for the following events which
are due to the Contractor’s risks:
(a) loss of or damage to the Works, Plant, and Materials;
(b) loss of or damage to Equipment;
(c) loss of or damage to property (except the Works, Plant,
Materials, and Equipment) in connection with the
Contract; and
(d) personal injury or death.
37.2 The Contractor shall deliver policies and certificates of insurance
to the Engineer, for the Engineer’s approval, before the Start
Date. All such insurances shall provide for compensation to be
payable in the types and proportions of currencies required to
rectify the loss or damage incurred.
37.3 If the Contractor does not provide any of the policies and
certificates required, the Employer may effect the insurance
which the Contractor should have provided and recover the
premiums the Employer has paid from payments otherwise
due to the Contractor or, if no payment is due, the payment of
the premiums shall be a debt due.
37.4 Alterations to the terms of insurance shall not be made without
the approval of the Engineer.
37.5 Both parties shall comply with conditions of the insurance
policies.
38. Management 38.1 Either the Engineer or the Contractor may require the other to
and Progress attend a management and progress meeting. The business of
Meetings such meeting shall be to review the progress and plans for
remaining work and to deal with matters raised in accordance
with the early warning procedure.
39. Corrupt, 39.1 The Government requires that Employer, as well as the
Fraudulent, Contractor shall observe the highest standard of ethics during
Collusive or the implementation of procurement proceedings and the
Coercive execution of the Contract under the Contract.
Practices
39.2 The Government requires that Employer, as well as the
Contractor shall, during the Procurement proceedings and the
execution of the Contract under public funds, ensure-
(a) strict compliance with the provisions of Section 64 of the
Public Procurement Act, 2006;
(b) abiding by the code of ethics as mentioned in the
Rule127 of the Public Procurement Rules, 2008;
(c) that neither it, nor any other member of its staff, or any
other agents or intermediaries working on its behalf
engages in any such practice as detailed in GCC Sub
Clause 39.3.
39.3 For the purposes of GCC Sub Clause 39.2, the terms set forth
below as follows:
(a) “corrupt practice” means offering, giving or promising
to give, receiving, or soliciting either directly or indirectly,
to any officer or employee of a Employer or other public
or private authority or individual, a gratuity in any form;
employment or any other thing or service of value as an
inducement with respect to an act or decision or method
followed by a Employer in connection with a Procurement
proceeding or Contract execution;
(b) “fraudulent practice” means the misrepresentation or
omission of facts in order to influence a decision to be taken
in a Procurement proceeding or Contract execution;
Document1 49
(c) “collusive practice” means a scheme or arrangement
between two (2) or more Persons, with or without the
knowledge of the Employer, that is designed to arbitrarily
reduce the number of Tenders submitted or fix Tender
prices at artificial, non-competitive levels, thereby denying
a Employer the benefits of competitive price arising from
genuine and open competition; or
(d) “coercive practice” means harming or threatening to harm,
directly or indirectly, Persons or their property to influence
a decision to be taken in the Procurement proceeding or
the execution of the Contract, and this will include
creating obstructions in the normal submission process
used for Tenders.
B. Time Control
40. Commencement 40.1 Except otherwise specified in the PCC , the Commencement
of Works Date shall be the date at which the following precedent
conditions have all been fulfilled and the Engineer’s instruction
recording the agreement of both Parties on such fulfilment and
instructing to commence the Works is received by the
Contractor:
(a) signing of the Contract Agreement by both parties upon
approval of the by relevant authorities;
(b) except if otherwise specified in the PCC , possession of
the Site given to the Contractor as required for the
commencement of the Works; and
41. Completion of 41.1 The Contractor shall carry out the Works in accordance with the
Works Programme of Works submitted by the Contractor and as
updated with the approval of the Engineer as stated under GCC
Clause 42 to complete them in all respects by the Intended
Completion Date.
42. Programme of 42.1 Within the time stated in the PCC, the Contractor shall submit
Works to the Engineer for approval a Programme of Works showing
the general methods, arrangements, order, and timing for all
the activities in the Works. The programme may be in the form
of an Implementation Schedule prepared in any software or
other form acceptable to the Engineer.
42.2 The Contractor shall submit to the Engineer for approval of an
updated Programme at intervals no longer than the period
stated in the PCC. An update of the Programme shall be a
Programme showing the actual progress achieved on each
activity and the effect of the progress achieved on the timing of
the remaining work, including any changes to the sequence of
the activities.
42.3 If the Contractor does not submit an updated Programme of
Works at the intervals stated in the PCC, the Engineer may
withhold an amount as stated in the PCC from the next payment
certificate and continue to withhold this amount until the next
due payment after the date on which the overdue Programme
of Works has been submitted.
42.4 The Engineer’s approval of the Programme of Works shall not
alter the Contractor’s obligations. The Contractor may revise
the Programme and submit it to the Engineer again at any time
for approval. A revised Programme shall show the effect of
Variations and Compensation Events.
43. Pro Rata 43.1 The Contractor shall maintain Pro Rata progress of the Works.
Progress Progress to be achieved shall be pursuant to GCC Clause 42
and shall be determined in terms of the value of the works done.
43.2 Failure to achieve the progress in accordance with the updated
Programme of Works stated under GCC sub Clause 42.1and
42.2 by the Contractor may be treated as the fundamental
breach of the Contract under GCC Clause 95.1.
Document1 51
44. Early Warning 44.1 If at any time during performance of the Contract, the
Contractor or its Subcontractors should encounter events,
circumstances, conditions that may adversely affect the quality
of the work, increase the original Contract Price or delay the
execution of the Works, the Contractor shall promptly notify the
Engineer in writing of the delay, its likely duration, and its cause.
As soon as practicable after receipt of the Contractor’s notice,
the Engineer shall evaluate the situation, and the Contractor
shall cooperate with the Engineer in making and considering
proposals for how the effect of such an event or circumstance
can be avoided or reduced.
45. Extension of 45.1 The Contractor shall be entitled to an extension of the Intended
Intended Completion Date, if and to the extent that completion of the
Completion Works or any part thereof is or will be delayed by
Date Compensation Events or a Variation or Extra Work Order.
45.3 The Employer shall decide whether and by how much to extend
the Intended Completion Date within twenty-one (21) days of
the Contractor asking the Engineer for a decision upon the
effect of a Compensation Event or Variation and submitting full
supporting information. If the Contractor has failed to give early
warning of a delay or has failed to cooperate in dealing with a
delay, the delay by this failure shall not be considered in
assessing the extension of Intended Completion Date.
49. Suspension of 49.1 The Engineer may at any time instruct the Contractor to
Work suspend progress of part or all of the Works. During such
suspension, the Contractor shall protect, store and secure such
part or the Works against any deterioration, loss or damage.
49.2 The Engineer may also notify the cause for the suspension. If
and to the extent that the cause is notified and is the
responsibility of the Contractor, the following GCC Clauses 50,
51 and 52 shall not apply.
50. 50.1 If the Contractor suffers delay and/or incurs Cost from
Consequence complying with the Engineer’s instructions under GCC Clause
48 and/or from resuming the work, the Contractor shall give
Document1 53
s of notice to the Engineer and shall be entitled subject to GCC
Suspension Clause 99 to:
(a) an extension of time for any such delay, if Completion is
or will be delayed, under GCC Clause 44, and
(b) payment of any such cost, which shall be included in the
Contract Price.
50.2 After receiving this notice, the Engineer shall proceed to agree
or determine these matters.
50.3 The Contractor shall not be entitled to any extension of time for,
or to any payment of the cost incurred in, making good the
consequences of the Contractor’s faulty design, workmanship
or materials, or of the Contractor’s failure to protect, store or
secure in accordance with GCC Clause 49.
51. Payment for 51.1 The Contractor shall be entitled to payment of the value, as at
Plant and the date of suspension, of Plant and/or Materials which have
Materials in not been delivered to Site, if:
Event of (a) the work on Plant or delivery of Plant and/or Materials
Suspension has been suspended for more than twenty (28) days,
and
(b) the Contractor has marked the Plant and/or Materials as
the Employer’s property in accordance with the
Engineer’s instructions.
52. Prolonged 52.1 If the suspension under GCC Clause 49 has continued for more
Suspension than eighty four (84) days, the Contractor may request the
Engineer’s permission to proceed. If the Engineer does not give
permission within twenty eight (28) days after being requested
to do so, the Contractor may, by giving notice to the Project
Manger, treat the suspension as an omission under GCC
Clause 65 of the affected part of the Works. If the suspension
affects the whole of the Works, the Contractor may give notice
of termination pursuant to GCC Clause 93.
53. Resumption of 53.1 After the permission or instruction to proceed is given, the
Work Contractor and the Engineer shall jointly examine the Works and
the Plant and Materials affected by the suspension. The
Contractor shall make good any deterioration or defect in or loss
of the Works or Plant or Materials, which has occurred during the
suspension after receiving from the Engineer an instruction to
this effect under GCC Clause 65.
C. Quality Control
54. Execution of 54.1 The Contractor shall construct, install and carry out the Works
Works and Physical services in accordance with the Specifications
and Drawings as scheduled in GCC Clause 6.
55. Examination 55.1 All works under the Contract shall at all times be open to
of Works examination, inspection, measurements, testing and
56. Identifying 56.1 The Engineer shall check the works executed by the Contractor
Defects and notify the Contractor of any Defects found. Such checking
shall not relieve the Contractor from his or her obligations. The
Engineer may also instruct the Contractor to search for a Defect
and to uncover and test any work that the Engineer considers
may have a Defect.
57. Testing 57.1 The Contractor shall carry out the Testing of works in
accordance with this Clause after providing the relevant
documents.
57.2 The Contractor shall give to the Engineer not less than
twenty one (21) days’ notice of the date after which the
Contractor will be ready to carry out each of the Testing.
Unless otherwise agreed, Testing shall be carried out
within fourteen (14) days after this date, on such day or
days as the Engineer shall instruct.
58. Rejection58.1
of 58.1 If, as a result of an examination, inspection, measurement or
Works testing, of Works it is found to be defective or otherwise not in
accordance with the Contract, the Engineer may reject the
Works by giving notice to the Contractor, with reasons. The
Contractor shall then promptly make good the defect and
ensure that the rejected Works subsequently complies with the
Contract.
59. Remedial 59.1 Notwithstanding any test or certification, the Engineer may
Work instruct the Contractor to:
(a) remove from the Site and replace any Plant or Materials
which is not in accordance with the Contract,
Document1 55
(b) remove and re-execute any other work which is not in
accordance with the Contract, and
(c) execute any work which is urgently required for the
safety of the Works, whether because of an accident,
unforeseeable event or otherwise.
59.2 The Contractor shall comply with the instruction issued under
GCC Sub Clause 59.1 within a reasonable time, which shall be
specified in the instruction, or immediately if urgency is
specified under GCC Sub Clause 59.1(c).
59.3 If the Contractor fails to comply with the instruction issued under
GCC Sub Clause 59.2, the Employer shall be entitled to employ
and pay other persons to carry out the work. Except to the
extent that the Contractor would have been entitled to payment
for the work, the Contractor shall be liable to pay all such costs
arising from this failure.
60. Correction of 60.1 The Engineer shall issue a Defects Liability Schedule for
Defects correction of Defects within fifty six (56) days from the
Contractor’s request for Final Payment stating the scope of
corrections or additions that are necessary.
60.2 The Engineer shall give notice to the Contractor, with a copy to
the Employer and others concerned, of any Defects before the
end of the Defects Liability Period, which begins at Completion
Date, and is defined in the PCC.
60.3 Every time notice of a Defect is given, the Contractor shall
correct the notified Defect within the length of time specified by
the Engineer’s notice.
60.4 The Defects Liability Period shall be extended for as long as
Defects remain to be corrected.
60.5 If the corrections or additions scheduled or notified by the
Engineer have been completed by the Contractor, the Engineer
shall issue a Defects Correction Certificate.
61. Uncorrected 61.1 If the Contractor has not corrected a Defect within the time
Defects specified in the Engineer’s notice, the Engineer shall assess the
cost of having the Defect corrected by it, and the Contractor
shall remain liable to pay the expenditures incurred on account
of correction of such Defect.
D. Cost Control
62. Contract Price 62.1 The Contract price shall be agreed or determined under GCC Sub
Clause 62.2 and as specified in the PCC.
62.2 The Contractor shall pay all of taxes, duties, fees, levies, and other
charges required to be paid under the Applicable Law under the
Contract pursuant to GCC Clause 18 and the Contract Price shall
not be adjusted for any of these costs except as provided under the
Conditions of the Contract.
63.3 Items of works quantified in the Bill of Quantities for which no rates
or prices have been quoted shall be deemed covered by the
amounts at rates and prices of other items in the Contract and shall
not be separately paid for.
64. Changes in 64.1 A new rate or price for items included in the Bill of Quantities
the Quantities shall, however, be appropriate for an item of work if:
and Unit Rate (a) the final measured quantity of the work done for any
or Price particular item in the Bill of Quantities is increased or
decreased by more than twenty five (25) percent
from the quantity of this item in the Bill of Quantities;
(b) the cost resulting from such increase or decrease in
quantity of this particular item in the Bill of Quantities
multiplied by its specified rate or price is exceeded
by one (1) percent of the original Contract price;
(c) this particular item is not specified in the Contract as
a “fixed rate item”;
(d) this particular item is not specified in the Contract as
for which no rates or prices have been quoted and
deemed covered by the amounts at rates and prices
of other items in the Bill of Quantities stated under
GCC Sub Clause 63.3; and
64.2 The new rate or price for the particular item of work included in
the Bill of Quantities described under GCC Sub Clause 64.1
shall be adjusted by the Engineer from any relevant rates or
prices within the Contract by taking into consideration the
context and threshold of the Variation Order as stated under
GCC Clause 65.
65. Variations 65.1 The Employer may issue a Variation Order for Procurement of
Works and Physical services from the original Contractor to
cover any increase or decrease in quantities, including the
introduction of new work items that are either due to change of
plans, design or alignment to suit actual field conditions, within
the general scope and physical boundaries of this Contract .
65.2 The Employer may also issue an Extra Work Order to cover
the introduction of such new works necessary for the
completion, improvement or protection of the original works
Document1 57
which were not included in the original contract, on the grounds
where there are subsurface or latent physical conditions at the
site differing materially from those indicated in the contract, or
where there are duly unknown physical conditions at the site of
an unusual nature differing materially from those usually
encountered and generally recognized as inherent in the work
or character provided for in the Contract.
65.7 The Head of the Procuring Entity may, in exceptions to the GCC
Sub Clause 65.6, and subject to the availability of funds and to
his or her satisfaction, authorize the immediate start of work
under any Variation or Extra Work Order under any or all of the
following conditions -
(a) in the event of an extreme emergency where the carrying
out of the work is required urgently to avoid causing
66.3 For new items of works that are not included in the Bill of
Quantities of the original Contract as stated under GCC Sub
Clause 65.1, the unit rates or prices of those new work items
shall be based on ;
(i) the direct unit costs used in the Bill of Quantities of original
Contract for other items (e.g. unit cost of cement, steel rebar,
formwork, labor rate, equipment rental, etc) as indicated in the
Document1 59
Contractor’s price breakdown of the cost estimate, if available;
or
(ii) fixed prices acceptable to both the Employer and the Contractor
based on market prices; or
(iii) the direct cost of the new work items based on (i) and (ii) above
shall then be combined with the mark-up factor (i.e. taxes,
overheads and profit) used by the Contractor in his or her
Tender to determine the unit rate or price of the new work item.
66.5 If the Engineer decides that the urgency of varying the work
would prevent a quotation being given and considered without
delaying the work, no quotation shall be given and the Variation
shall be treated as a Compensation Event under GCC Sub
Clause 72.
67. Cash Flow 67.1 When the Programme of Works is updated under GCC Sub
Forecasts Clause 42.2, the Contractor shall provide the Engineer with an
updated cash flow forecast.
68. Payment 68.1 The basis for payment certificates shall be Bill of Quantities
Certificates used to determine the Contract price.
69. Payments to 69.1 The Employer shall pay the Contractor the amounts certified by
the Contractor the Engineer within twenty eight (28) days of the date of each
certificate after due adjustments for deductions for advance
payments, retention and any other additions or deductions
which may have become due under the Contract or otherwise,
including those under GCC Clause 99.
70. Delayed 70.1 If the Contractor does not receive payments as stated under
Payment GCC Sub Clause 69.1, the Contractor shall be entitled to
receive financing charges compounded monthly on the amount
unpaid during the period of delay. This period shall be deemed
to commence on the date due for payment specified in GCC
Sub Clause 69.1.
71. Payments to 71.1 The Contractor shall pay to the Nominated Subcontractor(s) the
Nominated amounts shown on the Nominated Subcontractor’s invoices
Subcontractor approved by the Contractor which the Engineer certifies to be
(s) due in accordance with the subcontract included under the
Contract.
Document1 61
(a) The Employer does not give access to or possession of
the Site or part of the Site by the Site Possession Date
stated in the GCC Sub Clause 13.1;
(b) The Employer modifies the Schedule of other Contractors
in a way that affects the works of the Contractor under the
Contract;
(c) The Engineer orders a delay or does not issue Drawings,
Specifications, or instructions required for execution of the
Works on time;
(d) The Engineer instructs the Contractor to uncover or to
carry out additional tests upon work, which is then found
to have no Defects;
(e) The Engineer unreasonably does not approve a
subcontract to be let, if applicable;
(f) Ground conditions are substantially more adverse than
could reasonably have been assumed before issuance of
the Notification of Award from the information issued to
Tenderers (including the Site Investigation Reports), from
information available publicly and from a visual inspection
of the Site;
(g) The Engineer gives an instruction for dealing with an
unforeseen condition, caused by the Employer, or
additional work required for safety or other reasons;
(h) Other Contractors, public authorities, utilities, or the
Employer do not work within the dates and other
constraints stated in the Contract, and they cause delay or
extra cost to the Contractor;
(i) The advance payment is delayed;
(j) The effects on the Contractor of any of the Employer’s
Risks;
(k) The Engineer unreasonably delays issuing a Completion
Certificate;
(l) A situation of Force Majeure has occurred, as defined in
GCC Clause 88; and
(m) Other Compensation Events described in the Contract or
determined by the Engineer in the PCC shall apply.
73. Adjustments 73.1 Unless otherwise specified in the Contract, if between the date
for Changes in twenty-eight (28) days before the submission of Tenders for the
Legislation Contract and the date of the last Completion Certificate, any
law, regulation, ordinance, order or bylaw having the force of
law is enacted, promulgated, abrogated, or changed in
Bangladesh (which shall be deemed to include any change in
interpretation or application by the competent authorities) that
subsequently affects the Completion Date and/or the Contract
price, then such Completion Date and/or Contract price shall be
correspondingly increased or decreased, to the extent that the
Contractor has thereby been affected in the performance of any
of its obligations under the Contract.
73.2 The Engineer shall adjust the Contract Price on the basis of the
change in the amount of taxes, duties, and other levies payable
by the Contractor, provided such changes have not already
been accounted for in the price adjustment as defined in GCC
Clause 74 and/or reflected in the Contract price.
74. Price 74.1 Prices shall be adjusted for fluctuations in the cost of inputs only
Adjustment if provided for in the PCC. If so provided, the amounts as
certified in each payment certificate, before deducting for
Advance Payment, shall be adjusted by applying the respective
price adjustment factor to the payment amount. The generic
formula indicated below in the form as specified in the PCC
applies:
P= A + B (Im/Io)
where:
P is the adjustment factor
A and B are Coefficients specified in the PCC,
representing the nonadjustable and adjustable portions,
respectively, of the Contract; and
Im is the Index during the month the work has been
executed and Io is the Index prevailing twenty eight (28)
days prior to the deadline for submission of Tender.
The Indexes to be used is as published by the Bangladesh
Bureau of Statistics (BBS) on a monthly basis. In case not
available, then other countries or authorities of the sources
mentioned in Appendix to the Tender may be used.
74.2 If the value of the Index is changed after it has been used in a
calculation, the calculation shall be corrected and an
adjustment made in the next or in the final payment certificate.
Document1 63
The Index value shall be deemed to take account of all
changes in price due to fluctuations.
75. Retention 75.1 The Employer shall retain from each progressive payment
Money due to the Contractor at the percentage specified in the PCC
until completion of the whole of the Works under the Contract.
75.2 On completion of the whole of the Works, the first half the total
amount retained under GCC Sub Clause 75.1 shall be repaid
to the Contractor and the remaining second half after the
Defects Liability Period has passed and the Engineer has
certified in the form of Defects Corrections Certificate as
stated under GCC Sub Clause 60.5 that all Defects notified by
the Engineer to the Contractor before the end of this period
have been corrected.
75.3 On completion of the whole of the Works, the Contractor may
substitute an unconditional Bank Guarantee an internationally
reputable Bank which has a correspondent Bank located in
Bangladesh in the format as specified (Form PW5-11)
acceptable to the Employer for the second half of the retention
money as stated under GCC Sub Clause 75.2.
75.4 Deductions of Retention Money shall be applicable in this
Contract, if no advance payment has been made to the
Contractor and in such case, the provisions under GCC Sub
Clauses 79.1 and 79.2 shall be applied.
75.5 If the provision of Retention Money is not included in this
Contract these Sub Clauses shall not apply except the
relevant ones.
76. Liquidated 76.1 The Contractor shall be liable to pay Liquidated Damages or
Damages in other words the Delay Damages to the Employer at the rate
per day as specified in the PCC for each day of delay from the
Intended Completion Date, for the uncompleted Works or for
any part thereof.
76.2 The total amount of Liquidated Damages shall not exceed the
amount defined in the PCC.
77. Bonus 77.1 The Contractor shall be paid a Bonus calculated at the rate
per calendar day if stated in the PCC for each day (less any
days for which the Contractor is paid for acceleration) that the
Completion of the whole of the Works is earlier than the
Intended Completion Date. The Engineer shall require
certifying that the Works are complete, although they may not
have fallen due to being complete as per approved updated
Programme of Works.
78. Advance 78.1 The Employer shall make advance payment, if so specified in
Payment the PCC, to the Contractor in the amounts and by the dates
specified in the PCC against an Unconditional Bank
Guarantee issued by an internationally reputable Bank which
has a correspondent Bank located in Bangladesh in the format
as specified (Form PW5-10) and acceptable to the Employer,
of an amount equal to the advance payment.
78.2 The Guarantee stated under GCC Sub Clause 78.1 shall
remain effective until the advance payment has been repaid
by the Contractor, but the amount of the Guarantee shall be
progressively reduced by the amounts repaid. No interest will
be charged on the advance payment made.
78.3 The Contractor shall use the advance payment only to pay for
Equipment, Plant, Materials, and mobilization expenses
required specifically for execution of the Contract. The
Contractor shall demonstrate that advance payment has been
used for such specific purposes by supplying copies of
invoices or other documents to the Engineer.
79. Performance 79.1 Without limitation to provisions of any of these Sub Clauses,
Security whenever the Engineer determines an addition or a reduction
to the Contract price as a result of change in cost and/or
legislation or a result of Variation or Extra Work Order
Document1 65
amounting to more than fifteen (15) percent of the original
Contract price, the Contractor shall at the Engineer’s request
promptly increase, or may decrease, as the case may be, the
amount of the Performance Security furnished at the time of
signing of the Contract Agreement by an equal percentage.
79.3 The amount of the new Security under GCC Sub Clause 79.1
to be provided by the Contractor shall be calculated based on
the final Contract Price and shall cover twenty eight (28) days
beyond the Defects Liability Period.
79.4 The Employer shall notify the Contractor of any claim made
against the Bank issuing the Performance Security.
79.5 The Employer may claim against the security if any of the
following events occurs for fourteen (14) days or more.
(a) The Contractor is in breach of the Contract and the
Employer has duly notified him or her ; and
(b) The Contractor has not paid an amount due to the
Employer and the Employer has duly notified him or her.
79.7 The Employer shall not make any claim under the
Performance Security, except for amounts to which the
Employer is entitled under the Contract.
80. Provisional 80.1 Provisional Sums shall only be used, in whole or in part, in
Sums accordance with the Engineer’s instructions and the Contract
price shall be adjusted accordingly. The total sum paid to the
Contractor shall include only such amounts, for the work,
supplies or services to which the Provisional Sum relates, as
the Engineer shall have instructed.
81. Dayworks 81.1 If applicable, the Dayworks rates in the Contractor’s Tender
shall be used for small additional amounts of work only when
the Engineer has given written instructions in advance for
additional work to be paid for in that way.
84. Completion 84.1 The Engineer shall, within twenty eight(28) days after
Certificate and receiving the Contractor’s application stated under GCC Sub
Taking Over Clause 83.1:
(a) issue the Completion Certificate to the Contractor,
stating the date on which the Works or part thereof
were completed in accordance with the Contract,
except for any minor outstanding work and defects
which may not substantially affect the use of the Works
or part thereof for their intended purpose (either until
or whilst this work is completed and these defects are
remedied); or
(b) reject the application, giving reasons and specifying the
work required to be done by the Contractor to enable
the Completion Certificate to be issued. The Contractor
shall then complete this work before issuing a further
notice under this Sub Clause.
Document1 67
the case may be, are substantially in accordance with the
Contract, the Completion Certificate shall be deemed to have
been issued on the last day of that period.
84.3 The Employer shall Take-Over the Site and the Works within
seven (7) days of the Engineer issuing a Completion
Certificate under GCC Sub Clause 84.1.
85. Amendment to 85.1 The amendment to Contract shall generally include extension
Contract of time to the Intended Completion Date, increase or decrease
in original Contract price and any other changes duly
approved under the conditions of the Contract.
86. Final Account 86.1 The Contractor shall submit with a detailed account of the total
amount that the Contractor considers payable under the
Contract to the Engineer before the end of the Defects Liability
Period.
86.2 The Engineer shall certify the Final Payment within fifty six
(56) days of receiving the Contractor’s account if the payable
amount claimed by the Contractor is correct and the
corresponding works are completed.
86.3 If it is not, the Engineer shall issue within fifty six (56) days a
Defects Liability Schedule under GCC Sub Clause 60.1 that
states the scope of the corrections or additions that are
necessary.
87. As-built 87.1 If “As Built” Drawings and/or operating and maintenance
Drawings and manuals are required, the Contractor shall supply them by the
Manuals dates stated in the PCC.
87.2 If the Contractor does not supply the Drawings and/or Manuals
by the dates specified in GCC Sub Clause 87.1, or they do not
receive the Engineer’s approval, the Engineer shall withhold a
nominal amount specified in the PCC from payments due to
the Contractor.
88. Force Majeure 88.1 Force Majeure may include, but is not limited to, exceptional
events or circumstances of the kind stated below;
(a) war, hostilities (whether war be declared or not),
invasion, act of foreign enemies ;
(b) rebellion, terrorism, sabotage by persons other than the
Contractor’s personnel, revolution, insurrection, military
or usurped power, or civil war ;
89.2 The notice under GCC Sub Clause 89.1 shall be given within
fourteen (14) days after the party became aware, or should
have become aware, of the relevant event or circumstance
constituting Force Majeure.
90. Duty to 90.1 Each party shall at all times use all reasonable endeavors to
Minimize minimize any delay in the performance of the Contract as a
Delay result of Force Majeure.
90.2 A party shall give notice to the other party when it ceases to
be affected by the Force Majeure.
Document1 69
91.2 After receiving notice under GCC Sub Clause 89.2, the
Engineer shall proceed to determine these matters under the
provisions of the Contract.
92. Force Majeure 92.1 If any Subcontractor is entitled under any contract or
Affecting agreement relating to the Works to relief from Force Majeure
Subcontractor on terms additional to or broader than those specified in this
Clause, such additional or broader Force Majeure events or
circumstances shall not be relieved of the Contractor’s non-
performance or entitle him or her to relief under this Clause.
93. Optional 93.1 If the execution of substantially all the Works in progress is
Termination, prevented for a continuous period of eighty four (84) days by
and Release reason of Force Majeure of which notice has been given under
GCC Sub Clause 89, or for multiple periods which total more
than one hundred forty (140) days due to the same notified
Force Majeure, then either party may give to the other party a
notice of termination of the Contract. In this event, the
termination shall take effect seven (7) days after the notice is
given, and the Contractor shall proceed to cessation of Works
and removal of Contractor’s Equipment from Site.
94. Release from 94.1 Notwithstanding any other provision of this Clause, if any
Performance event or circumstance outside the control of the parties
(including, but not limited to, Force Majeure) arises which
makes it impossible or unlawful for either or both parties to
fulfil its or their contractual obligations or which, under the law
governing the Contract, entitles the parties to be released from
further performance of the Contract, then upon notice by either
party to the other party of such event or circumstance:
(a) the parties shall be discharged from further
performance, without prejudice to the rights of either
party in respect of any previous breach of the Contract,
and
(b) the sum payable by the Employer to the Contractor shall
be the same as would have been payable under GCC
Sub Clause 96.3 if the Contract had been terminated
under GCC Sub Clause 95.3.
Document1 71
such termination becomes effective. The termination
shall take effect twenty eight (28) days after the later
dates on which the Contractor receives this notice or
the Employer returns the Performance Security.
(b) The Employer shall not terminate the contract under
GCC Sub Clause 95.3 (a) in order to execute the Works
itself or to arrange for the Works to be executed by
another contractor or to avoid a termination of the
Contract by the Contractor as stated under GCC Sub
Clause 95.1(a).
95.4 In the event the Employer terminates the Contract in whole or
in part, the Employer shall accept the portion of the Works that
are complete and ready for handing over after the Contractor’s
receipt of notice of termination of the Contract. For the
remaining portion of the Works, the Employer may elect:
(a) to have any portion completed by the Contractor at the
Contract terms and prices; and /or
(b) to cancel the remainder and pay to the Contractor an
agreed amount for partially completed Works and for
materials and parts previously procured by the
Contractor, or
(c) except in the case of termination for convenience as
stated under GCC Sub Clause 95.3 (b), engage
another Contractor to complete the Works, and in that
case the Contractor shall be liable to the Employer for
any cost that may be incurred in excess of the sum
that would have been paid to the Contractor, if the
work would have been executed and completed by
him or her.
(a) the amounts payable for any work carried out for
which unit rates or prices are stated in the Contract;
(b) the cost of Plant and Materials ordered for the Works
which have been delivered to the Contractor, or of
which the Contractor is liable to accept delivery: this
Plant and Materials shall become the property of
(and be at the risk of) the Employer when paid for by
the Employer, and the Contractor shall place the
same at the Employer’s disposal;
(c) other costs or liabilities which in the circumstances
were reasonably and necessarily incurred by the
Contractor in the expectation of completing the
Works;
(d) the cost of removal of Temporary Works and
Contractor’s Equipment from the Site; and
(e) the cost of repatriation of the Contractor’s staff and
labor employed wholly in connection with the Works
at the date of termination.
97. Property 97.1 All Materials on the Site, Plant, Equipment, Temporary
Works, and Works shall be deemed to be the property of the
Employer if the Contract is terminated because of the
Contractor’s default stated under GCC Sub Clause 93.1.
Document1 73
99.2 If the Contractor fails to give notice of a claim within such
period of twenty eight (28) days, the Intended Completion
Date shall not be extended, the Contractor shall not be
entitled to additional payment, and the Employer shall be
discharged from all liability in connection with the claim.
99.3 Within forty two (42) days after the Contractor became
aware or should have become aware of the event or
circumstance giving rise to the claim, or within such other
period as may be proposed by the Contractor and approved
by the Engineer, the Contractor shall send to the Engineer
a fully detailed claim which includes full supporting
particulars of the basis of the claim and of the extension of
time and/or additional payment claimed, for settlement.
Amicable settlement
100. Settlement of
Disputes
100.1 The Employer and the Contractor shall make every effort to
resolve amicably by direct informal negotiation any
disagreement or dispute arising between them under or in
connection with the Contract.
Arbitration
100.2 If, after twenty-eight (28) days, the parties have failed to resolve
their dispute or difference by such mutual consultation as stated
under GCC Clause 100.1, then either the Employer or the
Contractor may give notice to the other party of its intention to
commence arbitration in accordance with GCC Sub Clause
100.3, as to the matter in dispute, and no arbitration in respect
of this matter may be commenced unless such notice is given.
Any dispute or difference in respect of which a notice of intention
to commence arbitration has been given in accordance with this
Clause shall be finally settled by arbitration.
Instructions for completing the Particular Conditions of Contract are provided in italics in parenthesis
for the relevant GCC Clauses.
Document1 75
[Name, address, and name of authorized representative]
[usually a civil works contract designating the project Consultant as “Engineer” requires the
written approval of the “Employer”]
GCC 1.1 (dd) The original Contract price is [insert the amount in the NOA]
GCC 1.1(aa) The Intended Completion Date for the whole of the Works shall be [insert date]
GCC 1.1(ll) The Site is located at [location] and is defined in drawings No:
[insert numbers]
[it is the last date when the Contractor shall commence execution of the Works under the
Contract reasonably immediately after the Commencement Date; refer to GCC Clause 40]
[state brief summary, including relationship to other Contracts under the Project]
GCC 3.1 The Employer’s address for the purpose of communications under this contract is :
Contact person:
Address:
Tel:
Fax:
e-mail address:
The Contractor’s address for the purpose of communications under this contract is :
Contact person:
Address:
Tel:
Fax:
e-mail address:
GCC 6.1 (j) Other documents forming part of the Contract are;
GCC 9.1 A Contractor or a Subcontractor that is a national of, or registered in, the following
countries are not eligible:
GCC 9.2 Materials, Equipments Plants and supplies shall not have their origin in the following
countries:
GCC 13.1 Possession of the Site or part(s) of the Site, to the Contractor shall be given on the
following date(s);
GCC 19.1 Following Key Personnel to carry out the functions stated in the Schedule shall be
employed by the Contractor;
[insert name(s)]
____[insert name(s)]___________________________________________
shall be entitled to execute the following specific components of the Works
GCC 23.1 The Contractual matters between the Employer and the Contractor shall be decided
by
(a) The maximum deductible for insurance of the Works and of Plant and
BangladeshTaka
Materials is USD/GBP/EU R/JPY/BDT [insert amount] and/or
deleteif not appropriate
delete not appropriat e
[insert amount]
[the Contractor shall provide this amount at the time of Contract signing].
(b) The minimum cover for insurance of the Works and of Plant and Materials in
respect of the Contractor’s faulty design is USD/GBP/EU R/JPY/BDT [insert
delete not appropriat e
BangladeshTaka
amount] [insert amount].
deleteif not appropriate
[the amount could be 110% of the value of the works, plant and materials that may be lost
in a worst case scenario].
Document1 77
(c) The maximum deductible for insurance of Equipment is USD/GBP/EU R/JPY/BDT
delete not appropriat e
BangladeshTaka
[insert amount] [insert amount].
deleteif not appropriate
[the Contractor shall provide this amount at the time of Contract signing]
(d) The minimum cover for loss or damage to Equipment is USD/GBP/EU R/JPY/BDT
delete not appropriat e
BangladeshTaka
[insert amount] [insert amount].
deleteif not appropriate
(e) The maximum deductible for insurance of other property is USD/GBP/EU R/JPY/BDT
delete not appropriat e
BangladeshTaka
[insert amount] [insert amount].
deleteif not appropriate
[the Contractor shall state this amount at the time of Contract signing]
(f) The minimum cover for insurance of other property is USD/GBP/EU R/JPY/BDT
delete not appropriat e
BangladeshTaka
[insert amount] [insert amount].
deleteif not appropriate
[it is the responsibility of the Contractor to obtain adequate insurance cover for such risks –
recommended value 10% of contract price]
GCC 40.1
Commencement Date of Works shall be as follows;
[insert different commencement dates for different parts of the Works, if deemed appropriate]
GCC 42.1 The Contractor shall submit a Programme for the Works within [insert days] days of
signing the Contract.
GCC 42.3 The amount to be withheld for late submission of an updated Programme is
BangladeshTaka
USD/GBP/EU R/JPY/BDT [insert amount ] [insert amount]
deleteif not appropriate
delete not appropriat e
GCC 62.1 The Contract Price is USD/GBP/EU R/JPY [insert amount] and/or
BDT
[insert
deleteif not appropriate
delete not appropriat e
amount]
GCC 69.3 The particulars of the Bank Account nominated are as follows :
[information furnished by the Contractor shall be substantiated by the concerned Bank and
authenticated by the Employer]
GCC 70.2 The Contractor shall be entitled to receive financing charges for delayed payment
during the period of delay at the annual rate of interest of [insert rate] ;
GCC 72.1(m) The following additional events shall also be the Compensation Events:
[list events or state none ]
Document1 79
The Contract is subject to price adjustment applying the following formulae and the
weightings or coefficients :
[Price Adjustment Formulae to be applicable if stated under ITT Sub Clause 27.10 shall be specified
here]
Example:
P= A + a (Lm/Lo)+ b (BIm/BIo)+ c (CEm/CEo)+ d (RSm/RSo)+ e (STm/STo)+ f (BRm/BRo)+g (MIm/MIo)
+ h (FUm/FUo)+ etc
where;
L= Labor, BI=Bitumen, CE=Cement, RS=Reinforcing Steel, ST=Stone, BR=Bricks, MI=Miscellaneous,
FU= Fuel ]
Weighting or Coefficient A equals between 0.10 and 0.15 and, B (a+b+c+d+e+f+g+h+etc) equals
between 0.90 and 0.85.
GCC 76.1 The amount of Liquidated Damages or in other words Delay Damages for the
uncompleted Works or any part thereof is [insert percentage] percent of its Contract
price per day of delay.
[usually the percent-rate of liquidated damages is set at between 0.05 and 0.10 of ONE (1) percent of
its Contract price per day of delay]
GCC 76.2 The maximum amount of Liquidated Damages for the uncompleted Works or any
part thereof is [insert percentage] percent of the final Contract price of the whole of the
Works.
[ usually the total amount of liquidated damages shall not exceed ten (10) percent of the final Contract
price for the whole of the Works]
The maximum amount of Bonus for the whole of the Works is [insert percentage]
percent of the final Contract price.
[if early completion would provide benefits to the Employer, this clause should remain, otherwise
state “Not Applicable”. The bonus is usually numerically equal to the Liquidated Damages]
GCC 78.1 The Advance Payment shall be USD/GBP/EU R/JPY/BDT [insert amount] and/or
delete not appropriat e
BangladeshTaka
[insert amount] and, shall be paid to the Contractor not later than [insert
deleteif not appropriate
date].
[for 100 percent GoB funded procurement, advance payments are not recommended unless
otherwise specifically decided by the Government. An advance payment, if admissible, shall be
made for mobilisation, considering the nature of the works. The recommended maximum advance
payment is ten (10) percent of the original Contract price against an unconditional Bank Guarantee
(Form PW5-10). On the contrary, advance payments may be applicable for procurements under
aided projects]
GCC 78.4 Repayment of Advance Payment shall be at the rate of [insert percentage] from the
progressive payments of invoices.
[Advance Payment is to be repaid in pro rata instalments starting with the month
when twenty (20) percent of the value of the Contract has been certified and shall be
completely reimbursed to the Employer by the time the certified completion is eighty
(80) percent of the Contract price]
____% (_________percent)
[state none, if not applicable. Usually covers the VAT, profit and overhead costs]
GCC 87.1 The date by which “as-built” drawings are required is [insert date]
The date by which operating and maintenance manuals are required is [insert date]
GCC 87.2 The amount to be withheld for failing to produce “as-built” drawings and/or operating
and maintenance manuals by the date required is USD/GBP/EU R/JPY/BDT [insert amount]
delete not appropriat e
BangladeshTaka
and/or [insert amount].
deleteif not appropriate
GCC 96.1 The percentage to apply to the contract value of the works not completed,
representing the Employer’s additional cost for completing the uncompleted Works,
is [state percentage] percent.
Document1 81
[ usually between ten (10) to twenty (20) percent depending on the nature of the Works]
The rules of procedure for arbitration proceedings shall be as follows:
GCC 100.3
(i) In the case of a dispute between the Employer and the foreign Contractor, [insert
any of the following options]
(ii) In the case of a dispute between the Employer and the national Contractor, in
particular, the arbitration shall be conducted in accordance with the
Arbitration Act (Act No 1 of 2001) of Bangladesh as at present in force and
in the place [state name of place with location and district].
[In Tables below, the Procuring Entity shall indicate the source and base
values with dates of Indexes, unless otherwise instructed to be quoted by
the Tenderer, for the different Cost Components and mention its
Weightings or Coefficients]
Note:
1. The sources of Indexes and its values with dates shall be Bangladesh Bureau of
Statistics (BBS) unless otherwise mentioned by the Procuring Entity or instructed to
be quoted by the Tenderer.
2. The Procuring Entity may require the Tenderer to justify its proposed Indexes, if
quoted by the Tenderer.
3. The Base Value of the Indexes shall be those prevailing twenty eight (28) days prior
to the deadline for submission of the Tenders.
Document1 83
Table 1.2: Price Adjustment Data
[GCC Sub Clause 74.1: To be provided by the Procuring Entity]
Coefficients
or Coefficients or Weightings for
Weightings adjustable Cost Components
Item Bill No. if Index
for non- Total
Group applicable Descriptions
adjustable
Cost
Component a b c d e f g h i j
Note:
The Weightings or Coefficients of the Cost Components shall be mentioned by the
Employer based on the proportion of components involved in the work items caused to
be impacted by rise and fall in its prices.
Form Title
Tender Forms
Contract Forms
PW5 –11 Bank Guarantee for Retention Money Security (when this option is chosen)
Forms PW5 -1 to PW5 -6 comprises part of the Tender Format and should be completed as
stated in ITT Clause 20.
Forms PW5 -7 to PW5 -11 comprises part of the Contract as stated in GCC Clause 6.
Document1 85
Tender Submission Letter (Form PW5-1)
[This letter should be completed and signed by the Authorised Signatory
preferably on the Letter-Head Pad of the Tenderer]
To: Date:
[Contact Person]
[Name of Procuring Entity]
[Address of Procuring Entity]
This Package is divided into the following Number of Lots [indicate number of Lot(s)]
We, the undersigned, offer to execute in conformity with the Conditions of Contract and
associated Contract documents, the following Works and Physical services, viz:
In accordance with ITT Clauses 23 and 24, the following prices and discounts apply to our
Tender:
In signing this letter, and in submitting our Tender, we also confirm that:
(a) our Tender shall be valid for the period stated in the Tender Data Sheet (ITT Sub
Clause 29.2) and it shall remain binding upon us and may be accepted at any time
before the expiration of that period;
(b) a Tender Security is attached in the form of a bank guarantee in the amount stated
in the Tender Data Sheet (ITT Sub Clause 31.2) and valid for a period of twenty
eight (28) days beyond the Tender validity date;
(d) we have examined and have no reservations to the Tender Document, issued by
you on [insert date]; including Addendum to Tender Document No(s) [state
numbers] , issued in accordance with the Instructions to Tenderers (ITT Clause 11).
[insert the number and issuing date of each addendum; or delete this sentence if
no Addendum has been issued];
(e) we, including as applicable, any JVCA partner or Specialist Subcontractor for any
part of the contract resulting from this Tender process, have nationalities from
eligible countries, in accordance with ITT Clause 5;
(f) we are submitting this Tender as a sole Tenderer in accordance with ITT Sub
Clause 36.3
or
we are submitting this Tender as the partners of a JVCA, comprising the following
other partners in accordance with ITT Sub Clause 36.4;
(h) we, including as applicable any JVCA partner, declare that we are not associated,
nor have been associated in the past, directly or indirectly, with a consultant or any
other entity that has prepared the design, specifications and other documents
in accordance with ITT Clause 5;
(i) we, including as applicable any JVCA partner or Specialist Subcontractor for any
part of the contract resulting from this Tender process, have not been declared
ineligible by the Government of Bangladesh on charges of engaging in corrupt,
fraudulent, collusive or coercive practices in accordance with ITT Clause 5;
(j) furthermore, we are aware of ITT Clause 4 concerning such practices and pledge
not to indulge in such practices in competing for or in executing the Contract;
(k) we intend to subcontract an activity or part of the Works, in accordance with ITT
Clause 14, to the following Specialist Subcontractor(s);
Document1 87
(l) we, including as applicable any JVCA partner, confirm that we do not have a record
of poor performance, such as abandoning the works, not properly completing
contracts, inordinate delays, or financial failure as stated in ITT Clause 5, and that
we do not have, or have had, any litigation against us, other than that stated in the
Tenderer Information (Form PW5-2);
(m) we are not participating as Tenderers in more than one Tender in this Tendering
process. We understand that your written Notification of Award shall constitute the
acceptance of our Tender and shall become a binding Contract between us, until
a formal Contract is prepared and executed;
(n) we, including as applicable any JVCA partner, confirm that we do not have a record
of insolvency, receivership, bankrupt or being wound up, our business activities
were not been suspended, and it was not been the subject of legal proceedings in
accordance with ITT Clause 5;
(o) we, including as applicable any JVCA partner, confirm that we have fulfilled our
obligations to pay taxes and social security contributions applicable under the
relevant national laws and regulations of Bangladesh in accordance with ITT
Clause 5;
(p) we understand that you reserve the right to reject all the Tenders or annul the
Tender proceedings, without incurring any liability to Tenderers, in accordance with
ITT Clause 57.
[If there is more than one (1) signatory, or in the case of a JVCA, add other boxes
and sign accordingly].
Attachment 1:
[ITT Sub Clause 36.3 and 36.4]
Written confirmation authorising the above signatory(ies) to commit the Tenderer
[and, if applicable]
Attachment 2:
[ITT Sub Clause 13.2]
Copy of the JV Agreement / Letter of Intent to form JV with draft proposed Agreement submitted
at the time of pre-qualification
Partnership
Government-owned Enterprise
Others
[please describe, if applicable]
1.5 Tenderer’s year of registration
1.6 Tenderer’s authorised representative details
Name
National ID number, if any
Address
Telephone / Fax numbers
e-mail address
1.7 Litigation [ITT Cause 13]
Information on non-performance of contract and pending litigation furnished in PW5-12
1.8 Tenderer to attach photocopies of
the original documents mentioned
aside [All documents required under ITT Clauses 5 and 25]
Document1 89
The following two information are applicable for national Tenderers
1.9 Tenderer’s Value Added Tax
Registration (VAT) Number
1.10 Tenderer’s Tax Identification
Number(TIN)
[The foreign Tenderers, in accordance with ITT Clause 5, shall provide evidence by a written
declaration to that effect to demonstrate that it meets the criterion]
2. Qualification Information of the Tenderer [ITT Clause 12]
2.1 General Experience in Construction Works of Tenderer
Start End Years Contract No and Name of Contract Role of
Month Month Name and Address of Employer Tenderer
Year Year [Prime/Sub
Brief description of Works
/Managem
ent]
2.5 Financial Resources available to meet the construction cash flow [ITT Sub Clause 12.2]
No Source of Financing Amount Available
In order to confirm the above statements the Tenderer shall submit , as applicable, the documents
mentioned in ITT Clause 28.
2.6 Contact Details [ITT Clause 28]
Name, address, and other contact details of Tenderer Bankers and other Employer(s) that
may provide references, if contacted by this Employer
2.7 Qualifications and experience of key technical and administrative personnel proposed for
Contract administration and management [ITT Clause 28]
Position
Years of Specific Experience
Name
Years of General Experience
[Tenderer to complete details of as many personnel as are applicable. Each personnel listed
above should complete the Personnel Information (Form PW5-5)]
2.8 Major Construction Equipments proposed to carry out the Contract [ITT Clause 28]
Condition Owned, leased or to
Item of Equipment (new, good, be purchased
average, poor) (state owner, lessor
or seller)
Document1 91
JVCA Partner Information (Form PW5-3)
[This Form should be completed by each JVCA partner].
The following two information are applicable for national JVCA Partners only
1.9 JVCA Partner’s Value Added Tax
Registration (VAT) Number
1.10 JVCA Partner’s Tax Identification
Number (TIN)
[The foreign JVCA Partners, in accordance with ITT Clause 5, shall provide evidence by a written
declaration to that effect to demonstrate that it meets the criterion]
Document1 95
2. Key Activity(ies) for which it is intended to be joint ventured [ITT Clause 13]
Elements of Activity Brief description of Activity
Employer’s Name
Address
Tel / Fax
e-mail
Brief description with
justifications of the
similarity compared to the
[state justification in support of its similarity compared to the
Employer’s requirements
proposed works]
3.3 Average annual construction turnover [ITT Sub Clause 12.2]
[total certified payments received for contracts in progress or completed for each year of works
in progress or completed; using selling exchange rate quoted by the source being Bangladesh Bank
on the date reported, if applicable]
3.5 Financial Resources available to meet the construction cash flow [ITT Sub Clause 12.2]
No Source of financing Amount available
In order to confirm the above statements the JVCA Partner shall submit, as applicable, the
documents mentioned in ITT Clause 28.
3.6 Contact Details [ITT Clause 28]
Name, address, and contact details of Tenderer’s Bankers and other Employer(s) that may
provide references if contacted by this Employer
3.7 Qualifications and experience of key technical and administrative personnel proposed for
Contract administration and management [ITT Clause 28]
Position Years of Specific Experience
Name
Years of General Experience
__________________________________________
Signature
(Name of Authorized Signatory of the JVCA Partner)
Document1 97
Specialist Subcontractor Information (Form PW5-4)
[This Form should be completed by each Subcontractor, preferably on its Letter-Head Pad]
Invitation for Tender No: [indicate IFT No]
Tender Package No [indicate Package No]
This Package is divided into the following Number of Lots [indicate number of Lot(s)]
Partnership
Limited Liability Concern
Government-owned Enterprise
Other
(please describe)
Address
e-mail address
1.7 Attach copies of the following original documents All documents to the extent relevant
to ITT Clause 5 and 25 in support of
its qualifications
The following two information are applicable for national Subcontractors
2.2 List of Similar Contracts in which the proposed Subcontractor had been engaged
Name of Contract and Year of Execution
Value of Contract
Name of Employer
B. Personal Data
Name:
Date of Birth:
National ID Number:
Professional Qualifications:
1.
D. Professional Experience
Summarise professional experience over the last twenty (20) years, in reverse chronological order. Indicate
particular technical and managerial experience relevant to the project.
Document1 99
__________________________
(Name and Signature of the Proposed Personnel)
Bank Guarantee for Tender Security (Form PW5-6)
[This is the format for the Tender Security to be issued by an internationally reputable Bank which has a
correspondent Bank located in Bangladesh in accordance with ITT Clause 31 & 32]
To:
[Name and address of the Employer]
We have been informed that [name of Tenderer] (hereinafter called “the Tenderer”) intends to
submit to you its Tender dated [date of Tender] (hereinafter called “the Tender”) for the execution
of the Works of [description of works] under the above Invitation for Tenders (hereinafter called
“the IFT”).
Furthermore, we understand that, according to your conditions, the Tender must be supported by
a Bank Guarantee for Tender Security.
At the request of the Tenderer, we [name of bank] hereby irrevocably undertake to pay you, without
cavil or argument, any sum or sums not exceeding in total an amount of USD/GBP/EU R/JPY [insert
delete not appropriat e
BangladeshTaka
amount in figures and words] and/or [insert amount in figures and words] upon
deleteif not appropriate
receipt by us of your first written demand accompanied by a written statement that the Tenderer is
in breach of its obligation(s) under the Tender conditions, because the Tenderer:
a. has withdrawn its Tender after opening of Tenders but within the validity of the Tender
Security; or
b. refused to accept the Notification of Award (NOA) within the period as stated under
ITT; or
c. failed to furnish Performance Security within the period stipulated in the NOA; or
d. refused to sign the Contract Agreement by the time specified in the NOA; or
e. did not accept the correction of the Tender price following the correction of the
arithmetic errors as stated under ITT.
(a) if the Tenderer is the successful Tenderer, upon our receipt of a copy of the
Contract Agreement signed by the Tenderer or a copy of the Performance Security
issued to you in accordance with the ITT;
or
(b) if the Tenderer is not the successful Tenderer, twenty eight (28) days after the
expiration of the Tenderer’s Tender validity period, being [date of expiration of the
Tender validity plus twenty eight (28) days ].
Consequently, we must receive at the above-mentioned office any demand for payment under this
guarantee on or before that date.
[Name of Contractor]
This is to notify you that your Tender dated [insert date] for the execution of the Works for
[name of project/Contract] for the Contract Price of USD/GBP/EU R/JPY [insert amount in figures and
delete not appropriat e
BangladeshTaka
words] and [insert amount in figures and in words], as corrected and modified
deleteif not appropriate
in accordance with the Instructions to Tenderers, has been approved by [name of Employer].
issuance of this Notification of Award but not later than (specify date), in
accordance with ITT Clause 63.2.
iii. sign the Contract within twenty eight (28) days of issuance of this Notification
of Award but not later than (specify date), in accordance with ITT Sub Clause
65.2.
You may proceed with the execution of the Works only upon completion of the above tasks.
You may also please note that this Notification of Award shall constitute the formation of this
Contract which shall become binding upon you.
We attach the draft Contract and all other documents for your perusal and signature.
Signed
Date:
Document1 101
Contract Agreement (Form PW5-8)
THIS AGREEMENT made on this [day] day of [month] [year] between [name and address of
Employer] (hereinafter called “the Employer”) of the one part and [name and address of Contractor]
(hereinafter called “the Contractor”) of the other part:
WHEREAS the Procuring Entity invited Tenders for certain works named [brief description of works]
and has accepted the Tender submitted by the Tenderer for the execution of those works in the
BangladeshTaka
sum of USD/GBP/EU R/JPY [insert amount] and/or [insertamount][Contract price in figures
deleteif not appropriate
delete not appropriat e
and in words] (hereinafter called “the Contract Price”).
2. The documents forming the Contract shall be interpreted in the following order of priority:
(a) the signed Contract Agreement
(b) the Notification of Award
(c) the completed Tender and the appendices to the Tender
(d) the Particular Conditions of Contract
(e) the General Conditions of Contract
(f) the Technical Specifications
(g) the General Specifications
(h) the Drawings
(i) the priced Bill of Quantities and the Schedules
(j) any other document listed in the PCC forming part of the Contract.
4. The Procuring Entity hereby covenants to pay the Contractor in consideration of the
execution and completion of the works and the remedying of defects therein, the Contract
Price or such other sum as may become payable under the provisions of the Contract at
the times and in the manner prescribed by the Contract.
IN WITNESS whereof the parties hereto have caused this Agreement to be executed in
accordance with the laws of Bangladesh on the day, month and year first written above.
Signature
Name
National ID No.
Title
In the presence
of
Name
Address
To:
We have been informed that [name of Contractor] (hereinafter called “the Contractor”) has
undertaken, pursuant to Contract No [insert reference number of Contract] dated [insert date of
Contract] (hereinafter called “the Contract”), the execution of works [description of works] under
the Contract.
Furthermore, we understand that, according to your conditions, the Contract must be supported
by a Bank Guarantee for Performance Security.
At the request of the Contractor, we [name of bank] hereby irrevocably undertake to pay you,
without cavil or argument, any sum or sums not exceeding in total an amount of
BangladeshTaka
USD/GBP/EU R/JPY/BDT and/or [insert amount in figures and in words] upon receipt
deleteif not appropriate
delete not appropriat e
by us of your first written demand accompanied by a written statement that the Contractor is in
breach of its obligation(s) under the Contract conditions, without you needing to prove or show
grounds or reasons for your demand of the sum specified therein.
This guarantee is valid until [date of validity of guarantee], consequently, we must receive at the
above-mentioned office any demand for payment under this guarantee on or before that date.
Document1 103
Bank Guarantee for Advance Payment (Form PW5-10)
[This is the format for the Advance Payment Guarantee to be issued by an internationally reputable Bank which
has a correspondent Bank located in Bangladesh in accordance with GCC Clause 78]
To:
We have been informed that [name of Contractor] (hereinafter called “the Contractor”) has
undertaken, pursuant to Contract No [insert reference number of Contract] dated [insert date of
Contract] (hereinafter called “the Contract”), the execution of works [description of works] under
the Contract.
Furthermore, we understand that, according to your Conditions of Contract under GCC Clause 78,
the Advance Payment on Contract must be supported by a Bank Guarantee.
At the request of the Contractor, we [insert name of bank] hereby irrevocably undertake to pay you,
without cavil or argument, any sum or sums not exceeding in total an amount of
BangladeshTaka
USD/GBP/EU R/JPY/BDT and/or [insert amount in figures and in words] upon receipt
deleteif not appropriate
delete not appropriat e
by us of your first written demand accompanied by a written statement that the Contractor is in
breach of its obligation(s) under the Contract conditions, without you needing to prove or show
grounds or reasons for your demand of the sum specified therein.
We further agree that no change, addition or other modification of the terms of the Contract to be
performed, or of any of the Contract documents which may be made between the Employer and
the Contractor, shall in any way release us from any liability under this guarantee, and we hereby
waive notice of any such change, addition or modification.
This guarantee is valid until [insert date of validity of guarantee], consequently, we must receive at
the above-mentioned office any demand for payment under this guarantee on or before that date.
Demand Guarantee
We have been informed that [insert name of Contractor] (hereinafter called "the Contractor") has
entered into Contract Number [insert reference number of the Contract] dated [insert date] with you, for
the execution of [insert name of Contract and brief description of Works] (hereinafter called "the
Contract").
Furthermore, we understand that, according to the conditions of the Contract, when the Taking-Over
Certificate has been issued for the Works and the first half of the Retention Money has been certified
for payment, payment of [insert the amount of the second half of the Retention Money] which becomes
due after the Defects Liability Period has passed and certified in the form of Defects Correction
Certificate, is to be made against a Retention Money Guarantee.
At the request of the Contractor, we [insert name of Bank] hereby irrevocably undertake to pay you any
BangladeshTaka
sum or sums not exceeding in total an amount of USD/GBP/EU R/JPY/BDT and/or [insert
deleteif not appropriate
delete not appropriat e
amount in figures and words]) upon receipt by us of your first demand in writing accompanied by a
written statement stating that the Contractor is in breach of its obligation under the Contract because
the Contractor failed to properly correct the defects duly notified in respect of the Works.
It is a condition for any claim and payment under this guarantee to be made that the payment of the
second half of the Retention Money referred to above must have been received by the Contractor on
its account number[insert A/C no] at [name and address of Bank].
This guarantee is valid until [insert the date of validity of Guarantee that being twenty eight (28)
days beyond the Defects Liability Period]. Consequently, we must receive at the above-mentioned
office any demand for payment under this guarantee on or before that date.
Document1 105
Section 6. Bill of Quantities
Objectives
(b) when a Contract has been entered into, to provide a priced BOQ for use in the
periodic valuation of Works executed.
In order to attain these objectives, the items in the Bill of Quantities should be grouped into
sections to distinguish between those parts of the Works that by nature, location, access,
timing, or any other special characteristics may give rise to different methods of
construction, phasing of the Works, or considerations of cost. General items common to all
parts of the Works may be grouped as a separate section in the Bill of Quantities. Consistent
with these requirements, the layout and content of the BOQ should be as simple and brief
as possible. Quantities should be computed net from the Drawings, unless directed
otherwise in the Contract, and no allowance should be made for bulking, shrinkage, or
waste. Quantities should be rounded up or down where appropriate and spurious accuracy
should be avoided.
The quantities given in the Bill of Quantities are estimated and provisional, and are given to
provide a common basis for Tendering. The basis of payment will be the actual quantities
of work ordered and carried out, as measured by the Contractor and verified by the Engineer
and valued at the rates or prices quoted in the priced Bill of Quantities, where applicable,
and otherwise at such rates or prices as the Engineer may fix within the terms and conditions
of the Contract.
The method of measurements of completed works for payment shall be based on metric
system unless otherwise unavoidable.
Bill of Quantities
[ITT Clause 24]
Name of Works:___________________________________________________________
Document1 107
IFT No.____________ Package No.______________Lot No._________
1 2 3 4 5 6 7=6 8=5x6
1 2 3 4 5 6 7=6 8=5x6
& so on & so on
above are examples only
B. DM 200 MATERIALS
DM 202 Cement kg
DM 203 GI Pipe m
& so on
& so on
above are examples only
Note:
1. Nominal quantities in the schedule shall remain invariable and shall also require prior approval of the authority
sanctioning the official estimate.
2. Follow the Guidance Notes under Section 6 in filling this Schedule.
Document1 109
Daywork Summary
In Words
___________________________________________________________________________
Note:
This Summary refers to Schedule of Dayworks
___________________________________________________________________________
Note:
1. Appointment of Nominated Subcontractor(s) shall follow due procedures and shall require prior approval of
the Competent Authority.
2. Provisional Sums for meeting expenditures other than those for Nominated Subcontractor (s) may not exceed
one (1) percent of the estimated Contract price and its inclusion in the BOQ shall also require prior approval
of the authority sanctioning the official estimate.
3. Follow the Guidance Notes under Section 6 in filling this Schedule.
Document1 111
Grand Summary
Name of Works:___________________________________________________________
IFT No.____________ Package No.______________Lot No._________
Notes on Specifications
A set of precise and clear specifications is a prerequisite for Tenderers to respond realistically and
competitively to the requirements of the Procuring Entity without introducing deviations or conditionalities
in their Tenders. In the context of national competitive Tendering, the specifications must be drafted to
permit the widest possible competition and, at the same time, present a clear statement of the required
standards of workmanship, materials, and performance of the works to be procured. Only if this is done
will the objectives of economy, efficiency, and fairness in procurement be realized, responsiveness of
Tenders be ensured, and the subsequent task of Tender evaluation facilitated. The specifications should
require that all goods and materials to be incorporated in the Works be new, unused, of the most recent
or current models, and incorporate all recent improvements in design and materials, unless provided
otherwise in the Contract.
Samples of specifications from previous similar projects are useful in this respect. Most specifications
are normally written specially by the Procuring Entity or Engineer to suit the Contract Works in hand.
There is no standard set of Specifications for universal application in all sectors, but there are established
principles and practices, which are reflected in these documents.
There are considerable advantages in standardizing General Specifications for repetitive Works in
recognized public sectors, such as highways, ports, railways, urban housing, flood control, drainage and
irrigation, and water supply, where similar conditions prevail. The General Specifications should cover
all classes of workmanship, materials, and equipment commonly used in construction, although not
necessarily to be used in a particular Works Contract. Deletions or addenda should then adapt the
General Specifications to the particular Works. Such General Specifications are those issued by the
specialised ministries/professional bodies in Bangladesh and/or those of the International Standards
Organisation (ISO)
Care must be taken in drafting specifications to ensure that they are not restrictive. In the specification
of standards for goods, materials, and workmanship, recognized national standards should be used as
much as possible. Where other particular standards are used the specifications should state that goods,
materials, and workmanship that meet other authoritative standards, and which ensure substantially
equal or higher quality than the standards mentioned, will also be acceptable.
Provision as such be kept that wherever reference is made in the Contract to specific standards and
codes to be met by the goods and materials to be furnished, and work performed or tested, the provisions
of the latest current edition or revision of the relevant standards and codes in effect shall apply, unless
otherwise expressly stated in the Contract.
THESE NOTES FOR PREPARING SPECIFICATIONS ARE INTENDED ONLY AS INFORMATION FOR
THE PROCURING ENTITY OR THE PERSON DRAFTING THE TENDER DOCUMENT AND SHOULD
NOT BE INCLUDED IN THE FINAL TENDER DOCUMENT.
Document1 113
Section 8. Particular Specifications
Notes on Particular Specifications
If an item of the Works is not covered in the General Specifications or if any specification clause
requires that further details as to precise requirements for the particular Works are to be given or
needs to be modified or clarified then these should be reflected in the Particular Specifications.
Where the Particular Specification clause replaces or clarifies an existing clause of the General
Specification then the same clause numbering system need to be followed.
Notes on Drawings
Insert here a list of Drawings. The actual Drawings, including site plans, should be attached to
this section or annexed in a separate folder. The Drawings shall be dated, numbered and show
the revision number.
Document1 115
FORMAT
The Invitation for Tenders (IFT) is a copy of the standard format as appears on the website and used
for published advertisement that provides relevant and essential information to help Tenderers to
decide whether or not to participate in the particular Tender. This is provided in the Tender Document
for information only. This should not be included in the TENDER DOCUMENT.
<select> : these fields are “pop-up” fields and the Employer will only have to select the correct name, address or
date in order to complete the form.
<type in name> : these fields are to be completed by typing in the relevant data.
Document1 117
Invitation for Tenders
[for use when there are MULTIPLE lots in a package
This is the website format and as used for published advertisement.
It is included in this document for information only]
GOVERNMENT OF THE PEOPLE’S REPUBLIC OF BANGLADESH
1 Ministry/Division < select > V
2 Agency < select > V
3 Procuring Entity Name < type in name >
4 Procuring Entity Code Not used at present
5 Procuring Entity District < select > V
6 Invitation for < select > V < select > V < select > V
7 Invitation Ref No < type in name >
8 Date < select > V
KEY INFORMATION
9 Procurement Method < select > V < select > V
FUNDING INFORMATION
10 Budget and Source of Funds < select > V
11 Development Partners (if applicable) < type in name >
PARTICULAR INFORMATION
12 Project / Programme Code (if applicable) < use MOF code >
13 Project / Programme Name (if applicable) < use MOF name >
14 Tender Package No. < type in name >
15 Tender Package Name < type in name >
Date
16 Tender Publication Date < select > V
17 Tender Last Selling Date < select > V
(must be the date prior to the day of Tender
Closing Date)
Date Time
18 Tender Closing Date and Time < select > V < select > V
19 Tender Opening Date and Time < select > V < select > V
(within one hour of Tender Closing at primary
place)
20 Name & Address of the office(s) Address
- Selling Tender Document (Principal) < type in name >
- Selling Tender Document (Others) < type in name >
- Downloading Tender Document
(This is optional. If permitted by the Procuring Entity;
mention the web address where the electronic
version of TD will be available. Specify the detail
procedures for payment of the cost of TD by the
Tenderers.)
NO CONDITIONS APPLY FOR SALE , PURCHASE OR DISTRIBUTION OF TENDER DOCUMENTS
- Receiving Tender Document < type in name >
- Opening Tender Document < type in name >
21 Place / Date / Time of < type in name >
Pre-Tender Meeting (Optional) Date Time
< select > V < select > V
INFORMATION FOR TENDERER
22 Eligibility of Tenderer < type in name >
23 Brief Description of Works < type in name >
24 Brief Description of Physical Services < type in name >
25 Price of Tender Document < type in price >
Lot No Identification of Lot Location Tender Security Amount Completion Time in
Weeks / Months
26 1 < type in name > < type in name > <type in> <type in>
27 2 < type in name > < type in name > <type in> <type in>