CFRD/D001--2008

-----------------------------------------------------------------------------------------

Guidelines for Design


High Concrete Face Rockfill Dam
(Draft)

Sponsor:

vn
CFRD INTERNATIONAL SOCIETY

-----------------------------------------------------------------------------------------

d.
FOREWORD
ol
The concrete face rockfill dam (CFRD) has been constructed widely all over the
world now its stability, taking full advantage of local excavated materials and
constructed simply, and economically, and best adaptability to geology and
nc
topography, operation safely and easily remedy. CFRDs >100m are 200 or so

spreading around the world ; the extra high CFRDs (>150 m ) are much more built
.v

or underway such as Shuibuya (233m, China), Jiangpinghe (221m , China), La Yesca


(210m, Mexico), Bakun (205m , Malaysia), Campos Novos (202m , Brazil), Guxian
w

(199m, China), Kárahnjúkar (196m, Iceland), El Cajon ( 189m, Mexico), Aguamilpa


(187m, Mexico), Sanbanxi (186m, China), Barra Grande (185m, Brazil), Mazar
w

(185m, Ecuador), Hongjiadu (179.5m, China), Tianshengqiao I ( 178m, China),


Tankeng (162m, China) and Areia ( 160 m, Brazil), Zipingpu (158m, China), Bashan
w

(155m, China), Jilingtai (152m, China), etc.


Cracks and ruptures at face slabs and high leakages (> 1,000 liter/s) currently
recorded at many high CFRDs in the world shown that different factors have been
affected CFRD behavior. However such ruptures or cracklings at face slabs of a
CFRD shall never impact its stability and safety. Nevertheless we must pay great
attention to these problems since the CFRD construction has entered into very high
construction stage, more or larger cracks may increase amount of leakage from
reservoirs, wasting water resources for generating power, etc. We ought to resolve
these problems in CFRD design and construction.
CFRD INTERNATIONAL SOCIETY hereby organized CFRD experts from relative countries for
comprehensive summing up the experiences of constructions of world concrete face rockfill dam
(CFRD) and studied the technical problems occurred recent years in the constructions of world

1
high and very high CFRDs, and presented the effective measures for overcoming them in May
2007 so as to meet the requirements for development of the world high CFRDs. It is hereby to
formulate this draft for High Concrete Face Rockfill Dam Design Code. The purpose of this Code
is to provide guidance to the word CFRD builders to construct high CFRDs successfully.
The main contents of this code include the basic stipulations and requirements for layouts of
high and very high CFRDs and their related outlet and draining structures; detailed zonings of
dam body rockfills or gravel materials; property of dam filling materials and filling quality
standards; dam body design and calculation; excavation and treatment of dam foundation and
bank slopes ; design of concrete plinth, face slab and connecting plate; design of joint water stops
for all types of joints such as perimeter joints and vertical joints; construction in stages and raising
of built CFRDs and arrangement design of prototype observations, etc.
This guidelines will help to the design and construction of world high CFRDs.

vn
CFRD/D001--2008

d.
-----------------------------------------------------------------------------------------

Finalizers:
ol
Bayardo Materon Brazil President of CFRD International Society
Yang Xiaoming China Member of CFRD International Society
nc
Humberto.Marengo Mexico Vice-president of CFRD International Society
Paulo Cruz Brazil Vice-president of CFRD International Society
Alberto Escueiro Italy Vice-president of CFRD International Society
.v

Palmi Johannesson USA Member of CFRD International Society


Yan Youli China Northwest Hydro Consulting Engineers
Yousef Hammamji Canada Member of CFRD International Society
w

Tan Young leong Malaysia Bakun Hydropower Project, Malaysia


Ren Shangqing China Consultant of CFRD International Society
w

Drafters:
w

Manoel S. Freitas Jr Brazil Member of CFRD International Society


Fan Jianpeng China Northwest Hydro Consulting Engineers
Yuan Hui China Nanjing Hydraulic Research Institute
Pham Hong Giang Vietnam VNCOLD
Chen Qian China Secretary General of CFRD International Society
Zhou Pingji China Guodian Changyuan Laodukou Hydropower
Development Company
Deng Shengquan China Enshi Institute of Water Resources& Investigation
Zhang Lizhi China Enshi Institute of Water Resources& Investigation
Wang Zhihong China Hangzhou Guodian Dam Safety Company Ltd

2
CFRD/D001--2008
-----------------------------------------------------------------------------------------

CONTENTS

1. Introduction ----------------------------------------------------------------------------------------------- 5
2. Terms and Symbos ---------------------------------------------------------------------------------------- 5
3. Dam Layout and zoning of CFRD Body----------------------------------------------------------------- 6
4. Filling Materials and Their Criteria ---------------------------------------------------------------------- 8
5. Design of CFRD Body -------------------------------------------------------------------------------------11
6. Treatment on CFRD Foundations-------------------------------------------------------------------------14

vn
7. Concrete Plinth ------------------------------------------------------------------------------------------- 15
8. Concrete Face Slab ----------------------------------------------------------------------------------------- 16
9. Jount Seal -------------------------------------------------------------------------------------------------- 19

d.
10. Stage Construction -------------------------------------------------------------------------------------- 20
11. Safety Monitoring---------------------------------------------------------------------------------------- 21

12. Design proposals for 300m CFRDs -------------------------------------------------------------- 22


ol
nc
1 Introduction
1.0.1 The guidelines are hereby formulated for the purpose of meeting the requirements of
.v

development in the world high CFRD construction and guide the design and construction of the
world high or very high CFRDs and to construct them in a safety and applied conditions,
economic and reasonable, and with updated CFRD construction technology and guaranteed
w

quality of CFRDs.
1.0.2 This guidelines are mainly applied to the designs and constructions of CFRDs above 150m
w

or lower than 250m in dam height. The designs for CFRDs higher than 250m shall be studied
specially; and some suggestions are made for 300m level CFRD design. The dependable design
w

proposal in harmony with local geological conditions can be made out by taking full advantage of
tests and analysis methods such as simulation analysis of dam construction and overall process of
river filling by using different mathematical model, and by application of geotechnical centrifugal
model test, etc
1.0.3 The design of high CFRDs should also meet the regulations of the country where the dam
site lies besides meeting that of this guide.

2. Terms and Symbols

2.1 Terms

3
2.1.1 Concrete face rockfill dam (CFRD):A general designation of a type of dam body filled

with rockfils or gravels compacted in layers, and also with its face slab as a anti-seepage
system .A dam body filled mainly with gravels is also called as concrete face gravel dam.

2.1.2 Dam height:A height from constructive foundation face of plinth calculated to crest

pavement. That can be calculated from the lowest constructive elevation at dam axis and with an
explanatory note.

2.1.3 Rockfill dam body:Filled body at downstream of face slab

2.1.4 Extruded curb:A concrete trapezium wall at upstream side curb of lean concrete over the

transition material before the construction of the next layer.

vn
2.1.5 Cushion layer:A direct carrier for extruded curb, transferring evenly water pressure to

rockfill dam body and the principal part for control on seepage flow stability

d.
2.1.6 Special cushion zone:Located at downstream side cushion zone of perimeter joint and

with the function of filtration for chokers for the perimeter joint and its nearby slab and for
reservoir deposits.
ol
2.1.7 Transition zone:Located between cushion zone and main rockfill zone or bank slope and
nc
rockfill zone, protecting cushion material and justifying the gradual change transient action
between rockfill bodies.

Main rockfill zone:Located in the upstream zone of dam body, a main support carrying
.v

2.1.8

water pressure.
w

2.1.9 Downstream rockfill zone:Located in the downstream zone of dam body, keeping the

stability of dam body together with main rockfill zone. The influence of its deformation is
w

indispensable on face slab.

2.1.10 Drainage zone:Located in gravel zone or at upstream side of soft rock main rockfill zone,
w

or strong pervious drainage zone at the bottom part of dam body and divided as vertical and
horizontal drainage zone.

2.1.11 stone riprap zone:Located at downstream dam toe, formed by dumped hard rock

blocks.

2.1.12 Downstream slope paving:Rubble pitching heaped and laid with block stones to protect

downstream slope of dam body.

2.1.13 Upstream blanket:Silt,fine sand , flyash or any other material covered over face slab and

perimeter joints, as additional anti seepage function.

4
2.1.14 Weighted zone:Debris covered over upstream blanket, keeping stability of upstream

blanket zone with a protection function.

2.1.15 Plinth:concrete slab connecting impermeable carrier at base of foundation and face slab

2.1.16 Plinth reference line :Intersecting line of face slab bottom and foundation rock surface of

plinth

2.1.17 Concrete face slab:A concrete plate type structure located at upstream face of rockfill

dam body, with the function of anti seepage

2.1.18 Parapet:A concrete wave wall located at upstream crest side and connecting to face slab

vn
crest.

2.1.19 Perimeter joint:Joint between face slab and plinth or toe wall

d.
2.1.20 Vertical joint:Vertical abutment joint between strips of face slab

Horizontal joint:Joint between face slab and parapet, and horizontal joint for
2.1.21
ol
stage construction of face slab
nc
2.1.22 Flexible filler:Flexible material prepared with asphalt, rubber and filler, and for water

sealing.

Hard rock:rocks with saturation unconfined compression strength ≥30MPa


.v

2.1.23

2.1.24 Soft rock:rocks with saturation unconfined compression strength <30MPa


w

2.2 Symbols
w
w

1A——upstream blanket zone 3C——Downstream rockfill zone

1B——Weighted zone 3D——Downstream slope paving

2A——Cushion zone 3E——Dumped rock zone (or filter dam heel

zone)
2B——Special cushion zone
3F——Drainage zone
3A——Transition zone
F——Concrete face slab
3B——Main rockfill zone
C —— Extruded curb

5
P —— Connecting plate “X”line——reference line of plinth

3 Dam Layout and Zoning of CFRD Body

3.1 Dam Layout

3.1.1 Dam axis should be selected based on topographical and geological features around dam
site area in favor of layouts of plinth and hydroproject, and combining with construction
conditions, etc, and then made selection after comprehensive technical and economic
comparison .

vn
3.1.2 A gravel CFRD can be constructed on a dense gravel layer in case no weak interlayer such
as fine silt sand or clayey soil, etc influencing the deformation and stability of the dam body in the
alluvium on the river bed.
3.1.3 It is best to select a plinth line according to the following requirements:

d.
A Place a foundation base of plinth on a firm ground; a weathered rock foundation can
also serves as a plinth foundation after being treated with some engineering measures.
B
ol
A favorable topography should be selected for a plinth line, laying it flat and up and
down slope as possible; The bank slopes shouldn’t be too steep at downstream of the plinth line.
The requirements for foundation base is the same as that for plinth.
nc
C A plinth line should keep away from the adverse geological foundation such as fracture
development, intense weathered , intercalated clay or karst foundation, leaving a minimum for
excavating and treating the plinth foundation.
.v

D A second laying out can be carried out based on specific geographic and geological
conditions and adjust the line location of the plinth after excavation of overburden of plinth
foundation in the initial stage of construction and also the geological and topographic
w

defect can be treated through engineering measures. The designs of high toe wall and
seai should be well done as for the mountain slope (equating with the peripheral joint
w

water seal ) when a high toe wall is adopted for treating the slope.
3.1.4 The juncture layout between slab and other structures and design of seal connecting to
perimeter joint should be well done when other structures are arranged at abutments.
w

3.1.5 The grout curtain of the foundation of dam, abutment spillway and other related
structures should be connected with one another, forming an integral closed seepage proof
curtain. Special attention shall be paid to anti-seepage stability and durability of antiseepage
curtain, especially to the quality of shallow deep hole consolidation grouting of the dam
foundation and increasing properly lines of grout holes for consolidation grouting based on
hydrogeological conditions with the increment of dam height resulting in that the head of
Seepage water will be higher and higher in the dam foundation.
3.1.6 The layout and excavation of construction structures of hydro project should be analytical
investigated in detail, and a comprehensive comparison carried out on balance cuts and fills so as
to offer material source for dam construction as possible.

6
3.2 Zoning of CFRD Body

3.2.1 The principle for zoning of CFRD body is to use local practicable materials and only the
insufficient part of dam filling materials to be excavated from a quarry under the premise of
ensuring engineering safety and economy , and meet the requirements of stability, infiltration flow
and deformation control. The zoning should be divided based on material source and the
requirements such as strength of dam filling material, permeability, compressibility, expedient
construction and reasonable economical efficiency and formulate corresponding filling criteria
for the dam. The dam body is suitable to divide as extruded curb zone, cushion zone, transition
zone, main rockfill zone, downstream rockfill zone, and special cushion zone located at
downstream side of perimeter joint; a upstream blanket zone and a weighted zone should be
designed at the bottom of slab upstream face from upstream to downstream; an extruded curb on

vn
the cushion layer. The main rockfill zone extends on to dam axis downstream and an underwater
rockfill zone designed below downstream flood level according to different dam heights, quality
and storage of rockfills .
The permeability of dam material for each zone should augment from upstream to downstream

d.
and meet hydraulic transient requirement. The dam material is free from this restriction below
downstream water level at downstream rockfill zone. The upstream portion of rockfill dam body
ol
should be of low compressibility. The deformation difference shouldn’t be too big between
downstream and upstream portion of the rockfill dam body.
A tipped hard rockfill can be placed at downstream dam heel in case the downstream cofferdam
nc
connects to the dam body.
3.2.2 The zones of dam can be fluctuated according to demand in case the dam body is filled
with gravel; The gravel materials should be filled in the regions of high stress of upstream and
.v

central portion of the dam.


3.2.3 A vertical drainage zone should be designed in the upstream zone of the dam body and
connecting to the horizontal drainage zone at the dam bottom so as to drain the possible water
w

seepage out of the dam and keeping the dam body in a dry condition at downstream zone as for
the sandy gravels or softrock dam body whose permeability doesn’t meet the requirements of
w

free drainage . A field stone prism body can be designed at downstream dam heel if necessary
with a role of filtration function.
w

3.2.4 The horizontal width of cushion layer zone should be determined by dam height, landform,
construction technology and economic comparison. It shouldn’t be less than 3~6m in case
construction is carried with a mechanized construction and can be decreased adequately
and the width of transition zone is increased correspondingly when backhoes and loaders
are adopted through cooperating spreading manually. A up to down variational width
layout may be adopted for the cushion layer zone which should be extended downstream
properly along bedrock contact surface. Its extension will be defined according to landform
of bank slopes, geological conditions and dam height. A flatness requirement should be
put forward as for the upstream bank slope of cushion layer zone. A special cushion layer
zone with compacted thin layers should be designed at the downstream side of
perimeter joint.
3.2.5 A crest too wide as for extrude curb will lower capacity for deformation adaptability

7
of the curb. Thereby its maximum crest width shouldn’t be greater than 12 cm with a inside
slope ratio of 8:1. The upstream slope ratio will be adopted based on the design slope ratio with a
layer thickness of 40 cm.

4. Filling Material and Their Criteria

4.1 Filling Material

4.1.1 Borrow investigation should find out its storability , quality and exploitation conditions for
all materials; The investigation on constructional materials should be carried out in the excavated
area according to the requirements of the borrow when using excavated rock materials from

vn
structure area , and a test on indoor physical mechanic property should be carried out.
4.1.2 Indoor tests on rocks should mainly include specific density, density, percent sorption,
compressive strength and elastic modulus, etc. The chemical analysis should be made on mineral
composition and ores should be done.

d.
zone based on test results and engineering analogy.
The indoor tests on dam filling materials should include gradation, porosity, shear strength and
ol
compressive modulus, etc. A permeability test and filtration erosion test should also be done for
cushion layers, sandy gravels and softrock materials. Stress and strain parameters tests should be
also done .
nc
The characteristic index of physical mechanics should be defined reasonably for each subzones
based on test results and combining with engineering analogies.
4.1.3 Borrow planning and filling planning should be made out for rock materials (or sandy
.v

gravels) and rock materials in the structure area based on the layout of water control projects
and the requirements of dam filling material sources and their quality and to arrange them in detail
in the construction design.
w

4.1.4 A medium hardness rockfills ( wet compressive strength > 40MPa ) or sandy gravel
w

material should be used for the downstream portion of main rockfill zone. The rockmass strength
can be properly decreased based on the raise of filling elevation by inches. The scope of main
rockfill zone should be extended as possible. The shed line between the main rockfill zone and
w

downstream rockfill zone inclines to downstream of dam axis by not less than 1:0.2. The

downstream rockfill zone should be also roller compacted to a higher density, making the
difference value of modulus between them to minimum. The excavated rock materials from water
control project should be used for upper dry zone of downstream secondary zone or lower stress
zone , of which is suitable for quality requirements of main rockfill zone or downstream rockfill
zone may be also used for the lower portion of main rockfill zone or downstream rockfill zone
4.1.5 A hard rock material should drain freely with a higher compacted density and
deformation modulus after being compacted. The maximum size of the dam material shouldn’t

exceed the thickness of compacted layer, the content of particles < 5mm shouldn’t exceed 20%

8
and that < 0.075mm shouldn’t exceed 5%.

4.1.6 The rockfill materials of soft rocks should have lower compressibility and a certain
compressive strength and may use for a dried zone above downstream water level at downstream
rockfill zone. A special justification and design should be carried out if they are used in the main
rockfill zone. A drainage measures can be designed in the dam in case permeability can not meet
requirements. Dam slopes and water seal structure of the perimeter joint should be suitable for
rockfill material property of soft rocks.
4.1.7 The sandy gravel materials will have a higher shear strength and lower compressibility
after compaction suitable for filling a main rockfill zone. The design of seepage flow control
should be made for the dam body according to the regulations of Article 5.5 in this guide. .
4.1.8 The portion below downstream water level at dam bottom of downstream rockfill zone
should be filled with rocks with free drainage and strong weatherproof capacities; The portion

vn
above downstream water level at that zone may use the same materials with that of the main
rockfill zone. However the compacting criteria can be suitably cut down , or use of lower quality
rocks such as all kinds of soft rock materials or weathered stones, etc.

d.
4.1.9 A fine rockfill material specially produced, screened natural sandy gravel or tunnel
excavated ballast may be used for the transition zone. The fines particles of the maximum size of

80~100mm are required continuous gradation.They should have low compressibility and high
ol
shear strength and free drainability after compaction.. The content less than 5mm particles should
nc
be 35~55% and that less than 0.075mm particles should be lower than 2~10%.

4.1.10 The cushion material should have continuous gradation with the fines content of 40%~
.v

55%, a maximum size of 80~100mm, the content of size < 5mm of 30%~50%,that of


w

size <0.075mm of less than 8%. It should have internal percolation stability, low compressibility,

high shear strength and good workability after compaction.


w

4.1.11 The sandy gravels selected by sifting, artificial aggregates or the other admixtures can be
used for cushion materials. The artificial aggregates should be processed by sound mother rocks
w

with strong weatherproof capacities.


4.1.12 The special cushion layer at downstream side of perimeter joint should be filled with a
maximum size less than 40mm , and with a fine filter material of internal stability. It should be
compacted in thin layer to consolidation and reducing deformation of perimeter joint as possible,
meanwhile placing silt or flyash on the top of joint as a filtering layer.
4.1.13 The upstream blanket zone (1A) of concrete slab should be placed with muddy soil, silt,
flyash or other low cohesive materials.
4.1.14 Ballast aggregates can be applied for upstream weighted zone(1B) .
4.1.15 The downstream slope protection is built by laying block stones or placing oversized
block stones with bid ends outwards, selected from the rockfill body and conveyed to downstream
ramp slope.
4.1.16 Weather-proof rocks or gravels and with good drainability should be selected for

9
vertical and horizontal drainage bodies if they are designed in the dam body.

4.1.17 The extruded curb provides a stable and reliable supporting plane, ensuring which is a even
thickness of slab, reducing construction sequence and keeping the slab from rain impact erosion or
wave scour, which is a low strength and semipervious trapezium concrete guard wall.

4.1.18 The concrete compactness of extruded curb should meet the requirements for percolation ,
strength and elastic modulus and easy to construction, i.e. designing in a mix ratio of first order
gradation dry concrete with slump of 0, scale of intensity of C3~C5 and ;permeability coefficient

ofι×10-4cm/s.

vn
4.2 Filling Criteria

4.2.1 The filling criteria for filling materials for cushion zone, transition zone, main rockfill zone,

d.
and downstream rockfill zone should be integratively defined based on some factors such as
grade , height, valley form of the dam, and seismic intensity and borrow features and referring to
the same type of engineering experiences
ol
The roller compaction parameters for filling are defined based on compaction function of
compacting plants through compaction tests. Equipments with stronger compaction function
nc
should are adopted as possible so as to increase filling density, reducing deformation.
4.2.2 The filling criteria for each subzone material can be tentatively defined based on
experiences. Their values can be selected within the range of Table 4.2.2. Meanwhile the porosity
(or relative density), range of gradation of dam materials and compacting parameters should be
.v

defined in the design. The design dry density can be conversed from porosity and rock density.
The mean dry density shouldn’t be less than the dry density value conversed from design porosity
w

( or relative density), Its standard deviation shouldn’t be bigger than 0.1g/cm3.The porosities of
w

main and secondary rockfill zones are of substantial agreement. The filling criteria for the special
cushion zone should be increased at downstream side of perimeter joint so as to reduce
deformation of perimeter joint. The design index , filling criteria and portion for soft rockfill
w

materials should be defined through tests and engineering analogy.

Table 4.2.2 Filling criteria for dam materials

aterial or zone Porosity (%) Relative density

Cushion material
15~18

Transition zone
18~20

Main rockfill zone


19~21

10
Downstream rockfill zone
< 22

Gravel material zone


0.80~0.85

4.2.3 Watering requirements should be defined for the dam material filling. The water addition
can be determined by experiences or tests. Some measures should be adopted to reach the design
requirements for the dam without water addition in the course of roller compaction in winter
seasons in a severe cold region.

5 Design of CFRD Body

vn
5.1 Crest Structure

The crest width should be defined according to the requirements of operation , layout of

d.
5.1.1

crest facilities and construction, adopting 5~8m according to different dam height. The crest
ol
width should also be selected according to pertinent regulations of a country where the dam lies in
case a traffic request exists on the dam crest.------
5.1.2 A parapet wall should be placed at upstream side of crest. Its height can be 4~6m, the
nc
parapet crest towers 1~1.5m above dam crest. The bottom elevation of parapet should be higher
than normal storage water level. The joint with face slab should be designed in detail. A U-type
groove structure may be adopted , effectively reducing filling volume of the dam body.
.v

om of the parapet so as to walk for inspection.

A viaduct of 0.6~0.8m in width should be designed so as to travel for inspection at bottom


w

portion of parapet.
5.1.3 The parapet ought to be indurate and watertight and by checking computation in stability
w

and strength. It should be designed with expansion joints; its waterstop should be connected to that
between face slab and the parapet and the expansion joint should offset apart from the joint of face
slab.
w

5.1.4 A settlement reservation freeboard of a dam crest should be set. Its value can be defined by
computation or reference to similar projects.
5.1.5 The dam body over the bottom elevation at parapet crest should be placed with fine
rockfill materials and lay a pavement. The crest pavement should be designed according to the
highway criteria of a country where the dam site lies. A good drainage system should be well
designed at dam crest in case a dam crest road exists.
5.1.6 A dam crest structure should be economic and practical, and attractive and durable in
architectural treatment, and with well designed lighting facilities .

5.2 Dam Slope

11
5.2.1 The up and downstream dam slopes can be 1:1.3~1:1.4 and selected based on physical

circumstances. The slopes of soft rock rockfill body should be properly eased. The up and

downstream dam slopes can be 1:1.5~1:1.6 in case a dam is filled with good quality natural

gravel materials.
5.2.2 The actual dam slopes between roads may be slightly steeper than the slope value
stipulated in Article 5.2.1 of this code, but the average dam slopes should meet the
above-mentioned requirements if no roads on the downstream dam slope.

5.3 Stability Analysis

vn
5.3.1 A stability analysis should be carried out on a dam slope of a high or very high CFRD in
view of the extreme condition possibly occurred. The corresponding stability analysis and
corresponding analytical justification should be carried out when one of the following cases exist.
A weak interbed or fine sand bed, siltage , or cohesive soil interlayer exists in the

d.
sandy gravel layer in the dam foundation;

B a dam site located at seismic design intensity, 8°~ 9;


ol
C a rockfill body is overflowed by flood or the rockfill dam body passes a flood season
with a cushion layer during construction period , and the depth of retaining water is deeper;
nc
D a dam body filled with soft rockfill materials ;
E adverse terrain conditions .
5.3.2. The shear strength of dam materials should be determined by triaxial compression
.v

apparatus.
The material for analogy tests should show the mechanical property of dam materials; the
testing conditions should simulate the actual operation conditions.
w

The shear strength of open grain materials and normal stress has a nonlinear relation; such
feature should be taken account for as calculation.
w

5.3.3 The stability calculation of rockfill dam body should follow the regulations of a country
where the dam site lies .The downstream slope should be protected by mesh reinforcement or
another economic and practicable protection measure during construction .
w

5.3.4 The stability calculation against earthquake should be carried out according to the
regulations of a country where the dam site is.

5.4 Stress and Deformation Analysis

5.4.1 Different mathematical models should be adopted to analytical study stress deformation at
dam body of very high CFRDs; The overall process of simulation calculation should be carried
out on construction and impoundment of CFRDs so as to study their deformation rule and disclose
the influence law of stress and deformation of large deformation and rheology factors on concrete

12
face slab and perimeter joint of the dam body through research on issues such as special border
simulation ( vertical and perimeter joint between straps, interface between face slab and cushion
layer, etc ) of the face slab and the rockfill creep, etc.
The parameters calculated by finite element method should be defined through testing and
combining with similar engineering analysis The simulating materials, sampling conditions and
load modes for the tests should reflect mechanical properties of the dam materials.
5.4.2 The mechanical properties of the discontinuous interface of the dam body should be
reflected and simulating multi-stage load conditions for the dam body based on filling in stage and
impoundment process in the finite element analysis on stress and deformation .

5.4.3 A dynamic analysis should be carried out on the dam body with finite element method so
as to make a synthetic judgment on their anti-seismic safety as for the high dams in a seismic

vn
design intensity of 8°~ 9º and /or liquefiable soil exists in the foundation. A dynamic test should

be done for such dams.


5.4.4 The rationality of computing results should be studied based on construction quality

d.
inspection data and prototype observation data from dam body , and analysis in time in order to
check and revise computation schema and parameters, and revise the design when necessary.
ol
5.5 Seepage Flow Control on Dam Body
nc
5.5.1 The seepage status , stress deformation and monolithic stability within the dam body
should be researched under a extreme case (both failures of perimeter joint and anti seepage
system).------ An overall evaluation is made on seepage flow stability of dam body and monolithic
.v

stability against sliding based on computing results and presenting the corresponding engineering
measures to improve and increase stability and safety of a CFRD.
The cushion materials for CFRDs should be continuous gradation and internal seepage stability,
w

and meet the regulations in Article 4.1.10 and Article 4.1.11 of this code. The coefficients of

percolation after compaction should be 1×10-4 cm/s.


w

5.5.2 The drainability in the drainage zone should be ensured to discharge all the water seepage
freely out of the dam in case the dam body is mainly filled with sandy gravels and arranged
w

vertical and horizontal drainage zones. The crest elevation at vertical drainage zone should be
higher than normal reservoir level; the hydraulic transient requirements should be met between
drainage zone and dam body; A filter layer may be designed when necessary.
5.5.3 A seepage calculation should be made and recheck the seepage stability for a rockfill dam
body to retain flood temporarily by the cushion materials during a high water season. The
seepage calculation can be made referring to the calculation method of a country where the dam
site is.

5.6 Earthquake Resistant Measures for Dam Body in Seismic Area

5.6.1 The dam crest should be widened, and flatten the dam slope with a gentle gradient at upper

13
portion but a steep gradient at lower portion of the dam slope and bermes are designed at

variable slopes as for the design intensity of earthquake of 8°~ 9°. The crest of downstream slope

face should be reinforced by dry laid block stones, or by reinforced rockfills and the surface
strengthened by mesh reinforcement (geogrid ) and reinforced concrete grid. A lower parapet wall
should be adopted and measures taken to increase the stability of the wall.
5.6.2 The surge height of earthquake should be included when defining the free board of the
dam in the earthquake area. The free board should be taken into account to the additional
settlement under the action of earthquake on dam and dam foundation when the

earthquake design intensity of 8°~ 9°.

5.6.3 The width of cushion zone should be increased and strengthening its join with foundation
and bank slopes . A contact length should be extended properly between cushion material and

vn
bedrock and a finer cushion material is used in case the bank slopes are steeper.
5.6.4 Several vertical joints should be selected at a middle portion of face slab and enlarging the
gabs between slab joints of face slab , into which, fill compressible high molecular material or

d.
other infill plates with a certain elasticity
5.6.5 The reinforcement ratio should be increased at face slab of upper portion on the middle of
river valley ------- .
ol
5.6.6 The compacted density should be increased for rockfill material of the dam body ,
especially where breaks exist.
5.6.7 The drainage ability should be increased in discharge zone in case a dam body is filled
nc
with a sandy gravel material. The rockfill should be filled in a certain zone within downstream
dam slope.
.v

6 Treatment on Dam Foundation


w

6.1 Excavation of Dam Foundation and Bank Slopes


w

6.1.1 The cut surface of dam foundation should try to be of easement, obviating risks of
potential structural cracks .
w

6.1.2 The cut surface of plinth should try to be of easement, obviating escarps and adverse
slopes and cutting slopes and leveling by backfill concrete if necessary .
6.1.3 The foundation base of plinth should be excavated to upper portion of weakly weathered
layer. A special justification should be made in case the foundation base can be only on weathered
and broken or incompetent bed because of restriction of topographical and geological conditions
and corresponding reinforced measures should be taken.
6.1.4 The excavation criterion differs with location for rock foundation of dam body. A rockfill
body can be placed on weathered rocks unless the deformation modulus is adaptable. The bases
for cushion layer and transition material is the same as that for plinth. The foundation of the dam

body should be of low compressibility in the range of about 0.3~0.5 times of the dam height at

downstream plinth. The compressibility for the foundation of dam body out of the range of 0.5

14
times of dam height may be widened.
6.1.5 The thick gravel alluvium should be remained as possible as foundation of dam body; but
defined after testing and justification through detail investigation.
6.1.6 The rocky bank slopes above the plinth should be excavated as stable slope or that after
being treated so as to safety during its operation period.

6.1.7 The bank slopes should be excavated into a 1:0.5 slope within the range of 0.3~0.5 times

of dam height of plinth downstream at foundation of rockfill body. A stable slope gradient less
than 1:0.25 can be excavated in case the bank slopes are very steep, but a low compressive rockfill
zone or patched slope by backfilling concrete should be designed. The escarps and overhanging
structures obstructing the rockfill body to be compacted should be cleared away. The bank
slopes at dam axis downstream should be defined according to the requirements of meeting
its self stability

vn
6.2 Dam Foundation Treatment

d.
6.2.1 The dam foundation treatment should get to lessen foundation deformation, increase
compressive strength , prevent seepage and erosion on foundation material, and improve flatness
ol
on foundation surface so as to meet the requirements of normal and safety performance.
6.2.2 The rock foundation of plinth should be treated by consolidation and curtain groutings.
nc
6.2.3 The consolidation grouting should be in 2~4 lines and the range of grouting depth is

6~20m.
6.2.4 The curtain grouting should be arranged in the middle portion of plinth and can be
.v

combined with consolidation grouting. The curtain should be in 1~3 lines with seepage ratio of

1~5lu. The depth of curtain may be 5m below relative impermeable bed; also can be selected at a
w

dam height of 1/3~1/2 based on geological conditions. The layout, depth, and the extended length
w

towards both banks should be defined by calculation and combining the similar engineering
experiences under the complicated hydrogeological conditions or a deeper imbedded depth for a
relative impermeable bed.
w

6.2.5 The parameters such as rising extent of grouting pressure , grout proportion and grout
acceptance should be defined by testing. The measures should be worked out in the grouting
design for increasing durability of grout curtain and grouting pressure of surface bedrock.
6.2.6 The bedrocks within the range of plinth should be treated carefully one by one based on
their occurrence , size and constructional material if unfavorable geological conditions exist such
as fault, fractured zone and weak interbed , etc , and by replacement treatment with concrete
plugs , extending to a certain distance towards to downstream, and by covering them with filter
material and reinforcing the grouting into plinth.
6.2.7 The karst development status should be found out in case plinth lies in a karst foundation
and a special justification should be carried out on their anti seepage treatment measures.
6.2.8 The plinth foundation can be treated with following measures in case it is on a deep
weathered fractured and weak rock formation so as not be excavated to a moderated weathered

15
stratum:
A. extending seepage path such as widening plinth, designing downstream anti seepage
plate and concrete cut-off wall ,etc
B. adding expansion joints
C. covering filter material over the downstream

7 Concrete Plinth

7. 0 1 The following 3 modes for selection of plinth layout:


A. The contour line of plinth surface perpendicular to its line of reference;
B. The contour line of plinth surface perpendicular to dam axis;
C. The contour line of plinth surface meeting the requirements of excavated rock face

vn
The Scheme A is called as flat plinth. The flat plinth is easy to construct and considered firstly
to adopt.
7.0.2 Rrequisite expansion joints should be designed based on topographical and geological
conditions for the plinth on bedrock and staggered arrangement to the vertical joints at face slab;

d.
The construction joints at plinth can be designed based on construction conditions; The outer
corner of plinth takes the form of junction block as its body type.
ol
7.0.3 The allowable hydraulic gradient of the rock foundation underneath the plinth should be

Table 7.0.3 allowable hydraulic gradient of rock foundation


nc
Rock rot degree allowable Rock rot degree allowable hydraulic

hydraulic gradient
.v

gradient
w

Fresh,weak weathering ≥20 Intense weathering 5~10


w

Moderate weathering 10~20 Full weathering 3~5


w

7.0.4 The plinth width on rock foundation is defined according to allowable hydraulic gradient.
The plinth should be adopted with different width according to head in elevation section. A

minimum width of a plinth shouldn’t be less than 3m;

An additional downstream anti seepage plate can also meet the requirements of hydraulic gradient
for plinth; still the width of plinth should meet the requirements of grouting. The surface and the
downstream of a downstream anti seepage plate should be covered with filter materials.
7.0.5 The thickness of plinth on rock foundation may be less than that of face slab connecting
to it ; A minimum design thickness shouldn’t be less than 0.3m; that of bottom plinth shouldn’t be
less than 0.5m and a different thickness may be adopted according to its elevation in sections.
7.0.6 The height of the plinth downstream surface normal to the basal plane of face slab
shouldn’t be less than 0.9m with a slipform construction.

16
7.0.7 The plinth foundation overexcavated over 1m should be filled and leveled up with
concrete firstly before placing the plinth.
7.0.8 The plinth should be defined based on the terrain condition and will have a length of
repose not less than 0.6m so as for railless slipforming for face slab in case the face slab and
the plinth are in the same plane.
7.0.9 The concrete property and its requirements of crack control for plinth are the same as that
of face slab, referring to the regulations in Articles 8.3 and 8.5 of this Code.

7.0.10 The steel ratio in each way for reinforcing bar of plinth on bedrock can be 0.3%~0.4%

of design thickness of flat plate section ; The bar arrangement should be in single layer and double

way with a protective covering thickness of 10~15cm.

7.0.11 The plinth should be joined to the bedrock with grouted bolts. The parameters for the

vn
bolts can be defined according to experiences and should be defined by stability and resistance to
grouting pressure in case low dip angle structural plane around base level of plinth.
7.0.12 Generally, no stability analysis is needed for plinth. The stability and stress analysis are

d.
needed if the thickness of plinth exceeds 2m. The method of limit equilibrium for rigid body is
applied for the stability analysis for plinth. The anchor bar effect and the transport power between
face slab and plinth won’t be accounted for in the calculation. The rockfill pressure can only take
ol
into account of active pressure of the rockfill or of lateral pressure generated by rockfills under
face slab after carrying reservoir pressure.
nc
8 Concrete Face Slab
.v

8.1 Parting and Partitioning of Face Slab


w

8.1.1 The parting and partitioning of face slab should be done based on deformation of dam

body and construction conditions. The space between vertical joints can be 12~18m . A
w

permanent horizontal joint is designed at 1/3 dam height of upper portion of face slab as the case
may be for above 200 m high CFRDs according to the actual conditions .
w

8.1.2 The tensile vertical joints should be designed for the face slab near both the abutments,
and for the other parts of face slab compressive vertical joints are designed. The Number .of
tensile vertical joints are defined based on topographical and geological conditions and referring
engineering experiences or finite element calculation.
8.1.3 The arrangement of construction joints at face slab should meet the requirement of
temporary water retaining or water storage in phases. The joint surface of concrete
construction joint should be green cutted, cleaned clearly, the joint surface wetted with
water, and placing a thin layer of high strength mortar before going on placing concrete.
Face slab steel bars should go though joints. The horizontal construction joint of slab
should be parallel with its normal direction. The thickness in normal direction shouldn’t be
less than 1/2 slab thickness at least

17
8.1.4 The construction joints at face slab placed in stage should be lower than the crest
elevation at the filling body and the height difference should be higher than 5m. The face
slab concrete should be additionally placed after impregnating densely with low grade and
low compressive mortar in case any cavity is found between placed face slab and
cushion layer so as to ensure them well bonded

8.2 Face Slab Thickness

8.2.1 The definition of face slab thickness should meet the following requirements:
A. Facility to installation of steel reinforcement and water stops within it. The minimum
thickness is 0.30m.
B. Controlling percolation hydraulic gradient doesn’t exceed 200;

vn
C. A thinner thickness of face slab should be selected for increasing flexibility of face slab and
decreasing its construction cost with the premise of meeting the above requirements.
8.2.2 The thickness at corresponding height of face slab can be defined according to the
following computation expressions:

T= 0.30+0.0035H (m)

d.
Where, T = Thickness in meters;
ol
H = Height in meters.
nc
8.2.3 The minimum thickness of face slab can increase to 40cm, T= 0.40+0.0035H (m)for the

easy extruded failure zone of central face slab on the valley section with respect to the high CFRD
in a narrow valley.
.v

8.3 Face Slab Concrete


w

8.3.1 Face slab concrete should be of food workability, crack resistance, impermeability and
w

durability. The corresponding indexes are as follows:


The level of face slab concrete strength shouldn’t less than C25;
The grade of concrete frost resistance should be defined according to the regulations of a
w

country where the dam lies.


8.3.2 A composite Portland cement or ordinary Portland cement should be used for the face
slab concrete. A comparative test should be carried out for defining type of concrete in case
adopting another variety or strength grade of cement.
8.3.3 The flyash or other quality admixtures should be mixed in the concrete of face slab. The

degree of flyash fineness shouldn’t be bigger than 45 μm, the content of flyash should be 15%~

30% ,or define based on relative regulations of a country where the dam lies.

8.3.4 A proper amount of flyash can be admixed in case poor aggregate gradation and coarser
sand material for improving concrete workability; Substitution of flyash may be possible to
reduce cement and sand material so as to improve concrete performance.

18
8.3.5 The concrete of face slab should be admixed with air entraining agent, simultaneously with
highly active or common water reducing agent . Other type of additives may be also added to
adjust the set time of concrete according to the requirements. The type and content of admixtures
or additives should be defined by testing.
8.3.6 A Gradation II aggregates should be adopted for face slab concrete with a maximum size
not bigger than 40mm. The percent sorption of sand materials for face slab should not bigger

than 3.0%, the silt content not bigger than 2.0%, and fineness modulus within 2.4~2.8. The

percent sorption of stone materials for face slab should not bigger than 2.0% and silt content

not bigger than 1.0%.

vn
8.3.7 Water cement ratio of concrete of face slab should be less than 0.50 in temperate area, and
less than 0.45 in cold or severe cold area. The slump should meet the construction requirement ,

the slump at access point of chute should be controlled by 3~7cm in case concrete is conveyed

d.
with a chutting system . The air content of concrete should be controlled at 4%~6%.
ol
8.4 Steel Reinforcement Installation
nc

8.4.1 A single layer and two way steel reinforcement should be installed on the centre portion of

the face slab cross section with ratio of 0.3%~0.4% each way and the ratio in horizontal
.v

direction may be less than that in vertical direction.


8.4.2 A reinforced steel bar may be properly deployed at strong tensile stress zone or perimeter
w

joint at both banks and its vicinity. A resisting extruding constructional reinforcement should be
placed at both sides of vertical joints close to perimeter joint, but such placement of reinforcement
w

shouldn’t influence installation of waterstops and the quality of vibrated concrete nearby the
waterstops.
8.4.3 The double-layertwo-way reinforcement should be designed as for the compression
w

steel in the face slab on the middle portion of a narrow valley


8.4.4 The area of reinforcement should be calculated based on the design thickness of face slab
concrete.

8.5 Anti-cracking Measures for Face Slab


8.5.1 The base surface of face slab and the foundation of both abutments should be flat without
oversize waviness , local kolks nor cusps. The side forms should be straight.
8.5.2 The 28d compressive strength should be about 5MPa in case stabilizing the slope of
cushion material with roller compacted mortar or shotcreting so as to reduce constraint on the
base surface of face slab.
8.5.2 Additives and admixtures should be adopted in the mix ratio for face slab concrete so as to
reduce cement content and water consumption and lessen temperature rise due to hydration

19
heat ,and shrinkage strain. An aggregate of low thermal expansion coefficient should be
selected according to actual conditions of the project so as for the slab concrete to
have a higher tensile strength and ultimate tensile value.
8.5.3 The concrete of face slab should be placed in a low temperature season and control the
placing temperature , and strengthening damp-preservation curing and insured curing on the
surface of concrete face slab ,and stop curing until water impoundment or 90d at least.
8.5.4 The parapet concrete should be then placed with as the settling volume can be controlled

within 5~6mm/m after the concrete of face slab is placed up to crest.

8.5.5 A special measure should be adopted to treat the cracks when they are wider than 0.2mm
or defined as permeable cracks. The strict treating standard should be defined for the cracks at
face slab of CFRDs in severe cold region or pumped storage stations. One layer of
anti-seepage, insulation and anticrack paint sprayed or coated on face slab can prevent

vn
temperature cracking at face slabs.

9 Joint Seal

d.
9.1 Installation of Joint Waterstops
ol
9.1.1 A waterstop should be installed in the perimeter joints. The bottom copper waterstops
nc
should be installed as the basic anti seepage line, the medium PVC or rubber waterstops and
waterstops at upper portion should be selected according to actual conditions. The upper sealing
system is generally made up of flexible filler, fine silts (or flyash), etc, may be one type of sealing
.v

material , and also a flexible filler and cohesionless material. Bottom and upper waterstops or
bottom, middle and upper waterstops should be adopted for high or very high CFRDs, depending
on actual conditions. The seal structure of perimeter joint in a macroseismic area should be
w

defined based on the findings of related dynamic calculation and joint tests. The thickness of
bituminizing joint board should be determined based on the findings of related dynamic
w

calculation and joint tests in view of a greater deformation of the perimeter joint in a macroseismic
area.
9.1.2 The compressive vertical joints should be changed into construction joints. The steel
w

reinforcement should go through joints in the face slab and cancel waterstops and a hard flat joint
structure should be adopted; one bottom waterstop is needed for all these cases. . An anti-seize
compound should be coated at one side face of joint such as asphalt emulsion, etc. and the hard
flat joint is additionally packed with bituminous wood plate. PVC pads should be placed and
bonded the cement mortar pad under the copper waterstops. The base angles at both sides of
copper waterstops should be placed with bitumen stop-grouting strap.
The vertical web height of copper waterstop is about 3 cm. the strap doesn’t account for the
thickness of face slab. Reduce depth of the V- notch or not use V notch.
9.1.3 The vertical tension joints should be adopted with bottom and / or upper waterstops and the
structures are the same of compression joints.
9.1.4 The steel reinforcement should go through the horizontal construction joints at face slab
without installation of waterstops .

20
9.1.5 A copper waterstop, PVC waterstop or rubber waterstop can be adopted for expansion
joints at plinth., forming a closed system with the parimeter joint waterstops.
9.1.6 The horizontal joint between parapet wall and face slab. should be designed with bottom
and top waterstops
9.1.7 The middle and top waterstops should be joined together with the bottom waterstops at the
connected joints and forming a closed structure. The PVC waterstops or flexible filler should be
connected with bottom waterstops at the vertical joints by holding device. The waterstop face
membrane should be felted or welded and fastened into face slab.
9.18 Angle bars should not be used at a water fluctuation section in stage in a cold region.
Expansion bolt is used as fixed parts for waterstops, flexible filler face membrane. The fixed parts
should be binding materials so as to avoid being ruptured due to frost heaving, bereaving its
fixation.
9.1.9 The joint seal between concrete cut-off wall and connecting plate should be designed

vn
according to that of perimeter joint watertops.

d.
10. Stage Construction
ol
10.1 Construction in Stage
nc
10.1.1 Stage construction plans should be reasonably worked out for dam body filling and fce
slab placement based on the requirements such as topography at dam site, construction progress,
diversion and safety in the high water season, reservoir filling, etc. The presettling time should
.v

be 5~7 months for the rockfill body underneath the face slab and the settling value shouldn’t be

greater than 5~6 mm in the converging month during the presettling period.
w

The construction of modern CFRDs require equilibrium rise of upstream and downstream
rockfill body. The backfilling level of the downstream rockfill material is slightly higher
w

than that of the upstream rockfill material so as to eliminate the influence of differential
deformation on face slab behavior, which results from differences of modulus and time
between upstream and downstream rockfills except for the requirement that the rockfill
w

should be filled to the flood retention elevation within the first low water period.
10.1.2 The stage filling planning for rockfill dambody should keep to the follow principles.
A Cushion and transition materials should be filled levelly with adjacent part of rockfill
materials.
B The binding slope gradient between rockfill materials shouldn’t be steeper than 1:1.3, and
that between natural sandy gravel materials not steeper than 1:1.5.
C Temporary ramp roads can be designed for transporting dam filling materials in the
rockfill zone.
D The filling zones should be in accordance with requirements of safety of high water season
when retaining water with a temporary cross section or flood passing cross the dam in a high
water season.
E The binding site should be treated as filling the next cross sections , avoiding block stones

21
to be centralized; Clean out noncohesive materials on sections properly and strengthening roller
compaction on binding sites.
10.1.3 The requirements of anti-sliding stability and seepage stability should be met in case
temporary section of dam body is used to retain flood in a high water season.
10.1.4 The waterway surface , downstream slope surface and toe of slope all should be protected
appropriately when flood passes through the dam body surface so as to avoid erosion by currents
in a high water season during construction period .
The means for protection should be determined based on the physical circumstances such as
waterway surface type and flow speed, protected materials, etc. A hydraulic model test should be
carried out for the important projects so as to offer the reference for selection of protective
measures
10.1.5 The horizontal joint is treated according to construction joint as the concrete face slab is
placed in stages and following the stipulates in Article 8.1.3 of the guide.

vn
10.1.6 The CFRD built in stages should be reached to the design specification for the finalized
size. The plinth, slab, seal , parting and dam foundation treatment of the first stage works should
be constructed according to final planned section. No parapet is designed for the first phase works.

d.
ol
11 Safety Monitoring
nc
11.0.1 The safety monitoring should be defined according to the relative regulations of a
country where the dam site lies for high CFRDs. Some necessary observation instruments should
be placed following the principle as “few but best ” based on grade , height, structural type of a
.v

dam, and topographical and geological conditions; a systematic observation to be carried out
during construction and performance periods , and taking order with analytic data in time.
11.0.2 The following observation items designed for high CFRDs:
w

A vertical and horizontal displacement at dam face


B vertical displacement within dm body
w

C joint displacement
D deformation and strain at face slab
E seepage flow
w

F horizontal displacement within dam body


G settlement at alluvium of dam foundation
H seepage pressure on foundation and body of dam and roundabout seepage at abutments
I Thrust of ice cover on face slab in a cold region
J crack monitoring on concrete face slab
K earth and contact pressures
L monitoring on concrete cut-off wall
M monitoring on toe wall or retaining wall
N Monitoring on separation of face slab
O. Seismic response
11.0.3 The design of safety monitoring should be meet requirements of observations during
construction period and obtain the early observation data so as to guide construction and

22
optimize design.
11.0.4 The selection of observation instruments should be in line with the principles as reliability,
durability, economy and practicality and try for update instruments; Realizing observation
automation if condition allowance.
The observation instruments should be arranged according to the following principles such as,
A capable for reflecting service behavior of the dam all roundly
B outer surface deformation observation points can be generally installed in an
equidistance
C internal observation instruments should be installed at least along a cross section at a
maximum dam height. Additional observation sections can be arranged along longitudinal profile
of dam axis, not less than 3 observed profiles at least in necessary.
D internal observation instruments should avoid construction disturbance as possible and
convenient for observation activities, and ensure possibility for observation on necessary items

vn
under the condition of an atrocious weather
E strengthening observation items such as deformation of concrete face slab, three way
deflection at perimeter joint and seepage rate , etc. The seepage rate observation should try to

d.
distinguish the seepage rates from the both banks or dam foundation so as to estimate exactly the
status of seepages from dam foundation and both banks , and performance of dam and its
foundation.
ol
12 Design Proposals for 300m CFRDs
12.0. 1 Zoning of 300m CFRDs
nc
Higher requirements of both stress transition and seepage flow transition are needed for 300m
CFRDs. So, The main materials are divided into 11 zones for CFRD body (See Fig.1).
.v
w
w
w

23
vn
d.
ol
nc
2A1—cushion material zone, horizontal width of 3~6m,underneath face slab and narrow

according to lineation based on acting head.


.v

2A2— mini zone material, lies at perimeter joint of cushion material portion, bottom width of
w

4 m, slope of 1:1.4 towards downstream


w

3A1—filter transition material zone , horizontal width of 3~6m, 3 layers divided by the

principle in height difference of about 100m of main rockfill material so as to make the most of
w

using dam filling material with different property; 100 m at the lower portion,main rockfill
material Zone I

3B1— 100 m at the middle portion , main rockfill Zone II

3B2— 100m at upper portion , main rockfill Zone III

3B3— downstream rockfill zone, divided into 4 subzones,The height difference of division

is substantial agreement with the main rockfill zone.

3D1— about 100m at bottom portion, downstream rockfill material Zone I ( drainage zone )

3C1— about 100m at middle portion within the dam shell , secondary rockfill material

24
Zone I

3C2— about 100m at upper portion inside the dam shell, secondary rockfill material

Zone II;

3D2— outside 3C1 and 3C2 Zones, 20m close to dam slope , downstream rockfill material

Zone II

The shed line of upstream main rockfill zone(3B1,3B2,3B3)and downstream rockfill zone

(3D1,3C1,3C2)should incline downstream and the slope gradient shouldn’t be steeper than 1:

0.2 in view of the trajectory of principal stress.


The upstream cover material zones shouldn’t be 1/3 of the dam height and divided as blanket

vn
material Zone I A and weighted material Zone 1B.
Zone 1A is incoherent material and the cushion material should form the filter protection of it
Zone 1B should mainly retain the stability of upstream slope.

d.
12.0.2 A special compacted zone should be added as for steep bank slopes for CFRDs in the
narrow river valley. The compactness of this zone is the same as that of transition material so s to
decrease adverse effect of side slopes on deformation of dam body.
ol
A filter material zone should be added at portion with special geological conditions.
12.0.3 Select compaction equipments with great power and high performance
nc
12.0.4 Select high performance joint sealing materials suitable for high head and large
deformation
12.0.5 Present well targeted antiseismic engineering measures
17.0.6 Select monitoring instruments suitable for monitoring properties of high CFRDs ; define
.v

the burying technologies ensuring instruments to be well buried .


w
w
w

25