0% found this document useful (0 votes)
65 views2 pages

SPU/SDOT As-Built Drawing Requirements

This document outlines the requirements for submitting red-line and as-built drawings to the City of Seattle for water and sewer infrastructure projects. Key requirements include submitting 30%, 60%, 90%, and 100% design drawings for review, providing sample as-built drawings within 2 weeks of completion, and submitting final record drawings and data to the City per the contract agreement. As-built drawings must incorporate all design changes in red without references to other documents, and include additional details as needed for clarity.

Uploaded by

Ahmed
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
65 views2 pages

SPU/SDOT As-Built Drawing Requirements

This document outlines the requirements for submitting red-line and as-built drawings to the City of Seattle for water and sewer infrastructure projects. Key requirements include submitting 30%, 60%, 90%, and 100% design drawings for review, providing sample as-built drawings within 2 weeks of completion, and submitting final record drawings and data to the City per the contract agreement. As-built drawings must incorporate all design changes in red without references to other documents, and include additional details as needed for clarity.

Uploaded by

Ahmed
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 2

SPU/SDOT Red-Line/As-Built Drawing Requirements

SPU/SDOT As-Built Drawing


Requirements
Submit 30%, 60%, Completed by Within the first two Completed by the

Red-Lines
Design Drawings

As-Built Drawings

Record Drawings
90% & 100% contractor in the weeks, submit City of Seattle
drawings to City of field sample as-built Data exported to
Seattle for CAD drawings to the City City of Seattle GIS
reviews of Seattle for review
Plan set stored in
Submit all design Completed as-built the SPU Engineering
change drawings to drawings shall be Records Center
the City of Seattle submitted to the
As-designed data City of Seattle per
exported to City of the contract
Seattle GIS agreement

General Requirements
 As-Built drawings shall incorporate all deviations to the original design without any references to
RFIs, FCRs, payment items, DCs, etc. As-Built drawings shall be accurate, clean, clear and easily
readable. In congested areas, additional blow-up details may be required for readability.
 Items not built shall be crossed out.
 All As-Built drawing sheets shall be stamped “AS-BUILT DRAWING”.

Submittals
Submit to [email protected] in one of four formats: AutoCAD DWG, DWF, PDF or print
(paper). AutoCAD DWG files are required if available.

Submittal Option 1: AutoCAD Requirements


 Drawings shall be done in AutoCAD or AutoCAD Civil 3D and must conform to the standards as
defined in the CAD Manual: Seattle.gov/util/CAD
 Civil layers for As-Built linework and annotation to be plotted/shown in red have the “CR-” discipline
designator (see Section 5: Layers in the CAD Manual) and use colors 32-38 (see Section 8:
Plotting/Printing in the CAD Manual).
 Items not built shall be put on the CR-NBLT layer (lines can be broken) and crossed out with the CR-
ANNO layer (not deleted).
 Annotation shall have the text style name set to "COS-Record" with the “font name” set to
RomanS.shx, the “paper text height” set to 0.00, the “width factor” set to 1.00 and the “oblique
angle” set to 20 (see Section 7: Annotation in the CAD Manual). The plotted text height shall be
1/8”.
 All As-Built drawing sheets shall have the “AS-BUILT DRAWING” stamp block affixed (see Section 2:
Support Files in the CAD Manual).

Page 1 of 2
SPU/SDOT Red-Line/As-Built Drawing Requirements

 Sheet bar codes shall be correct (prior to printing, the “Barcode Modifier” field in the Sheet Set
Custom Properties of Sheet Set Manager must be updated to: -A).
 PDF, DWF or a hard-copy of the plan set created for reference per Section 8: Plotting/Printing in the
CAD Manual with the standard plot style table.

Submittal Option 2: DWF Requirements


 Markups must be done with Autodesk Design Review on full-size drawings (at least 22”x34”).
 Markups must be done in RED color with the markup tools located in the “Markup & Measure” tab.
 Text must be 14 pt.

Submittal Option 3: PDF Requirements


 Markups must be done with Adobe Acrobat (not reader) on full-size drawings (at least 22”x34”).
 Markups must be done in RED color with the following “Comment & Markup” tools: Callout Tool,
Text Box Tool, Cloud Tool, Arrow Tool, Line Tool, Rectangle Tool, Oval Tool, Polygon Line Tool and/or
Polygon Tool (sticky notes are not valid).
 Text must be approximately 1/8”.

Submittal Option 4: Print Requirements


 Markups must be done in RED ink on full-size (at least 22x34) drawing prints.
 Handwriting must be clearly written with 1/8” lettering.