Final Account Procedures 1st Edition PGguidance 2015
Final Account Procedures 1st Edition PGguidance 2015
Final Account Procedures 1st Edition PGguidance 2015
rics.org/guidance
rics.org
1st edition
Acknowledgments
RICS would like to thank for the following for their contributions to this
guidance note:
Working group
Contents
Acknowledgments ii
1 Introduction 3
1 Introduction
This guidance note summarises what a final account is
and how they are used to establish a final adjustment
to the contract price. The practical issues of how to
prepare a final account in accordance with the contract
and the process of cooperation between the parties and
negotiation will also be discussed.
The procedures, as set out in the various forms of Remember that it is not the role of the QS to agree
contract, contain slight differences in terminology and variations or final accounts. The QS’s role is to value
procedure (i.e. between the JCT and the NEC contracts), variations in accordance with the contract and adjust the
but essentially they produce the same result. Most final account as necessary.
contracts require the contractor to substantiate their
accounts to the employer so it can be properly assessed. Appendix A shows an example statement of final
account.
The NEC forms of contract do not refer to final accounts
as it is assumed that the final account is adjusted as the
project proceeds on the basis that the compensation
event procedure is followed.
The JCT defines the process for final accounts and final
payments under clause 4.12 of the Design and Build
Contract or Clause 4.5 of the JCT Standard Form. Note
that the timelines are different between the Standard
Building Contract and the Design and Build Contract.
•• agreeing prime cost sums (where applicable) Disputes can occur where key members of either the
employer’s or contractor’s team changes throughout the
•• any loss and expense associated with extensions of project duration.
time
At the commencement of the project, the project
•• adjustment of provisional/approximate quantities manager should produce a project execution plan
(PEP), and within this plan, there should be a procedure
•• fluctuations
set out for contract administration of the project. This
•• any set-off/contra charges (typically a subcontractor should include the change control mechanism and the
issue) or procedure for contract instructions. This helps to provide
a framework for auditability to keep good contract
•• any other items affecting total cost. documentation, which can be referred to during the final
account negotiations.
Note that standard building contracts do not contain
any express provision for dealing with contra charges,
therefore, if agreed between the contractor and employer 3.3 Importance of change
they should be instructed as a variation to the contract.
If the contractor does not agree then any off-sets/contra control
charges must go through the ‘pay less notice’ process
outlined in the Local Democracy, Economic Development Change control is the administrative process that
and Construction Act 2009 (which will be referenced as implements the contract mechanisms for instructing
‘The Construction Act’ in this guidance note). change. The process must adhere to the contract
requirements for notification and approval of change by
From the contractor’s perspective, they will also go the identified parties.
through a similar exercise in preparation for the final
account, but also ensuring that all possible variations Change control is also a critical part of a well-run and
from subcontractors and suppliers are picked up and audited project. Any potential changes should go through
reported to the employer. The contractor will not want to this process before an instruction is given so that the
enter final account negotiations without having accurate employer feels they are able to make informed decisions.
costs from their supply chain, although there may be It also ensures that the contractor is not going ahead
no direct contractual link between the contractor’s and acting on changes that they believe they’ve been
entitlement to be paid by the employer when compared instructed to do, only to find out that they were not
with an obligation to pay their subcontractors. actually communicated to the employer.
3.4 Final account meetings - Provisional sums are often included within a contract for
elements of the works that have not been fully designed.
preparation and procedure Provisional sums can be split into two main categories:
• defined provisional sums and
The final account meetings are generally held between
the contractor and the quantity surveyor, although it • undefined provisional sums
is not unusual for the project manager, the designer, The definition of defined and undefined provisional sums
or a representative from the employer to also attend. can be found in the RICS New rules of measurement 2:
It is an opportunity to exchange information and Detailed measurement for building works (NRM 2).
present methodologies for valuation of each variation in
accordance with the contract. It is not a forum to make Technically the NEC suite of contracts does not recognise
agreements on the valuation of variations beyond the provisional sums, although it is not uncommon for ‘Z’
contract conditions. clauses to be included to allow for their inclusions.
Most of the preparatory work should have been carried Provisional sums should be distinguished from prime
out ahead of time so that the final account meeting can cost.
focus on agreeing the few outstanding items that may
be still in abeyance. If there is a difference of opinion It is good practice that any provisional sums have a
between the contractor and the employer’s quantity design deliverables date agreed so that they can be
surveyor then it is suggested that further work is done to converted into fixed prices at an opportune time during
close the gap using telephone calls and more informal the contract period. If this happens properly, then at final
meetings between the employer and contractor. The final account stage most of the provisional sums should have
account meeting should certainly not be the first time already been converted into fixed prices and instructed
that parties have seen each other’s positions; this would as such.
indicate that the change control process has not been
working properly. There may be a few provisional sums outstanding at the
conclusion of the contract; these can often be items such
as statutory utilities, provisional sums associated with
3.5 Structure of the final external works, provisional sums associated with furniture
fittings and equipment. In these instances, the agreement
account of these provides provisional sums that may be a part of
the final account process. Any unused provisional sums
There are no firm rules about how a final account should should be formally omitted by instruction.
be structured and as long as both parties agree, then a
structure for the final account can take whatever form It is crucial that earlier provisional sums agreed
is sensible for the contract. The structure may also be throughout the contract period and are reported and
dictated by employer requirements, particularly when communicated to the employer in the monthly financial
seeking to apportion costs between different cost centres reports.
or departments.
2. Approximate quantities
The document may follow the original pricing document
– so if, for example, there was a bill of quantities it might If the contract is a remeasurable contract then the final
be adjusted section by section or it might be more account should deal with changes in quantities. This
appropriate to deal with variations in total. This would should be an academic exercise, as the bills of quantities
depend on what the changes are, and how they are would have already prescribed which quantities are to be
instructed. remeasured.
Summarised in this subsection are a list of typical final Remeasures should generally be taken from drawings or
account headings and descriptions: a digital model. Only in exceptional circumstances should
quantities be remeasured from site works.
Approximate quantities should be avoided if possible as consulted for full understanding of variations. In terms of
they provide a greater uncertainty to the employer. the final account, the only contractually entitled change to
the contract sum will be for variations, which have been
3. Prime cost sums formally instructed under the contract.
Prime cost sums may be included for items of work There are different procedures in terms of instructing
when the final specification of the work item has not variations depending on the contract type but the
been decided at contract stage. An example of a prime principles remain the same. If there are any changes,
cost sum might be a carpet (i.e. the cost of the material), which are agreed by both parties but have not been
the contract may allow for the laying of a carpet to the formally instructed then strictly contract instruction
designated areas at a prime cost sum of £25/m2. The should be issued for that particular change to ensure
laying of the carpet cost is usually fixed irrespective of all the necessary paperwork is in place so that that the
the cost of the carpet (although this might also change relevant monies can formally be paid.
if the prime cost is for ‘flooring’ and the choice is made
between, for example, carpet or vinyl). Care is needed to Contract instructions
understand the basis of the prime cost sum.
All agreed changes should have a contract instruction,
When a final specification of the carpet is decided any which formally records that change. It is not unusual at
variants to a prime cost sum will be reflected in the final final account stage to have a number of items, which
account, so for example, if the final selected carpet is are either being claimed by the contractor, which they
£30/m2, but the contract states a prime costs sum of consider being a variation but have not formally been
£25/m2 then the £5/m2 difference over the designated instructed, or for new variations, which has only recently
area will be the adjustment to the contract sum. been agreed but have not been formally instructed.
However, if the final account has not been agreed and defects at his or her own cost. Various contracts have
a difference of opinion remains then the employer is different timescales and mechanisms for dealing with
entitled to release retention only up to the amount he or them but, in essence, the contractor should be notified of
she believes is payable under the contract. When the the defect and then have a set amount of time to rectify
final account is agreed it is not uncommon for another that defect. If they are not dealt with in the allocated
payment certificate to be issued. timeframe, then the employer will become entitled to
make good the works at their own cost and deduct the
Final certificate cost from the retention still held.
The second release of retention occurs at the end of the
Difficulties emerge when there is a dispute about the
defects liability period. In the event that the final account
liability of the defect and whether it is actually a defect.
is still not agreed at this point in time then a similar
principle applies, full retention can be released on the
amount agreed between the two parties but the value of 3.10 Loss and expenses and
disputed items is not released. The final certificate cannot
be issued until the final account is agreed. liquidated damages
For the purposes of the agreement of the final account
3.8 Dealing with defects as part it is important to understand that loss and expense is
of the final account instructed and included within the final account statement
but the employer deducts liquidated damages.
Most standard forms of contract are prescriptive about If during the course of the project any relevant matters
how to deal with defects in the works. The difference affect the contractor then they may be due loss and
between patent and latent defects must also be expense. It is good practice to ensure that the amount
understood: due to the contractor is agreed between the contractor
and PQS as soon as possible following the event.
•• Patent defects can be discovered by reasonable
inspection. The subject of ascertaining loss and expense claims
•• Latent defects cannot be discovered by reasonable is beyond the scope of this guidance note (see the
inspection. RICS guidance note Ascertaining loss and expense, 1st
edition (2015)). In the scenario that the amount has been
It is good practice to alert the contractor to the defect agreed, then this simply gets added to the final account
and allow them the opportunity to make good the defect. calculation. As both parties had previously agreed, this
If this is carried out to the employer’s satisfaction then should create no major surprises.
the final account can be agreed as if the defect had not
occurred, however, if the defect is either not fixed to the Unfortunately, it is common in the industry for any
employer’s satisfaction or not carried out at all by the potential loss and expense to not be agreed at practical
contractor then most standard forms of contract enable completion. This complicates matters as the very factual
the employer to engage another contractor to make good part of the agreeing the final account based on instructed
the defect and deduct that value from the contractor’s variations becomes confused with a sometimes more
final account. This can be a sensitive issue and it will be subjective view when dealing with loss and expense.
common for a difference of opinion to occur.
Good practice would suggest that the best course of
If this difference of opinion cannot be settled amicably, action would be isolate the loss and expense calculation
then some form of dispute resolution maybe necessary. from the remainder of the account, ensuring that it is
For the purposes of the final account it would not be agreed in a fair and reasonable manner and then turn the
possible to agree the final account while a dispute is attention towards the rest of the account. The previously
apparent. agreed loss and expense figure can then be included at
the end.
Where a defect is rectified by an alternative contractor
and is accepted by the contractor then the value of the Note that one of the major advantages of the NEC suite
adjustment to the final account must be agreed between of contracts is that it dictates that all associated loss and
the employer and the contractor and will form part the expenses is agreed as part of the compensation event as
statement of final account. the project proceeds. If the NEC contract is used properly
then, in theory, it should lead to fewer disputes at final
account stage, but this is on the understanding that all
3.9 Defects during the defects/ parties actually engage in the NEC process.
rectification period If the contractor has finished late on the project and
missed the completion date (with a certificate of non-
If the final account is agreed at practical completion and completion issued by the contract administrator), then
then a defect emerges during the defects period, then liquidated damages (delay damages) become due, this
the contractor is entitled to attempt to make good those should not impact the final account procedure as the
damages are deducted from the agreed final account by The type of information that should be presented by the
the employer (by use of a pay less notice). contractor should include the following:
‘… the Pay Less Notice has to state the amount It must be recognised that each form of contract and
that will be paid as well as what will be withheld. The variant form will have different timescales. Furthermore,
benefit of this is that you will now know whether an solicitors’ amendments may change the timescales. It is
underpayment is because of a dispute over valuation, therefore important that the timescales associated with
a claim for contra charges or both.’ the particular contract being used are understood and
adhered to.
© NSCC Ltd
It should be recognised that adherence to the timescales
So in terms of the final account it is the employer’s within a contract is also important to employers and
responsibility to deduct the amount that is being contra contractors as a measure and a key performance
charged from the final account settlement. indicator (KPI). Sign-off of the final account can
sometimes be more important to the employer or
contractor than arguing over any minimal remaining
3.12 Timescales – contractual costs.
and non-contractual
It is a critical issue to understand what information
should be in the adjustment of the final account and the
timescales involved. If the timescales are not adhered to
then there is a risk of this leading to a formal dispute.
4.3 Dealing with items not be part of the negotiation. It is likely that they would only
need to be there for the part of the meeting that concerns
formally instructed them.
One of the common reasons that items aren’t agreed is Both parties in the negotiating process should avoid
because they haven’t been formally instructed. This is being a ‘post box.’ For a smooth negotiation, the work of
also relevant for loss and expense claims (which may discussing with upstream or downstream parties should
not have a formal extension of time issued) as it is for be done beforehand.
variations. Just because a subcontractor or supplier has a claim or
The reason for items not being formally instructed may be variation with the contractor that does not necessarily
because they were in dispute for a period of time, or there mean that the contractor has a claim with the employer.
might be some late changes, (sometimes even occurring The word of the contract cannot be forgotten during
post-practical completion). For a well-run project, this the negotiating process. Each party should listen to the
will be straightforward to deal with by issuing a ‘wrap- others point of view, but it is not always the cast that the
up’ instruction to formalise these few outstanding items. contractors are back to back.
These should be clearly categorised as subsections Remember that although the QS may be negotiating the
within one instruction. final account figure, the final agreement is between the
However, if a contract is more problematic with lots of parties to the contract (i.e. employer and contractor).
variations that have not been formally instructed then it This needs to be recorded as do any other terms of the
is even more important that the contract administrator is settlement (such as the inclusion of LADs etc.).
present at the final account negotiations to ensure that
values being agreed are for real and agreed variations. 4.5 Adjustment of the final
There is little point in spending time agreeing final
account figures and a proposed settlement only for the account
contract administrator or employer to maintain that the
items are not true variations. Each form of contract has different timescales related to
the provision and timing of information. For example, the
If the difference of opinions is so fundamental then a NEC is very prescriptive about timing of information and
separate meeting to discuss the validity of the variations doesn’t define a final account period, with the date of the
should be held before the final account can be discussed. last variation and the timescales governing that being the
This doesn’t need to change the advice included in status of the final account. However, the JCT sets down
financial report as they can still be dealt with as potential very specific timeframes for receipt of information from
variations or early warnings but the final account cannot the contractor (six months) and if it is not provided in a
agree until these have been formally instructed. timely manner then the employer can issue the necessary
information. The PQS then has three months to respond
The JCT contract enables verbal instructions to be issued and issue the final account.
using confirmation of verbal instructions (CVI’s) under
clause 4.3.2 of the JCT contract. If the information is not provided within the defined
timescales then by the contract the obligation falls to
However, it is suggested that all verbal instruction are the employer (by the PQS on their behalf) to ascertain
backed up with a formal written instruction. the final account based on the information provided. The
different forms of contract deal with this differently and
4.4 Agreeing the final account the timescales involved:
4.6 Bespoke and amended There is no such thing as a final account application
under NEC contracts. The final payment has to be
contracts certified within four weeks of the supervisor’s defects
certificate (clause 11.2(6)).
It is not uncommon in the construction industry for
bespoke contracts to be used or heavily amended The time and cost impact of compensation events are
standard forms. These may include amendments of deemed to be included in the agreed compensation
differences to the way that standard forms deal with final event, therefore there is no additional final account time
account procedures. allowance post completion for agreeing for final account,
as it is assumed that all compensation events have been
The most important point to understand is that any agreed as the contract proceeded.
amendments or bespoke contracts cannot and must not
contradict the common law position and especially that
of the Construction Act. It is therefore not permissible
4.8 Patent and latent defects
to introduce ‘pay when paid’ clauses or withholding
unreasonable amounts. In any event, this shouldn’t be Patent defects
done as it is would not be within the spirit of the contract. Any patent defects (which were observed before the final
certificate), are usually rectified by the contractor within
Bespoke contracts and amendments may also be made a reasonable period (dictated by the form of contract). If
to reinforce a partnering approach and may include the contractor does not carry them out then they can be
provisions for shared savings, which may be dependent carried out by another contractor and contra-charged as
upon the final account figure. Therefore a bespoke or part of the final account settlement.
amended contract may include a more detailed process
arrangement of how this might be dealt with. For Latent defects
example, a contractor may be entitled to a bonus should
The agreement of the final account does not affect either
they complete within a certain timeframe or within a
party’s rights under the contract when it comes to latent
certain cost envelope. This will affect the final account
defects.
and should be set out.
If the defect occurs during the defects liability period then
Any specific changes to the final account procedures
the defects liability period then the contractor should be
should be properly communicated to the contractor at
given the opportunity to rectify the defect.
the tender stage so they understand the implications
of the contract, as contractors can be apprehensive of Once the defects liability period has expired then any
bespoke or heavily amended contracts. further defects will be subject to a separate claim for
damages and for breach of contract, or for negligence.
Due to their nature, bespoke contracts are also untested
in court and, therefore, should any disputes arise the These are usually time barred anytime up to six years
legal position would be less clear. from the date of breach, see section 5 of the Limitation
Act 1980.
4.7 NEC procedures (early For a contract under seal, the period is extended to 12
warnings, etc.) years (see section 12 of the Limitation Act 1980).
The NEC contract contains many processes designed to •• Value of variation – while the validity of the variation
avoid or resolve disputes as the works proceed but does may agree the parties cannot come to an agreement
not have a final account or final statement type process. on the value of that variation.
•• Loss and expense – even if the principle of loss and It is also very important to check the maths and carry
expense has been agreed there may still be a dispute out adequate computation checks as soon as the draft
over the value and the heads of claim used. final account is received and before the final version is
presented for conclusion.
•• Extension of time – If an extension of time has
been claimed for there may be a dispute as to the An example of a type of audit checklist:
entitlement of the employer to claim liquidated
damages. •• project control plan
Rather than enter into legal proceedings (which can be •• contract documents examined to determine:
time consuming and costly to both parties) they may
–– the period for final measurement of the works
agree on a settlement. However, the quantity surveyor
is not empowered to negotiate unless instructed the –– responsibility for preparing the final account
employer.
–– if not specified, agreed with the contractor
Whatever is agreed must be a ‘full and final’ settlement
and the payment thereof in full to ensure the deal is •• staff resources to prepare final account agreed with
binding and all parties’ written agreement to the final team manager/partner
certificate before it is issued. The full and final settlement •• register maintained of architect/contract
should contain as few caveats/conditions as possible administrator
as they increase the chance of a further dispute arising
in the future. If there are any outstanding defects or •• instructions
maintenance issues, they should be wrapped up in the
final account. •• final account calculation assembled
•• including, as appropriate:
The final account settlement should not change the
parties’ obligations to each other in terms of the contract –– the summary page
conditions in respect of issues such as latent defects,
warranties and bonds. –– adjustment of prime cost and provisional sums
or contract administrator under a covering letter up by offsetting against the construction budget, so
it is important that this is reviewed throughout the
•• disputes regarding the final account resolved, course of the contract, otherwise when it comes to
disputed points recorded the final account stage there could be a significant
•• where the contractor prepared the final account discrepancy.
sufficient checks carried out to ensure its •• Section 106/278: any section 106 or 278
correctness, all checks recorded on office copy contributions are often subsumed into the contract,
•• necessary deductions made (when permitted by the but they may also be provided by means of a
form of contract) if defective or non-compliant work separate contract. Therefore, this must be reviewed.
identified •• CIL (Community Infrastructure Levy): where
•• any variations issued after practical completion CIL applies the PQS may have to advise on the
evaluated and included under a separate heading implications for the budget and ensure that any
charges are included within the overall project
•• if the employer required final account to be audited, budget.
was the auditor supplied with a copy of all backup
information required. •• VAT: this is a complex issue and the amount of
VAT liable on any project should be calculated and
As well as internal audits some employers will demand an advised by a VAT specialist. However, the PQS may
audit of the final account, sometimes by an independent have to report these figures and ensure they are up-
auditor. to-date.
It is advised that audits are carried out before the final •• Employer internal costs: some employers will have
account is agreed and a statement of final account their own internal costs (such as finance costs, legal
signed. This way if any discrepancies are found they can costs, etc.). These can vary a great deal and are
be addressed with the other party before the account is obviously not a part of the contractor’s final account,
agreed. but they should still be included in the overall
financial report.
Audits are a powerful tool and should be encouraged
both internally and externally. They provide accountability
and a safety net. They should not be seen as a criticism 4.12 Possibility of the agreed
of work carried out but simply as a way to reduce
mistakes, misunderstandings and crucially to learn to
final account being used in
ensure weaknesses or shortcoming are addressed. disputes
When a project doesn’t go according to plan, the
4.11 Items that the QS may be employer can often suffer a financial setback. The
asked to advise on reasons for a project not going as planned can vary
enormously and can include the following:
There are often items, which form part of the overall
•• the contractor is overrunning due to being badly
project budget but are not part of the contractor’s final
resourced
account. However, it is not uncommon for a final account
report to be issued at the same time as the final account. •• employer-owned risks coming to fruition
The PQS may, therefore, need to advise on items or
costs, which sit outside of the contractor’s account. •• significant variations due to design development or
These may include (but are not limited to the following): employer change or
•• Loose furniture, fittings and equipment: it is not •• errors in the design (particularly on traditional
unusual for fixed goods to be included within the contracts).
building contract (i.e. fixed wardrobes or shelves) Where the employer considers that the problems in the
but any loose furniture (i.e. chairs, beds, tables etc.) project were caused by the design team (i.e. errors in the
are not usually part of the contractor’s contract. The initial design requiring significant variations) then they
loose furniture, fittings and equipment budget may may choose to take this up with the member(s) of the
be a separate contract (administered in its own way) design team that they view to be responsible for these
or may be a direct order from the employer. Either issues.
way the PQS needs to understand how this relates to
the overall budget. Initially, this may be informally but can sometimes lead
to legal action. In these instances of dispute, the final
•• Professional fees: while the professional fees budget account documentation can be an important forensic
may not be administered by the PQS, they will often tool if it has been ordered properly. From the final
need to have a good understanding of the budget account information the employer (or dispute resolution
and ensure it is tracked throughout the course of the practitioner) may be able to ascertain the value of works
contract. Any shortfall in this budget is often made
over and above the contract sum, which they consider If you receive liquidated damages, you are not
to be the fault of the design team. However, on the other receiving payment for a supply by you and no VAT is
hand, a badly organised and recorded final account can due on that amount.
weaken the employer’s position (and could implicate the
quantity surveyor in the dispute). If you are due to make a payment for liquidated
damages and due to receive from the other party
While most employers and contractors do not set out for a payment for a supply made by you, you cannot
a dispute at the beginning of a project all final account reduce the value of your supply (and therefore cannot
documentation should be treated as though it could be reduce the amount of VAT chargeable) even if you set
used as evidence in a court of law. the amounts off against each other.’
Issues become a little more difficult where a deal has The guidance is, therefore, clear that VAT is not to be paid
been reached as the member of the design team involved on liquidated damages and the same principle applies to
in the dispute could simply state that their opinion does any contra charge. See the RICS guidance note Interim
not represent a good deal and as there is a degree of valuations and payment, 1st edition (2015).
subjectivity it makes things difficult. It is therefore vital
that the build-up to the deal, demonstrating that it does
represent the employer’s liability to the contractor (and 4.14 Insurance recovery
that they could have paid more if the dispute continued)
must be kept to counter any of these sorts of criticisms. It is important that risks in the contract are owned by the
party best able to manage that risk and they will usually
attempt to take out insurances to cover this risk. In a
4.13 VAT on final payments construction contract, the most common insured risks
and interim valuations when are all-risk insurance for the works on site, insurance
of the works, public liability insurance and professional
damages/contra charges have indemnity insurance.
been applied These insurances will sit outside of the final account
negotiations and should not affect the methodology
In most normal circumstances, VAT is applied at the previously discussed to arrive at the agreed figure. If
standard rate. However, there are some circumstances liquidated damages are to be applied, then the contractor
when VAT is either exempt of zero-rated and even more may have taken out an insurance policy against this.
confusingly there are plenty of circumstances where there While this is not a concern for the employer who will levy
is a partial exemption. damages in accordance with the terms of the contract
it is a concern for the contractor, as their insurers may
The topic of VAT on construction projects is a complex want to see justification for the claim. This, therefore,
issue and outside the scope of this guidance note but, as goes back to the rationale of ensuring that accounts
a general principle, surveyors should be aware that final are properly kept and audited as it is protection for both
account decisions can impact VAT paid on a project and, parties to the contract.
therefore, the overall project budget.
If there are any variations in the contract, which were
As an example, if a building is partially VAT exempt and as a result of an insured risk on the employer’s site (i.e.
VAT is calculated based on the proportions of the building if there was a flood which caused damage), then the
used for a given purpose, then how do variations to the employer’s insurers may not pay unless their specific
building contract affect that calculation? If a variation procedures are followed. In this circumstance, it is
impacts the entire building (i.e. if a new heating system is crucial that the contractor, employer and insurance
instructed for the entire building) then the logical effect is company representative liaise to make sure the insurance
a pro-rata update to the VAT calculation. company’s provisions are being followed. The contractor
will still be paid by the employer (as if it were normal
However, a surveyor needs to be alert to whether a variations) and included in the final account statement but
variation only impacts the proportion of the building the specific cost should be identified so that the employer
that is liable for VAT (e.g. the ground floor retail unit in can then recover this cost from their insurers.
a student accommodation scheme). In this case, the
surveyor should advise their employer to seek expert VAT
advice to review the implications of the change. 4.15 Full development costs
There is also the question of VAT on damages. VAT Notice The agreement of the final account of the main contract is
708: buildings and construction states that: only part of the overall budget for the employer. They will
be interested in the full development costs and how that
‘Liquidated damages are agreed pre-estimated sums
translates into their budget.
to be paid in the event of a breach of contract by one
of the parties. The amount is either a set figure or
determined by a formula.
This will be different depending on the type of project, The insolvency practitioner will be a party to the
but it may be made up of a number of different accounts negotiations, and it will be in their interests to agree the
such as an enabling works contract, furniture, fittings and highest value possible on the works carried out to protect
equipment contract, or landscaping contract. the creditors to the company in administration.
There will also be other cost centres to tie up, such as There is also likely to be a premium to be paid to the
agreement of all fees (including any fee claims submitted contractor stepping in to take over the works, to be
for prolongation, etc.), it is therefore very important that deducted from the contractor. The final account should
before the development cost final account is submitted also clarify the scope of work remaining to complete the
to the employer that those responsible for other cost work to the contractual obligations. The final account
centres have closed out their accounts. must also take into account any pay less notices issued
by the client.
For example, the main contract final account may show
that not all of the contingency was spent. However, If the contract is terminated due to a reason outlined
before this is reported it is important to check that there in the contract then the rules in most forms of contract
is not another cost centre (such as professional fees) are clear and will stipulate the types of loss that can be
which has been overspent (perhaps due to fee claims claimed and, possibly, the limits on recovery.
etc.) which will need to offset some of those savings.
If the contract isn’t prescriptive then the common law
The final VAT calculation will also have an important remedies are wider, and will look to put the innocent party
impact and often this cannot be fully calculated until all into a position they were in prior to the termination and
the other elements have been closed out. It should also this may include loss of profit.
be the VAT specialist that does this calculation as there is
always a risk associated with VAT calculations. If an employer terminates before the end of the contract
then they must realise the implications and that they may
Before any remaining risk allowance is returned to the be forgoing any liquidated damages that are owed.
employer’s budget, all cost centres must be closed down.
If the contract is terminated due to force majeure (i.e.
if it is neither party’s fault) then the same procedures
4.16 ‘Notional’ final accounts apply but there will be more of a willingness from both
caused by the contractor going parties to reach an acceptable agreement due to the
circumstances.
into liquidation or administrative
receivership
In most cases, final accounts represent the end of
a project and occur when the employer is taking
possession of their new building. However, there are
also occasions when final accounts have to be settled
in the middle of a project. This can be due to one of the
following reasons:
Dated: …................................…………………….................................................
Between: …................................……………………............................................
At: …................................…………………….......................................................
£
1 Contract sum 10,000,000
2 LESS risk allowances 0
SUBTOTAL 10,000,000
3 Net omissions/additions (compensation events, early warning notices and adjustment to provisional
50,000
sums up to and including the project manager’s instruction (PMI))
Final account TOTAL (exclusive of VAT) 10,050,000
We hereby agree to accept the sum of £10,050,000 (ten million and fifty thousand pounds) (excluding VAT) in full and
final settlement of the final account for the above contract.
This sum is in full and final settlement of the amount claimable under the final account including all sums claimable by
the main contractor ConBuild or by any subcontractor engaged by a contractor or any suppliers to ConBuild or their
subcontractors.
This settlement does not in any way affect the contractual obligations of either party in relation to other matters that
might arise under the terms of the contract including but not limited to defects, warranties and retention.
Signed: …................................……………………...............................................
Position: …................................…………………….............................................
Dated: …................................…………………….................................................