0% found this document useful (0 votes)
2K views1 page

Inspection Report For Installation of JB, Juncation Box

This inspection report checklist is for the fabrication and erection of a cable tray for a modular skid project for Saudi Aramco. The checklist ensures that junction boxes and local control panels are properly installed according to the layout and specifications, are undamaged, aligned correctly with tight fasteners, have earth bonding and terminal blocks, and protected. Inspectors from the company and Saudi Aramco will sign off after verifying all checklist items.

Uploaded by

nayum
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
2K views1 page

Inspection Report For Installation of JB, Juncation Box

This inspection report checklist is for the fabrication and erection of a cable tray for a modular skid project for Saudi Aramco. The checklist ensures that junction boxes and local control panels are properly installed according to the layout and specifications, are undamaged, aligned correctly with tight fasteners, have earth bonding and terminal blocks, and protected. Inspectors from the company and Saudi Aramco will sign off after verifying all checklist items.

Uploaded by

nayum
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 1

Date : --------------------- Checklist No.

:-----------
Project : Modular Skid For Saudi Aramco
Company :Oil and Gas Equipment Industries

Checklist Sheet-INSPECTION REPORT FOR FABRIACATION AND ERECTION OF CABLE


TRAY

Plant No. Inspection Date


Observation No.

Area/Location No. Inspection Time

Descriptions Def. Remarks


Found

Check the JB / LCP installation is as per the layout

Check tag no /specification details of the JB / LCP is as


per the data sheet

Check for any physical damage

Check for the installation as per the required


alignment & tightness of all fasteners

Ensure earth bonding is provided

Ensure proper size of terminal blocks & numbering of


terminals
Ensure proper protection of JB / LCP.

OSC Inspector SA Inspector

Name

Signature