100% found this document useful (1 vote)
553 views9 pages

Template

The document provides a template for a cost management plan with sections for project details, cost estimation, baseline, control and reporting processes, budget, and approval. It aims to compile all aspects of cost management to ensure costs are properly planned and monitored throughout the project.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
100% found this document useful (1 vote)
553 views9 pages

Template

The document provides a template for a cost management plan with sections for project details, cost estimation, baseline, control and reporting processes, budget, and approval. It aims to compile all aspects of cost management to ensure costs are properly planned and monitored throughout the project.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
You are on page 1/ 9

COST MANAGEMENT PLAN TEMPLATE

This template enables you to compile and complete each aspect of a project Cost Management Plan one of the most critical plans required for all
projects. This plan provides a detailed record of the processes that will be adhered to ensuring project costs are properly managed. One of these
process that is critical to any project’s successful completion is the one that defines the actions required when a cost variance occurs.
Without careful and detailed planning project costs can be miss communicated to stakeholders and its sponsor. This is because of a poor or lack of
explanation as to what the costs covers and any assumptions that have been made in the process of detailing these costs. A project manager must
have the processes and reporting structure in place to ensure that costs are accurately monitored and controlled. This arrangement guarantees
that the cost base is well managed throughout the project’s duration and that the final product is delivered to the approved budget.
The Work Breakdown Structure (WBS) along with the scope and schedule baselines allows the costs of each activity to be properly estimated. An
description of how these figures have been calculated including what assumptions and where appropriate what constraints have been made to
arrive at this figure. The cost performance baseline is created and forms the basis for presenting the final project budget to the sponsor and
stakeholders for approval.
A project cost management plan has the following elements. Each will relate to the culture of the organization and the nature of the project being
undertaken.
 Unit of measure (used to create the estimates)
 Level of precision (extent of rounding up or down that has been used)
 Level of accuracy (e.g. 10%)
 Organizational procedures links (WBS gives the framework & control account for the plan)
 Control thresholds (cost variance that will be tolerated before action is needed)
 Rules of performance measurement (e.g. EVM – Earned Value Measurement)
 Reporting formats & frequency
 Description of all cost processes.

DESCRIPTION: this page details the typical items found on the cover of cost management plan. Amend its
FRONT COVER
contents to reflect the needs of your specific project and organization’s culture.
 Author / Project manager is listed along with their contact details.
 Project Name that this plan relates to.
 Version & date of Cost Management Plan
Displays a top-level summary of
– Version history will be shown in relevant appendix.
essential information relating to
the Cost Management Plan.  Approval:
– Lists the names and job titles of each person who as given approval and sign-off of this plan.
– The date and version they have approved accompany their signature.
 Circulation List of who (name, location & organization) has received stated version.

 www.free-management-ebooks.com All Rights Reserved


INTRODUCTION – outlines the purpose of this plan and describes how it will document and communicate with its stakeholders and other team
members.

COST MANAGEMENT PLAN SUMMARY – provides an overview of the cost management process as it applies to the project. The regularity of reporting
is clearly indicated and the percentage of variance (suggestions shown below in blue italics) required at different stages of formulating this plan.

PROJECT WORKING TITLE: VERSION: DATE:

REPORTING REQUIREMENTS DEGREE OF ESTIMATION REQUIRED @

Frequency of Frequency of
Conception of Project 25%
Cost Monitoring: Cost Budget:

10%
Responsibility of: Project Charter
Email:
Contact Number: Alternative No.: Cost Baseline 5%

 www.free-management-ebooks.com All Rights Reserved


SPENDING LIMIT AUTHORITY LEVELS

$ COST LIMIT PROJECT POSITION NAME & CONTACT DETAILS

< $8,000

< $20,000

< $50,000

< $100,000

< $250,000

COST VARIANCE ACTION PLAN: outlines what actions need to be taken in the event of a cost variance occurring, alter the template examples
(shown below in blue italics) to reflect the needs of the organization and project. All variance must be detailed in reporting process as described in
this process and appropriate justification for the change.
VARIANCE % ACTION REQUIRED RESPONSIBILITY OF:

0-5% Report variance in reporting with explanation of cause.

Commitment to costs can only be given with Project Managers written approval &
5-20%
reported appropriately.
Written approval is needed from Project Sponsor & Project Manager, plus reported
20-45%
appropriately.
Necessary to re-estimate project work package or deliverable before presenting to
45-95% Project Sponsor, Project Manager & appropriate stakeholder if necessary. Only with
written approval of all parties can project continue.

+95% Abandon project - inform stakeholders & project sponsor

 www.free-management-ebooks.com All Rights Reserved


COST MANAGEMENT APPROACH – defines the procedures and policies that are designed to monitor, control and manage the project costs from
inception to closure. It will also outline how the planning and estimation of costs should be conducted and documented.

Procedures & Policies:

Documentation:

COST ESTIMATION – defines the process to be used when estimating costs for each of the project’s activities. This section defines the level of
variation as it relates to estimations as throughout the project duration. It classifies the units of measurement, precision, accuracy, thresholds, rules
of performance measurement and element of risk.

 www.free-management-ebooks.com All Rights Reserved


COST BASELINE – the WBS defines the project’s individual work packages / activities and is an integral part of developing an aggregate of cost
estimate for each package. This section also defines how the project will be funded including the control accounts, element of planned contingency
and management reserve.

COST CONTROL & REPORTING PROCESS – defines how costs are measured during the project and the metrics that need to be used in relation to
each threshold .

Cost Management Reporting Process:

 www.free-management-ebooks.com All Rights Reserved


CHANGE CONTROL PROCESS – describes the process that enables changes can be made to the cost baseline and the actions required for each
change to gain approval or be rejected.

PROJECT BUDGET – this section provides the final figures for each of the budget areas listed below that are appropriate to this version of the cost
management plan.

PROJECT BUDGET

$ ‘000 $ ‘000
Fixed Costs TOTAL Project Costs
Material Costs
Contractor Costs Management Reserve

 www.free-management-ebooks.com All Rights Reserved


Project Version:
Project Description:
Working Title: Date:
Project Contact tel: Plan Contact tel: Organization:
Sponsor: email: Author: email:

COST MANAGEMENT PLAN APPROVAL


Printed Name & Job Title Project Role Signature Date Approved
Project Sponsor
Appropriate Stakeholders

CIRCULATED TO:

- -
- -
- -
- -
- -

 www.free-management-ebooks.com All Rights Reserved


APPENDIX A – VERSION HISTORY

This appendix records the version history of this plan. For each new and approved version the reasoning behind its creation are described below
Version Date Release Date
Name of Implementation Author Approved by Reasoning behind new version
Number Revised Date Approved
1.0

APPENDIX B – GLOSSARY OF PROJECT TERMS

Each project uses standard acronyms and develops their own for the ease of communication. It is important to record them in this plan to ensure
clarity of description and terminology is consistent in every communication.

Acronym / Term Standard or Project Definition

PMO Project Management Office


SV Schedule Variance
CV Cost Variance
SPI Schedule Performance Index
CPI Cost Performance Index
EVM Earned Value Measurement

 www.free-management-ebooks.com All Rights Reserved


APPENDIX C – DOCUMENTATION REFERENCES

Any professionally managed project has extensive documentation the purpose of this appendix is to record which documents (plus the version
used, if applicable) have been used in the production of and in conjunction with of this plan.

No. & Version Document Author

 www.free-management-ebooks.com All Rights Reserved

You might also like