Summary of DPWH Standard Specs and Min Test Requirment

Download as xls, pdf, or txt
Download as xls, pdf, or txt
You are on page 1of 26

DPWH STANDARD SPECIFICATION AND MINIMUM TEST REQUIREMENTS

TABLE OF CONTENT

Part A FACILITIES FOR THE ENGINEER

Part B OTHER GENERAL REQUIREMENT

Part C EARTHWORKS
Item No.
100 Clearing and Grubbing
1 Trees diameter will be measured 1.4m from the ground and a diameter less than 150mm will not be
considered in payment.
2 Method of measurement. 150mm to 900mm designated as small. Over 900mm designated as large

101 Removal of Existing Structure and Obstruction

102 Excavation

103 Structure Excavation


1 Sample test for every 1500 cu.m, Sample is 50kg for Routinary Test, Moisture Density Relation and CBR and 20kg for
Classification
2 For every 150mm uncompacted depth conduct FDT

104 Embankment
1 Conduct FDT for every 500 sq.m or fraction thereof at least on set of three in situ test. Result of FDT shall
have 95% MDD min.
2 Suitable
A Selected Borrow for Topping - gradation that all particle will pass sieve 75mm (3 inches)
and not more than 15 mass percent will pass 0.075 (no.200) sieve
B Plasticity Index (PI) = 6% max, and Liquid Limit (LL) = 30% max
3 Unsuitable
A LL = exceed 80, and PI = exceed 55
B natural water content exceeds 100%
C natural density 800 kg/cu.m max.
4 Sample test for every 1500 cu.m, Sample is 50kg for Routinary Test, Moisture Density Relation and CBR and 20kg for
Classification

105 Subgrade Preparation


1 Conduct FDT for every 500 sq.m or fraction thereof at least on set of three in situ test. Result of FDT shall
have 95% MDD min.
2 Plasticity Index (PI) = 6% max, and Liquid Limit (LL) = 30% max
3 Sample test for every 1500 cu.m, Sample is 50kg for Routinary Test, Moisture Density Relation and CBR and 20kg for
Classification
4 If an area of subgrade is soft and unstable, the most effective and cheaper method to stabilize the the soil prior to
subbase coure construction is geotextiles
5 The best soil for road subgrade would have a group index of 4max

106 Equipment Compaction and Control Density Strips

107 Overhaul

Part D SUB BASE AND BASE COURSE


Item No.
200 Aggregate Sub base Course
1 Sample Test for grading and plasticity test (for every 300 cu.m or fraction thereof)
A Fraction passing the 0.075 (no.200) sieve < 2/3 fraction passing 0.425mm (No.40)
B Fraction passing 0.425mm (no.40) shall have LL = 35% max, PI = 12% max
2 The coarse portion retain on a.2.00 mm (no.10) sieve shall have a mass percent of wear 50% max
by Los Angeles Abrasion Test
3 Required thickness when compacted is 150mm max. per one layer, At least one group of three in situ FDT
should be conducted in Trial Section for about 500 sq.m or fraction thereof per material or procedure, Result
of compaction shall have 100% MDD min. (FDT result)
4 For every 1500 cu.m or fraction thereof, Sample is 50kg for Routinary Test, Moisture Density Relation and CBR and
20kg for Classification, 1 Laboratory Compaction Test
5 For every 2500 cu.m or fraction thereof, 1 California Bearing Ratio (CBR) = 25% min obtained from MDD
6 Determining thickness of in place sub base course can be determined by test pitting (test pitting are excavated 1m x
1m excavation to a depth of up to 6m. Soil sample is recovered every meter.)

201 Aggregate Base Course


1 If in some area, base course are non-available, 40% weathered limestone blended w/ 60%
crushed stones or gravel shall be allowed
2 Sample Test for grading and plasticity test (for every 300 cu.m or fraction thereof)
A Fraction passing the 0.075 (no.200) sieve < 2/3 fraction passing 0.425mm (No.40)
B Fraction passing 0.425mm (no.40) shall have LL = 25% max, PI = 6% max
3 For every 1500 cu.m or fraction thereof, 1 Laboratory Compaction Test and coarse portion retain on a.2.00
mm (no.10) sieve shall have a mass percent of wear (abrasion loss) 50% max by Los Angeles Abrasion Test
Sample is 50kg for Routinary Test, Moisture Density Relation and CBR and 20kg for Classification, 1 Laboratory
Compaction Test
5 For every 2500 cu.m or fraction thereof, Material passing 19mm (3/4") sieve shall have a soaked CBR = 80% min
obtain at MDD
6 Filler shall be free from hard lumps and not more than 15% retain on 4.75mm (no.4)
7 Required thickness when compacted is 150mm max. per one layer, At least one group of three in situ FDT
should be conducted in Trial Section for about 500 sq.m or fraction thereof per material or procedure, Result
of compaction shall have 100% MDD min. (FDT result)

Page 1 of 26
DPWH STANDARD SPECIFICATION AND MINIMUM TEST REQUIREMENTS
TABLE OF CONTENT

202 Crushed Aggregate Base Course


1 Sample Test for grading and plasticity test (for every 300 cu.m or fraction thereof)
A Fraction passing the 0.075 (no.200) sieve < 2/3 fraction passing 0.425mm (No.40)
B Fraction passing 0.425mm (no.40) shall have LL = 25% max, PI = 6% max
2 For every 1500 cu.m or fraction thereof, 1 Laboratory Compaction Test and coarse portion retain on a.2.00 mm
(no.10) sieve shall have a mass percent of wear (abrasion loss) 45% max by Los Angeles Abrasion Test, not less than
50% mass shall have at least 1 fracture face, Sample is 50kg for Routinary Test, Moisture Density Relation and CBR
and 20kg for Classification, 1 Laboratory Compaction Test
5 Material passing 19mm (3/4") sieve shall have a soaked CBR = 80% min obtain at MDD
6 Filler shall be free from hard lumps and not more than 15% retain on 4.75mm (no.4)
7 Result of compaction shall have 100% MDD min.
8 Trial Section for about 500 sq.m per material or procedure

203 Lime Stabilized Roadmix Aggregate Base Course


1 Sample Test for grading and plasticity test (for every 300 cu.m or fraction thereof)
A Soil Aggregate Fraction passing 4.75mm (no.4) shall have PI = 4% to 10% only
B 1 Laboratory Compaction Test (Proctor Test)
C Unconfined Compression Test (UCT) molded and compacted must not be less than 2.1 Mpa (300psi)
at 100% MDD
D Mixture passing 19mm (3/4") sieve shall have a soaked CBR = 100% min obtain at MDD
2 Soil Aggregate. For every 1500 cu.m or fraction thereof,mass percent of wear (abrasion loss) 50% max
Sample is 50kg for Routinary Test, Moisture Density Relation and CBR and 20kg for Classification, 1 Laboratory
Compaction Test
3 Lime 3% to 12% mass percent of dry soil
4 For every 150m or fraction thereof and @ 150mm layer compacted depth
A 100% min MDD must be attain (FDT)
B 1 Thickness Determination
5 For every 100t or fraction thereof, 1 Quality Test should be conducted
6 if lime slurry is employed the typical ratio is 1 tonne lime to 2 cu.m water
7 Curing Period (at least 5 days of protection)
Different Methods
A maintain moist condition by sprinkling water
B cover 50mm of sand or earth and maintain moist condition
C apply on surface asphalt membrane of the type and qty approved by the Engr.
D apply on surface liquid membrane curing compund of the type and qty approved by the Engr.
8 Trial Section must be at least 2 weeks before actual execution of work
9 Trial Section for about 500 sq.m per material or procedure

204 Portland Cement Stabilized Aggregate Base Course


1 Sample Test for grading and plasticity test (for every 300 cu.m or fraction thereof)
A Soil Aggregate Fraction passing 4.75mm (no.4) shall have PI = 4% to 10% only
B 1 Laboratory Compaction Test (Proctor Test)
C Unconfined Compression Test (UCT) molded and compacted must not be less than 2.1 Mpa (300psi)
at 100% MDD
D Mixture passing 19mm (3/4") sieve shall have a soaked CBR = 100% min obtain at MDD
2 Soil Aggregate. For every 1500 cu.m or fraction thereof,mass percent of wear (abrasion loss) 50% max
Sample is 50kg for Routinary Test, Moisture Density Relation and CBR and 20kg for Classification
3 Cement. 6% to 10% mass percent of dry soil
4 For every 150m or fraction thereof and @ 150mm layer compacted depth
A 100% min MDD must be attain (FDT)
B 1 Thickness Determination
5 For every 2000 bags or fraction thereof of cement, 1 (10kg) Quality Test should be conducted
5 if portland cement slurry is employed the typical ratio is 1 tonne portland cement to 2 cu.m water
7 Curing Period (at least 5 days of protection)
Different Methods
A maintain moist condition by sprinkling water
B cover 50mm of sand or earth and maintain moist condition
C apply on surface asphalt membrane of the type and qty approved by the Engr.
D apply on surface liquid membrane curing compund of the type and qty approved by the Engr.
8 Trial Section must be at least 2 weeks before actual execution of work
9 Trial Section for about 500 sq.m per material or procedure

Page 2 of 26
DPWH STANDARD SPECIFICATION AND MINIMUM TEST REQUIREMENTS
TABLE OF CONTENT

205 Asphalt Stabilized Aggregate Base Course


1 Sample Test for grading and plasticity test (for every 300 cu.m or fraction thereof)
A Soil Aggregate Fraction passing 4.75mm (no.4) shall have PI = 4% to 10% only
B 1 Laboratory Compaction Test (Proctor Test)
C Unconfined Compression Test (UCT) molded and compacted must not be less than 2.1 Mpa (300psi)
at 100% MDD
D Mixture passing 19mm (3/4") sieve shall have a soaked CBR = 100% min obtain at MDD
2 Soil Aggregate. For every 1500 cu.m or fraction thereof,mass percent of wear (abrasion loss) 50% max
Sample is 50kg for Routinary Test, Moisture Density Relation and CBR and 20kg for Classification
3 Asphatic Material
A shall be Anionic or Cationic Emulsified Asphalt
B 4% to 7% mass percent of dry soil
4 For every 150m or fraction thereof and @ 150mm layer compacted depth
A 100% min MDD must be attain (FDT)
B 1 Thickness Determination
5 For every 40t or 200drums or fraction thereof of emulsified asphalt, 1 Quality Test (5 liters) should be conducted
6 Trial Section for about 500 sq.m per material or procedure

206 Portland Cement Treated Plant Mix Base Course


1 Sample Test for grading and plasticity test (for every 300 cu.m or fraction thereof)
A Soil Aggregate Fraction passing 4.75mm (no.4) shall have PI = 4% to 10% only
B 1 Laboratory Compaction Test (Proctor Test)
C Unconfined Compression Test (UCT) molded and compacted must not be less than 2.1 Mpa (300psi)
at 100% MDD
D Mixture passing 19mm (3/4") sieve shall have a soaked CBR = 100% min obtain at MDD
2 Soil Aggregate. For every 1500 cu.m or fraction thereof,mass percent of wear (abrasion loss) 50% max
Sample is 50kg for Routinary Test, Moisture Density Relation and CBR and 20kg for Classification
3 Cement. 6% to 10% mass percent of dry soil
4 For every 150m or fraction thereof and @ 150mm layer compacted depth
A 100% min MDD must be attain (FDT)
B 1 Thickness Determination
5 For every 2000 bags or fraction thereof of cement, 1 Quality Test (10 kgs.) should be conducted
Trial Section must be at least 2 weeks before actual execution of work
6 Method
A Travel Plant Method
A.1 Soil Aggregate shall be pulverized until at least 80% pass 4.75mm (no.4) except for gravel & stone
A.2 Any Material Retained on 50mm (2") sieve shall be removed
A.3 Max 2hrs. Shall be permitted for wet mixing, lay down and finishing
B Central Plant Method
7 no more than 60mins. Elapsed from the start of mixing and the time start of compaction
8 Curing Compund. Bituminous Curing Seal, applied 0.5 L/m2 to 1 L/m2 of surface, maintain at least 5 days

207 Aggregate Stockpile

Part E SURFACE COURSE


Item No.
300 Surface Aggregate Course
1 Sample Test for grading and plasticity test (for every 300 cu.m or fraction thereof)
A Fraction passing the 0.075 (no.200) sieve < 2/3 fraction passing 0.425mm (No.40)
B Fraction passing 0.425mm (no.40) shall have LL = 35% max, PI = range from 4% to 9%
2 For every 1500 cu.m or fraction thereof, Sample is 50kg for Routinary Test, Moisture Density Relation and CBR and
20kg for Classification
A 1 Laboratory Compaction Test (Proctor Test)
B The coarse portion retain on a.2.00 mm (no.10) sieve shall have a mass percent of wear 45% max
by Los Angeles Abrasion Test
3 Required thickness when compacted is 150mm max. per one layer, At least one group of three in situ FDT
should be conducted in Trial Section for about 500 sq.m or fraction thereof per material or procedure, Result
of compaction shall have 100% MDD min. (FDT result)
4 When crushed aggregate is used,
A For every 1500 cu.m or fraction thereof, 50% min of particle retain on 4.75mm (no.4) shall have at least 1
fractured face
B Soak CBR value at MDD, 25%min for gravel surface course and 80%min for crushed aggregate surface
course

Page 3 of 26
DPWH STANDARD SPECIFICATION AND MINIMUM TEST REQUIREMENTS
TABLE OF CONTENT

301 Bituminous Prime Coat


1 Definition. Application of low viscosity cutback to an absoerbent surface. It is used only on untreated base prior to
placement of asphalt pavement.
2 Material shall either be Rapid Curing (RC) or Medium Curing (MC) Cut-Back Asphalt
3 Equipment used must be a pressure distributor w/ cap. 1000 lit. min. w/ a heating
device attached to a tank able to heat up to 180 oC
4 Bituminous Material shall be applied 1 to 2 liters per sq.m
5 it shall be left undisturbed at least 24 hours.
6 Conduct 1 (5 liters) Quality Test for every 40t or 200 drums or fraction thereof
7 It shall be applied only to dry surface or slightly moist. Also applied for newly pavement as in on top of well graded and
compacted base course

302 Bituminous Tack Coat


1 Tack coat serve as a bonding b/n the new asphalt to the existing one. Tack coat is applied on existing asphalt or
concrete pavement. The new asphalt can be laid when the coat is already sticky.
2 Material shall either be Rapid Curing (RC) Cut-Back Asphalt or Emulsified Asphalt (Cationic or Anionic)
3 Bituminous Material shall be applied 0.2 to 0.7 liters per sq.m
4 Conduct 1 (5 liters) Quality Test for every 40t or 200 drums or fraction thereof

303 Bituminous Seal Coat


1 Serve as a preservation of asphalt original color, protect from the sunlight and water. This may also be used in
existing bituminous surface with or w/o application of aggregates.
2 Type 1 Type 2 Type 3
Bituminous Material, L/sq.m 0.2 - 0.5 0.5 - 1 0.85 - 1.5
Cover Aggregate, kg/sq.m none 5 - 10 8 - 14
3 Bituminous Material shall be Asphalt Cement, Penetration Grade 120-150, and Cut-back Asphalt
(Rapid Curing or Medium Curing)
4 Cover Aggregate for Type 2 consist of sand and fine aggregate while Type 3 consist of crushed stone,
crushed gravel or crushed slag
5 Cover Aggregate. 75 cu.m or 200t or fraction thereof, 1 grading test. For abrasion test, shall have a mass percent
of wear (abrasion loss) 40%max
6 If crushed slag is used in cover aggregate the density must be 960 kg/cu.m (60 lbs/ cu.ft.) min.
7 Seal coat shall be applied 10 days min. on compacted bituminous, except if instructed by the Engineer
8 Bituminous Material shall be applied by pressure distributor at the rate of 0.9 to 1.8 lit/sq.m for
asphalt cement and 1.5 to 3.0 lit/sq.m for cut-back asphalt
9 Cover Aggregate shall be spread at the rate of 0.004 to 0.007 cu.m/sq.m
10 For bituminous material, 40t or 200 drums or fraction thereof, 1 (5 liters) quality test shoul be conducted

304 Bituminous Surface Treatment


1 Single Surface Treatment (SST) - single application of bituminous material and single spread of aggregate
Double Surface Treatment (SST) - double application of bituminous material and single spread of aggregate
2 Bulk Specific Gravity of aggregates must be 2.55 to 2.75, if not met proportionate correction must conduct
until it reaches 2.65
5 If crushed slag is used in cover aggregate the density must be 960 kg/cu.m (60 lbs/ cu.ft.) min.
6 Asphaltic Material shall be applied at least 24 hours after surface had been prime coated
7 Cut-back asphalt or asphalt cement shall be applied on dry surface, while
Emulsified Asphalt on moist surface
8 Spray should commence if road temperature is 20 oC min.
9 Sprayed surface must be covered immediately by aggregate 2 minutes max.
10 Until the asphaltic has not set yet vehicles must only travel at a speed of 40km/hr.max and
all all vehicles must not be allowed to turn around
11 For Aggregates
A For every 75 cu.m or 200t or fraction thereof, 1 Grading test
B For every 1500 cu.m or fraction thereof, should have a mass percent of wear (abrasion loss) 40%max.
When crushed gravel is used, 50% min of particle retain on 4.75mm (no.4) shall have at least 1 fractured
face, Sample is 50kg for Routinary Test, Moisture Density Relation and CBR and 20kg for Classification
12 For Bituminous Material
A When using cut-back asphalt, asphalt cement or emulsified asphalt - 1.58 to 2.04 L/sq.m
B One quality test for 40t or 200 drums or fraction thereof

305 Bituminous Penetration Macadam Pavement - consists of placing one or more aggregate and one or more
bituminous material followed by a seal coat w/ cover aggregate
1 Bulk Specific Gravity of aggregates must be 2.55 to 2.75, if not met proportionate correction must conduct
until it reaches 2.65
2 bituminous material shall be made only when aggregate is dry and atmospheric temp. in the shade is 15 oC min
3 prior to application of bituminous material the aggregate layer will be tested by the Engineer using a 3m straight
edge at selected location, variation shall not exceed 10mm max

Page 4 of 26
DPWH STANDARD SPECIFICATION AND MINIMUM TEST REQUIREMENTS
TABLE OF CONTENT

4 For Aggregates
A For every 75 cu.m or 200t or fraction thereof, 1 Grading test
B For every 1500 cu.m or fraction thereof, should have a mass percent of wear (abrasion loss) 40%max.
When crushed gravel is used, 50% min of particle retain on 4.75mm (no.4) shall have at least 1 fractured
face. When crushed gravel is subjected to five cycles of sodium sulfate soundness test, the weight shall be
12%max (soundness loss), Sample is 50kg for Routinary Test, Moisture Density Relation and CBR and 20kg
for Classification
C If crushed slag is used in aggregate the density must be 1120 kg/cu.m (70 lbs/ cu.ft.) min.
5 For Bituminous Material
A Quantity 7.20 to 11.00 L/sq.m
B One (5 liters) quality test for 40t or 200 drums or fraction thereof

306 Bituminous Road Mix Surface Course (Mixed in Place Construction)


1 Procedure. The aggregate should be place first to the surface the spray the bituminous material (either cutback asphalt
or emulsified asphalt). Spraying may be done in 150oC to 200oC. Then initial roll using pneumatic roller with a force of
80 psi. Final rolling is done by three wheel or tandem type steel wheel roller (temp of 220 to 225 oC), travelling
5km per hour not less. than 10 tons to eliminate roller marks and a minimun of 95 mass percent of the density at
laboratory compacted. Rolling is done from the side toward the center, so the asphalt will be confined in the
pavement and not spread toward the shoulder. An area of 500 sq.m is to be prepared as trial section for asphalt
pavement. The surface of the asphalt pavement will be allowed a tolerance of 6mm using 3m straight edge. When tar
is used 66 to 107oC temperature is maintained during construction.
2 Any salvaged aggregate appearing in the surface of lay down and finishing appearing not passing 37.5mm (1 1/2")
sieve shall be removed.
3 Bituminous material on the basis of dry aggregate, 4.5% to 7% mass percent when using cut-back asphalt and
6% to 10% mass percent when using emulsified asphalt.
4 During mixing operation, 0.5% to 1% mass percent of hydrated lime, dry aggregate basis, shall be added
lower percentage limit is applicable to aggregate which are predominantly calcareous.
5 When the compacted thickness of the roadmix surface is to be more than 50mm (2"), the mixture shall be
spread and compacted two 2 layers
6 For Aggregates
A For every 75 cu.m or 200t or fraction thereof, 1 Grading test
B For every 1500 cu.m or fraction thereof, should have a mass percent of wear (abrasion loss) 40%max.
When crushed gravel is used, 50% min of particle retain on 4.75mm (no.4) shall have at least 1 fractured
face. When crushed gravel is subjected to five cycles of sodium sulfate soundness test, the weight shall be
12% max (soundness loss), Sample is 50kg for Routinary Test, Moisture Density Relation and CBR and 20kg
for Classification
7 For Bituminous Material
A 4.5% to 7% mass percent of dry soil aggregate if using cutback asphalt
B 6% to 10% mass percent of dry soil aggregate if using emulsified asphalt
C One (5 liters) quality test for 40t or 200 drums or fraction thereof

307 Bituminous Plant Mix Surface Course General


1 The bituminous mixture shall be composed of aggregate, mineral filler, hydrated lime, and bituminous material
2 At least three weeks prior to production, Contractor shall submit a job-mix formula for Egineer' approval.
3 Job Mix Formula consists of single values for
A percentage of aggregate in each sieve
B percentage of bituminous material to be added
C temperature of mixture deliivered on the road
D kind and percentage of additive to be used
E kind and percentage of mineral filler to be used
4 All mixture furnished for the project shall conform within the range of tolerances
A passing no. 4 and larger sieve ± 7%
B passing no. 8 to no.100 sieve ± 4%
C passing no. 200 sieve ± 2%
D bituminous material ± 0.4%
E temperature of mixture ± 10oC
5 For aggregates
A For every 75 cu.m or 200t or fraction thereof, 1 grading test and PI = 4.0% max
B For every 1500 cu.m or fraction thereof, should have a mass percent of wear (abrasion loss) 40%max.
When crushed gravel is used, 50% min of particle retain on 4.75mm (no.4) shall have at least 1 fractured
face. When crushed gravel is subjected to five cycles of sodium sulfate soundness test, the weight shall be
12% max (soundness loss),Sample is 50kg for Routinary Test, Moisture Density Relation and CBR and 20kg
for Classification
6 For Bituminous Material
A Proportion of bituminous material, on the basis of dry aggregate, shall be from 5% to 8% mass percent
B One (5 liters) quality test for 40t or 200 drums or fraction thereof
C 2 types of bitumen that are commonly used are tar (viscous liquid obtain from distillation of coal or wood)
and petroleum asphalt (are products of the distillation of crude oil). (3 major petroleum asphalt produced
is asphalt cement, emulsified asphalt, and cutback asphalt)
D commonly used bituminous material is Asphalt Cement (AC). Asphalt cement is also called hot asphalt.
Asphalt cement is refined asphalt or combination of refined asphalt and flux oil

Page 5 of 26
DPWH STANDARD SPECIFICATION AND MINIMUM TEST REQUIREMENTS
TABLE OF CONTENT

7 For Hydrated Lime


A For every 100t or fraction thereof, conduct 1 grading test and 1 plasticity test
B During mixing operation, 0.5% to 1% mass percent of hydrated lime, dry aggregate basis, shall be added
lower percentage limit is applicable to aggregate which are predominantly calcareous.
8 During mixture, for every 75 cu.m or 130mt or fraction thereof
A The mixture shall have a minimum compressive strength of 1.4 Mpa (200psi)
B The mixture shall have a mass percent air voids with the range of 3 to 5
C For aggregates having maximum size over 25mm (1") cylindrical sample will be modified to use 150mm x
150mm (6"x6")
D 97% min. of density laboratory compacted specimen must be obtained
E The Index of Retained Strength of the mixture is 70% min.
9 During construction. The correct temperature of the mixture shall be place as measured in the truck prior to dumping is
107oC. But if Tar is used the temperature is 66oC to 107oC. To attain required density, the compaction should be done
when the mixture is still hot and workable. In order to determine the number of passes that would attain the
required density, trial section must be conducted. Temperature must be control during mixing and compaction, it is
a great significance in the strength of resulting pavement. Then initial roll using pneumatic
roller (not less than ten tons) with a force of 80 psi. Final rolling is done by three wheel or tandem type steel
wheel roller (temp. must be 220 to225oC), travelling 5km per hour not less. than 10 tons to eliminate roller marks.
Rolling is done from the side toward the center, so the asphalt will be confined in the pavement and not spread
toward the shoulder.
10 For acceptance of the finished pavement,sample shall be at least 150mm x 150mm (square section when using saw)
or 100mm diameter full depth when using core drill. At least one, but not more than 3 samples shall be taken during
the day's operation. If no core sample were taken during the day's operation, core sample should be taken for every
100 L.M. per lane, degree of compaction should be 95% min lab density
11 No acceptance should be made on finish pavement unless core test for thickness determination is conducted, except
for Barangay Roads which is allowed to waive test.
12 The cored sample should not be accepted if the deficiency in the density is more than 2%
13 Tolerance for pavement thickness is -5mm max, averaging of cored samples for density and thickness is not permitted.
Additional layer shall be permitted to meet thickness with a minimum of 50mm (2")
14 For surface tolerance, using 3m straight edge test the variation should not exceed 6mm
15 Properties of Bituminous Pavement. 1) Stability - resistance to deformation or displacement due to an imposed load.
2) Durability - resistance to disintegration or deterioration due to action of water, traffic, and climate change.
3) Flexibility - ability to adjust itself to the settlement or to bend slightly without cracking.4) Fatigue Resistance -
Ability to withstand repeated flexing cause by passage wheel loads, 5) Skid Resistance - ability to resist slipping or
skidding of vehicles tires, 6) Workability - ease w/ which paving mixture may placed and compacted
16 The recommended thickness to be overlay is 75mm to 125mm (3" to 5")
17 During Delivery of mixed bituminous materiat, a thermometer should be place at a depth of 6"
18 In molding specimen the temperature must be 134±10oC
19 Air voids = (theoretical max density - bulk density of compacted Marshall specimen) / theoretical maximum density
the requirement is 3% to 5% air voids.
20 Voids in mineral aggregates = (100 - bulk density of compacted Marshall specimen) / bulk specific gravity of composite
aggregfates
21 Voids filled with asphalt = (voids in mineral aggregate - air voids) / voids in mineral aggregate x 100

308 Cold Asphalt Plant Mix


1 Shall be composed of coarse mineral aggregate, fine mineral aggregate, mineral fillers and chemically
bonding bitumen. These are plant mix either dense or open graded, which may be spread at normal
atmospheric temperature
2 At least three weeks prior to production, Contractor shall submit a job-mix formula for Egineer' approval.
3 Job Mix Formula consists of single values for
A percentage of mineral aggregate in each sieve
B percentage of chemically bonding bitumen material to be added
C temperature of mixture deliivered on the road
D kind and percentage of additive to be used
E kind and percentage of mineral filler to be used
4 For aggregates
A For every 75 cu.m or 200t or fraction thereof, 1 grading test and PI = 4.0% max
B For every 1500 cu.m or fraction thereof, should have a mass percent of wear (abrasion loss) 40%max.
When crushed gravel is used, 50% min of particle retain on 4.75mm (no.4) shall have at least 1 fractured
face. When crushed gravel is subjected to five cycles of sodium sulfate soundness test, the weight shall be
12% max (soundness loss), Sample is 50kg for Routinary Test, Moisture Density Relation and CBR and 20kg
for Classification
5 Bituminous material on the basis of dry aggregate, 4.5% to 7% mass percent when using cut-back asphalt and
6% to 10% mass percent when using emulsified asphalt. One (5 liters) quality test for 40t or 200 drums or fraction
thereof. (Note: cold mix is either with cutback asphalt or emulsified asphalt)
6 During mixture, for every 75 cu.m or 130t or fraction thereof
A The mixture shall have a minimum compressive strength of 1.4 Mpa (200psi)
B The mixture shall have a mass percent air voids with the range of 3 to 5
C For aggregates having maximum size over 25mm (1") cylindrical sample will be modified to use 150mm x
150mm (6"x6")
D 97% min. of density laboratory compacted specimen must be obtained

Page 6 of 26
DPWH STANDARD SPECIFICATION AND MINIMUM TEST REQUIREMENTS
TABLE OF CONTENT

7 For Hydrated Lime


A For every 100t or fraction thereof, conduct 1 grading test and 1 plasticity test
B During mixing operation, 0.5% to 1% mass percent of hydrated lime, dry aggregate basis, shall be added
lower percentage limit is applicable to aggregate which are predominantly calcareous.
8 For acceptance of the finished pavement, sample shall be at least 150mm x 150mm (square section) using saw or
100mm diameter full depth using core drill. At least one, but not more than 3 samples shall be taken during the
day's operation. If no core sample were taken during the day's operation, core sample should be taken for every 100 L.M.
per lane, degree of compaction should be 97% min lab density
9 Asphalt surface mixture shall not be place if the temperature of base course is below 10oC (50oF)

309 Bituminous Plant Mix (Stockpile Maintenance Mixture)


1 composed of bituminous stockpile maintenance mixture (such as aggregate, mineral filler, hydrated lime,
and bituminous material)
2 If crushed slag is used in aggregate the density must be 1120 kg/cu.m (70 lbs/ cu.ft.) min.
3 For aggregates
A For every 75 cu.m or 200t or fraction thereof, 1 grading test and PI = 4.0% max
B For every 1500 cu.m or fraction thereof, should have a mass percent of wear (abrasion loss) 40%max.
When crushed gravel is used, 50% min of particle retain on 4.75mm (no.4) shall have at least 1 fractured
face. When crushed gravel is subjected to five cycles of sodium sulfate soundness test, the weight shall be
12% max (soundness loss). Combined aggragate after going through the drier, shall have a sand equivalent
value of not less than 40% (Sand Equivalent Test). Sample is 50kg for Routinary Test, Moisture Density
Relation and CBR and 20kg for Classification
4 For Bituminous Material
A Quantity 4 to 10 mass % of total mix. Upper limit may be raised when using absorptive aggregate.
B One (5 liters) quality test for 40t or 200 drums or fraction thereof
5 During mixture, for every 75 cu.m or 130t or fraction thereof
A The mixture shall have a minimum compressive strength of 1.4 Mpa (200psi)
B The mixture shall have a mass percent air voids with the range of 3 to 5
C For aggregates having maximum size over 25mm (1") cylindrical sample will be modified to use 150mm x
150mm (6"x6")
D 97% min. of density laboratory compacted specimen must be obtained
6 For Hydrated Lime
A For every 100t or fraction thereof, conduct 1 grading test and 1 plasticity test
B During mixing operation, 0.5% to 1% mass percent of hydrated lime, dry aggregate basis, shall be added
lower percentage limit is applicable to aggregate which are predominantly calcareous.
7 For acceptance of the finished pavement, sample shall be at least 150mm x 150mm (square section using saw) or
100mm diameter full depth when using core drill. At least one, but not more than 3 samples shall be taken during the
day's operation. If no core sample were taken during the day's operation, core sample should be taken for every
100 L.M. per lane, degree of compaction should be 95% min lab density

310 Bituminous Concrete Surface Course


1 Same as In Item 307 (Bituminous Plant Mix Surface Course - general) except testing of from aggregate (fracture face)
2 In defintion it is a combination of aggregates that are uniformly mixed and coated with asphalt cement. This must
be spread and compacted while in a heated condition.

311 Portland Cement Concrete Pavement


1 Cement
A Sampling for every 2000 bags or fraction thereof subjected for 1 (10kg) Quality Test
B Cement which become partialy set or which contain lumps of caked will be rejected
C Shall be conform to Item 700 (Hydraulic Cement). Type of cement used in DPWH infrastructure as indicated
in the blue book is Portland Cement Type 1.However, Portland Pozzolan Cement Type IP meeting the
requirements of AASHTO M240/ASTM C S95 can be allowed.
2 For fine aggregates. Beach sand should not be allowed without the approval of the Engineer. It shall not
contain more than 3% mass percent of material passing 0.075mm (no.200) nor more than 1% mass percent of clay
lumps or shale. If subjected to 5 cycle of sodium sulfate soundness test, the weighted loss shall not exceed 10 mass
percent. If subjected to colorimatic test for organic impurities and a color darker than the standard is produced, it shall
be rejected.However, when tested for the effect of organic impurities of strength of mortar, it may be used if the relative
strength at 7 and 28 days is 95% min. Sampling of aggregates for grading should be for every 75 cu.m or fraction thereof.
3 For coarse aggregate. The material should not contain more than 1 mass percent passing 0.075mm (no.200) sieve, not
more than 0.25 mass percent of clay lumps, nor not more than 3.5 mass percent of soft fragments.If subjected to 5
cycle of sodium sulfate soundness test, the weighted loss shall not exceed 12 mass percent. It shall have a mass
percent of wear 40% max. If slag is used, density shall be 1120 kg/cu.m (70 lbs/cu.ft) min. (same item in 309-
Bituminous Plant Mix Stockplile Maintenance Mixture and 305-Bituminous Penetration Macadam Pavement)
Sampling of aggregates should be for every 75 cu.m or fraction thereof.
4 Drinkable water no need for test
5 In reinforcing steel, tie bars should be deformed bars and dowels (use as load transfer) should be plain round bars.
Before delivery to the sight of work one half of the length of each dowel shall be painted with one coat of approved
lead, thin film of bitumen or tar paint. For every 10,000kgs or fraction thereof for each size, conduct 1 (1m sample)
Quality Test (tension, bending, and chemical DB

Page 7 of 26
DPWH STANDARD SPECIFICATION AND MINIMUM TEST REQUIREMENTS
TABLE OF CONTENT

6 Concrete
A Fly ash can be used as 20% partial replacement of Portland Cement in concrete mix
B It is the intent of this Specification to require at least 364kg (9 bags) of cement per cu.m to meet min.
strength req.
C Concrete slump requires 40 to 75mm (1 1/2" to 3") if not vibrated or 10 to 40mm (1/2" to 1 1/2") if vibrated
Flexural strength not less than 3.8 Mpa (550 psi) when tested by third point method or 4.5 Mpa (650psi)
on mid-point method at 14 days. Compressive strength of 24.1 Mpa (3500 psi) for cores taken at 14 days
D Vibrators shall operate at a frequency of 8,300 to 9,600 impulse per minute and in no case shall the vibrator
be operated longer than 15 seconds in one location. Over vibration will result to segregation of aggregate.
E Batch concrete weight shall have the tolerance of 1% of cement and 2% of aggregates
F Concrete temperature during hot weather shall not exceed 90oF (32oC)
G Concrete not in place within 90 min. from the time of mixing shall not be used.
H When concrete shall be placed adjoining previously constructed lane and mechanical equipment will be
operated on the existing lane, that previously constructed shall have attained strength for 14 day concrete. If
only finishing equipment is carried on the existing lane, paving in adjoining lane may be permitted after 3 days.
I For test specimen, as work progresses, at least one set consisting of three concrete beam shall be
taken, 150mm x 150mm x 525mm or 900mm shall be taken from each 330 sq.m, 230mm depth or
fraction thereof place nor volume of concrete not more than 75 cu.m.
J Concrete layed shall not be left exposed for more than 1/2 hour of curing period (Curing period of 72 hrs
(3days))
K Removal of forms is permitted 24hrs min.after concrete pouring
L The strength level of concrete will be satisfactory if the average of the 3 sample equal or exceed specified
strength and no individual strength test result is deficient by more than 15% of specified strength. If not meet
the stated requirement, core test can be conducted w/ 3 sample obtained and the result of the average of
three specimen is equal to at least 85% of the required strength and no single sample is less than 75% of
required strength.
20 If strength specimen does not meet requirement and it is not advisable to obtain cores due to structural consideration.
Adjustment of price should be conducted due to deficiency:
Deficiency in strength of Concrete Percent (%) of Contract
Specimens (%) Price Allowed
Less than 5 100
5 to less than 10 80
10 to less than 15 70
15 to less than 20 60
20 to less than 25 50
25 or more 0
15 In surface test using 3m straight edge, areas showing high spot more than 3mm but not exceeding 12mm shall be
grind.Any area or section so removed shall not be less than 1.5m in length.
18 Seal joint should be place below pavement surface approximately 6mm
21 Opening to traffic. Pavement will be open unless it met the specified minimum strength requirement or if test is not yet
conducted, it can be opened 14 days min.
22 No acceptance should be made on finish pavement unless core test for thickness determination is conducted, except
for Barangay Roads which is allowed to waive test. A core specimen for thikness determination shall have a diameter
of at least 100mm (4"). A core specimen for compressive strength determination the dia. of core specimen must be
at least 2 times the max. size of coarse aggregates
23 Tie Bar is placed perpendicular to logitudinal joint and not to be painted.
24 Transverse Contraction Joint also called Weakened plane joint is constructed usually every 4.5m, the depth of the
joint should not be less than 50mm and not more than 6mm width. Sawing of this joint commence as soon as the
concrete has hardened sufficiently, usually within 24 hrs.
25 Transverse Construction Joint is also called cold joint, constructed when there is an interruption of more than
30min in concreting operations. No cold joint shall be constructed within 1.50m of an expansion joint, contraction joint,
or plane of weakness.
26 Corrugation produce in the surface shall be uniform in appearance and not more than 1.5mm in depth
27 Coring for thickness determination. The completed pavement is accepted on a lot basis. A lot shall be considered as
1000 lm. For single lane and 500 lm For two lanes. (Note: if the next length of lane is at least 1/2 of the nominal length
it is considered also another lot. Other areas such as entrance cross over, ramps, etc is considered
1 lot. Each lot will be divided to 5 equal segment and one core will be obtain at each segment. When the
measurement of any core is less than the specified thickness by more than 25mm additional core will be taken at no
less than 5m intervals parallel to the center line in each direction from the affected location. Obtaining a core will be
stopped until cored sample is not deficient by 25mm thk.
28 In evaluating a core sample, it is divided into 9 measurement, one at the center and the other 8 divided in equal
portion.When one measurement exceed the specified thickness by more than 5mm it will be considered as specified
thickness plus 5mm. When one measurement is less than the specified thickness by more than 25mm it shall not be
included in the average. Then average the 5 cored sample.
29 Deficiency in average thickness Percent (%) of Contract
per lot (mm) Price Allowed
0-5 100
6 - 10 95
11 - 15 85
16 - 20 70
21 - 25 50
more than 25 remove and replace (NP)
30 Mixing time for concrete at mixing plant shall not be less than 50 sec. but not greater than 90 seconds
31 In transporting concrete the time elapsed from the time water added to the mix until the concrete deposited in place
must not exceed 45min if hauled by non agitating trucks and 90min when hauled in truck mixers of truck agitators.
32 Steel forms are prescribed to be used in concrete pavement construction.

Page 8 of 26
DPWH STANDARD SPECIFICATION AND MINIMUM TEST REQUIREMENTS
TABLE OF CONTENT

Part F BRIDGE CONSTRUCTION


Item No.
400 Piling
1 Piling not part of the structure shall be removed or cut at least 300mm below the bottom of the footing.
2 For concrete piles. Concrete shall be class "C" with a slump of 6"-8" (150mm to 200mm) self compacting mix.
3 For precast concrete piles. Removal of forms is permitted 24hrs min.after concrete pouring. Piles shall not be moved
until the test indicates that the concrete attained a compressive strength of at least 80% of required strength and shall
not be transported or driven until required strength has attained. If testing is not available, piles shall not be moved until
14 days after casting and shall not be transported or driven prior to 28 days after casting. If high early strength is
used piles should not be moved, transported or driven prior to 7 days of casting.
4 Timber Piles. The heads of untreated piles should be treated with 2 coats hot creosote oil or other approved
preservatives. The weight of the gravity hammer to be use in piling is 2,000 kg.

401 Railing

402 Timber Structures


1 For using preservatives, creosote oil ot creosote petroleum oil blend shall be use.When timber is intended for
marine use creosote petroleum oil shall not be used.
2 The minimum penetration of the preservatives to the surface of the timber is 20mm
3 The Engineer shall be notified at least 10 days prior to the treatment process (application of preservatives)
4 Lumber is well seasoned if the moisture content contains 12% to 18%

403 Metal Structures

404 Reinforcing Steel Bars


1 For every 10,000kgs or fraction thereof for each size, conduct 1 (1m sample) Quality Test (tension, bending, and
chemical analysis)
2 Minimum distance for Lap Splice for reinforcing bars
Splice Type Grade 40 Grade 60 But not less than
Tension 24 bar dia 36 bar dia 300mm
Compression 20 bar dia 24 bar dia. 300mm

405 Structural Concrete


1 Classes and Uses of Concrete
Class A all superstructure and heavily reinforced substructures
Class B footings, pedestals, unreinforced or small amount of reinforcement
Class C thin reinforced section, railing, precast R.C piles
Class P Prestressed concrete structure
Seal concrete deposited in water.
2 Sampling of cement 2000 bags or fraction thereof, conduct 1 (10kg.) Quality Test infrastructure as indicated in the
blue book is Portland Cement Type 1 (portland cement is a cement which has cementitious effect).
3 For test specimen, at least one set of three samples, 150mm x 300mm (6" x 12") shall be taken from each 75 cu.m or
fraction thereof place each day and must not represent not more than 75 cu.m
4 Class of Concrete Min. Cement Content (bag or kg)/cu.m) Min Strength Req. Range in Slump
Class A 9 bags 360 kg. 20.7Mpa or 3000psi 50-100mm (2" - 4")
Class B 8 bags 320 kg. 16.5Mpa or 2400psi 50-100mm (2" - 4")
Class C 9.5 bags 380 kg. 20.7Mpa or 3000psi 50-100mm (2" - 4")
Class P 11 bags 440 kg. 37.7Mpa or 5000psi 100mm max (4"max)
Seal 9.5 bags 380 kg. 20.7Mpa or 3000psi 100 to 200mm (4" to 8")
based on 40 kg / bag
5 For Aggregates
A Washed aggregates must be drained at least 12 hrs. prior to batching
B For fine and coarse aggregate sampling shall be 75 cu.m or fraction thereof for 1 Grading Test
6 Testing of rebars, for every 10,000kgs or fraction thereof for each size, conduct 1 (1m) Quality Test (tension, bending,
and chemical analysis)
7 For admixture, it shall be measured with an accuracy of ± 3%, the use of calcium chloride as an admixture is not
permitted.
8 The interval of delivery of batched concrete shall not exceed 30 min. interval during casting. Exceptional cases may
consider when using volumetric which requires less than 75 cu.m per day pouring,
9 Mixing time for concrete at mixing plant shall not be less than 50 sec. but not greater than 90 seconds
10 In transporting concrete the time elapsed from the time water added to the mix until the concrete deposited in place
must not exceed 45min if hauled by non agitating trucks and 90min when hauled in truck mixers of truck agitators.
(required revolution for truck mixers is 4 to 6 rpm)
11 If there is a need to add water to the concrete mix in order to increase workability after the initial time of mixing, it shall
be permitted not exceeding 45min. (provided not to exceed slump and water cement ratio)
12 Design of concrete mix specified in the blue blook is based on Absolute Volume Method
13 Removal of forms
min time min % design strength
centering under girder, beam frames or arches 14 days 0.80%
floor slab 14 days 0.70%
walls 1 day 0.70%
columns 2 days 0.70%
sides of beams and all vertical surfaces 1 day 0.70%
14 Limit for water cement ratio ranges from 0.50 to 0.60
15 Concrete that is properly vibrated has a higher strength result than that of not thoroughly consolidated by 20% to 25%

Page 9 of 26
DPWH STANDARD SPECIFICATION AND MINIMUM TEST REQUIREMENTS
TABLE OF CONTENT

406 Prestressed Structural Concrete


1 For wire strand. 1 Quality Test for every 20t or fraction thereof
2 Concrete strength of at least 28 Mpa should be attained prior to tensioning of the prestressing reinforcement unless
otherwise specified.

407 Concrete Structure

408 Steel Bridge

409 Welded Structure

410 Treated and Untreated Timber

411 Paint
1 Sampling. One 20-L or one 4-L can or every for every 100 can or fraction thereof
2 Paint use in concrete pavement is thermoplastic while in asphalt pavement is reflectorized
3 The insoluble powdered solid mixture of paint is called pigments. Pigments having high refractive indices are
classified as prime. Then colored pigment use as primer for metallic surface is called red lead.
4 The most common popular dry oil paint is called linseed oil paint
5 A volatile solvent use to reduce consistency of paint is thinner

412 Elastomeric Bearing Pad

413 Pre molded joint filler for concrete paving

Part G DRAINAGE AND SLOPE PROTECTION STRUCTURES


Item No.
500 Pipe Culvert and Storm Drain
1 Joint Mortar for concrete pipes should consist of 1 part Portland Cement and 2 part sand. Mortar shall be used within
30 mins after its preparation.
2 Sampling of Pipes. 1 pipe for every 50pcs. (for strength, absorption, dimension test)
3 Alternative test on no. 2. Concrete Sample 1 set consisting of three cylinder sample for not more than 25pcs cast and
1 inspection report on casted pipe for not more than 25 pcs.
4 Test for cement and aggregates same as item 405 (Structural Concrete)
5 Storm pipe shall be embedded below the finished grade line not less than 0.60m
6 Minimum spacing of hoop rebars on RCP is 86mm, w/ net protective covering of 25mm (1")

501 Underdrain

502 Catch Basin, Inlet and Manholes


1 Same as item 405 (Structural Concrete), Class A

503 Steel Grating w/ Frame

504 Reconditioning and Cleaning of Existing Drainage

505 Riprap and Grouted Riprap


1 Classes of Stones used:
Class A ranging from a minimum of 15kg to max 25kg. With at leat 50% weighing more than 20kg.
Class B ranging from a minimum of 30kg to max 70kg. With at leat 50% weighing more than 50kg.
Class C ranging from a minimum of 60kg to max 100kg. With at leat 50% weighing more than 80kg.
Class D ranging from a minimum of 100kg to max 200kg. With at leat 50% weighing more than 150kg.
2 Mortar mixed shall be one part cement , and three parts sand and applied a minimum thickness of 20mm between
stones
3 Spacing of weepholes shall not be more than 2m and must be in staggered manner with a diameter of at least 50mm.
4 Placement of stone is perpendicular to the slope
5 Quantity. For cement 3 bags/cu.m of riprap, For fine aggregates: 0.17 cu.m/cu.m of riprap

506 Stone Masonry


1 Mortar for masonry shall consists of one part portland cement and two part fine aggregates
2 Mortar that is not used within 90min. After the water has been added shall be discarded.
3 Placement of stone is parallel to the slope.
4 Quantity. For cement 2 bags/cu.m of riprap, For fine aggregates: 0.17 cu.m/cu.m of riprap

507 Rubble Concrete


1 Stones to be used shall be more than 0.015 cu.m and not less than 75% of the total volume of rock embankment
2 Concrete shall be Class "B"
3 In no case shall vibrator be operated longer than 10 seconds.
4 After removal of forms if there is a voids or honeycomb spot shall be filled with one part cement and two parts sand.
5 Spacing of weepholes shall not be more than 2m and must be in staggered manner with a diameter of at least 50mm.
6 minimum thickness of rubble concrete is 12" or 300mm.

508 Hand Laid Rock Embankment


1 Stones to be used shall be more than 0.015 cu.m and not less than 75% of the total volume of rock embankment

509 Sheet Piles

Page 10 of 26
DPWH STANDARD SPECIFICATION AND MINIMUM TEST REQUIREMENTS
TABLE OF CONTENT

510 Concrete Slope Protection


1 Concrete shall be class "B"

511 Gabions and Matresses


1 Filter cloth shall consist of 70% polypropylene and 30% polyethylene

Part H MISCELLANEOUS STRUCTURES


Part I MATERIAL DETAIL

Other Minimum Requirements for Submission of Samples

Materials Minimum Test Requirement Minimum Quantity of Sample


1 Asphalt Mix for every 130t or fraction thereof 20 kg
2 Aggregates for every 1500cu.m or fraction thereof
a. coarse aggregate 70 kg
b. fine aggregates 50 kg
3 CHB for every 10,000 units or fraction thereof 6 units 3 units for compression
3 units for moisture
Classification of CHB:
A) Load Bearing CHB - thickness ranges 6" to 8" or more, capable of carrying superimposed load aside from its own weight.
B) Non Load Bearing CHB - thickness ranges 3" to 4", which are not capable of carrying load and carrying just their own
weight.
Strength Requirement: For Load Bearing For Non Load Bearing
Individual 800psi min. 500psi min
Average 1000psi min. 600psi min
Absorption 240kg/cum max 240kg/cum max
Moisture Content 45% max 45% max
4 Steel Sheet (galvanized) for every 1,000 sheets or fraction thereof 1 sheet
(Note: minimum lapping for GI sheet is 2 1/2 corrugations, galvanized iron sheet is tested for 1)thickness and dimension
and 2) zinc coating)

Page 11 of 26
DPWH STANDARD SPECIFICATION

TABLE OF CONTENT
Part A FACILITIES FOR THE ENGINEER
Part B OTHER GENERAL REQUIREMENT
Part C EARTHWORKS
Item No.
100 Clearing and Grubbing
101 Removal of Existing Structure and Obstruction
102 Excavation
103 Structure Excavation
104 Embankment
105 Subgrade Preparation
106 Equipment Compaction and Control Density Strips
107 Overhaul
Part D SUB BASE AND BASE COURSE
Item No.
200 Aggregate Sub Base Course
201 Aggregate Base Course
202 Crushed Aggregate Base Course
203 Lime Stabilized Roadmix Aggregate Base Course
204 Portland Cement Stabilized Roadmix Aggregate Base Course
205 Asphalt Stabilized Roadmix Aggregate Base Course
206 Portland Cement Treated Plant Mix Base Course
207 Aggregate Stockpile
Part E SURFACE COURSE
Item No.
300 Surface Aggregate Course
301 Bituminous Prime Coat
302 Bituminous Tack Coat
303 Bituminous Seal Coat
304 Bituminous Surface Treatment
305 Bituminous Penetration Macadam Pavement
306 Bituminous Road Mix Surface Course
307 Bituminous Plant Mix Surface Course General
308 Cold Asphalt Plant Mix
309 Bituminous Plant Mix (Stockpile Maintenance Mixture)
310 Bituminous Concrete Surface Course - hot laid
311 Portland Cement Concrete Pavement
Part F BRIDGE CONSTRUCTION
Item No.
400 Piling
401 Railing
402 Timber Structures
403 Metal Structures
404 Reinforcing Steel Bars
405 Structural Concrete
406 Prestressed Structural Concrete
407 Concrete Structure
408 Steel Bridge
409 Welded Structure Steel
410 Treated and Untreated Timber
411 Paint
412 Elastomeric Bearing Pad
413 Pre molded joint filler for concrete paving
Part G DRAINAGE AND SLOPE PROTECTION STRUCTURES
500 Pipe Culvert and Storm Drain
501 Underdrain
502 Catch Basin, Inlet and Manholes
503 Drainage Steel Grating w/ Frame
504 Reconditioning and Cleaning of Existing Drainage
505 Riprap and Grouted Riprap
506 Stone Masonry
507 Rubble Concrete
508 Hand Laid Rock Embankment
509 Sheet Piles
510 Concrete Slope Protection
511 Gabions and Matresses
Part H MISCELLANEOUS STRUCTURES
Part I MATERIAL DETAIL
DPWH STANDARD SPECIFICATION

PART A FACILITIES FOR THE ENGINEER


B OTHER GENERAL REQUIREMENTS
C EARTHWORKS
100 CLEARING AND GRUBBING
101 REMOVAL OF EXISTING STRUCTURE
102 EXCAVATION
103 STRUCTURE EXCAVATION
104 EMBANKMENT
105 SUBGRADE PREPARATION
106 EQUIPMENT COMPACTION AND CONTROL DENSITY STRIPS
107 OVERHAUL

D SUB BASE AND BASE COURSE


200 AGGREGATE SUBBASE COURSE
201 AGGREGATE BASE COURSE
202 CRUSHED AGGREGATE BASE COURSE
203 LIME STABILIZED ROADMIX AGGREGATE BASE COURSE
204 PORTLAND CEMENT STABILIZED ROADMIX AGGREGATE BASE COURSE
205 ASPHALT STABILIZED ROADMIX AGGREGATE BASE COURSE
206 PORTLAND CEMENT TREATED PLANT MIX BASE COURSE
207 AGGREGATE STOCKPILE

E SURFACE COURSE
300 AGGREGATE SURFACE COURSE
301 BITUMINOUS PRIME COAT
302 BITUMINOUS TACK COAT
303 BITUMINOUS SEAL COAT
304 BITUMINOUS SURFACE TREATMENT
305 BITUMINOUS PENETRATION MACADAM PAVEMENT
306 BITUMINOUS ROADMIX SURFACE COURSE
307 BITUMINOUS PLANT MIX SURFACE COURSE - GENERAL
308 COLD ASPHALT PLANT MIX SURFACE COURSE
309 BITUMINOUS PLANT MIX (STOCKPILE MAINTENACE MIXTURE)
310 BITUMINOUS CONCRETE SURFACE COURSE - HOT LAID
311 PORTLAND CEMENT CONCRETE PAVEMENT

F BRIDGE CONSTRUCTION
400 PILING
401 RAILING
402 TIMBER STRUCTURE
403 METAL STRUCTURE
404 REINFORCING STEEL BARS
405 STRUCTURAL CONCRETE
406 PRESTRESSED CONCRETE
407 CONCRETE STRUCTURE
408 STEEL BRIDGE
409 WELDED STRUCTURE
410 TREATED And UNTREATED TIMBER
411 PAINT
412 ELASTOMERIC BEARING PAD
413 PREMOLDED JOINT FILLER W/ CONCRETE PAVING

G DRAINAGE AND SLOPE PROTECTION STRUCTURE


500 PIPE CULVERT AND STORM DRAIN
501 UNDERDRAIN
502 INLET, Manhole, and catch basin
503 DRAINAGE STEEL GRATING W/ FRAME
504 RECONDITIONING AND CLEANING OF EXISTING DRAINAGE
505 riprap and grouted riprap
506 stone masonry
507 rubble concrete
508 hand held rock embankment
509 sheet pile
510 concrete slope protection
511 gAbions and mattress

H MISCELLANEOUS STRUCTURES
I MATERIAL DETAIL
Percentage of
Item No. Description Cement, Lime, LL PI
Asphalt

percentage from dry conduct test on aggregate


soil paasing 0.425mm (no.40)

103 Structure Excavation

104 Embankment (suitable) 30 max 6 max

104 Embankment (unsuitable) 80min 55min

105 Subgrade Preparation 30 max 6 max

200 Subbase Course 35 max 12 max

201 Base Course 25 max 6 max

202 Crushed Aggregate Base Course 25 max 6 max

conduct test on aggregate


paasing 4.75mm (no.4)

203 Lime Stabilized Base Course 3 to 12 % 4 to 10


204 Portland Cement Stabilized Base Course 6 to 10 % 4 to 10

205 Asphalt Stabilized Base Course 4 to 7 % 4 to 10

206 Portland Cemet Treated Plant Base Course 6 to 10 % 4 to 10

conduct test on aggregate


paasing 0.425mm (no.40)

300 Surface Course 35 max 4 to 9


Required
Compression
CBR Abrasion Loss MDD
Test (unconfined)
@ 7day

soaked aggregate aggregate retain on


passing 19mm (3/4") no.10 (2mm)

95 min

95 min

25 min 50 max 100 min

80 min 50 max 100 min

80 min 45 max 100 min

100min 50 max 100 min 300


100min 50 max 100 min 300

100min 50 max 100 min 300

100min 50 max 100 min 300

25max for gravel


surface course
80max for 45 max 100 min
crushed
aggregate
surface course
Sample Remarks

for every 1,500cu.m or fraction thereof 1Grading,


Plasticity, Compaction Test and CBR

for suitable embankment all particle pass


for every 1,500cu.m or fraction thereof 1Grading,
75mm and not more than 15mass percent will
Plasticity, Compaction Test and CBR
pass 0.075mm
natural water content exceed 100% and natural
density is 800kg/cu.m max.
if there is an are w/c is soft and unstable, the
for every 1,500cu.m or fraction thereof 1Grading, most effective and cheaper method to stabilize
Plasticity, Compaction Test and CBR soil prior to subbase course is geotextile, the
best soil for subgrade had a group index of
4max

in grading aggregates, fraction passing


for every 300cu.m or fraction thereof 1 grading and 0.075mm (No.200) < 2/3 passing 0.425mm
plasticity test for every 1,500cu.m or fraction thereof 1 (no.40), in determining the thickness of
Lab. Compaction and Abrasion Test, for every subbase course it can be determine by test
2,500cu.m or fraction thereof 1 CBR pitting (excavated 1m x 1m at a depth of 6m
recovered sample every meter)

in grading aggregates, fraction passing


for every 300cu.m or fraction thereof 1 grading and 0.075mm (No.200) < 2/3 passing 0.425mm
plasticity test for every 1,500cu.m or fraction thereof 1 (no.40), if base course is unavailable 40%
Lab. Compaction and Abrasion Test, for every weathered limestone blended w/ 60% crushed
2,500cu.m or fraction thereof 1 CBR stone or gravel shall be allowed, filler shall be
free from hard lumps not more than 15% retain
on 4.75mm (no.4)
for every 300cu.m or fraction thereof 1 grading and
plasticity test for every 1,500cu.m or fraction thereof in grading aggregates, fraction passing
1 Lab. Compaction and Abrasion Test (at least 50 0.075mm (No.200) < 2/3 passing 0.425mm
mass % shall have at least 1 fracture face), for every (no.40), filler shall be free from hard lumps not
2,500cu.m or fraction thereof 1 CBR more than 15% retain on 4.75mm (no.4)

For soil aggregate. for every 300cu.m or fraction


if lime slurry is employed typical ratio is
thereof 1 grading and plasticity test for every 1,500cu.m
1tonne lime to 2cu.m water. Curing period at
or fraction thereof 1 Abrasion Test. For Lime for every
least 5 days) Trial section must be at least 2
100t or fraction thereof.1 quality test. For mixture, every
weeks for about 500sq.m
300 cu.m or fraction thereof 1 CBR
For soil aggregate. for every 300cu.m or fraction
thereof 1 grading and plasticity test for every if cement slurry is employed typical ratio is
1,500cu.m or fraction thereof 1 Abrasion Test. For 1tonne cement to 2cu.m water. Curing period
Cement for every 2000 bags or fraction thereof.1 at least 5 days. Trial section must be at least
(10kg of cement) quality test. For mixture, every 300 2 weeks for about 500sq.m
cu.m or fraction thereof 1 CBR

For soil aggregate. for every 300cu.m or fraction


thereof 1 grading and plasticity test for every
1,500cu.m or fraction thereof 1 Abrasion Test. For
Trial section must be at least 2 weeks for
Asphaltic Material (either anionic or cationic emulsified
about 500sq.m
asphalt) for every 40t or 200drums or fraction
thereof.1(5 liters of asphaltic material) quality test. For
mixture, every 300 cu.m or fraction thereof 1 CBR

For soil aggregate. for every 300cu.m or fraction


thereof 1 grading and plasticity test for every
1,500cu.m or fraction thereof 1 Abrasion Test. For Trial section must be at least 2 weeks for
Cement for every 2000 bags or fraction thereof.1 about 500sq.m
(10kg of cement) quality test. For mixture, every 300
cu.m or fraction thereof 1 CBR
GRADING REQUIREMENTS
Sieve Designation Mass Percent Passing
Standard,mm US Standard SUBBASE BASE COURSE
A

50 2" 100 100


37.5 1-1/2" -
25 1" 50-85 60-85
19 3/4" -
12.5 1/2" 35-65
9.5 40-75
4.75 No. 4 20-50

0.425 No. 40 5-20

0.075 No. 200 0-12 0-12

ITEM 200 1TEM 201


Permitted variation from
design THICKNESS OF ±20mm ±10mm
LAYER

Permitted variation from


+10mm, -20mm -5mm, -10mm
design LEVEL OF SURFACE

Permitted surface irregularity


measured by 3-m straight 20mm 5mm
edge

Permitted variation from


±0.3% ±0.2%
design cross fall or camber

Permitted variation from


design longitudinal grade over ±0.1% ±0.1%
25m length
nt Passing Pay Item No. Description Unit of Measurement
BASE COURSE 200 AGGREGATE SUBBASE cu.m.
B COURSE

201 AGGREGATE BASE cu.m.


COURSE

100
-
60-85
-

30-55

GRADING
8-25
REQUIREMENTS

Sieve
2-14
Designation

Stan US Mass
dard Standar Percent
, mm d Passing
50 2" 100
25 1" 50-85
9.5 3/8" 40-75
0.075 No. 200 0-12
TEST SIGNIFICANCE

Particle size/sieve analysis is defined as


is the determination
PARTICLE of particle size distribution in soils by
SIZE/SIEVE sieve, hydrometer or a
ANALYSIS combined analysis where the method
which should be used.
LIQUID LIMIT
DETERMINATIO
N The liquid limit is defined as the lowest
moisture content at which the soil will flow
upon the application of very small
shearing force. The liquid limit gives a
certain measure of the shearing resistance
of a soil when mixed with water.

PLASTIC LIMIT
DETERMINATIO The Plastic Limit is defined as the
N minimum moisture content at which the
soil can be readily mold without breaking
or crumbling. Plasticity index indicates
compressibility; high P.I. means high
degree of compressibility of a soil. It is
also related to permeability; the higher the
P.I. the lower the permeability; and vice
versa.

You might also like