Activity ID Activity Name Original Duration BL1 Start BL1 Finish Start Finish
Cochin Khayal Hotel first floor 219 06-Mar-18 01:00 27-Aug-18 16:00 06-May-18 16:00 A 10-Oct-18 12:00
Sub/super Structure works 219 06-Mar-18 01:00 27-Aug-18 16:00 06-May-18 16:00 A 10-Oct-18 12:00
Basement -02 Floor Slab Casting 219 06-Mar-18 01:00 27-Aug-18 16:00 06-May-18 16:00 A 10-Oct-18 12:00
Base slab Including Hexagon Pile cap 130 06-Mar-18 01:00 13-Jul-18 16:00 01-Jul-18 01:00 A 13-Jul-18 16:00
Hexagon 3 06-Mar-18 01:00 09-Mar-18 00:00 01-Jul-18 01:00 A 04-Jul-18 00:00 A
A7820 Reinforcement work 3 06-Mar-18 01:00 09-Mar-18 00:00 01-Jul-18 01:00 A 04-Jul-18 00:00 A
Trench 3 06-Mar-18 01:00 09-Mar-18 00:00 02-Jul-18 01:00 A 07-Jul-18 00:00 A
A7830 Reinforcement work 3 06-Mar-18 01:00 09-Mar-18 00:00 02-Jul-18 01:00 A 05-Jul-18 00:00 A
A7930 Pipe laying(supply of material by client) 1 06-Jul-18 00:00 A 07-Jul-18 00:00 A
Base slab 130 04-Jul-18 08:00 13-Jul-18 16:00 04-Jul-18 00:00 A 13-Jul-18 16:00
A7840 Backfilling for balance area(manually) 4 04-Jul-18 08:00 07-Jul-18 16:00 04-Jul-18 00:00 A 05-Jul-18 00:00 A
A7850 PCC 1 08-Jul-18 08:00 08-Jul-18 16:00 06-Jul-18 00:00 A 07-Jul-18 00:00 A
A7940 Heavy rain 1 09-Jul-18 08:00 A 09-Jul-18 16:00 A
A7950 Heavy Rain(Often) 1 10-Jul-18 08:00 A 10-Jul-18 16:00 A
A7860 Reinforcement work 4 09-Jul-18 08:00 12-Jul-18 16:00 05-Jul-18 08:00 A 12-Jul-18 16:00
A7870 Concrete pouring 1 13-Jul-18 08:00 13-Jul-18 16:00 13-Jul-18 08:00 13-Jul-18 16:00
Retaining Wall 155 30-Apr-18 16:00 06-Aug-18 15:00 06-May-18 16:00 A 03-Oct-18 11:00
Retaining wall(B3~B2) Except Ramp area 85 30-Apr-18 16:00 24-Jul-18 16:00 06-May-18 16:00 A 08-Jul-18 00:00 A
A1010 Starter fixing and concrete(M40) 19 02-May-18 16:00 21-May-18 16:00 06-May-18 16:00 A 26-Jun-18 16:00 A
A1000 Reinforcement work 18 30-Apr-18 16:00 18-May-18 16:00 28-May-18 16:00 A 29-Jun-18 16:00 A
A1020 Shuttering 19 02-May-18 16:00 21-May-18 16:00 03-Jun-18 16:00 A 04-Jul-18 00:00 A
A1030 RCC 19 05-Jul-18 16:00 24-Jul-18 16:00 04-Jun-18 16:00 A 05-Jul-18 00:00 A
A1040 De-shuttering 1 05-Jul-18 16:00 06-Jul-18 16:00 06-Jun-18 16:00 A 08-Jul-18 00:00 A
Retaining wall Ramp Area 92 03-Jul-18 08:00 06-Aug-18 15:00 03-Jul-18 08:00 A 03-Oct-18 11:00
Retaining wall(B3~B2) up to ramp level 92 03-Jul-18 08:00 06-Aug-18 15:00 03-Jul-18 08:00 A 03-Oct-18 11:00
A7730 Sheetpile installation at palal area 3 03-Jul-18 08:00 05-Jul-18 16:00 03-Jul-18 08:00 A 01-Sep-18 10:24
A7710 Earthwork for beam and slab 3 03-Jul-18 08:00 05-Jul-18 16:00 03-Jul-18 08:00 A 01-Sep-18 12:48
A7720 PCC for beam and slab 1 06-Jul-18 08:00 06-Jul-18 16:00 01-Sep-18 12:48 02-Sep-18 12:48
A7740 collapsed soil removal 8 06-Jul-18 08:00 13-Jul-18 16:00 01-Sep-18 10:24 09-Sep-18 10:24
A7750 Rectification of steel at collapsed area 6 14-Jul-18 08:00 19-Jul-18 16:00 09-Sep-18 10:24 15-Sep-18 10:24
A7660 Reinforcement work including the base slab 21 06-Jul-18 16:00 27-Jul-18 11:00 02-Sep-18 13:00 23-Sep-18 08:00
A7670 Starter fixing and concrete including the base slab 0 28-Jul-18 11:00 28-Jul-18 15:00 24-Sep-18 08:00 24-Sep-18 11:00
A7680 Shuttering for retaining wall up to base slab 6 29-Jul-18 15:00 04-Aug-18 15:00 25-Sep-18 11:00 01-Oct-18 11:00
A7690 RCC 0 05-Aug-18 15:00 05-Aug-18 15:00 02-Oct-18 11:00 02-Oct-18 11:00
A7700 De-shuttering 0 06-Aug-18 15:00 06-Aug-18 15:00 03-Oct-18 11:00 03-Oct-18 11:00
STP 144 06-Mar-18 01:00 27-Jul-18 16:00 02-Jun-18 01:00 A 27-Jul-18 12:00
STP Wall(B3~B2) Up to 1.9 m height-1 13 06-Mar-18 01:00 19-Mar-18 00:00 02-Jun-18 01:00 A 29-Jun-18 16:00 A
A7760 Reinforcement work 9 06-Mar-18 01:00 15-Mar-18 00:00 04-Jun-18 01:00 A 29-Jun-18 16:00 A
A7770 Starter fixing and concrete(M40) 8 11-Mar-18 01:00 19-Mar-18 00:00 02-Jun-18 01:00 A 29-Jun-18 16:00 A
A7780 Shuttering 10 06-Mar-18 01:00 16-Mar-18 00:00 11-Jun-18 01:00 A 29-Jun-18 16:00 A
A7790 RCC 8 08-Mar-18 01:00 16-Mar-18 00:00 14-Jun-18 01:00 A 29-Jun-18 16:00 A
A7800 De-shuttering 8 06-Mar-18 01:00 14-Mar-18 00:00 15-Jun-18 00:00 A 29-Jun-18 16:00 A
STP Wall(B3~B2) up to B2 18 10-Jul-18 08:00 27-Jul-18 16:00 05-Jul-18 00:00 A 27-Jul-18 12:00
A1320 Shuttering for slab at 1.90m 3 10-Jul-18 08:00 12-Jul-18 16:00 05-Jul-18 00:00 A 12-Jul-18 12:48
A1330 Reinforcement of slab 2 14-Jul-18 08:00 15-Jul-18 16:00 13-Jul-18 12:48 15-Jul-18 12:48
A1060 Starter fixing and concrete(M40) 0 16-Jul-18 16:00 16-Jul-18 16:00 16-Jul-18 13:00 16-Jul-18 13:00
A1080 RCC for slab 0 16-Jul-18 16:00 16-Jul-18 16:00 16-Jul-18 13:00 16-Jul-18 13:00
A1050 Reinforcement work for wall up to B2 2 17-Jul-18 16:00 19-Jul-18 16:00 17-Jul-18 13:00 19-Jul-18 12:00
A1070 Shuttering for wall 4 19-Jul-18 16:00 23-Jul-18 16:00 19-Jul-18 13:00 23-Jul-18 12:00
A1340 RCC for wall 1 24-Jul-18 08:00 24-Jul-18 16:00 23-Jul-18 12:00 24-Jul-18 12:00
A1090 De-shuttering 2 25-Jul-18 16:00 27-Jul-18 16:00 25-Jul-18 13:00 27-Jul-18 12:00
Shear wall 75 24-Jul-18 16:00 10-Aug-18 15:00 24-Jul-18 13:00 07-Oct-18 11:00
Shear Wall(B3~B2) for 1 Lift 10 24-Jul-18 16:00 03-Aug-18 16:00 24-Jul-18 13:00 03-Aug-18 12:00
A7890 Starter fixing and concrete(M40) 1 24-Jul-18 16:00 25-Jul-18 16:00 24-Jul-18 13:00 25-Jul-18 12:00
A7880 Reinforcement work 2 25-Jul-18 16:00 27-Jul-18 16:00 25-Jul-18 13:00 27-Jul-18 12:00
A7900 Shuttering 3 28-Jul-18 16:00 31-Jul-18 16:00 28-Jul-18 13:00 31-Jul-18 12:00
A7910 RCC 1 01-Aug-18 16:00 02-Aug-18 16:00 01-Aug-18 13:00 02-Aug-18 12:00
A7920 De-shuttering 1 02-Aug-18 16:00 03-Aug-18 16:00 02-Aug-18 13:00 03-Aug-18 12:00
Shear Wall(B3~B2) for 2 Lift 5 05-Aug-18 15:00 10-Aug-18 15:00 02-Oct-18 11:00 07-Oct-18 11:00
A1120 Shuttering 3 05-Aug-18 15:00 08-Aug-18 15:00 02-Oct-18 11:00 05-Oct-18 11:00
A1130 RCC 1 08-Aug-18 15:00 09-Aug-18 15:00 05-Oct-18 11:00 06-Oct-18 11:00
A1140 De-shuttering 1 09-Aug-18 15:00 10-Aug-18 15:00 06-Oct-18 11:00 07-Oct-18 11:00
Column(B3~B2) 11 14-Jul-18 08:00 24-Jul-18 16:00 14-Jul-18 08:00 24-Jul-18 16:00
A1350 Retrival of RFC Dwg for Roof slab (Assumption) 1 14-Jul-18 08:00 14-Jul-18 16:00 14-Jul-18 08:00 14-Jul-18 16:00
A1150 Reinforcement work 2 14-Jul-18 16:00 16-Jul-18 16:00 14-Jul-18 16:00 16-Jul-18 16:00
A1160 Starter fixing and concrete(M40) 2 17-Jul-18 16:00 19-Jul-18 16:00 17-Jul-18 16:00 19-Jul-18 16:00
A1170 Shuttering 2 18-Jul-18 16:00 20-Jul-18 16:00 18-Jul-18 16:00 20-Jul-18 16:00
A1180 RCC 1 20-Jul-18 16:00 21-Jul-18 16:00 20-Jul-18 16:00 21-Jul-18 16:00
A1190 De-shuttering 2 22-Jul-18 16:00 24-Jul-18 16:00 22-Jul-18 16:00 24-Jul-18 16:00
Ramp Slab 8 05-Aug-18 15:00 13-Aug-18 16:00 02-Oct-18 11:00 10-Oct-18 12:00
A1240 Shuttering 3 05-Aug-18 15:00 08-Aug-18 15:00 02-Oct-18 11:00 05-Oct-18 11:00
A1250 Reinforcement work 4 08-Aug-18 15:00 12-Aug-18 15:00 05-Oct-18 11:00 09-Oct-18 11:00
A1260 RCC 0 13-Aug-18 15:00 13-Aug-18 16:00 10-Oct-18 11:00 10-Oct-18 12:00
Roof Slab(B2) 30 28-Jul-18 16:00 27-Aug-18 16:00 28-Jul-18 16:00 27-Aug-18 16:00
A1280 Shuttering 14 28-Jul-18 16:00 11-Aug-18 16:00 28-Jul-18 16:00 11-Aug-18 16:00
A1290 Reinforcement work 14 11-Aug-18 16:00 25-Aug-18 16:00 11-Aug-18 16:00 25-Aug-18 16:00
A1300 RCC 1 26-Aug-18 16:00 27-Aug-18 16:00 26-Aug-18 16:00 27-Aug-18 16:00