0% found this document useful (0 votes)
86 views1 page

Inspection Report For Installation of Panel

The document is an inspection report for the installation of a marshalling cabinet and control system. It details checks made for the cabinet/panel location and installation, tag numbers and dimensions, scratches or damage, fastener tightening, lock functionality, and wiring connection tightness. Inspectors from both the company and Saudi Aramco signed off on the inspection.

Uploaded by

nayum
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
86 views1 page

Inspection Report For Installation of Panel

The document is an inspection report for the installation of a marshalling cabinet and control system. It details checks made for the cabinet/panel location and installation, tag numbers and dimensions, scratches or damage, fastener tightening, lock functionality, and wiring connection tightness. Inspectors from both the company and Saudi Aramco signed off on the inspection.

Uploaded by

nayum
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 1

Date : --------------------- Checklist No.

:-----------
Project : Modular Skid For Saudi Aramco
Company :Oil and Gas Equipment Industries

INSPECTION REPORT FOR INSTALLATION OF MARSHALLING CABINET AND CONTROL SYSTEM

Plant No. Inspection Date


Observation No.

Area/Location No. Inspection Time

Descriptions Def. Remarks


Found

Check the cabinet / panel located as per the approved layout


drawing

Confirm the cabinet / panel rear and front side installation is


correct as per the layout drawing

Check for tag no. and dimension as per the specification

Check for any scratch or physical damage on the panel

Check for proper tightening of anchor fasteners and Nuts &


Bolts.

Check all keys are available and working of the locks

Ensure tightness of connection of control wiring