BSR Analyses
BSR Analyses
BSR Analyses
1. Excavation 9-13
3. Earthwork 14-16
5. Concrete 20-46
7. Steel reinforcement 53
8. Brickwork 54-61
1
25. Gutters & Down pipes 127-130
The Material and Labour component required for the various items of work
including the minimal plant required for same is detailed in the analysis of the
Basic Rates which have been included in the following pages.
Basic Rate
The basic rate is analyzed under the following headings:
(a) Materials
The quantities of material required for the items are computed from
known data and experience. Their total value is calculated on the basis
of current costs of purchase at sources of supply. Unless, otherwise
stated wastage is allowed in the norms.
(b) Transport
This component provides for the cost of transport of material from
sources of supply to the sites of work. This component is usually added
to the material cost.
(c) Labour
The labour wages are as approve d by the Government from time to
time and on the basis of an 8 hour working day.
(d) Plant
This component provides for the minimum plant required for the items of
work. The cost of tools and implements is provided for tin the overheads
allowances.
2
The Basic Cost is the sum of the costs of items (a), (b), (c) & (d) above.
The common items that make up the overhead costs are listed below. The
cost of the overhead items involved on a job is assessed as a percentage of
the Basic cost of the job. In the case of the construction Agencies executing
building construction works the overheads component may be listed as below:
3. Temporary works:
(a) Access Road and Maintenance 0.2
(b) Site buildings for accommodation of part labour 0.7
(c) Central sores building 0.6
(d) Fencing and protection 0.3
(e) Provision of water, lights etc. 0.3
(f) Clearing and tidying up 0.2
(g) Collection of building materials including cement
and steel 0.40
4. Watchers for field stores and security of sites. 0.8
3
5. Tools and implements for miscellaneous work 0.9
6. (a). Setting out and measurements 0.5
(b). Providing samples for testing 0.2
7. Transportation of supervisory staff 1.0
8. Job office, furniture, stationary, supplies, water, lights etc. 0.9
9. Wages of job office staff 1.2
10. Transportation of job office staff 0.4
11. (a). Bonds for Bid performance and fidelity Guarantee 0.3
(b). Insurance of work and workmen’s compensation 0.5
12. (a). Interest in Capital Investment 1.6
(b). Business Turnover Tax 3.0
19.0
General Overheads
13. Head office and rent, lights, telephone, stationary
supplies, furniture etc. for same 0.6
14. Salaries of Head Office Manager, Engineers,
Technical Assistants, Draughtsman, Clerks, Stenos, Typists,
Minor staff and Drivers 1.2
15. Transportation and subsistence of Head office staff 1.0
16. Insurance, Interest and Taxes on business 0.4
17. Legal expenses and Consultancy fees 0.2
18. Workshop & Yard rents, sheds, garages & supplies 2.20
19. Salaries of workshop & yard storekeepers, Drivers, Foremen
Mechanics & workmen 0.4
6.0
Profits
Ten percent (10%) of the Basic costs is allowed as profit to the Contractor.
4
on the Basic Rate. ie the Basic Rate is multiplied by the factor 1.35 to obtain
the working rate.
This Basic Rate Analysis does not include for the use of heavy plant and
equipment. This analysis provides for a labour intensive method of work with
a minimal use of machinery. The machinery allowed in this analysis is the
concrete mixer, the vibrator and a hoist in the case of a multi-storeyed
building for the lift of materials to the various floors.
This analysis is applicable for a building having a maximum of four storeys –ie
ground and three floors.
If a building has more than four floors or when the Contract period is
compressed to a few months, then it will be necessary to allow for the use of
heavy machinery such as tower cranes, mobile cranes, dumpers loaders,
batching plant for the mixing of concrete, bins for the storage of concrete
material etc. and also for the employment of contract managers and additional
staff.
The cost of such items of work will not be accommodated within the 35%
“Mark-up” and will have to be provided for in separate items such as
preliminaries to the contract.
5
Allowances to be made in the .................. got lift in respect of work on upper
floors -
In the analysis of the various items of work in the following pages the rates
refer to work on the ground floor.
To these rates the percentages (of the surround floor rates) indicated in the
table below should be added to obtain the rates applicable to the 1 st, 2nd and
3rd floors. This S.S.R. is limited to work on the ground and 3 upper floors only.
NOTE:
EARTH WORK AND LANDSCAPING
6
2. The analysis has been prepared for each of the above categories as
shown in items Nos 3-9.
4. This classification has been adopted (where tenders are called) to avoid
any dispute that may arise as to the exact nature of the soil that will be
met with when the actual excavation is carried out. The tenderer is
expected to examine the site and to form his own opinion of the nature
of the soil that is met with and rate his tender accordingly.
5. The classification of the soils in Note 1 above and the analysis provided
for the different type of soil will help the estimator in arriving at the
actual cost of excavation, for which he will have to allow in his estimate.
6. Under Note 1 (6) b Hard Rock, and analysis is provided for removing
Hard Rock met with in foundation excavations where blasting is
prohibited or cannot be done, like in built up areas where blasting can
cause damage to adjoining buildings.
7
Item Description Rate Amount
1. Removing top soil to a depth not exceeding 6”
& deposition as directed within site.
Per Square
Consider an area of 10.oo sqrs. ie 5.00 cubs of
excavation. 10 days U/SK labourer
Rate per 10.00 square.
Per cube
Per cube-
8
Item Description Rate Amount
Per cube
Per cube
3 ½ days U/Sk labourer
Per cube
9
Item Description Rate Amount
Per cube
Materials
Labour
1 day Sk labourer
10
Item Description Rate Amount
9. Benching rock in foundation in 3’’-6’’ steps.
(Blasting prohibited)
Per 10-souare feet
1 ½ day Sk labourer
per 10 sq.ft.
Materials
20 gals water
Labour
11
Item Description Rate Amount
Per cube
1 day U/Sk labourer
Per cube
1 ¼ U/Sk labourer
Per cube
12
Item Description Rate Amount
14. Filling under floors including leveling, watering
& compacting in 3” layers with imported
selected earth.
Per cube
1.0 cube earth delivered at site.
allow for 15% compaction
2 days U/Sk labourer
13
Item Description Rate Amount
Materials
Labourer
1 days carpenter
14
Item Description Rate Amount
17. Earthwork support (close plunking) in trenches
up to 5’ 0’’ depth.
Materials
Labour
2 days carpenter
15
Item Description Rate Amount
3’ 6’’ at bottom
Materials
Labour
8 days carpenter
16
CONCRETE
Preamble
Assumptions:
1. Mixing concrete using a concrete mixer 14/10 cu.ft. Capacity and manual
loading are the basis on which the norms are worked.
2. A gang of one skilled and six unskilled labourers produce 3.00 cubes of
concrete per day using a 14/10 cu.ft capacity concrete mixer. This is as per
accepted practice.
17
Item Description Rate Amount
Materials
Labour
NOTE :
water.
18
Item Description Rate Amount
Per cube
Materials
Labour
Note:
water.
19
Item Description Rate Amount
21.
Mixing concrete 1:2:4 (3/4”)
Per cube
Materials
water-(120 gals)
labour
NOTE:
of water.
20
Item Description Rate Amount
Per cube
Materials
Labour
NOTE:
21
Item Description Rate Amount
Per cube
Materials
Labour
NOTE:
22
Item Description Rate Amount
Per square
Materials
Labour
NOTE:
23
Item Description Rate Amount
Per square
Materials
¼ cube concrete
Labour
NOTE:
24
Item Description Rate Amount
Per square
Materials
Labour:
½ day Sk labourer
NOTE:
25
Item Description Rate Amount
27. Cement concrete in 4 ½” * 6” columns in
ground floor.
Consider 24 No. columns each 4½“* 6”*10’0”
ie 0.45 cubes.
Materials
Labour
1 day mason
1 day carpenter
Curing
water -170gals
26
of column.
NOTE:
Materials
0.45 cubes concrete
Add 10% for wastage
1 day hire of vibrator
Labour
1 day mason
1 day carpenter
1 day Sk labourer (vibrator)
3 days U/Sk labourer
Curing
28
Item Description Rate Amount
Labour
1 day mason
1 day carpenter
1 day SK labourer (vibrator)
3 days U/Sk labourer
Curing
Jute Hessian -60 sq.ft
water -100 gals
½ day U/Sk labourer
Total per 0.45 cubes
or 80 l.ft of column.
Materials
40sq.ft-Jute Hessian
Labour
1 day mason
1 day carpenter
50l.ft of column
31
Item Description Rate Amount
31. Cement concrete in 13 ½” * 13 ½ “columns in
ground floor.
Consider 4 No. Columns 13 ½” * 13 ½“each
10’0” high i.e. 0.51 cubes.
Materials
Curing
Water-100 gals
Or 40 1.ft of column
Note:
32
Item Description Rate Amount
32. Cement concrete in 6”*6” beam upto 1st floor
level.
Consider 180 L.ft of beam 6”*6” i.e.0.45 cubes.
Labour
1 day mason
1 day carpenter
1 day SK labourer (vibrator)
4 days U/Sk labourer
Curing
Jute Hessian 90 sq.ft.
water 180 gals
1½ days U/Sk labourer
Total per 0.45 cube
or 180 1.ft of column.
33
Item Description Rate Amount
st
33. Cement concrete in 9”*6” beam upto 1 floor
level.
Consider 120 L.ft 9”*6” beam i.e.0.45 cubes.
Materials
Labour
1 day mason
1 day carpenter
1 day SK labourer (vibrator)
4 days U/Sk labourer
Curing
Jute Hessian 75 sq.ft.
water 150 gals
1½ days U/Sk labourer
Total per 0.45 cube
or 120 1.ft of beam.
34
Item Description Rate Amount
st
34. Cement concrete in 9”x9” beam upto 1 floor
level.
Consider 80’0” length of 9”x9” beam i.e.0.45
cubes.
Materials
Labour
1 day mason
1 day carpenter
1 day SK labourer (vibrator)
4 days U/Sk labourer
Curing
Jute Hessian 60 sq.ft.
water 120 gals
1½ days U/Sk labourer
Total per 0.45 cube
Or 80 1.ft of beam.
35
Item Description Rate Amount
st
35. 5” thick R.CC floor slab in 1 floor.
Consider 5” thick slab 10’ 0” x 12’ 0”
Materials
Labour
1 day mason
1 day carpenter
1 day SK labourer (vibrator)
4 days U/Sk labourer
Curing
Jute Hessian 30 sq.ft.
water 150 gals
1½ days U/Sk labourer
36
Item Description Rate Amount
st
36. 6” thick R.CC floor slab in 1 floor.
Consider 10’ 0” X 10’ 0” panel= 50 cu.ft
Materials
Labour
1 day mason
1 day carpenter
1 day SK labourer (vibrator)
4 days U/Sk labourer
Curing
Jute Hessian 25 sq.ft.
water 90 gals
1½ days U/Sk labourer
37
Item Description Rate Amount
37. Cement concrete in 4 ½“ X 6” lintels in ground
floor.
Consider 240 L.ft i.e. 45 cu.ft.
Materials
Labour
1 day mason
1 day carpenter
1 day SK labourer (vibrator)
4 days U/Sk labourer
Curing
Jute Hessian 10 sq.ft.
water 90 gals
1½ days U/Sk labourer
per 0.45 cube
or 240 L.ft of lintel.
38
Item Description Rate Amount
38. Cement concrete in 9”*9” lintels in ground floor.
Consider 80 L.ft of lintel i.e. 45 cu.ft concrete.
Materials
Labour
1 day mason
1 day carpenter
1 day SK labourer (vibrator)
4 days U/Sk labourer
Curing
Jute Hessian 60 sq.ft.
water 90 gals
1½ days U/Sk labourer
39
Item Description Rate Amount
40. Cement concrete in 12”*15” lintels in ground
floor.
Consider length of 36’ 0” i.e. 45 cu.ft
Materials
Labour
1 day mason
1 day carpenter
1 day SK labourer (vibrator)
4 days U/Sk labourer
Curing
Jute Hessian 40 sq.ft.
Water 90 gals
1½ days U/Sk labourer
40
Item Description Rate Amount
41. Sawn timber formwork to 9” x 9” cement
concrete column in ground floor.
Per square ft.
(1) Materials
1½ lb wire nails.
(2) Fabricating
½ day carpenter
Materials
Labour
¼ day carpenter
(per use)
¼ day carpenter0
42
Item Description Rate Amount
42. Sawn timber formwork for concrete beams in
ground floor
mould.
Labour
00000000
Assuming 4 uses
(B). Assembling
Materials
(10 uses)
props.
props.
(e). 22 Nos
Labour
square. 00000000
(B). Assembling
Materials
(a). 690 l.ft 4”x2” vertical timber props.
(10uses)
(b). 66 l.ft 2”x2” bracing for props.
(c). 122 No. wedges.
45
(d). 33 sq.ft 1” base plates for props.
46
Item Description Rate Amount
44. Mild steel/for steel reinforcement to lintels slab
beams for columns bent to shape laid in position
and tied G.I. wire as directed.
Materials
Labour
1 Day blacksmith
47
Item Description Rate Amount
45.
Brick work in cement sand 1:5 in foundation up
to D.P.C
Per Cube
Materials
1450 bricks
Add 5% wastage
Labour
3 days mason
48
Item Description Rate Amount
46.
Brick work cement & sand 1:8 in foundation up
to D.P.C
Per cube
Materials
1450 bricks
Add 5% wastage
Labour
3 days mason
49
Item Description Rate Amount
47.
Brickwork in cement and sand 1:5 in 4” thick
walls in ground floor
Per square
Materials
550 bricks
Add 5% for wastage
1.30 cwt cement (50 Kg bags)
0.10 cubes sand
water (50 gals)
Labour
1 ½ days mason
2 days U/Sk labourer
Scaffolding –Add 5% 0000000
Total 0000000
50
Item Description Rate Amount
48.
9” thick brick wall cement sand 1:5 in ground
floor.
Per square
Materials
1090 bricks
Add 5% for wastage
3.00 cwt cement (50 Kg bags)
0.20 cubes sand
Water (115 gals)
Labour
2 1/4 days mason
3 3/4 days U/Sk labourer
Scaffolding –Add 3% 0000000
Total 0000000
51
Item Description Rate Amount
49.
Brickwork 13 ½ thick in cement sand 1:5 in
superstructure in ground floor.
Per square
Materials
1630 bricks
Add 5% for wastage
4.50 cwt cement (50 Kg bags)
0.30 cubes sand
Water (170 gals)
Labour
3 ½ days mason
5 ½ days U/Sk labourer
Scaffolding –Add 2% 0000000
Total 0000000
52
Item Description Rate Amount
50.
9” brick walls in cement sand 1:8 in
superstructure in ground floor.
Materials
1090 bricks
Add 5% for wastage
1.75 cwt cement (50 Kg bags)
0.30 cubes sand
Water (115 gals)
Labour
2 1/4 days mason
3 days U/Sk labourer
Scaffolding –Add 3% 0000000
Total 0000000
53
Item Description Rate Amount
51.
4 ½ thick brick wall (wire cut) in cement and
sand 1:5 in ground floor.
Per square
Materials
550 wire cut bricks
Add 2% for wastage
1.20 cwt cement (50 Kg bags)
0.80 cube sand
Water – 30 gals
Labour
1½ days mason
2 days U/Sk labourer
Scaffolding –Add 5% 0000000
Total 0000000
54
Item Description Rate Amount
52.
9” thick in cement and sand 1:5 with wire cut
bricks.
Per square
Labour
2 ¼ days mason
Total 0000000
55
Item Description Rate Amount
53. 13 ½” thick brick wall (wire cut) in cement and
sand 1:5 in ground floor.
(Facing to brick work measured separately)
Per square
Materials
1630 wire cut bricks
Add 2% for wastage
4.50 cwt cement (150 Kg bags)
0.30 cubes sand
Water 150 gals
Labour
3 ¾ days mason
5 ½ days U/Sk labourer
Scaffolding –Add 2% 0000000
Total 0000000
Rate per square
54. Extra over for facing including raised pointing
1/8” thick in cement and sand 1:1 mixture in
ground floor.
Per square
Materials
Water 10 gals
Labour
5 days mason
56
Item Description Rate Amount
55. 3” thick floor paved in lime mortar 2:5 in ground
floor.
Per square
Materials
350 bricks
Labour
1 ¼ days mason
Per 10 l.ft
Materials
120 bricks
Labour
½ day mason
57
Item Description Rate Amount
57. Brick drains in cement and sand 1:5, 9” wide and
6”-9” average depth including cement rendering
½“ thick 1:2 to exposed faces with 1’6” ramp
including necessary excavation.
Per 10 l.ft
Materials
140 bricks
Labour
1 ¼ day mason
58
Item Description Rate Amount
58. Brick drains in cement and sand 1:5, 9” wide and
6”-9” average depth including cement rendering
½“ thick 1:2 to exposed faces without ramp
including necessary excavation.
Per 10 l.ft
Materials
110 bricks
Labour
1 day mason
59
Item Description Rate Amount
59. 8” thick Hollow block work in cement and sand
mortar 1:5 in ground floor (cavities unfilled)
Per square
Materials
Labour
1½ days mason
Total 000000000
60
Item Description Rate Amount
60. 4” thick Hollow block masonry in cement and
sand mortar 1:5 with cavities unfilled.
Per square
Materials
Labour
1 day mason
Total 000000000
61
Item Description Rate Amount
61. Random Rubble masonry in cement mortar 1:5 in
foundation.
Per cube (14” thick)
Materials
Labour
4 days mason
Materials
Labour
4 ½ days mason
Total 0 00
Per square
Materials
¼ lb wax polish
¼ lb coloured pigment
Labour
4 days mason
63
Item Description Rate Amount
Per square
Materials
1 lb white cement
Labour
4 days mason
64
Item Description Rate Amount
Per square
Materials
½ lb wax polish
2 lb cotton waste
Labour
4 days mason
65
Item Description Rate Amount
Materials
Add 5% wastage
Labour
7 days carpenter
Materials
750 titles
Labour
3 days carpenter
Materials
Labour
2 ½ days carpenter
67
Item Description Rate Amount
69. Roof covering with corrugated asbestos sheets
(timber frame work and ridge covering measured
separately).
Materials
Labour
1 day carpenter
Per square
Materials
Labour
68
Item Description Rate Amount
71. Asbestos close fittings ridging fixed complete
with roofing screws or bolts (hook)
Per 13’ 4” length
Materials
4 pairs ridges 3’ 8” long
16 roofing screws or bolts
Labour
¼ day carpenter
¼ day U/Sk labourer
Per 13’ 4” ridging
9 ridge tiles
½ lb colouring powder
Labour
¼ day mason
69
Item Description Rate Amount
73. ¾” x9” high valance board fixed with brass
screws to ends of rafters (for tile roofing)
Per 100 l.ft
Materials
75.00 sq.ft 1” planks
Add 5% for wastage
70 Nos. 1 ½” brass screws
Labour
3 days carpenter
3 days U/Sk labourer
Scaffolding – Add 5% 0000
Total per 100 l.ft Total 0000
Labour
3 days carpenter
3 days U/Sk labourer
Scaffolding – Add 5% 0000
Total per 100 l.ft Total 0000
Rate per L.ft
70
Item Description Rate Amount
75. ROOF PLUMBING
18 B.W.G. (1.2 mm) galvanised iron sheet valley
gutter 3’ 0” girth overall once bent with end laps
not less than 9” width including ¾” tongued and
grooved planks laid to slope and profile on timber
members.
Consider 15’ 0”
Materials
2 G.I sheet (8’ x 4’)
¼ gal wood preservative
0.10 cwt cement (50Kg bags)
0.05 cwt slaked lime
1.00 cu.ft sand
50.00 sq.ft planks
2 1bs 1 ¼” wire nails
Labour
(a). Fixing boarding and applying
wood preservative
1 day carpenter
1 day U/Sk labour
71
76. 18 B.W.G. (1.2 mm) galvanised iron flashing 1’
6” girth overall 3 times bent with end laps not
less than 6”, lead soldered, turned and tucked up
to not less than 6” into chase cut in wall and
printed in cement mortal 1:2 lower and dressed
over roof covering not less than 1’ 0” wide.
Materials
1 G.I. sheet 8’ x 0” x 4’ 0”
1 lb soldering lead
Labour
½ day tinker
72
Item Description Rate Amount
77. ......... framework for 4’ 0” x 4’ 0” flat asbestos
ceiling (sheet measured separately), Comprising
of 4” x 2” joists and 2” x 2” bearers in class I
timber.
Materials
1 Lb 2” nails
25 lbs cement
2” brush- ¼ use
Labour
2 ½ days carpenter
½ day mason
Total 0000
73
Item Description Rate Amount
78. Horizontal ceiling lining using 4’ 0” X 4’ 0” flat
asbestos cement sheets fixed with and including
beading and cove mouldings on timber
framework. (Timber framework & painting
measured separately).
Materials
¼ lb – ¼” clout nails
Labour
1 ½ days carpenter
Total - 0000
74
Item Description Rate Amount
79. ¾” thick tongued and grooved Lunumidella
ceiling boards fixed horizontal on 4” x 2” class I
timber joists at 2’ 0” centres with 1 ½” brass
nails.
Materials
Labour
Making holes, fixing joists & making good-
1 day mason
1 day carpenter
3 days U/Sk labourer
75
Item Description Rate Amount
80. ¾” x 6” wide tongued and grooved Lunumidella
ceiling boards fixed to underside of roof rafters,
(existing) with 1 ½” brass nails including
levelling with timber strips where necessary.
Consider room 15’ 0” x 12’ 0”
1.80 squares.
Materials
Labour
3 days carpenter
Total 0000
76
Item Description Rate Amount
81. Door single hung 3’ 3” x 7’ 0” high overall with
frame having 1 ¼“ thick sash and 3 ¾” X 2 ¾”
timber frame. ( glazing, ironmongery & painting
measured separately)
Per 22.75 square feet (3’ 3” x 7’ 0” )
Materials
(a). Frame-
1 ½ cu.ft 4” x 3” timber
(b). Sash-
14 sq.ft 1 ½ planks
5 sq.ft 1” planks
Labour
5 days carpenter
77
Item Description Rate Amount
82. Door glazed and panelled double hung 4’ 0” x
7’0” high overall with frame including 1 ¼” thick
sash and 3 ¾” x 2 ¾” frame. (glazing,
ironmongery and painting measured separately)
Per28.00 square feet (4’ 0” x 7’ 0”)
Materials
(a). Frame
4” long screws
dowels 4” long.
(b). Sashes
6 days carpenter
78
Item Description Rate Amount
83. Plywood door single hung 3’ 1 ½ “ x 6’ 1 ½ “
overall with frame having 1 ¼” thick sash and 3
¼” x 2 ¾” frame. (Ironmongery and painting
measured separately)
Per 21.75 square feet (3’ 1 ½” x 6’ 1 ½”
Materials
(a). Frame
(b). Sash-
1 No 6’ 9” x 2’ 9” plywood sash
Labour
79
Item Description Rate Amount
84. Door ledged, braced and battened single hung
2’6” x 6’6” overall, with frame having 7/9” thick
tongued & grooved planks and 3 ¾” x 2 ¾”
frame. (Ironmongery and painting measured
separately)
Per 16.25 sq.ft (2’ 6” x 6’ 6”)
Materials
(a). Frame-
2 No spur stones
6 No fibre/plastic plugs
4” long.
Labour
2 ¼ days carpenter
80
85. Window, glazed 7’ 0” x 4’ 0” high overall with
frame comprising 3 No openable sashes and 3
¾” x 2 ¾” frame and mullions.
(Glazing , ironmongery and painting measured
separately)
Per window
(a). Frame-
(b). Sashes-
Labour
6 days carpenter
81
Item Description Rate Amount
86. 1/6” clear sheet glass panes exceeding 1’ 0” but
not exceeding 4 square feet cut and fixed with
timber beadings to doors and windows.
Materials
30 L.ft ½” x ½” beading
Labour
½ day glazier
82
Item Description Rate Amount
87. IRONMONGERY
Btt hinges5” x 2 ½”
Materials
Labour
¼ day carpenter
Per 1 ½ pairs.
Materials
Labour
2 hrs carpenter
83
Item Description Rate Amount
89. Rim lock
Materials
1 rim lock with screws
Labour
2 hrs carpenter
2 hrs U/Sk labourer
Labour
½ day carpenter
½ day U/Sk labourer
84
Item Description Rate Amount
92. Door closer (Hydraulic)
Materials
1door closer
Labour
2 hrs carpenter
Materials
10 – ½“ brass screws
Labour
½ hr carpenter
½ hr U/Sk labourer
Materials
1 barrel bolt
Labour
½ hr carpenter
½ hr U/Sk labourer
85
Item Description Rate Amount
95.
Casement fasteners
Materials
6 casement fasteners
24-1/2” brass screws
Labour
½ day carpenter
½ day U/Sk labourer
Materials
Labour
½ day carpenter
86
Item Description Rate Amount
97. Draw rings
Materials
6 draw rings
Labour
1 hr carpenter
Materials
1 ½ gals bitumen
Water 10 gals
Labour
1¼ days mason
2½ U/Sk labourer
87
Item Description Rate Amount
99. 5/8” thick plastering to wall in lime and sand 2:5
including floating with lime putty.
Per square
Materials
Labour
1 day mason-
1 ¾ days U/Sk labourer
Scaffolding –Add 3% 0000
Total 0000
Labour
1 day mason
1 ½ days U/Sk labourer
Scaffolding – Add 3% 0000
Total 0000
88
Item Description Rate Amount
101. 3/8” thick plastering to soffit of slab in cement
and sand 1:3 including floating with lime putty.
Per square
Materials
Water 5 gals.
Labour
2 ½ days mason
water 5 gals
Labour
2 day mason
89
Item Description Rate Amount
103. 5/3” thick plastering to wall in lime cement and
sand 1:1:5 finished semi-rough with wooden
float.
Per square
Materials
Labour
1 days mason
Total 0000
Rate per square
104. 5/3” thick plastering to wall in lime cement and
sand 1:1:5 finished smooth with lime putty
floating.
Materials
0.80 cwt cement (50 Kg bags)
Labour
1 ½ days mason
90
Item Description Rate Amount
105. ½” thick rendering in cement and sand 1:3
finished smooth.
Per square
Materials
Water 10 gals
Labour
1 day mason
Materials
Water 10 gals.
Labour
1 day mason.
91
Item Description Rate Amount
107. ¾” thick rendering in cement and sand 1:3
finished smooth.
Per square
Materials
Water 10 gals
Labour
1 ¼” days mason
Labour
1 ¼ days mason
2 day U/Sk labourer
¼ day U/Sk labourer (curing)
92
Item Description Rate Amount
109. ¾” thick rendering in cement and sand 1:2 in
coloured cement floors finished smooth.
Per square
Materials
2.25 cwt cement (50 kg bags)
0.08 cubs sand
5 lbs powdered pigment
Water 10 gals
Labour
1 ¼ days mason
2 day U/Sk labourer
¼ day U/Sk labourer (curing)
Labour
3/8 day mason
5/16 U/Sk labourer
93
Item Description Rate Amount
111. Prepare and apply one coat of preservative (oil
type) to structural timber including touching up
cut ends etc. after fixing.
Per one square
Materials
2.75 ltr. wood preservative (oil type)
3” brush (1/10 use)
Labour
¾ day painter
½ day U/Sk labourer
Labour
1 ½ day painter
1 ½ day U/Sk labourer
94
Item Description Rate Amount
113. Apply one coat of anti-corrosive primer and two
coats enamel paint on already shop primed and
erected steel roof truss.
Consider one square
Materials
0.20 ltr. anti-corrosive primer
1 1/3 ltr. enamel paint
0.20 ltr. Mineral turpentine or thinner.
2” brush (1/5 use)
Labour
2 ½ days painter
1 day U/Sk labourer
Scaffolding –Add 3% 0000
Total 0000
Labour
½ day painter
¾ day U/Sk labourer
Total per 50 sq.ft
95
Item Description Rate Amount
115. Painting steel on new work with 2 coats of anti-
corrosive paint
Per square
Materials
2/3 ltr. anti-corrosive paint
2” brush (1/5 use)
Labour
1 ½ days painter
Labour
½ day painter
Labour
1 ½ days painter
½ day U/Sk labourer
Rate per square
96
118. White or colour washing two coats in single
storey.
Per 10 squares
Materials
0.50 cwt. boiled lime
2 lbs salt
½ lb yellow ochre
2 oze blue
6” brush (1/3 use)
Water 10 gals
Labour
2 ½ days painter
2 ½ days U/Sk labourers
Scaffolding –Add 3%
Scaffolding –Add 3%
000
Total 000
97
Item Description Rate Amount
120 Prepare and apply one coat of Alkali resistant
primer and two coats of emulsion paint to walls.
Per square
Materials
Primer 90 ltr. primer
1.40 ltr. emulsion paint
Water 0.10 gals
6” brush(1/10 use)
2 sand papers
Labour
1 ¼ day painter
scaffolding -Add 3% 000
Total 000
Labour
2 days painter
2 days U/Sk labourer
Scaffolding-Add 3 %
Total per 10.00 sqrs. 0000
Total 0000
Rate per 10.00 squares
98
Item Description Rate Amount
122. Painting walls with emulsion paint (2 coats)
Per square
Labour
¾ day painter
Scaffolding –Add 3% 0000
Total 0000
99
Item Description Rate Amount
124. Varnishing two coats with copal varnish after
sandpapering.
Per square
0.40 gals (1.80 ltr.) varnish
3” brush (1/3 use)
2 No sand paper
Labour
½ day painter
½ day U/Sk labourer
Labour
3hrs. U/Sk labourer
100
Item Description Rate Amount
126. PLUMBING – PVC PIPES
½” diameter PVC pipes fixed to walls (specials
paid separtely)
Per 10 L.ft
Materials
13 L.ft pipes
3 clips and rails
2 grams solvent cement
Labour
1 hr. plumber
1 hr U/Sk labourer
Total per 10. CO L.ft
Labour
1 hr. plumber
1 hr. U/Sk labourer
101
Item Description Rate Amount
128. 1” dia meter PVC pipes fixed to walls (specials
paid separately)
Labour
½ day plumber
½ day U/Sk labourer
Total per 100 L.ft
Labour
¾ day plumber
¾ day U/Sk labourer
Total per 100 L.ft
102
Item Description Rate Amount
130. 1 ½“ dia meter PVC pipes laid to walls (specials
paid separately)
Per 100 L.ft
Materials
100L.ft pipers
Add 5% for wastage
8- 1 ½” dia sockets
64 grms solvent cement
35 clips and nails
Labour
¾ day plumber
¾ day u/Sk labourer
Total per 100 L.ft
Labour
¾ day plumbers
¾ day U/Sk Labourer
Total per 100 L.ft
Labour
1day plumber
1 day U/Sk labourer
Total per 100 L.ft
104
Item Description Rate Amount
134. Chasing brick for laying ½” to 1 ½” dia PVC
pipes and making good average depth 2” (pipes
and specials paid separately)
Per 100 l.ft
Materials
0.10 cwt cement
0.01 cubes sand
Labour
3 days mason
3 days U/Sk labourer
Total for 100 L.ft
Labour
3 ½ days mason
3 ½ days U/Sk labourer
Total per 100 L.ft
105
Item Description Rate Amount
136. ½” dia PVC specials viz-elbows/ bends/sockets.
Per 10 specials
Materials
10-1/2” elbows/bends/socket
20 grms solvent cement
Labour
2 hrs plumber
Total per 10 No.
Labour
2 hrs. plumber
Total per 10 No.
106
Item Description Rate Amount
138. 1“ dia PVC specials viz elbows/ bends/sockets.
Per 10 specials
Materials
10 -1” dia elbows/bends/sockets
40 grms solvent cement.
Labour
2 hrs. plumber
Total per 10 No.
139.
1 ¼” dia PVC specials viz-elbows / bends
/sockets.
Per 10 specials
Materials
Labour
2 hrs plumber
107
Item Description Rate Amount
140. 1 ¼” dia PVC specials viz-elbows / bends
/sockets.
Per 10 specials
Materials
Labour
2 hrs plumber
141.
2” dia specials viz-elbows / bends /sockets.
Per 10 specials
Materials
Labour
½ day plumber
108
Item Description Rate Amount
142.
2” dia PVC specials viz-elbows / bends /sockets.
Per 10 specials
Materials
Labour
½ day plumber
10 - 3” dia elbows/bends/sockets.
Labour
½ day plumber
109
Item Description Rate Amount
Per 10 Tees
Materials
10- ½” tees
Labour
½ day plumber
Materials
Labour
½ day plumber
110
Item Description Rate Amount
146.
1” dia PVC specials viz-Tees
Per 10 Tees
Materials
Labour
½ day plumber
147.
1 ¼” dia PVC specials viz Tees
Per 10 Tees
Materials
Labour
½ day plumber
111
Item Description Rate Amount
148.
1 ½” dia PVC specials viz Tees
Per 10 Tees
Materials
10 - 1 ½” dia Tees
Labour
1 day plumber
149.
2” dia PVC specials viz Tees
Per 10 Tees
Materials
10 – 2” dia Tees
Labour
1 day plumber
112
Item Description Rate Amount
Materials
Labour
1 ½ days plumber
Materials
Labour
1 ½ days plumber
113
Item Description Rate Amount
Materials
50 – 4 “ dia EW pipes
2 lbs yarn
Labour
2 days plumber
Backfilling –
114
Item Description Rate Amount
Per 6’ 0” length
Materials
1- timber plug 6” x 6” x 2”
2- 3” iron screws
2lbs cement
Labour
¼ day plumber
Scaffolding – Add 5%
Total 0000
115
Item Description Rate Amount
Per 6’ 0” length
Materials
6 lbs lead
1 wood plug 6” x 6” 2”
Labour
¼ day plumber
Total 0000
116
Item Description Rate Amount
Per No.
Materials
1:2:4 (3/4”)
1-4” G. I. grating.
Labour
¼ day mason
117
Item Description Rate Amount
Materials
Labour
1 ½ days mason
118
Item Description Rate Amount
Per No.
Materials
1-1/2” tap
4 wooden plugs
6 – 1 ½” brass screws
2 lbs cement
Labour
½ day mason
119
Item Description Rate Amount
Per No.
Materials
2 L iron brackets
2 lbs cement
Labour
½ day mason
120
Item Description Rate Amount
Per No.
Materials
2 lbs cement
¼ cu.ft sand
Labour
¼ day mason
1 day plumber
121
Item Description Rate Amount
Per No.
1 clip
5 wooden plugs
¼ cwt cement
½ cu.ft metal
¼ cu.ft sand
Labour
½ day mason
1 day plumber
122
Item Description Rate Amount
161. Vitreous China bidet suite fixed complete to
working order
Per No.
Materials
1 bidet
Labour
1 day plumber
1 day U/Sk labourer
Labour
¼ day mason
1 day plumber
1 day U/Sk labourer
Total per 4 No.
Rate per No.
123
timber valance board including gutter joiner and
brackets fixed at 18” centres. (Other specials
paid separately)
Materials
1 joiner
17 gutter brackets
Labour
½ day plumber
124
Item Description Rate Amount
Materials
2 gutter joiners
2 gutter brackets
Labour
tt Total 0000
125
Item Description Rate Amount
Materials
1 mitre hand
2 gutter joiners
2 brackets
Labour
Total 0000
Rate per No.
Materials
Labour
Total 0000
Labour
1/3 day plumber
1/3 day U/Sk labourer
Scaffolding- Add 5% 0000
Total 0000
Rate per 24” 0’ L.ft
Rate per L.ft
168. 3 ½” dia PVC elbow
Materials
1-600 /800 elbow
32 grams solvent cement
Labour
1/16 day plumber
1/16 day U/Sk labourer
Scaffolding – Add 5% 0000
Total 0000
Rate per No.
127
Item Description Rate Amount
Materials
Labour
1/16 day plumber
1/16 day U/sk labourer
128