23 05 29 - HVAC Hangers and Supports
23 05 29 - HVAC Hangers and Supports
23 05 29 - HVAC Hangers and Supports
1. GENERAL
A. Pipe, ductwork, and equipment hangers, supports, anchors, saddles and shields.
B. Mechanical flashing.
C. Equipment curbs.
G. Pipe Stands
A. Quality assurance.
B. References.
C. Submittals.
2. PRODUCTS
A. Hydronic Piping:
1. Conform to International Mechanical Code, ASME B31.9, ASTM F708, MSS SP58, MSS
SP69 and MSS SP89 as applicable.
1. Conform to International Mechanical Code, ASME B31.1, ASTM F708, MSS SP58, MSS
SP69, MSS SP89, as applicable.
C. Refrigerant Piping
1. Conform to International Mechanical Code, ASME B31.1, ASTM F708, MSS SP58, MSS
SP69, MSS SP89, as applicable.
1. Hangers for Hot and Cold Pipe Sizes 1/2 to 1-1/2 Inch, Carbon steel, adjustable swivel, band
type.
2. Hangers for Cold Pipe Sizes 2 Inches and Over: Carbon steel, adjustable, clevis.
3. Hangers for Hot Pipe Sizes 2 to 4 Inches; Carbon steel, adjustable, clevis.
4. Hangers for Hot Pipe Sizes 6 Inches and Over: Adjustable steel yoke, cast iron roll, double
hanger.
5. Multiple or Trapeze Hangers: Steel channels with welded spacers and hanger rods.
6. Multiple or Trapeze Hangers for Hot Pipe Sizes 6 Inches and Over: Steel channels with
welded spacers and hanger rods, cast iron roll.
7. Wall Support for Hot Pipe Sizes 6 Inches (150 mm) and Over: Welded steel bracket and
wrought steel clamp with adjustable steel yoke and cast iron roll.
8. Wall Support for Pipe Sizes to 3 Inches: Cast iron hook.
9. Wall Support for Pipe Sizes 4 Inches and Over: Welded steel bracket and wrought steel
clamp.
10. Vertical Support: Steel riser clamp.
11. Floor Support for Cold Pipe: Cast iron adjustable pipe saddle, lock nut, nipple, floor flange,
and concrete pier or steel support.
12. Floor Support for Hot Pipe Sizes to 4 Inches: Cast iron adjustable pipe saddle, lock nut,
nipple, floor flange, and concrete pier or steel support.
13. Floor Support for Hot Pipe Sizes 6 Inches and Over: Adjustable cast iron roll and stand, steel
screws, and concrete pier or steel support.
14. Copper Pipe Support: Carbon steel ring, adjustable, copper plated.
15. Roof Support for Hot and Cold Pipe: See PIPE STANDS section below.
16. Hangers for insulated pipe shall be enlarged to compensate for insulation thickness so that
hangers support insulation. See Section 23 07 19.
A. Strap and Rod Sizes: Comply with SMACNA's "HVAC Duct Construction Standards - Metal and
Flexible," Table 5-1, "Rectangular Duct Hangers Minimum Size," and Table 5-2, "Minimum Hanger
Sizes for Round Duct."
B. Steel Cables for Galvanized-Steel Ducts: Galvanized steel complying with ASTM A 603.
C. Steel Cables for Stainless-Steel Ducts: Stainless steel complying with ASTM A 492.
D. Steel Cable End Connections: Cadmium-plated steel assemblies with brackets, swivel, and bolts
designed for duct hanger service; with an automatic-locking and clamping device.
E. Duct Attachments: Sheet metal screws, blind rivets, or self-tapping metal screws; compatible with
duct materials.
2.3 ACCESSORIES
A. Hanger Rods: ASTM A36 steel or galvanized threaded both ends, threaded one end, or continuous
threaded.
1. Ductwork: Use double nuts and lock washers on threaded rod supports.
2.4 INSERTS
A. Inserts: Malleable iron case of galvanized steel shell and expander plug for threaded connection
with lateral adjustment, top slot for reinforcing rods, lugs for attaching to forms; size inserts to suit
threaded hanger rods.
2.5 FLASHING
2.7 SLEEVES
A. Sleeves for Pipes through Fire Rated Floors and Walls: Schedule 40 steel pipe.
B. Sleeves for Pipes Through Non-fire Rated Floors and Walls: 18 gage galvanized steel.
D. Sealants:
A. Mechanical Seals: Modular mechanical type, consisting of interlocking EPDM synthetic rubber links
shaped to continuously fill annular space between pipe and sleeve, connected with type 316
stainless steel bolts and reinforced plastic polymer pressure plates which cause rubber sealing
elements to expand when tightened, providing a watertight and gas-tight seal and electrical
insulation.
1. Provide high-temperature silicone links rated for 400 Deg. F for steam and condensate
applications.
a. Thermoplastic sleeves: Sleeve shall have smooth walls and shall be made of molded
non-metallic high density polyethylene (HDPE) with an integral solid water stop,
Advance Products & Systems Model PWS or equivalent.
b. Steel sleeves: Sleeve shall have smooth walls, shall be made of Schedule 40 steel
with an integral welded solid water stop, and shall have corrosion-resistant coating,
Advance Products & Systems Model GWS or equivalent.
A. General Requirements for Pipe Stands: Shop or field –fabricated assemblies made of manufactured
corrosion-resistant components to support roof-mounted piping.
1. Description: Assembly of base, vertical and horizontal members, and pipe support, for roof
installation without membrane penetration.
2. Base: Plastic
3. Vertical Members: Two or more cadmium-plated-steel or stainless-steel, continuous-thread
rods.
4. Horizontal Member: Cadmium-plated-steel or stainless-steel with plastic or stainless-steel,
roller-type pipe support.
1. Description: Assembly of Bases, vertical and horizontal members, and pipe supports, for roof
installation without membrane penetration.
2. Bases: One or more; plastic
3. Vertical Members: Two or more protective-coated-steel channels.
4. Horizontal member: Protective-coated-steel channel.
5. Pipe Supports: galvanized-steel, clevis-type pipe hangers.
E. Curb-Mounted-Type Pipe Stands: Shop- or field-fabricated pipe supports made from structural-steel
shapes, continuous-thread rods, and rollers, for mounting on permanent stationary roof curb.
3. EXECUTION
3.1 INSTALLATION
3.2 INSERTS
B. Provide inserts for suspending hangers from reinforced concrete slabs and sides of reinforced
concrete beams.
C. Provide hooked rod to concrete reinforcement section for inserts carrying pipe over 4 inches.
D. Where concrete slabs form finished ceiling, locate inserts flush with slab surface.
B. Support fire protection systems piping independently from other piping systems. Fire main piping
may be trapezed with other piping systems. Coordinate trapeze hangers with the Sprinkler
Contractor.
C. Install hangers to provide minimum 1/2 inch space between finished covering and adjacent work.
F. Support horizontal cast iron pipe adjacent to each hub, with 5 feet maximum spacing between
hangers.
G. Support vertical piping at every floor and at intervals of no more than 12 ft. Support vertical cast
iron pipe at each floor at hub.
H. Where several pipes can be installed in parallel and at same elevation, provide multiple or trapeze
hangers.
J. Provide copper plated hangers and supports for non-insulated copper pipe.
L. Prime coat steel hangers and supports in the mechanical room and other exposed areas. Refer to
the Architectural reflected ceiling plans for location of exposed ceilings. Hangers and supports
located in attic space, crawl spaces, pipe shafts, and suspended ceiling spaces are not considered
exposed.
M. Adjust hangers to distribute loads equally on attachments and to achieve specified pipe slopes.
1. Install protection saddles MSS Type 39 where insulation without vapor barrier is indicated.
Fill interior voids with segments of insulation that match adjoining pipe insulation.
2. Install protective shields MSS Type 40 on cold piping that has vapor barrier. Shields shall
span an arc of 180 degrees (360 degrees on trapeze hangers with U-bolt clamps) and shall
have dimensions in inches not less than the following:
A. Comply with SMACNA's "HVAC Duct Construction Standards - Metal and Flexible," Chapter 5,
"Hangers and Supports."
C. Hanger Spacing: Comply with SMACNA's "HVAC Duct Construction Standards - Metal and
Flexible," Table 5-1 (Table 5-1M), "Rectangular Duct Hangers Minimum Size," and Table 5-2,
"Minimum Hanger Sizes for Round Duct," for maximum hanger spacing; install hangers and
supports within 24 inches of each elbow and within 48 inches of each branch intersection.
E. Support vertical ducts with steel angles or channel secured to the sides of the duct with welds, bolts,
sheet metal screws, or blind rivets; support at each floor and at a maximum intervals of 16 feet.
A. Install anchors at proper locations to prevent stresses from exceeding those permitted by ASME
B31.9 and to prevent transfer of loading and stresses to connected equipment.
B. Fabricate and install anchors by welding steel shapes, plates, and bars to piping and to structure.
Comply with ASME B31.9 and with AWS Standards D1.1.
C. Where expansion compensators are indicated, install anchors in accordance with expansion unit
manufacturer's written instructions to control movement to compensators.
D. Anchor Spacings: Where not otherwise indicated, install anchors at ends of principal pipe runs, at
intermediate points in pipe runs between expansion loops and bends. Make provisions for preset
of anchors as required to accommodate both expansion and contraction of piping.
3.6 FLASHING
A. Provide flexible flashing and metal counterflashing where piping and ductwork penetrate weather or
waterproofed walls and floors.
B. Seal floor, shower, mop sink, etc. drains watertight to adjacent materials.
C. Adjust storm collars tight to pipe with bolts; caulk around top edge. Use storm collars above roof
jacks. Screw vertical flange section to face of curb.
3.7 SLEEVES
A. Provide pipe and duct sleeves at all fire/smoke rated partitions, exterior wall penetrations and wall
penetrations into exposed areas. Pipe and duct sleeves are not required for penetrations through
non-rated concealed partitions.
D. Size sleeves large enough to allow for movement due to expansion and contraction. Size so as to
allow for continuous insulation wrapping through sleeve.
E. Sleeves through floors shall extend a minimum 2” above the finish floor level. Sleeves through
walls should be flush with wall surface.
F. Where piping or ductwork penetrate non-rated ceilings or walls, close off space between pipe or
duct and adjacent work with urethane rod stock and caulk air tight.
1. Where piping is not located in a rated shaft and it penetrates a single non-rated floor, close off
space between pipe and adjacent work with urethane rod stock and caulk air tight.
2. Where piping is not located in a rated shaft and it penetrates multiple non-rated floors, close
off space between pipe and adjacent work with appropriate fire-rated sealant, insulation,
putty, or compound.
3. Where ductwork is not located in a rated shaft and it penetrates a single non-rated floor, close
off space between duct and adjacent work with appropriate fire-rated sealant, insulation,
putty, or compound.
H. Where piping or ductwork penetrate rated floor, ceiling, or wall, close off space between pipe or duct
with appropriate fire rated sealant, insulation, putty or compound. Refer to the Drawings for
fire/smoke rated wall locations and the appropriate ratings.
I. Provide on ductwork close fitting metal collar or escutcheon covers on the side of penetration that
are exposed to view.
K. Provide mechanical seals and sleeves through exterior wall and floor penetrations and 3 hour or
higher fire rated partitions.
L. All ductwork through exterior walls to be installed with flashing and counter flashing.
A. Reference International Plumbing Code and International Mechanical Code where applicable.
END OF SECTION 23 05 29