H 231
H 231
H 231
ENGINEERING SPECIFICATION
PDVSA N° TITLE
PDVSA
REVISION FECHA
Index
1 GENERAL . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3
1.1 Scope . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3
1.2 Specifications, Codes and Standards . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3
1.3 Regulations . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4
2 MATERIALS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4
2.1 Pipe and Fittings . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4
2.2 Bolting and Gaskets . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4
3 FABRICATION . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5
4 DRAWING . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5
5 CUTTING AND BEVELING . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5
5.1 Beveling . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5
5.2 Flame Cutting . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6
6 BENDING . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6
6.1 General . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6
6.2 Miter Bends . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6
6.3 Elbows . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6
6.4 Branch Connections . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6
7 FIT–UP JOINT . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 8
7.1 Line Joints . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 8
7.2 Tee and Lateral Joints . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 8
7.3 Flanges . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 8
8 WELDING . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 9
8.1 General . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 9
8.2 Welding Process . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 9
8.3 Welding Electrodes . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 9
8.4 Selection of Welding Electrodes . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 10
9 HEAT TREATMENTS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 10
9.1 Weldments . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 10
9.2 Special Heat Treatments . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 11
10 FINAL CORRECTIONS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 11
11 TOLERANCES . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 11
12 INSPECTION AND TESTS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 11
12.1 Inspection of Welds . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 11
12.2 Hardness Test . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 12
ENGINEERING SPECIFICATION PDVSA H–231
PDVSA
REVISION FECHA
1 GENERAL
1.1 Scope
1.1.1 This specification contains general, fabrication details, inspection and testing
requirements applicable to process and utility piping systems shop or field
fabricated. Piping or pipeline out of the scope of ASME Code B31.3 is not covered
by this specification.
1.1.2 Fabrication under this specification includes all components of a piping system, or
part thereof, entering into fabricated assemblies, but shall exclude all valves,
bolting, gaskets, flanged fittings, blind flanges, orifice plates, and all specialty items
PDVSA
REVISION FECHA
1.3 Regulations
Should there be any conflict between Venezuelan laws, standards and regulations,
this specification and ASME standards, the order of prevalences shall be as
follows:
1. Venezuelan laws, standards and regulations
2. This specification
3. ASME
2 MATERIALS
2.1 Pipe and Fittings
The material specification for each piping assembly will be indicated on the
Owner’s Drawings and/or in PDVSA Engineering Specification H–221, “Piping
Materials”, which supersede this specification in case of conflict.
PDVSA
REVISION FECHA
3 FABRICATION
3.1 For steam boilers, proper piping and external piping shall be identified accordingly.
3.2 The type of flanges, fittings, and connections shall be indicated on Owner’s
drawings and/or in the PDVSA Engineering Specification H–221, “Piping
Materials”.
3.3 Longitudinal or helical seams in adjoining lengths of welded pipe shall be staggered
and located to clear openings and external attachments.
4 DRAWING
4.1 Owner’s representative reserves the right to check sub–assembly fabricator’s
detail drawings and sketches total or partially, prior to initiate fabrication, in order
to guarantee Owner’s requirements.
4.2 The Fabricator shall be responsible for detail drawings and sketches conforming
with the Owner’s requirements.
4.3 Piping shall be fabricated in accordance with drawings. Pre fabricated spool pieces
shall be per isometric drawings.
4.4 Field weld symbol (FW) shall be indicated on drawings or isometrics for spools
where distances, separations or lengths are accurately known and no field
adjustment is required. Otherwise, fit field weld (FFW) symbol shall be indicated.
In this case, an extra length of 152 mm (6 inches) shall be provided for the straight
pipe portion to be adjusted.
No FW or FFW symbols indicate full welding.
4.5 Typical cases for FW and FFW for carbon steel pipes 4 inches and larger; and for
alloy steel pipes 3 inches and larger are:
FW:
– Straight piping requiring weld joints.
– Spools just for truck transportation.
– Spools to be installed close to or between “hard to access” existing piping.
FFW:
– To connect with rotating or static equipment.
– To connect with existing piping.
PDVSA
REVISION FECHA
5.1.2 Beveled ends may be cut, shaped and beveled for welding by machining, sawing
or grinding, or flame beveling.
6 BENDING
6.1 General
6.1.1 Piping bending shall be in accordance with PDVSA Engineering Specification
H–223, “Pipeline and Pipe Bends”.
6.3 Elbows
6.3.1 Elbows shall be long radius and buttwelding ends, unless otherwise approved by
Owner’s representative.
PDVSA
REVISION FECHA
6.4.2 Where possible and economical, connections for 2 inches NPS and greater
headers shall be made up by welding tee, weldolets or sockolets. Otherwise,
branch connections made up by welded nozzles may be used. In all cases,
requirements of ASME Code 31.3 shall be accomplished.
6.4.3 Integrally reinforced branch connections for 4 inches NPS or greater headers are
not permitted if:
a. d/D ratio is greater than 0,8.
D = header nominal diameter; d = branch nominal diameter
b. Header thickness is less than schedule standard thickness for same pipe.
c. Header thickness is less than 19 mm (0,75 in), nominal pipe size exceeds
36 inches and operating temperature is 426 °C (800 °F) or greater.
6.4.4 When branch and header nominal diameters are identical, branch shall be
reinforced with an encircled plate (full header diameter), with a length of twice
branch diameter and same thickness of header, at least.
6.4.5 Branch connections for 1–1/2 inch and smaller nominal diameter headers. Where
possible and economical, branch connections shall be made up by using straight
or reducing socket weld tee or sockolets. If using a coupling or half coupling, two
90º separated gusset strips, welded to pipe, shall be used. Gusset strips shall be
of compatible metallurgy of header and branch. For carbon steel, use P–1, P–3,
P–4 or P–5 strips (See Figure 3).
6.4.6 Minimum wall thickness for 2 inch or smaller niples.
PDVSA
REVISION FECHA
6.4.9 A pneumatic test shall be done after welding reinforcing plates, at a pressure of 0,7
– 1,03 barg (10 – 15 psig) for at least, 5 minutes. No leaks are permitted. Hole shall
be filled with appropiated grease to prevent from entering water.
7 FIT–UP JOINT
7.1 Line Joints
7.1.1 Non–consumable backing rings shall not be used.
7.1.2 All fit–ups and tack welds must be made to the satisfaction of the Buyer’s Inspector.
7.3 Flanges
7.3.1 Whenever possible, bolt holes of flanges in the vertical lines shall straddle the
north–south centerline of the pipe in the erected position. For flanges in the
horizontal lines, bolt holes shall straddle the vertical centerline unless otherwise
indicated on the Owner’s drawing.
7.3.2 Orifice flanges shall be welded to pipe with the drilled holes as shown on isometric
drawings.
ENGINEERING SPECIFICATION PDVSA H–231
PDVSA
REVISION FECHA
7.3.3 Slip–on flanges shall be provided with a vent and pneumatic test 1/8 inch NPT
drilled hole on the neck prior to welding.
7.3.4 A pneumatic test shall be done after welding of slip–on flanges, at a pressure of
0,7 – 1,03 barg (10 – 15 psig), for, at least, 5 minutes.
No leaks are permitted. Hole shall be filled with appropriate grease to prevent from
entering water.
8 WELDING
8.1 General
8.1.1 All welding of pressure parts of pipe, whether shop or field, shall be done by
qualified welders in accordance with the ASME Boiler and Pressure Vessel Code,
ASME Code for Process Piping and Owner’s qualification test.
8.1.2 In addition, the requirements of all jurisdictional codes within which the piping
systems are to be installed shall be met.
8.1.3 All field welding done by the piping Contractor or Owner shall be in accordance with
the applicable welding procedures approved by Owner.
8.1.4 Each welder or welding operator must successfully pass the Performance
Qualification Test Requirement in exact accordance with the details of the welding
procedures as submitted.
8.1.5 The piping Contractor shall also be required to conduct welder or welding operator
performance qualification tests as required by the Owner prior to the start of
production welding.
PDVSA
REVISION FECHA
9 HEAT TREATMENTS
9.1 Weldments
9.1.1 The annealing of nickel or chrome–molly steel may be substituted for
stress–relieving if approved by the Owner provided that:
a. The welding procedure is qualified in accordance with ASME B31.3 in a
thickness equal to or greater than the thickness of material to be welded in
production and the hardness requirements of paragraph 12.2 and ASME
B31.3 are met.
9.1.2 Heating by open torches is not permitted.
9.1.3 Minimum of two thermocouples on each weld are required when stress relieving
is done on ferritic alloy steels by localized heating.
9.1.4 Weldments in enclosed furnaces or oil heaters may be given their required thermal
treatments by heating the entire furnace to appropriate temperatures.
9.1.5 Adequate thermocouples shall be used to ensure that all weldments are properly
heated.
9.1.6 Piping shall be heated to a warm hand condition prior to welding when ambient
temperatures are below 10° C (50° F).
9.1.7 Heat treatment is required for all H2S service carbon steel line weldings, except as
indicated herein:
a. A solution with a concentration less than 50 ppm.
b. Multiple pass weldings in seamless pipes, done from outer surface only.
ENGINEERING SPECIFICATION PDVSA H–231
PDVSA
REVISION FECHA
c. External welding elements (gusset strips, clips, pipe supports, etc.), where
deposited metal does not touch wet H2S
d. Seal multipass weldings
e. Multipass weldings for branch connections, done from outer surface only
9.1.8 Heat treatment is required for all alkaline solution services line weldings, such as:
a. Alkali metal hydroxide caustic solutions, such as sodium or potassium
hydroxide
b. Amines defined as solutions for acid gas absorption or removal of acidic
components (i.e. H2S, CO2) from hydrocarbons and hydrogen streams.
These include monoethanolamine (MEA), diethanolamine (DEA), methyl
diethanolamine (MDEA) and FLEXSORB amines.
9.1.9 After heat treatment, no clips, gusset strips, support or any element shall be
welded to pipe wall, unless affected area be heat treated again following ASME
Code requirements.
10 FINAL CORRECTIONS
10.1 For carbon steel pipe, if any additional bending is required after the completion of
fabrication to meet dimensional requirements, such bending or correcting may be
made by any suitable method subject to the approval of the Owner’s Inspector.
10.2 For austenitic alloy pipe, and ferritic alloy steel pipe after final heat treatment, all
corrections must be made cold without the application of any heat.
10.3 If it is impossible to make the correction in ferritic alloy pipe cold, the piece should
be heated by a controlled method to 680° C to a maximum of 730° C.
11 TOLERANCES
11.1 See Figure 1, Dimensional Tolerances.
PDVSA
REVISION FECHA
12.1.2 The standards of acceptability for all radiographs shall be ASME B31.3.
12.1.3 All joints subject to 100% radiographic inspection shall have complete penetration.
12.1.4 For welds made with inert gas welding techniques, which are subject to
radiographic inspection, the radiographic standard of acceptability shall include
additional requirements as follows:
a. The root of the weld shall show a smooth contour and no evidence of
non–fused land at the edges of the base material.
b. “Sink” or depression of the root pass shall not result in a total thickness,
including weld reinforcement, which is less than the original wall thickness of
the material being welded. The total length of depression of the root pass shall
not exceed 20% of the circumference of the pipe.
13 SHIPMENT
13.1 Preparation for Shipment
13.1.1 All pipe shall be dry and free from all water, dirt, and loose foreign materials.
ENGINEERING SPECIFICATION PDVSA H–231
PDVSA
REVISION FECHA
a. All hot bends must be turbined or otherwise cleaned to completely remove all
adherent burned–on sand.
b. Special cleaning, such as sandblasting and chemical cleaning shall be done
only when required by the applicable Line Spec. of PDVSA Engineering
Specification H–221, “Piping Materials”.
c. Acid cleaning is not permitted on stainless steel piping.
d. Brushes or pads used on stainless steel shall be stainless steel and used only
for stainless steel.
13.1.2 All flange faces, thread ends, and other machined surfaces of all piping materials
shall be coated with grease type rust preventative applied as recommended by the
manufacturer. The brand of grease used must be approved by the Owner’s
Inspector.
13.1.3 All flange faces shall be protected against damage in shipment by suitable covers
of wood or plastic.
a. The covers shall be securely and tightly attached by at least three bolts or by
wiring through at least four bolt holes.
b. Threaded ends shall be provided with plastic thread protectors.
c. Beveled ends shall be protected with plastic caps.
PDVSA
REVISION FECHA
1
SPECIAL SERVICES
a. Design Temperature w
NORMAL 850 °F or Flange Rating
ITEM SERVICE w ASME Class 900
b. Where plastic or
elastomeric lines (lapped
over the flange faces)
$1/8 in. max. from indicated dimensions for face to face, center
1 provides
to face, location of attachments, etc. the gasket for
the joint
3 Bend flattening tolerance shall be in accordance with the
2 applicable code c. Piping over NPS 3 to be
connected to rotating
$1/8 in. max machinery
lateral translation $1/16 in. max. lateral translation of branches
3 of branches or or connections.
connections
$1/16 in. max. rotation of flanges from the indicated position,
measured as shown.
4 4
$1/64 in. for piping over NPS 3 to be connected to rotating
machinery
Per the applicable $1/64 in. max. out of alignment of flanges
5 Code from the indicated position, measured across
any diameter
PDVSA
REVISION FECHA
MAXIMUM PERMISSIBLE
DESIGN PRESSURE
PDVSA
REVISION FECHA
Fig 3.
Weld Gussets
to Strap
Use Reinforcement
Pad with Gussets
Note: Minimize the distance from the main line to the valve or weight
ENGINEERING SPECIFICATION PDVSA H–231
PDVSA
REVISION FECHA
Fig 4.
Two plane gusseting
General Note:
Bracing detail appliable to extended body type valve,
or compact body valve plus nipple (as illustrated)
9 in max.
(228 mm)