Vindair Engineers Pvt. LTD: Sl. No Description Observation Remarks

This document provides a checklist of prerequisites for validating an air handling unit (AHU) installation. It lists over 30 items that must be observed and verified, including confirming that ducting, dampers, filters, sensors, utilities and more are installed correctly before validation can begin. The checklist emphasizes cleaning the area and AHU, ensuring power and utilities are stable, and enforcing material movement discipline.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
100% found this document useful (1 vote)
150 views3 pages

Vindair Engineers Pvt. LTD: Sl. No Description Observation Remarks

This document provides a checklist of prerequisites for validating an air handling unit (AHU) installation. It lists over 30 items that must be observed and verified, including confirming that ducting, dampers, filters, sensors, utilities and more are installed correctly before validation can begin. The checklist emphasizes cleaning the area and AHU, ensuring power and utilities are stable, and enforcing material movement discipline.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 3

VINDAIR ENGINEERS PVT.

LTD
Page No:
1 of 3
PREREQUISITES CHECK LIST – VALIDATION

SL. NO DESCRIPTION OBSERVATION REMARKS

AHU Installed with complete


1
accessories

Fan & Motor installed and alignment


2
completed

Utilities like Chilled water/brine,


3 Electrical connection and HOT water
connected

Chilled water Pipe Hydro tested and


4
insulated

Ducting completed, Duct leak test


5 done and all leaks arrested and
insulated

All dampers checked for proper


6
functioning

7 All grilles/diffuser installed

Is AHU deep cleaned and blow down


8
completed?

9 Is AHU pre and fine filter installed?

All areas catered by this AHU


construction is complete with flooring,
1
false ceiling, light fittings, doors view
panels and other utilities?

2 Is area “Deep Cleaned”?

DOCUMENT NO: VEPL//01


VINDAIR ENGINEERS PVT. LTD
Page No:
2 of 3
PREREQUISITES CHECK LIST – VALIDATION

SL. NO DESCRIPTION OBSERVATION REMARKS

All field sensors installed, loop


1
checked and calibrated

2 Is VFD installed and commissioned?

All filters in AHU installed as per


1
specification and GA drgs?

All Terminal filters installed as per


2
specification and GA drawings?

Magnehelic gauges/DP sensors


1
installed and calibrated?

All leaks in area like cut outs for utility


2 pipes, electrical pendants,
instrumentation pendants closed?

The machines with exhaust to be


3
switched on.

The man & material movement


4
discipline is enforced strictly.

All doors, view panels, Pass box etc


5
are installed?

The power is made available


6 uninterrupted to attain stability in
conditions.

DOCUMENT NO: VEPL//01


VINDAIR ENGINEERS PVT. LTD
Page No:
3 of 3
PREREQUISITES CHECK LIST – VALIDATION

SL. NO DESCRIPTION OBSERVATION REMARKS

The preliminary fiters like EU3, 4 & EU


1 7, 8 ,as the case may be, should be
installed in the AHUs.

The fiters in the RA path like EU3, 4 as


2
the case may be should be installed.

Hepa filters to be installed and visible


3
gaps sealed with silicon sealent.

Cable connections to be checked at


4
fan motor end & panel end.

he utility viz. CHW / CHB / HW/ Steam


1 to be made available at the requisite
conditions.

2 Internal load to be switched on.

Chilled Water / Brine system is


3
balanced

The power is made available


4 uninterrupted to attain stability in
conditions.

Area deep cleaned and gowning


1
procedures

The man & material movement


2
discipline is enforced strictly.