0% found this document useful (0 votes)
168 views1 page

Unit I Software Process and Project Management: Hindusthan College of Engineering and Technology

The document appears to be an exam for a course on software analysis and design. It contains 31 questions across three parts about software engineering concepts like software processes, life cycle models, project management, estimation, scheduling, and risk management. The questions range from definitions to explanations of specific models and methods.

Uploaded by

Revathimuthusamy
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
168 views1 page

Unit I Software Process and Project Management: Hindusthan College of Engineering and Technology

The document appears to be an exam for a course on software analysis and design. It contains 31 questions across three parts about software engineering concepts like software processes, life cycle models, project management, estimation, scheduling, and risk management. The questions range from definitions to explanations of specific models and methods.

Uploaded by

Revathimuthusamy
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 1

Hindusthan College of Engineering and Technology

Approved by AICTE, New Delhi, Accredited with ‘A’ Grade by NAAC


(An Autonomous Institution, Affiliated to Anna University, Chennai)
Coimbatore – 641 032
AUTONOMOUS III SEMESTER UG DEGREE EXAMINATIONS
COURSE CODE AND NAME: 16CS3203 –SOFTWARE ANALYSIS AND DESIGN

UNIT I SOFTWARE PROCESS AND PROJECT MANAGEMENT


PART A
Marks COs
1. What is software engineering? 2 CO1
2. What is Software? 2 CO1
3. What are the characteristics of the software? 2 CO1
4. What do you mean by software process? 2 CO1
5. What are the fundamental activities of a software process? 2 CO1
6. What are the umbrella activities of a software process? 2 CO1
7. State the various perspective and specialized process models. 2 CO1
8. What are the merits of incremental model? 2 CO1
9. List the task regions in the Spiral model. 2 CO1
10. What are the drawbacks of spiral model? 2 CO1
11. State the drawbacks of waterfall model. 2 CO1
12. What are the steps in component-based development model? 2 CO1
13. What is software project management? 2 CO1
14. What are the activities in Software project planning? 2 CO1
15. What is COCOMO Model? 2 CO1
16. What is meant by Software project estimation? 2 CO1
17. What is Software project scheduling? 2 CO1
What are the two project scheduling methods that can be applied to software
18. 2 CO1
development?
19. What is earned value analysis? 2 CO1
20. What is meant by Software Risk? 2 CO1
21. What is RMM? 2 CO1
PART B
Explain iterative waterfall and spiral model and discuss various activities in each
22. 14 CO1
phase.
23. Explain in detail about various specialized process models. 14 CO1
24. Discuss in detail about the software process. 14 CO1
25. Explain COCOMO Model in detail. 14 CO1
26. Describe in detail about LOC and FP based estimation. 14 CO1
27. Explain in detail about Risk Management and RMM plan. 14 CO1
28. Describe in detail about project scheduling & EVA. 14 CO1
PART C
Compare various life cycle models based on their distinguishing factors, strengths and 10
29. CO1
weakness.
Explain Water fall Model. What are the problems that are sometimes encountered
30. 10 CO1
when the waterfall model is applied?
31. Explain Component Based Development model in detail. 10 CO1