Installation Qualification Protocol For Air Handling Unit & Air Distribution System
Installation Qualification Protocol For Air Handling Unit & Air Distribution System
OBJECTIVE
The objective of this protocol is to provide an outline for the inspection of static attributes, written
procedure and guidelines and respective acceptance criteria for the Installation and Operational
Qualification of Air handling unit .
Installation Qualification
Each installed components and sub component complies with the engineering design and
manufacture recommendations.
To ensure that appropriate interconnections are made for utilities / equipment that all the features
are defined before the start up of operational qualification.
The system meets the current good manufacturing practice requirements.
To prepare tentative standard operating procedures.
Calibration of instruments
Functional keys.
Design parameters
Alarms & interlock systems
Verification of standard operating procedures.
Sequential operation
Effect of power failure on the equipment
SYSTEM / EQUIPMENT DESCRIPTION
The Air Handling unit is designed to provide and maintain the following conditions in the area
where it caters
AHU Capacity of air filtration – __________ CFM.
Temperature — NMT 25 ºC
RH — NMT 60 %
Description:
Air handling unit is a recirculation system, in double skin modular construction. AHU will have
extruded aluminium frame with sandwiched panel of G.I. sheet duly pre coated from outside & 43
mm thick PUF filled in between.
Fresh air enters through 10µ fresh air filter. Air then passes through mixing section with (10 +5) µ
pre-filter, 6 rows deep chilled water coil (CH W) coil & 2 rows deep Hot water (H W) coil is placed
on condensate tray, Sandwiched type in SS-304 construction with proper drain point. The air will
then pass through 3µ fine filter installed in AHU supply plenum.
FA damper are provide with 10µ G-4 pre- filter, EA damper are provide with (0.3µ)H-13 HEPA
filter.
Filtered air after 3µ filter will be supplied to the room via leak proof GSS Ducting through ceiling
mounted Supply air Hepa (0.3 µ) H-13 and air will return through return air Riser via return duct to
mixing chamber.
Both ends of the GI ducts will have flanges & flanges will have neoprene gasket. GI ducts will be
thermally insulated by Polyethylene foam insulation. Air volume control dampers shall be installed
at (fresh, return) air inlet, (supply, bleed) air outlet of AHU and Supply air Hepa & Risers. Fire
damper should be installed on supply & return air duct near to AHU.
RESPONSIBILITY
Engineering and Maintenance Department
Preparation of the IQ protocol in conjunction with user .
Checking the protocol for adequacy and accuracy prior to the approval.
Providing guidance, wherever required to the related departments.
Quality Assurance Department
Providing guidance and check the protocol document.
Head Operations
Checking the protocol for adequacy and accuracy.
Providing required details to the Engineering / Maintenance.
Collection of data and preparation of final design.
Execution of the protocol and preparation of IQ summary report.
User department
Approval of protocol.
ABBREVIATIONS:
Sr. No. Term Explanation
2 DQ Design Qualification.
3 IQ Installation Qualification
4 OQ Operational Qualification
5 GI Galvanized Iron
6 SS Stainless Steel.
7 Temp Temperature
8 RH Relative Humidity
12 Cont. Continued
13 WC Water column
0
15 C Degree centigrade
16 m Micron
18 Min Minimum
19 Max Maximum
22 NA Not Applicable
33 AL. Aluminium
34 NR Not Required
36 DB Dry Bulb
38 KW Kilo Watt
39 HP Horse Power
40 Ph Phase
42 Pa Pascal
EXECUTION TEAM
Signature /
Department Responsibility Name Designation
Date
The following components were checked if they are according to the design specification:
Design Verification
Room Data Sheet
Floor Plan Drawing
INSTALLATION VERIFICATION
It was checked and proved that the Air Handling unit and the documentation correspond to the
order. In addition, changes and supplements were identified and documented. This review is the
basis for further functional reviews, maintenance and modification control.
The IQ protocol defines test procedures, acceptance criteria and the documents that are necessary to
prove that the Air Handling unit was installed correctly and corresponds to the specifications of the
manufacturers as well as client and that it is suitable for the planned application. The completely
executed and finally approved protocol confirms that the Air Handling system is corresponds to all
acceptance criteria.
The Installation-Qualification is valid as documented evidence, that the Air Handling Unit
corresponds with all checkpoints of design plans, all components of manufacturer’s documentation,
rules of technique and the defined requests, The basis for the installation qualification was the
detailed design, room tables and the technical Manufacturers documentation.
The following appendices, in the qualification protocol attached, were used for execution of the
installation qualification to prove the Air Handling Unit corresponds with the defined requests.
The following drawings were compared on site to the existing installation:
Fresh air filter (G-4)
Pre Filter (G-4 +F-5 ) Combo
Fine Filter (F-7)
Bleed Air Filter (H-13)
Supply Blower – Motor
Cooling coil
Heating Coil
Supply/Return Air dampers
Fire Dampers
Duct work
INSTALLATION CHECK
The listed drawings shall be compared on site to the existing installed and any discrepancy shall be
marked by redlining in the drawing. After the completion of the walk down, the checked drawings
have to be signed with date and signature and have to be attached to these protocols.
General Verification:-
Acceptance criteria fulfilled
Title Acceptance criteria
YES / NO
Remarks___________________________________________________________________
Component: Fresh air Pre Filter
Acceptance
Specification =
Feature
Acceptance Criteria criteria fulfilled How verified
YES / NO
Remarks____________________________________________________________________
Component: Pre Filter (Combo)
Acceptance
Feature Specification criteria fulfilled How verified
YES / NO
Filter Class /
10 µ +5 µ
Separation Efficiency
Physical
Model / Type Flange type Filter
Inspection along
with Unit Drawing
610 x 610 x 380
Dimensions (mm)
305 x 610 x 380
Remarks_________________________________________________________________
Component: Fine Filter
Acceptance
Feature Specification criteria fulfilled How verified
YES / NO
Manufacturer Air tech.
Filter Class /
3µ
Separation Efficiency
Physical
Model / Type Flange type Filter
Inspection
along with
Unit Drawing
610 x 610 x 305
Dimensions (mm)
305 x 610 x 305
Remarks__________________________________________________________________
Component: Bleed air Filter
Acceptance
Feature Specification criteria fulfilled How verified
YES / NO
Location AHU
Physical
Filter Class / Inspection
0.3 µ
Efficiency along with Unit
Drawing
Remarks__________________________________________________________________
Component: HEPA Filter
Acceptance
Feature Specification criteria fulfilled How verified
YES / NO
Manufacturer NA
Location NA
Filter Class /
NA
Separation Efficiency
Number of Filters NA
Installation NA
Remarks__________________________________________________________________
Component: Fan – Motor
Acceptance
Feature Specification criteria fulfilled How verified
YES / NO
Make Punker
Type PLUG Type (non spark proof)
Motor
Remarks_________________________________________________________________
Component: Damper
Acceptance
Specification =
Feature criteria fulfilled How verified
AcceptanceCriteria
YES / NO
Remarks__________________________________________________________________
Component: Ductwork
Specification = Acceptance
How
Feature Acceptance criteria fulfilled
verified
criteria YES / NO
Material GI sheets
Remarks__________________________________________________________________
Component: Outlet Terminal Box
Specification = Acceptance
Feature Acceptance criteria fulfilled How verified
criteria YES / NO
Manufacturer MKP
Ducting Layout
Type Swirl Diffuser & Visual
Inspection
Installation Completed
Remarks________________________________________________________________________
DOCUMENTATION REQUIREMENT
The purpose of documentation is to provide basis for further validation (OQ) and generated
documented evidence that the equipment / system was manufactured as per the desired design
criteria.
General : Purchase order
: System specification
DEVIATION REPORT
All discrepancies between specification and Acceptance criteria fulfilled yes / no on site concerning
the installation equipment, piping, supply and supervision facilities which are discovered during the
Acceptance criteria fulfilled yes / no of this protocol have to be documented in this divergence
report.
This page may be copied (as often as you need it in case of more than one discovered divergence).
Deviation No.: ______________________
Deviation
Action taken
CONCLUSION
———————————————————————————————————————————
———–
– 00 New