0% found this document useful (0 votes)
268 views1 page

Long Intl Cause-Effect Matrix For Delay-Disruption Claim

This document outlines a typical cause-effect matrix for construction delay and disruption claims. It lists primary causes such as late design drawings, design errors and changes, and owner/engineering problems. The intermediate effects are things like loss of productivity, resequencing work, increased crew sizes, and overtime. The resulting impacts are acceleration, time extensions not approved by the owner, and monetary damages from increased costs.

Uploaded by

Abdelmuneim
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
268 views1 page

Long Intl Cause-Effect Matrix For Delay-Disruption Claim

This document outlines a typical cause-effect matrix for construction delay and disruption claims. It lists primary causes such as late design drawings, design errors and changes, and owner/engineering problems. The intermediate effects are things like loss of productivity, resequencing work, increased crew sizes, and overtime. The resulting impacts are acceleration, time extensions not approved by the owner, and monetary damages from increased costs.

Uploaded by

Abdelmuneim
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

Typical Cause-Effect Matrix for a Delay / Disruption Construction Claim

Intermediate Effects
and Secondary Causes RES
UL

TE
DI
Owner Approves Time Extension for Excusable and Compensable Delays

N
No Time Extension Approved by Owner

Acceleration
Delay & Disruption
RES
UL

TE
D IN
IN
Primary Causes

D
TE
UL
RES
Typical Owner/Engineering Problems Productivity
Late IFC Drawings Loss
Design Basis/Drawing Errors & Omissions
Resequencing & Out-of-Sequence Work
Defective Specifications
Increased Number/Size of Crews
Understated/Overstated Quantities
Trade Stacking
Design Changes
Overtime Work
Requests for Scope Changes
Requests for Information

RES Shift Work


U L

Night Work Labor Rate Increase for Premium Time


Labor Rate Increase for Shift Differential
Increased Coordination
Dilution of Supervision/Coordination Problems
Increased Supervision
Congestion
TE
D

RES
IN

U L

TE
DIN
RES

Productivity
IN
UL

TE
Loss
TE

D
IN UL
RES

Late Responses to RFIs RES


UL

TE
Late Responses to Change Order Requests

D
IN
Scope Changes

RES
Secondary Causes
IN

UL
TE
D

D
TE

IN
Typical Owner-Caused RE S
UL
RES
UL
Administrative Problems

TE
D
Late Precedence Work by Others Direct Man-Hour Growth

IN
Work Access Constraints Indirect Man-Hour Growth
Delayed Review and Approval of Contractor’s Submittals Increased Equipment & Materials Quantities

Increased Field Indirect Costs


Increased Home Office Overhead Costs
Increased Direct Labor Costs
Increased Equipment & Material Costs
IN

N
DI
D

TE
TE

Typical Owner-Caused UL
LU

RES
RES

Procurement Problems
Improperly Tagged Equipment & Materials
Late Owner-Furnished Equipment & Materials
Ultimate
Effects
Misfabricated Owner-Furnished Equipment & Materials
IN
D
TE

Typical Problems Beyond RES


UL Allocation of
the Control of All Parties Responsibility
Weather Impacts for Total Cost
Labor Strikes Overrun
Other Force Majeure Issues
Owner $22,600,000
EPC Contractor $14,400,000
IN
D
TE

Typical Contractor-Caused UL Total Cost Overrun $37,000,000


RES
Problems
IN

Rework
D
TE

Lack of Qualified Construction Labor RES


UL

Lack of Supervision
Defective Construction
Vendor/Supplier Delivery Delays
Poor Planning and Scheduling Practices

000-13 C/E Matrix 1/10/08

You might also like