Mwea Irrigation Development Project-Development of Resettlement Areas NIB/T/004/2012-2013

Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 1

MWEA IRRIGATION DEVELOPMENT PROJECT- DEVELOPMENT OF RESETTLEMENT AREAS

NIB/T/004/2012-2013

CONTRACTOR PERFORMANCE REPORT

General information

Contractor name: ____________________________Contract No. ______________________________________

Contract description: __________________________________________________________________________

Original contract period: ______________________ Date of commencement: ____________________________

Original date for completion: ___________________ EOTs approved: ___________________________________

Actual date of completion: ___________________

Original contract price: ______________________ Final Contract Price_______________________

Contractor’s performance

Unsatisfactory Acceptable Good Superior

Time management

Standard of work

Quality systems

Quality of site personnel

Management of subcontractors

Contract administration

Health and safety management

Workforce or skills development

Cooperative relationships

Other

Overall performance

Suitability for further work Not Suitable Suitable

If ‘’not suitable’’ detailed


reasons must be given
The report has been forwarded to Contractor yes no

Recommended for further work yes no

If the recommendation is no, the unsatisfactory performance aspects have been discussed with:

Name of contractor’s representative_______________________________________

Telephone_____________________ Date of discussion_______________

Minutes of meeting and contractor’s response

Yes No

_________________________________ ________________________
Project Manager Date