Data Required For Re Wall Input For Drawing

The document outlines the inputs and outputs required for designing and drawing a retaining wall. It lists inputs such as the finished road level, toe cut slope, and ground level that are needed to draw the wall. It also specifies required inputs for the design like soil properties and wall type. The outputs to check include templates for the drawing, sheet settings based on panel numbers, and details of construction methodology. The design output check includes items like soil properties, bearing pressure charts, and pad distances.

Uploaded by

Naresh Sharma
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
101 views1 page

Data Required For Re Wall Input For Drawing

The document outlines the inputs and outputs required for designing and drawing a retaining wall. It lists inputs such as the finished road level, toe cut slope, and ground level that are needed to draw the wall. It also specifies required inputs for the design like soil properties and wall type. The outputs to check include templates for the drawing, sheet settings based on panel numbers, and details of construction methodology. The design output check includes items like soil properties, bearing pressure charts, and pad distances.

Uploaded by

Naresh Sharma
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 1

DATA REQUIRED FOR RE WALL

SR. NO INPUT FOR DRAWING AVIALBILITY

1. FRL AT OUTER EDGE/PNP IN AUTOCAD WITH SUPERELVATION DETAIL/EXCEL

2. TCS IN AUTOCAD FOR CLOSING WALL

3. GAD IN AUTOCAD WITH SKEW ANGLE DETAIL ,IF ANY

4. SERVICE ROAD LEVEL AT RE WALL EDGE/SRL PNP/GL AT EDGE OF RE WALL/EXCEL

5. STARTING AND END OF RE WALL

a. AS PER TCS b. 1 m DIFFERENCE B/W FRL AND SRL/GL

6. PANEL NUMBERING

7. STRUCTURE IN RE WALL GAD(PIPE,BOX CULVERTS)

8. CLOSING WALL AS PER SKEW ANGLE

INPUT FOR DESIGN

1. SOIL PROPERTY ( MAIL/HARDCOPY)

2. TYPE OF RE WALL (BLOCK/PANEL)

3. PANEL TYPE

4. MINIMUM/MAXIMUM PAD DEPTH BELOW GL/SRL

OUTPUT CHECK FOR DRAWING

1. TAMPLATE CHECK(CLIENT,AUTHORITY,DESIGNER,RIVISION,DATE,SHEET NO,TITLE

2. SHEET SETTING AS PER PANEL NO./CHAINAGE

3. CONTRUCTION METHODLOGY /PANEL/BLOCK DRAWING (AS PER TYPE OF RE WALL AND


CONNECTION)

OUTPUT CHECK FOR DESIGN

1. FRONT PAGE CHECK(SOIL PROPERTY/CLIENT/LOCTION/SEISMIC

2. REPORT PAGE NU.

3. BEARING PRESSURE CHART

4. PAD DISTANCE

5. SOIL IMPROVEMENT IF REQUIRED OR SCOPE