BSR Analyses

Download as doc, pdf, or txt
Download as doc, pdf, or txt
You are on page 1of 128

INDEX

CONTENT PAGE NO.

Introductory Notes 1-8

1. Excavation 9-13

2. Anti termite treatment 13

3. Earthwork 14-16

4. Earthwork support 17-19

5. Concrete 20-46

6. Timber formwork 47-53

7. Steel reinforcement 53

8. Brickwork 54-61

9. Hollow block masonry 62

10. Random Rubble masonry 63

11. Pressed tilling 64

12. Wall tiling & Terrazzo tiles 65-66

13. Roofing 67-71

14. Roof plumbing 72-73

15. Ceiling 74-77

16. Doors & windows 78-83

17. Ironmongery 84-89

18. Plastering 89-95

19. Pointing & Decorating 96-103

20. Plumbing (PVC) 104-116

21. External drainage (Ew pipes) 117

22. Plumbing (C.I. pipes) 118-119

23. Manholes & Gulleys 120-121

24. Sanitary fittings 122-126

1
25. Gutters & Down pipes 127-130

MATERIAL AND LABOUR ANALYSIS FOR BUILDING WORKS –

Analysis for Basic Rates

The Material and Labour component required for the various items of work
including the minimal plant required for same is detailed in the analysis of the
Basic Rates which have been included in the following pages.

Basic Rate
The basic rate is analyzed under the following headings:

(a) Materials
The quantities of material required for the items are computed from
known data and experience. Their total value is calculated on the basis
of current costs of purchase at sources of supply. Unless, otherwise
stated wastage is allowed in the norms.

(b) Transport
This component provides for the cost of transport of material from
sources of supply to the sites of work. This component is usually added
to the material cost.

(c) Labour
The labour wages are as approve d by the Government from time to
time and on the basis of an 8 hour working day.

(d) Plant
This component provides for the minimum plant required for the items of
work. The cost of tools and implements is provided for tin the overheads
allowances.

(e) Basic Cost

2
The Basic Cost is the sum of the costs of items (a), (b), (c) & (d) above.

Overhead s & Profit factor


Overhead costs include such cost that cannot be considered as direct
productive work on the job. These may be generally grouped as follows:

(a) Job Overheads


That vary with and are caused directly by the individual jobs and.

(b) General Overheads


Which include costs of maintaining an office, workshop and yard in which
to do business whether or not there is a job under way? Such expenses
are continuous and may be shared by the job turnover.

The common items that make up the overhead costs are listed below. The
cost of the overhead items involved on a job is assessed as a percentage of
the Basic cost of the job. In the case of the construction Agencies executing
building construction works the overheads component may be listed as below:

Job Overheads (Site Overheads) % of Basic Cost


1. Supervision of work (wages of work supervisors) 1.0
2. Supervision of labour (wages of Gangers) 4.0

3. Temporary works:
(a) Access Road and Maintenance 0.2
(b) Site buildings for accommodation of part labour 0.7
(c) Central sores building 0.6
(d) Fencing and protection 0.3
(e) Provision of water, lights etc. 0.3
(f) Clearing and tidying up 0.2
(g) Collection of building materials including cement
and steel 0.40
4. Watchers for field stores and security of sites. 0.8

3
5. Tools and implements for miscellaneous work 0.9
6. (a). Setting out and measurements 0.5
(b). Providing samples for testing 0.2
7. Transportation of supervisory staff 1.0
8. Job office, furniture, stationary, supplies, water, lights etc. 0.9
9. Wages of job office staff 1.2
10. Transportation of job office staff 0.4
11. (a). Bonds for Bid performance and fidelity Guarantee 0.3
(b). Insurance of work and workmen’s compensation 0.5
12. (a). Interest in Capital Investment 1.6
(b). Business Turnover Tax 3.0
19.0

General Overheads
13. Head office and rent, lights, telephone, stationary
supplies, furniture etc. for same 0.6
14. Salaries of Head Office Manager, Engineers,
Technical Assistants, Draughtsman, Clerks, Stenos, Typists,
Minor staff and Drivers 1.2
15. Transportation and subsistence of Head office staff 1.0
16. Insurance, Interest and Taxes on business 0.4
17. Legal expenses and Consultancy fees 0.2
18. Workshop & Yard rents, sheds, garages & supplies 2.20
19. Salaries of workshop & yard storekeepers, Drivers, Foremen
Mechanics & workmen 0.4
6.0

Profits
Ten percent (10%) of the Basic costs is allowed as profit to the Contractor.

Overheads and Profit Factor


Combining the factors for overheads and the profits factor we get 35% of the
Basic Rate as the Overhead and Profit factor which is also called the “Mark-up”

4
on the Basic Rate. ie the Basic Rate is multiplied by the factor 1.35 to obtain
the working rate.

This Basic Rate Analysis does not include for the use of heavy plant and
equipment. This analysis provides for a labour intensive method of work with
a minimal use of machinery. The machinery allowed in this analysis is the
concrete mixer, the vibrator and a hoist in the case of a multi-storeyed
building for the lift of materials to the various floors.

This analysis is applicable for a building having a maximum of four storeys –ie
ground and three floors.

If a building has more than four floors or when the Contract period is
compressed to a few months, then it will be necessary to allow for the use of
heavy machinery such as tower cranes, mobile cranes, dumpers loaders,
batching plant for the mixing of concrete, bins for the storage of concrete
material etc. and also for the employment of contract managers and additional
staff.

The cost of such items of work will not be accommodated within the 35%
“Mark-up” and will have to be provided for in separate items such as
preliminaries to the contract.

Conversion –Imperial to Metric

To Convert Rate per To Rate per Multiply by


Cube M3 0.353
Square M2 0.1075
Sq.ft M2 10.7584
L.ft M 3.28
Cwt Kg 0.02

5
Allowances to be made in the .................. got lift in respect of work on upper
floors -

In the analysis of the various items of work in the following pages the rates
refer to work on the ground floor.

To these rates the percentages (of the surround floor rates) indicated in the
table below should be added to obtain the rates applicable to the 1 st, 2nd and
3rd floors. This S.S.R. is limited to work on the ground and 3 upper floors only.

Ground to Ground to Ground to


1st floor 2nd floor 3rd floor
Concrete (cube) 3% 5% 7%
9” brick work (sqr.) 5% 7% 9%
9” brick work (cube) 5% 7% 10%
4 ½” Brickwork (sqr.) 5% 7% 10%
Steel Reinf ; (cwt) 2 ½% 5% 7%
Plastering (sqr) 5% 10% 15%
Painting (sqr) 3% 6% 9%
Floor tiling (sqr) 2% 4% 6%
Wall tiling (sqr) 2% 4% 6%
Roof calicut tiles (sqr) 3% 6% 9%
Roof Asbestos (sqr) 3% 5% 7%
Ceiling work 3% 5% 7%

NOTE:
EARTH WORK AND LANDSCAPING

1. Solis met with in excavation have been classified as follows:


1. Soft/Loose soil
2. Ordinary soil
3. Hard/Dense soil
4. Mud/Wet clay
5. Soft disintegrated rock (ie rock not requiring blasting)
6. Hard rock - (a). Where blasting is approved.
(b) Where blasting is prohibited.

6
2. The analysis has been prepared for each of the above categories as
shown in items Nos 3-9.

3. However, in the preparation of estimates for purposes of calling for


Tenders, only two B.O.Q. item would be included in the B.O.Q. as
against the B.S.R. item Nos. 3, 4, 5, 6, 7, 8 & 9. The description of
these two B.O.Q. items would be as follows.
(a). Excavation in any material met with except rock requiring blasting
(b). Excavation in rock requiring blasting.

4. This classification has been adopted (where tenders are called) to avoid
any dispute that may arise as to the exact nature of the soil that will be
met with when the actual excavation is carried out. The tenderer is
expected to examine the site and to form his own opinion of the nature
of the soil that is met with and rate his tender accordingly.

5. The classification of the soils in Note 1 above and the analysis provided
for the different type of soil will help the estimator in arriving at the
actual cost of excavation, for which he will have to allow in his estimate.

6. Under Note 1 (6) b Hard Rock, and analysis is provided for removing
Hard Rock met with in foundation excavations where blasting is
prohibited or cannot be done, like in built up areas where blasting can
cause damage to adjoining buildings.

7. In the excavation items Nos . 3 to 9, the labour norm allowed in the


items is for an excavation up to a maximum depth of 5’ 0”. For
excavations beyond the depth of 5’ 0” an additional unskilled labourer
should be added for every additional depth of 5’ 0’’ or part thereof for
each cube of excavation beyond the original 5’ 0’’ depth.

7
Item Description Rate Amount
1. Removing top soil to a depth not exceeding 6”
& deposition as directed within site.
Per Square
Consider an area of 10.oo sqrs. ie 5.00 cubs of
excavation. 10 days U/SK labourer
Rate per 10.00 square.

Rate per square

2. Excavation over site to reduce level, in any


material except rock requiring blasting
including depositing and leveling as directed up
to distance not exceeding 30’ 0”.

Per cube

1 5/8 day U/Sk labour

Rate per cube

3. Excavation in trenches for walls/column pits in


soft/loose soil from 0’ 0” to 5’ 0” deep and
depositing excavated material to distance not
exceeding 30’ 0” (Earth work support to be paid
separately where necessary).

Per cube-

1 day U/Sk labourer


Rate per cube

8
Item Description Rate Amount

4. Excavation in trenches for walls/column pits in


ordinary soil form o’ 0’’ to 5’ 0’’ deep and
depositing excavated material not exceeding
30’ 0’’.

Per cube

2 ¼ days U/Sk labourer

Rate per cube

Excavation in trenches for walls/column pits in


Hard/dense soil up to a depth of 5’ 0’’ and
5.
depositing excavated material up to a distance
not exceeding 30’ 0’’.

Per cube
3 ½ days U/Sk labourer

Rate per cube

Excavation in trenches for walls/column pits in


Mud/wet soil up to a depth of 5’ 0’’ and
6.
depositing excavated material to distance not
exceeding 30’ 0’’.

Per cube

3 days U/Sk labourer

Rate per cube

9
Item Description Rate Amount

7. Excavation in trenches for walls/column pits in


soft disintegrated rock (not requiring blasting)
up to a depth of 5’ 0’’ and depositing
excavated material to distance not exceeding
30’ 0’’.

Per cube

2 ½ days U/Sk labourer

Rate per cube

8. Excavation in trenches for walls/column pits in


Hard rock requiring blasting up to a depth of 5’
0’’ and depositing excavated material to a
distance not exceeding 30’ 0’’.
Per cube

Materials

0.75lbs blasting powder


10lft fuse
1lb jumper steel
Fuel & forge -20% of material cost

Labour

1 day Sk labourer

2 days U/Sk labourer

Rate per cube

10
Item Description Rate Amount
9. Benching rock in foundation in 3’’-6’’ steps.
(Blasting prohibited)
Per 10-souare feet

Drilling, chipping & wedging-

1 ½ day Sk labourer

Steel, fuel & forge-25% of labour cost.

Collecting & Disposing –

1 ½ day U/Sk labourer

per 10 sq.ft.

Rate per sq.ft.


10. ANTI-TERMITE TREATMENT

Anti-termite treatment on excavated


foundation and compacted soil under floors.
Per square

Materials

16 lbs D.D.T. powder

(8%in 20 gals of water)

20 gals water

Labour

½ day U/Sk labourer

Rate per cube

NOTE: Alternative Mixes:

(a). Copper Naphthenate (5% in 4 to 8

gals of fuel oil)

(b). Sodium Arsenate (10% in 12 to 20 gals)


of water.

(c). Dieldrine (0.3% in 19 gals of water).

11
Item Description Rate Amount

11. Earthwork –Backfilling & compacting


Backfilling to trenches with selected earth
available at site.

Per cube
1 day U/Sk labourer

Rate per cube

12. Back filling to trenches with imported material

Per cube

1.0 cube earth delivered at site.

Allow 15% compaction

filling & Compacting

1 ¼ U/Sk labourer

Rate per cube

13. Filling under floors including leveling, watering


& compacting in 3” layers with available and
selected earth at site.

Per cube

2 Days U/Sk labourer


Rate per cube

12
Item Description Rate Amount
14. Filling under floors including leveling, watering
& compacting in 3” layers with imported
selected earth.
Per cube
1.0 cube earth delivered at site.
allow for 15% compaction
2 days U/Sk labourer

Rate per cube


15. Cutting turf sods, loading to hand carts and
transporting up to 30 yards, laying and
watering for 30 days. (Royalty for
turf, pegging and transport beyond 30 yards
paid separately).
Per square
Cutting turf sods, loading and transporting to
site and unloading.
2 ½ days U/Sk labourer
Laying turf rods at site
½ days U/Sk labourer
Watering for 30 days
1 ½ days U/Sk labourer
60 gals. Water.

Rate per square


NOTE:
Rate does not include for :
(a). Royalty for turf
(b). Transport of turf
(c). Pegs on sloping site
(d). Water

13
Item Description Rate Amount

16. Earthwork support (open planking) in trenches


up to a depth of 5’ 0’’.

Consider trench 15’ 0’’ long

3’ 0’’ wide and 5’ 0’’ depth

Open planking to both faces.

Total area = 2/15’ 0’’ x 5’ 0’’ = 150 sq. ft

Per 150 sq. ft

Materials

17.50 sq.ft class II timber (4uses)

Add 5% on above for wedges.

Labourer

1 days carpenter

3 days U/Sk labourer

Total per 150 sq.ft

Rate per square

14
Item Description Rate Amount
17. Earthwork support (close plunking) in trenches
up to 5’ 0’’ depth.

Consider trench 15’ 0’’ long 3’ 0’’ wide and 5’


0’’ height of planking to both faces.

Total area of planking

2/15’ 0’’ * 5’ 0’’ ie 150 sq.ft.

Per 150 sq.ft.

Materials

30.00 cu.ft class II timber (4 uses)

Add 5% on above for wedges.

Labour

2 days carpenter

6 days U/Sk labourer

Total per 150 sq.ft.

Rate per square

15
Item Description Rate Amount

18. Earth work support (clone planking) in deep


excavation in trenches up to 15’ 0’’ depth.

Consider trench of length of 15’ 0’’

width 5’ 6’’ at top

3’ 6’’ at bottom

Then area supported is 2/15’ * 15’

ie. 450 sq.ft.

Materials

100.00 cu.ft class II timber (4 uses)

Add 5% on above for wedges.

Labour

8 days carpenter

20 days U/Sk labourer

Total per 450 sq.ft

Rate per square

16
CONCRETE

Preamble

Assumptions:

1. Mixing concrete using a concrete mixer 14/10 cu.ft. Capacity and manual
loading are the basis on which the norms are worked.

2. A gang of one skilled and six unskilled labourers produce 3.00 cubes of
concrete per day using a 14/10 cu.ft capacity concrete mixer. This is as per
accepted practice.

3. The production of concrete is at the mixer site; transporting mixed concrete


and placing same in position is paid for separately.

4. In concrete items 26 to 39 both inclusive, placing of concrete in columns,


beams and floor slabs on the ground floor the labour component allowed is
for the placing of concrete between the ground floor and the top of the 1 st
floor slab which area is called the ground floor area. Similarly the area
between the top of the 1st floor slab and the top of the 2 nd floor slab is
called the 1st floor area etc.

17
Item Description Rate Amount

Mixing concrete 1:3:6 (1 ½”)


19.
Per cube

Materials

13 cwt (50 kg bags) cement

0.53 cubes sand

0.92 cubes 1 ½” metal

1/3 day hire of mixer

water (110 gals)

Labour

1/3 day skilled labourer

2 days U/Sk labourer

Rate per cube

NOTE :

(a). Water available at site.

(b). If, water is not available allowances

should be made for transport of

water.

(c). Sand –includes 15% for bulking.

18
Item Description Rate Amount

20. Mixing concrete 1:2 ½ :5 (1”)

Per cube

Materials

14 cwt cement (50 kg. bags)

0.60 cubes sand

0.90 cubes 1” metal

1/3 day hire of mixer

water (100 gals)

Labour

1/3 day skilled labourer

2 days unskilled labourer

Rate per cube

Note:

(a). Water available at site.

(b). If water is not available allowance

should be made for transport of

water.

(c). Sand –Includes 15% for bulking.

19
Item Description Rate Amount
21.
Mixing concrete 1:2:4 (3/4”)

Per cube

Materials

18 cwt cement (50 Kg bags)

0.50 cubes sand

0.88 cubes ¾” metal

1/3 day hire of mixer

water-(120 gals)

labour

1/3 day skilled labourer

2 days U/Sk labourer

Rate per cube

NOTE:

(a). Water available at site

(b). If water is not available at site

allowance must be made for transport

of water.

(c). Sand- includes 15% for bulking.

20
Item Description Rate Amount

22. Mixing concrete 1: 1 ½ : 3 (3/4”)

Per cube

Materials

23 cwt cement (50 Kg bags)

0.42 cubes sand

0.82 cubes ¾” metal

1/3 day hire of mixer

Water (150 gals)

Labour

1/3 day skilled labourer

2 days U/Sk labourer

Rate per cube

NOTE:

(a). Water available at site.

(b). If water is not available allowance

must be made for transport of water.

(c). Sand-includes 15% for bulking.

21
Item Description Rate Amount

23. Mixing concrete 1: 1 ½ : 2 (3/4”)

Per cube

Materials

31 cwt cement (50 Kg bags)

0.44 cubes sand

0.96 cubes ¾” metal

1/3 day hire of mixer

Water (200 gals)

Labour

1/3 day skilled labourer

2 days U/Sk labourer

Rate per cube

NOTE:

(a). Water available at site.

(b). If water is not available allowance

must be made for transport of water.

(c). Sand-includes 15% for bulking.

22
Item Description Rate Amount

24. 2” thick cement concrete screed in foundation


at depths not exceeding 5’ 0”.

Per square

Materials

1/6 cube concrete

Add 10% for wastage

Labour

1/8 day Sk labourer

½ day U/Sk labourer

Rate per square

NOTE:

For laying concrete at depths more than 5’0”.


Add 1/6 day unskilled labourer for each
additional 5’ 0” or part thereof per square.

23
Item Description Rate Amount

25. 3” thick cement concrete screed in foundation


at depths not exceeding 5’ 0”.

Per square

Materials

¼ cube concrete

Add 10% for wastage

Labour

1/8 day Sk labourer

¾ day U/Sk labourer

Rate per square

NOTE:

For laying concrete at depths more than 5’ 0”.


Add ¼ day unskilled labourer for each
additional 5’ 0” or part thereof per square.

24
Item Description Rate Amount

26. 6” thick cement concrete floor (mass


concrete).

Per square

Materials

0.50 cubes concrete

Add 5% for wastage

Water (200 gals)

Labour:

½ day Sk labourer

1 ¼ day U/Sk labourer

Rate per square

NOTE:

(a). Water available at site.

(b). If water is not available allowance

must be made for transport of water.

25
Item Description Rate Amount
27. Cement concrete in 4 ½” * 6” columns in
ground floor.
Consider 24 No. columns each 4½“* 6”*10’0”
ie 0.45 cubes.

Per 0.45 cube

Materials

0.45 cubes concrete

Add 10% for wastage

1 day hire of vibrator

Labour

1 day mason

1 day carpenter

3 days U/Sk labourer

1 day Sk labourer (vibrator)

Curing

Jute Hessian -100 sq.ft.

water -170gals

1 day U/Sk labourer

Total for 0.45 cubes or

240 1.ft of columns.

Rate per cube

Or Rate per L.ft

26
of column.

NOTE:

1. For columns in 1st floor add 3% to


ground floor rate.

2. For columns in 2nd floor add 5% to


ground floor rate.

3. For columns in 3rd floor add 7% to


ground floor rate.

4. Water available at site.

5. If water is not available allowance must


be made for transport of water.

28. Cement concrete in 6” * 6” columns in ground


floor.
Consider 18 No. columns 6”*6” each 10’0”
high ie 0.45 cubes.

Per 0.45 cubes

Materials
0.45 cubes concrete
Add 10% for wastage
1 day hire of vibrator

Labour
1 day mason
1 day carpenter
1 day Sk labourer (vibrator)
3 days U/Sk labourer

Curing

Jute Hessian -80 sq.ft


27
water-140 gals

1 ½ days U/Sk labourer

Total for 0.45 cubes

or 180 1.ft of column

Rate per cube


Or Rate per L.ft of column
NOTE:
1. For columns in 1st floor add 3% to
ground floor rate.
2. For column in 2nd floor add 5% to
ground floor rate.
3. For columns in 3rd floor add 7% to
ground floor rate.
4. Water available at site
5. If water is not available allowance must
be made for transport of water.

28
Item Description Rate Amount

29. Cement concrete in 9” * 9 columns in ground


floor.

Consider 8 No. 9” * 9” columns each 10’0” high


ie 0.45 cubes.

Per 0.45 cubes


Materials
0.45 cubes concrete
Add 10% for wastage
1 day hire of vibrator

Labour
1 day mason
1 day carpenter
1 day SK labourer (vibrator)
3 days U/Sk labourer

Curing
Jute Hessian -60 sq.ft
water -100 gals
½ day U/Sk labourer
Total per 0.45 cubes
or 80 l.ft of column.

Rate per cube


Or Rate per 1.ft of column
NOTE:
1. For columns in 1st floor add 3% to
ground floor rate.
2. For columns in 2nd floor add 5% to
29
ground floor rate.
3. For columns in 3rd floor add 7% to
ground floor rate.
4. Water available at site
5. If water is not available allowance must
be made for transport of water.
30. Cement concrete in 12”*12” columns in ground
floor.
Consider 5 No. columns 12”*12” each 10’0” high.

Per 0.50 cubes

Materials

0.50 cubes concrete

Add 5% for wastage

40sq.ft-Jute Hessian

1 day hire of vibrator

water (100 gals)

Labour

1 day mason

1 day carpenter

1 day Sk labourer (vibrator)

3 days U/Sk labourer

1 ½ days U/Sk labourer (curing)

Total per 0.50 cube or

50l.ft of column

Rate per cube

Rate per l.ft of column


30
NOTE:

1. For column in 1st floor add 3% to ground floor


rate.

2. For columns in 2nd floor add 5% to ground


floor rate.

3. For columns in 3rd floor add 7% to ground floor


rate.

4. Water available at site.

5. If water is not available allowance must be


made for transport of water.

31
Item Description Rate Amount
31. Cement concrete in 13 ½” * 13 ½ “columns in
ground floor.
Consider 4 No. Columns 13 ½” * 13 ½“each
10’0” high i.e. 0.51 cubes.

Per 0.51 cubes

Materials

0.51 cubes concrete

Add 5% for wastage

1 day hire of vibrator

Curing

Just Hessian 45 sq.ft

Water-100 gals

1 ½ days U/Sk labourer

Total for 0.51 cubes

Or 40 1.ft of column

Rate per cube

Or Rate per 1.ft column

Note:

(a). water available at site.

(b). If water is not available allowances must be


made for transport of water.

32
Item Description Rate Amount
32. Cement concrete in 6”*6” beam upto 1st floor
level.
Consider 180 L.ft of beam 6”*6” i.e.0.45 cubes.

Per 0.45 cubes


Materials
0.45 cubes concrete
Add 10% for wastage
1 day hire of vibrator

Labour
1 day mason
1 day carpenter
1 day SK labourer (vibrator)
4 days U/Sk labourer

Curing
Jute Hessian 90 sq.ft.
water 180 gals
1½ days U/Sk labourer
Total per 0.45 cube
or 180 1.ft of column.

Rate per cube


Or Rate per 1.ft column
Note:
(a). water available at site.
(b). If water is not available allowance must be
made for transport of water.

33
Item Description Rate Amount
st
33. Cement concrete in 9”*6” beam upto 1 floor
level.
Consider 120 L.ft 9”*6” beam i.e.0.45 cubes.

Per 0.45 cubes

Materials

0.45 cubes concrete

Add 10% for wastage

1 day hire of vibrator

Labour

1 day mason
1 day carpenter
1 day SK labourer (vibrator)
4 days U/Sk labourer

Curing
Jute Hessian 75 sq.ft.
water 150 gals
1½ days U/Sk labourer
Total per 0.45 cube
or 120 1.ft of beam.

Rate per cube


Or Rate per 1.ft column
Note:
(a). water available at site.

(b). If water is not available allowance must be


made for transport of water.

34
Item Description Rate Amount
st
34. Cement concrete in 9”x9” beam upto 1 floor
level.
Consider 80’0” length of 9”x9” beam i.e.0.45
cubes.

Per 0.45 cubes

Materials

0.45 cubes concrete

Add 10% for wastage

1 day hire of vibrator

Labour

1 day mason
1 day carpenter
1 day SK labourer (vibrator)
4 days U/Sk labourer

Curing
Jute Hessian 60 sq.ft.
water 120 gals
1½ days U/Sk labourer
Total per 0.45 cube
Or 80 1.ft of beam.

Rate per cube


Or Rate per 1.ft column
Note:
(a). water available at site.

(b). If water is not available allowance must be


made for transport of water.

35
Item Description Rate Amount
st
35. 5” thick R.CC floor slab in 1 floor.
Consider 5” thick slab 10’ 0” x 12’ 0”

Volume of concrete 50.00 cu.ft.

Per 50.00 cubes

Materials

50.00 cu.ft. concrete

Add 10% for wastage

1 day hire of vibrator

Labour

1 day mason
1 day carpenter
1 day SK labourer (vibrator)
4 days U/Sk labourer

Curing
Jute Hessian 30 sq.ft.
water 150 gals
1½ days U/Sk labourer

Total per 50 cu.ft or 120 sq.ft.

Rate per cube


Or Rate per 1.ft column
Note:
(a). water available at site.

(b). If water is not available allowance must be


made for transport of water.

36
Item Description Rate Amount
st
36. 6” thick R.CC floor slab in 1 floor.
Consider 10’ 0” X 10’ 0” panel= 50 cu.ft

Materials

50.00 cu.ft. concrete

Add 10% for wastage

1 day hire of vibrator

Labour

1 day mason
1 day carpenter
1 day SK labourer (vibrator)
4 days U/Sk labourer

Curing
Jute Hessian 25 sq.ft.
water 90 gals
1½ days U/Sk labourer

Per 50.00 cu.ft


or 100.00 sq.ft

Rate per cube


Note:
(a). water available at site.

(b). If water is not available allowance must be


made for transport of water.

37
Item Description Rate Amount
37. Cement concrete in 4 ½“ X 6” lintels in ground
floor.
Consider 240 L.ft i.e. 45 cu.ft.

Materials

45.00 cu.ft. concrete

Add 10% for wastage

1 day hire of vibrator

Labour

1 day mason
1 day carpenter
1 day SK labourer (vibrator)
4 days U/Sk labourer

Curing
Jute Hessian 10 sq.ft.
water 90 gals
1½ days U/Sk labourer
per 0.45 cube
or 240 L.ft of lintel.

Rate per L.ft of lintel


Note:
(a). water available at site.

(b). If water is not available allowance must be


made for transport of water.

38
Item Description Rate Amount
38. Cement concrete in 9”*9” lintels in ground floor.
Consider 80 L.ft of lintel i.e. 45 cu.ft concrete.

Materials

45.00 cu.ft. cement concrete

Add 10% for wastage

1 day hire of vibrator

Labour

1 day mason
1 day carpenter
1 day SK labourer (vibrator)
4 days U/Sk labourer

Curing
Jute Hessian 60 sq.ft.
water 90 gals
1½ days U/Sk labourer

per 0.45 cube


or 80 L.ft of lintel.

Rate per L.ft


Note:
(a). water available at site.

(b). If water is not available allowance must be


made for transport of water.

39
Item Description Rate Amount
40. Cement concrete in 12”*15” lintels in ground
floor.
Consider length of 36’ 0” i.e. 45 cu.ft

Materials

45.00 cu.ft. concrete

Add 10% for wastage

1 day hire of vibrator

Labour

1 day mason
1 day carpenter
1 day SK labourer (vibrator)
4 days U/Sk labourer

Curing
Jute Hessian 40 sq.ft.
Water 90 gals
1½ days U/Sk labourer

per 0.45 cube


Or 36 L.ft of lintel.

Rate per L.ft of lintel


Note:
(a). water available at site.

(b). If water is not available allowance must be


made for transport of water.

40
Item Description Rate Amount
41. Sawn timber formwork to 9” x 9” cement
concrete column in ground floor.
Per square ft.

Consider column length of 5’ 0”

Contact area -15.0 sq.ft.

(a) . MAKING MOULD

(1) Materials

18.15” sq.ft 1” thick class II timber.

17.10 L.ft 2” x 2” class II timber in yokes.

16.12 L.ft 2” x 1” class II timber battens.

1½ lb wire nails.

(2) Fabricating

½ day carpenter

½ day U/SK labourer 00000000

Total Cost 000000000

Allow in ;4 uses cost


of mould per use - 0 00000000

(b). Assembling (Per use)

Materials

12 Nos. 16mm 18” long bolts (20 uses)

½ litre mould oil

35 L.ft 4” x 2” props (10 uses)

Labour

¼ day carpenter

¼ day U/Sk labourer


41
Cost of Assembling ; 000000000

Per use. 0 00000000

(c). Dismantling cleaning & repairing

(per use)

¼ day carpenter0

¼ day U/Sk labourer

Cost of dismantling 00000000

per use. 00000000

Rate per square

42
Item Description Rate Amount
42. Sawn timber formwork for concrete beams in
ground floor

Consider 9” x 12” beam of 20’ 0” long. Contact


area 55 sq.ft.

(A). Making the mould

(a). 60 sq. ft. 1” timber planks

(b). 24 L.ft 2” x 1” battens

(c). 45 L.ft 2” x 2” ledgers

(d). 30 L.ft 4” x 2” bearers at bottom of

mould.

(e). 2 lbs wire nails.

Labour

(a). 1 ½ day carpenter

(b). 2 day U/Sk laburers

Total cost of mould 00000000

00000000

Assuming 4 uses

Cost per use

Add 10% for repairs 00000000

Cost per use 00000000

(B). Assembling

Materials

(a). 110 L.ft 4” x 2” vertical props.

(10 uses)

(b). 80 L.ft 2” x 2” bracing to mould


43
and props.

(c). 50 L.ft 2” x 2” bracing to a set of

props.

(d). 6.0 sq.ft 1” timber base plate to

props.

(e). 22 Nos

Cost of materials for assembling.

Assuming an average of 6 uses.

Cost of materials per uses.

Add 10% cost of

materials for repairs. 00000000

Total cost of materials

Per use. 00000000

(C). Labour & Sundries

Labour

(a). 1 day carpenter

(b). 2 day U/Sk labourer

(c). ½ gal mould oil

(d). ½ lbs nails 00000000

Cost per use 00000000

(D). Dismantling and Cleaning Labour

(a). ½ day carpenter

(b). 2 day U/Sk labourer

Cost of labour for 00000000

dismantling per use. 00000000

Total cost for making the mould assembling


44
aligning dismantling and cleaning for 55 sq.ft per
use. (A+B+C+D)

Cost of formwork per 00000000

square. 00000000

43.. Sawn timber formwork for underside of first floor


slab.
Consider a slab of dimensions 20”0”x10’0”
Contact area = 2.0 sqrs.

(A). Making panels


(1). Materials
(a). 220 sq.ft 1” thick tongue and
grooved timber planks.
(b). 121 lft 4”x2” runners at 2’0”
centers.
(c). 4 lbs. wire nails.
(2). Labour
(a). 3 days carpenter
(b). 3 days U/Sk labourer 00000000
Total cost of making panels. 00000000

Assuming 4 uses cost per use.

Add 20% for repairs. 00000000


Total cost of panels per use. 0000000

(B). Assembling
Materials
(a). 690 l.ft 4”x2” vertical timber props.
(10uses)
(b). 66 l.ft 2”x2” bracing for props.
(c). 122 No. wedges.
45
(d). 33 sq.ft 1” base plates for props.

Cost of materials for assembling.


Assuming 6 uses cost of materials for assembling
per use.
Add 20% of above for repairs.
Total cost of materials for 00000000
assembling per use. 0000000

(C). Labour & sundries for assembling


(a). 1 day carpenter
(b). 4 days U/Sk labourer
(c). 1 gal mould oil for assembling.
(d). 2 lbs wire nails.
Total cost per use for 0000000
assembling. 0000000
(D). Dismantling & Cleaning Labour
(a). ½ day carpenter
(b). 2 days U/Sk labourer

Total cost for dismantling 0000000


per use. 0000000

Total cost for assembling per 0000000


use for 200 sq.ft (A+B+C+D) 0000000

Cost of formwork per square

46
Item Description Rate Amount
44. Mild steel/for steel reinforcement to lintels slab
beams for columns bent to shape laid in position
and tied G.I. wire as directed.

Materials

1 cwt M.S. /Tor steel rods including transport to


site.

(Allow for wastage 15%) 1 ½ lbs 16 BWG binding


wire

Add 1.5% of steel cost for spacers or chairs.

Labour

1 Day blacksmith

1 day U/sk labourer

Rate per cwt.

47
Item Description Rate Amount
45.
Brick work in cement sand 1:5 in foundation up
to D.P.C

Per Cube

Materials

1450 bricks

Add 5% wastage

4.0 cwt cement (50kg bags)

0.25 cubes sand

water (150 gals)

Labour

3 days mason

4 days U/Sk labourer

Rate per cube

48
Item Description Rate Amount
46.
Brick work cement & sand 1:8 in foundation up
to D.P.C

Per cube

Materials

1450 bricks

Add 5% wastage

2 1/3 cwt cement (50 Kg bags)

3/8 cubes sand

water (150 gals)

Labour

3 days mason

4 days U/Sk labourer

Rate per cube

49
Item Description Rate Amount
47.
Brickwork in cement and sand 1:5 in 4” thick
walls in ground floor

Per square

Materials
550 bricks
Add 5% for wastage
1.30 cwt cement (50 Kg bags)
0.10 cubes sand
water (50 gals)

Labour
1 ½ days mason
2 days U/Sk labourer
Scaffolding –Add 5% 0000000
Total 0000000

Rate per square

50
Item Description Rate Amount
48.
9” thick brick wall cement sand 1:5 in ground
floor.

Per square

Materials
1090 bricks
Add 5% for wastage
3.00 cwt cement (50 Kg bags)
0.20 cubes sand
Water (115 gals)

Labour
2 1/4 days mason
3 3/4 days U/Sk labourer
Scaffolding –Add 3% 0000000
Total 0000000

Rate per square

51
Item Description Rate Amount
49.
Brickwork 13 ½ thick in cement sand 1:5 in
superstructure in ground floor.

Per square

Materials
1630 bricks
Add 5% for wastage
4.50 cwt cement (50 Kg bags)
0.30 cubes sand
Water (170 gals)

Labour
3 ½ days mason
5 ½ days U/Sk labourer
Scaffolding –Add 2% 0000000
Total 0000000

Rate per square

52
Item Description Rate Amount
50.
9” brick walls in cement sand 1:8 in
superstructure in ground floor.

Per square (ie.0.75 cubes)

Materials
1090 bricks
Add 5% for wastage
1.75 cwt cement (50 Kg bags)
0.30 cubes sand
Water (115 gals)

Labour
2 1/4 days mason
3 days U/Sk labourer
Scaffolding –Add 3% 0000000
Total 0000000

Rate per square

53
Item Description Rate Amount
51.
4 ½ thick brick wall (wire cut) in cement and
sand 1:5 in ground floor.

(Facing to brickwork measured separately)

Per square

Materials
550 wire cut bricks
Add 2% for wastage
1.20 cwt cement (50 Kg bags)
0.80 cube sand
Water – 30 gals

Labour
1½ days mason
2 days U/Sk labourer
Scaffolding –Add 5% 0000000
Total 0000000

Rate per square

54
Item Description Rate Amount
52.
9” thick in cement and sand 1:5 with wire cut
bricks.

(Facing to brickwork measured separately)

Per square

1080 wire cut bricks

Add 4% for wastage

2.50 cwt cement (50 kg bags)

0.13 cubes sand

water (100 gals)

Labour

2 ¼ days mason

3 ¾ days U/Sk labourer

Scaffolding –Add 3% 0000000

Total 0000000

Rate per square

55
Item Description Rate Amount
53. 13 ½” thick brick wall (wire cut) in cement and
sand 1:5 in ground floor.
(Facing to brick work measured separately)
Per square
Materials
1630 wire cut bricks
Add 2% for wastage
4.50 cwt cement (150 Kg bags)
0.30 cubes sand
Water 150 gals

Labour
3 ¾ days mason
5 ½ days U/Sk labourer
Scaffolding –Add 2% 0000000
Total 0000000
Rate per square
54. Extra over for facing including raised pointing
1/8” thick in cement and sand 1:1 mixture in
ground floor.
Per square
Materials

0.50 cwt cement (50 Kg bags)

1.00 cu.ft sand

1/10 gals cid

Water 10 gals

Labour

5 days mason

3 ½ days U/Sk labourer

Rate per square

56
Item Description Rate Amount
55. 3” thick floor paved in lime mortar 2:5 in ground
floor.

Per square

Materials

350 bricks

1.20 cwt slaked lime

0.11 cubes sand

water (45 gals)

Labour
1 ¼ days mason

2 ½ days U/Sk labourer


Rate per square
56. Steps 1’-1 1/2” x 0’ 6” in brick in cement and
sand 1:5 with ½ “ thick cement and sand 1:2
rendering including necessary excavation.

Per 10 l.ft
Materials

120 bricks

0.50 cwt cement (50 Kg bags)

0.05 cubes sand

water (15 gals)

Labour

½ day mason

½ day U/Sk labourer

Rate per 10 l.ft

Rate per l.ft

57
Item Description Rate Amount
57. Brick drains in cement and sand 1:5, 9” wide and
6”-9” average depth including cement rendering
½“ thick 1:2 to exposed faces with 1’6” ramp
including necessary excavation.

Per 10 l.ft

Materials

140 bricks

0.80 cwt cement (50 Kg bags)

0.05 cubes sand

water (20 gals)

Labour

1 ¼ day mason

1 ¼ day U/Sk labourer

Rate per 10 l.ft

Rate per l.ft

58
Item Description Rate Amount
58. Brick drains in cement and sand 1:5, 9” wide and
6”-9” average depth including cement rendering
½“ thick 1:2 to exposed faces without ramp
including necessary excavation.

Per 10 l.ft

Materials

110 bricks

0.70 cwt cement (50 Kg bags)

0.04 cubes sand

water (15 gals)

Labour

1 day mason

1 ¼ day U/Sk labourer

Rate per 10 l.ft

Rate per l.ft

59
Item Description Rate Amount
59. 8” thick Hollow block work in cement and sand
mortar 1:5 in ground floor (cavities unfilled)

Per square

10’0” x 10’ 0” area (size of each block 16” x 8” x


3”)

Materials

112 Hollow cement bricks

Allow 5% for wastage

0.75 cwt cement (50 Kg bags)

0.06 cubes sand

Labour

1½ days mason

2½ days U/Sk labourer

Scaffolding –Add 3% 000000000

Total 000000000

Rate per square

60
Item Description Rate Amount
60. 4” thick Hollow block masonry in cement and
sand mortar 1:5 with cavities unfilled.

Per square

10’ 0” x 10’ 0” area (size of each block 16” x 8” x


4”)

Materials

112 Hollow cement bricks

Allow 5% for wastage

0.40 cwt cement (50 Kg bags)

0.03 cubes sand

Labour

1 day mason

2 days U/Sk labourer

Scaffolding –Add 5% 000000000

Total 000000000

Rate per square

61
Item Description Rate Amount
61. Random Rubble masonry in cement mortar 1:5 in
foundation.
Per cube (14” thick)

Materials

1.30 cubes 6” – 9” rubble

7.25 cwt cement (50 Kg bags)

0.30 cube sand.

Water 100 gals

Labour

4 days mason

6 days U/Sk labourer

Rate per cube


62. Random Rubble masonry in cement mortar 1:5 in
superstructure.
Per cube (14” thick)

Materials

1.30 cubes 6” – 9” rubble

7.25 cwt cement (50 Kg bags)

0.30 cube sand.

Water 100 gals

Labour

4 ½ days mason

7 days U/Sk labourer

Scaffolding- Add 3% 000 0

Total 0 00

Rate per cube


Item Description Rate Amount
63. Pressed floor tiles bedded in ½“ cement mortar
62
1:2 and pointing in neat cement in ground floor.

Per square

Materials

225 pressed titles 8” 8”

Add 5% for wastage

1 ¼ cwt cement (50 Kg bags)

0.07 cubes sand

¼ lb wax polish

¼ lb coloured pigment

2 lbs cotton waste

Labour

4 days mason

4 days U/Sk labourer

½ day U/Sk labourer for polishing

Rate per square

63
Item Description Rate Amount

64. Glazed tiles fixed to walls including bedding in


cement mortar 1:2 and raking in ground floor.
(Specials measured separately)

Per square

Materials

400 glazed tiles 6” x 6”

Add 10% for wastage on cutting

2 ½ cwt cement (50 Kg bags)

0.11 cubes sand

1 lb white cement

Labour

4 days mason

4 days U/Sk labourer

¼ day U/Sk labourer for cleaning

Rate per square

64
Item Description Rate Amount

65. Terrazzo floor tiles on ½” thick cement and sand


1:2 in ground floor.

Per square

Materials

100 12” x 12” terrazzo tiles

Add 5% for wastage

1 ¼ cwt cement (50 Kg bags)

0.07 cubes sand

Coloured pigment (2 lbs)

½ lb wax polish

2 lb cotton waste

Labour

4 days mason

3 days U/Sk labourer

½ day U/Sk labourer (polishing)

Rate per square

65
Item Description Rate Amount

66. Timber framework for calicut pattern tile hip roof


in single storey building consisting of wall plate,
beam, ridge plate, rafters etc. (preservative
treatment to be measured separately)

Per 6.00 square

Materials

34.00 cu.ft timber

Add 10% for wastage

660 1.ft 2” x 1” reefers

Add 5% wastage

8 lb wire nails 6” long

2 lb wire nails 2” long

Labour

7 days carpenter

8 days U/Sk labourer

Total per 6.00 squares.

Rate per square

Item Description Rate Amount


66
67. Roof covering with calicut pattern clay tiles in
single storied building.
(Timber frame work & ride covering measured
separately)

Per 6.00 square

Materials

750 titles

Labour

3 days carpenter

3 days U/Sk labourer

Per 6.00 squares.

Rate per square


68. Timber framework for corrugated asbestos sheet
roof in single storey building
Per 3.60 sqrs.

Materials

13 ½ cu.ft timber purling

Add 10% for wastage

Labour

2 ½ days carpenter

3 days U/Sk labourer

Total per 3.60 squares.

Rate per square

67
Item Description Rate Amount
69. Roof covering with corrugated asbestos sheets
(timber frame work and ridge covering measured
separately).

Per 3.60 squares

Materials

420 sq.ft asbestos corrugated sheets.

72 Nos. roofing screws and washers.

Labour

1 day carpenter

2 days U/Sk labourer

Per 3.60 square

Rate per square


70. One layer half round clay titles over corrugated
asbestos roof covering.

Per square

Materials

650 half round clay tiles

Labour

2 days U/Sk labourer

Rate per square

68
Item Description Rate Amount
71. Asbestos close fittings ridging fixed complete
with roofing screws or bolts (hook)
Per 13’ 4” length
Materials
4 pairs ridges 3’ 8” long
16 roofing screws or bolts

Labour
¼ day carpenter
¼ day U/Sk labourer
Per 13’ 4” ridging

Rate per lft.


72. Ridging covering with calicut pattern ridge tiles
bedded in cement lime mortar 1:1:4
Per 12 lft ridging
Materials

9 ridge tiles

1/3 cwt cement (50 Kg bags)

0.02 cubes sand

15 lbs slaked lime

½ lb colouring powder

Labour

¼ day mason

¼ day U/Sk labour

Per 12 l.ft ridging

Rate per l.ft

69
Item Description Rate Amount
73. ¾” x9” high valance board fixed with brass
screws to ends of rafters (for tile roofing)
Per 100 l.ft
Materials
75.00 sq.ft 1” planks
Add 5% for wastage
70 Nos. 1 ½” brass screws

Labour
3 days carpenter
3 days U/Sk labourer
Scaffolding – Add 5% 0000
Total per 100 l.ft Total 0000

Rate per L.ft


74. ¾” x 9” high barge board fixed with brass screws
at 2’ 0” centres to sides of rafters.
Per 100 l.ft
Materials
75.00 sq. ft 1” thick planks
Add 5% for wastage
50 Nos. 1 ½ brass screws

Labour
3 days carpenter
3 days U/Sk labourer
Scaffolding – Add 5% 0000
Total per 100 l.ft Total 0000
Rate per L.ft

70
Item Description Rate Amount
75. ROOF PLUMBING
18 B.W.G. (1.2 mm) galvanised iron sheet valley
gutter 3’ 0” girth overall once bent with end laps
not less than 9” width including ¾” tongued and
grooved planks laid to slope and profile on timber
members.
Consider 15’ 0”
Materials
2 G.I sheet (8’ x 4’)
¼ gal wood preservative
0.10 cwt cement (50Kg bags)
0.05 cwt slaked lime
1.00 cu.ft sand
50.00 sq.ft planks
2 1bs 1 ¼” wire nails

Labour
(a). Fixing boarding and applying
wood preservative
1 day carpenter
1 day U/Sk labour

(b). Making & fixing G.I sheets


½ day tinker
½ day U/Sk labourer

(c). Building sides-


¼ day mason
½ day U/Sk labourer
Total per 15.00 L.ft
Rate per L.ft
Item Description Rate Amount

71
76. 18 B.W.G. (1.2 mm) galvanised iron flashing 1’
6” girth overall 3 times bent with end laps not
less than 6”, lead soldered, turned and tucked up
to not less than 6” into chase cut in wall and
printed in cement mortal 1:2 lower and dressed
over roof covering not less than 1’ 0” wide.

Consider 15’ 0” L.ft

Materials

1 G.I. sheet 8’ x 0” x 4’ 0”

0.05 cwt cement (50 Kg bags)

1.00 cu.ft sand

1 lb soldering lead

Labour

Cutting bending, soldering & fixing

½ day tinker

1/3 day mason (caulking)

¾ day U/Sk labourer

Total per 15.00 L.ft

Rate per L.ft

72
Item Description Rate Amount
77. ......... framework for 4’ 0” x 4’ 0” flat asbestos
ceiling (sheet measured separately), Comprising
of 4” x 2” joists and 2” x 2” bearers in class I
timber.

Per 1.95 square

Materials

8.00 cu.ft timber class I

1 Lb 2” nails

26 Nos. fibre/ plastic plugs

25 lbs cement

2.00 cu.ft sand

2” brush- ¼ use

1/3 gal tar rap

Labour

2 ½ days carpenter

½ day mason

1 ½ days U/Sk labourer

Total per 1.95 square

Scaffolding – Add 3% 0000

Total 0000

Rate per square

73
Item Description Rate Amount
78. Horizontal ceiling lining using 4’ 0” X 4’ 0” flat
asbestos cement sheets fixed with and including
beading and cove mouldings on timber
framework. (Timber framework & painting
measured separately).

Per 1.95 square

Materials

210 sq. ft flat asbestos sheets 60 l.ft 2” x 2”


halmilla cove mouldings

125 l.ft 1 ½“ x ½” halmilla beadings

¼ lb – ¼” clout nails

8 doz 1 ½” brass screws

Labour

1 ½ days carpenter

2 days U/Sk labourer

Scaffolding -Add 3% 0000

Total - 0000

Total for 1.95 square 9

74
Item Description Rate Amount
79. ¾” thick tongued and grooved Lunumidella
ceiling boards fixed horizontal on 4” x 2” class I
timber joists at 2’ 0” centres with 1 ½” brass
nails.

Consider room 15’ 0” x 13’ 0” ie 1.95 sqrs.

Materials

115 L.ft 4” x 2” timber joists


215 sq.ft 6” x ¾ Lunumidella
Ceiling planks.
3 Lbs cement
4.00 cu.ft sand
4 Kg. 1½“ brass nails

Labour
Making holes, fixing joists & making good-
1 day mason
1 day carpenter
3 days U/Sk labourer

Fixing ceiling boards


3 days carpenter
4 days U/Sk labourer
Scaffolding – Add 3%
Total per 1.95 sqrs. 0000
Total 0000

Rate per square.

75
Item Description Rate Amount
80. ¾” x 6” wide tongued and grooved Lunumidella
ceiling boards fixed to underside of roof rafters,
(existing) with 1 ½” brass nails including
levelling with timber strips where necessary.
Consider room 15’ 0” x 12’ 0”

1.80 squares.

Materials

220.00 sq.ft ceiling planks

40.00 l.ft 2” x ¼” timber strips

2.00 Kg. ¾” nails

4.00 kg 1 ½” brass nails.

Labour

3 days carpenter

6 days U/Sk labourer

Scaffolding –Add 3% 0000

Total 0000

Total per 1.80 sqrs.

Rate per square.

76
Item Description Rate Amount
81. Door single hung 3’ 3” x 7’ 0” high overall with
frame having 1 ¼“ thick sash and 3 ¾” X 2 ¾”
timber frame. ( glazing, ironmongery & painting
measured separately)
Per 22.75 square feet (3’ 3” x 7’ 0” )

Materials

(a). Frame-

1 ½ cu.ft 4” x 3” timber

2 No. spur stones

6 No. fibre/plastic plugs

With 4” long brass screws.

2 No. 5/8” mild steel dowels 4” long.

(b). Sash-

14 sq.ft 1 ½ planks

5 sq.ft 1” planks

Labour

5 days carpenter

1 ½ days U/Sk labourer

Total per 22.75 sq.ft

Rate per square foot

77
Item Description Rate Amount
82. Door glazed and panelled double hung 4’ 0” x
7’0” high overall with frame including 1 ¼” thick
sash and 3 ¾” x 2 ¾” frame. (glazing,
ironmongery and painting measured separately)
Per28.00 square feet (4’ 0” x 7’ 0”)

Materials

(a). Frame

1 2/3 cu.ft 4” x 3” timber

2 No. spur stones

6 No. fibre/plastic plug with

4” long screws

2 Nos. 5/8” dia mild steel

dowels 4” long.

(b). Sashes

6 days carpenter

2 days U/Sk labourer

Total for 28.00 sq.ft

Rate per square foot

78
Item Description Rate Amount
83. Plywood door single hung 3’ 1 ½ “ x 6’ 1 ½ “
overall with frame having 1 ¼” thick sash and 3
¼” x 2 ¾” frame. (Ironmongery and painting
measured separately)
Per 21.75 square feet (3’ 1 ½” x 6’ 1 ½”

Materials

(a). Frame

1.80 cu.ft 4” x 3” timber

2 No. spur stones

6 No. fibre/Plastic plugs with

4” long brass screws.

(b). Sash-

1 No 6’ 9” x 2’ 9” plywood sash

Labour

3/4 day carpenter

3/8 day U/Sk labourer

1/4 day mason (fixing frame)

1/4 day U/Sk labourer (- do - )

Total per 21.75 square feet.

Rate per square foot

79
Item Description Rate Amount
84. Door ledged, braced and battened single hung
2’6” x 6’6” overall, with frame having 7/9” thick
tongued & grooved planks and 3 ¾” x 2 ¾”
frame. (Ironmongery and painting measured
separately)
Per 16.25 sq.ft (2’ 6” x 6’ 6”)

Materials

(a). Frame-

1.70 cu.ft 4” x3” timber

2 No spur stones

6 No fibre/plastic plugs

with 4” long brass screws

2 No 5/8” mild steel dowels

4” long.

(b). 21.00 sq.ft 1” thick planks

3 doz 1 ¼ long brass screws.

Labour

2 ¼ days carpenter

1 day U/Sk labourer

¼ day mason (fixing frame)

¼ day U/Sk labourer (- do- )

Total per 16 ¼ sq.ft

Rate per square foot

Item Description Rate Amount

80
85. Window, glazed 7’ 0” x 4’ 0” high overall with
frame comprising 3 No openable sashes and 3
¾” x 2 ¾” frame and mullions.
(Glazing , ironmongery and painting measured
separately)

Per window

7’ 0” x 4’ 0” (sashes) ie per 28.00 sq.ft

(a). Frame-

3.20 cu.ft 4” x 3” timber

4 No fibre/plastic plugs with

4” long brass screws

(b). Sashes-

9.25 sq.ft 3” x 1 ½ “ timber

Labour

6 days carpenter

2 ½ days U/Sk labourer

½ day mason (fixing frame)

½ day U/Sk labourer (-do-)

Total per 28.00 sq.ft

Rate per square foot

81
Item Description Rate Amount
86. 1/6” clear sheet glass panes exceeding 1’ 0” but
not exceeding 4 square feet cut and fixed with
timber beadings to doors and windows.

Consider sash 3’ 0” 4’ 0” high with 3” 1 ¼” style


and 4 Nos. glass panes.

Per 9.00 sq.ft

Materials

9.00 sq. ft glass panes

30 L.ft ½” x ½” beading

4 doz brass panel pins

Labour

½ day glazier

½ day U/Sk labourer

Total per 9.00 sq.ft

Rate per square foot

82
Item Description Rate Amount

87. IRONMONGERY

Btt hinges5” x 2 ½”

Materials

1 ½ pairs butt hinges

2 doz ¾” brass screws

Labour

¼ day carpenter

¼ day U/Sk labourer

Per 1 ½ pairs.

Rate per pair

88. Tee hinges 6” x 12”

Materials

1 pair Tee hinges

1 ½ doz ¾” iron screws

Labour

2 hrs carpenter

2 hrs U/Sk labourer

Rate per pair

83
Item Description Rate Amount
89. Rim lock
Materials
1 rim lock with screws

Labour
2 hrs carpenter
2 hrs U/Sk labourer

Rate per No.


90. Mortice lock
Materials
1 mortice lock with screws

Labour
½ day carpenter
½ day U/Sk labourer

Rate per No.


91. Casement stays.
Materials
4 casement stays
16- ½“ brass screws
Labour
2hrs carpenter
2 hrs U/Sk labourer
Total for 4 No.
Rate per No.

84
Item Description Rate Amount
92. Door closer (Hydraulic)

Materials

1door closer

8-3/4” brass screws

Labour

2 hrs carpenter

2 hrs U/Sk labourer

Rate per No.


93. Tower/skeleton brass bolts.

Materials

1 Tower/ skeleton bolt

10 – ½“ brass screws

Labour

½ hr carpenter

½ hr U/Sk labourer

Rate per No.


94. Barrel bolt 4”

Materials

1 barrel bolt

8-1/2” brass screws

Labour

½ hr carpenter

½ hr U/Sk labourer

Rate per No.

85
Item Description Rate Amount
95.
Casement fasteners

Materials

6 casement fasteners
24-1/2” brass screws

Labour

½ day carpenter
½ day U/Sk labourer

Total per 6 Nos.

Rate per No.


96.
Spring loaded fanlight catches.

Materials

6 brass fanlight catches

2 doz ½“ brass screws

Labour

½ day carpenter

½ day U/Sk labourer

Total for 6 Nos.

86
Item Description Rate Amount
97. Draw rings

Materials

6 draw rings

1 doz ½” brass screws

Labour

1 hr carpenter

1 hr. U/Sk labourer

Total for 6 Nos.

Rate per No.


98. ¾” thick DPC, in cement sand 1:2 finished with 2
coats hot tar and blinded with sand.
Per square

Materials

2.25 cwt cement

0.11 cube sand

1 ½ gals bitumen

firewood (10 lbs)

Water 10 gals

Labour

1¼ days mason

2½ U/Sk labourer

Rate per square

87
Item Description Rate Amount
99. 5/8” thick plastering to wall in lime and sand 2:5
including floating with lime putty.
Per square

Materials

1.30 cwt slaked lime


0.07 cubes sand
water 10 gals

Labour

1 day mason-
1 ¾ days U/Sk labourer
Scaffolding –Add 3% 0000
Total 0000

Rate per square


100. 5/8” thick plastering to wall in cement sand 1:3
including cement floating
Per square
Materials
1.40 cwt cement (50 Kg bags)
0.06 cube sand
Water 10 gals

Labour
1 day mason
1 ½ days U/Sk labourer
Scaffolding – Add 3% 0000
Total 0000

Rate per square

88
Item Description Rate Amount
101. 3/8” thick plastering to soffit of slab in cement
and sand 1:3 including floating with lime putty.
Per square
Materials

0.80 cwt cement (50kg bags)

0.16 cwt slaked lime

0.03 cubes sand

Water 5 gals.

Labour

2 ½ days mason

2 ½ days U/Sk labourer

Scaffolding- Add 3% 0000


Total 0000
Rat per sqr.
102. 3/8” thick plastering to sides and soffit of beams
in cement and sand 1:3 including floating with
lime putty.
Materials

0.80 cwt cement (50 Kg bags)

0.16 cwt slaked lime

0.03 cube sand

water 5 gals

Labour

2 day mason

2 days U/Sk labourer

Scaffolding –Add 3% 0000


Total 0000
Rate per square

89
Item Description Rate Amount
103. 5/3” thick plastering to wall in lime cement and
sand 1:1:5 finished semi-rough with wooden
float.
Per square
Materials

0.80 cwt cement (50 Kg bags)


0.40 cwt slaked lime

0.07 cubes sand

Water -10 gals

Labour
1 days mason

1 ½ days U/Sk labourer

Scaffolding –Add 3% 0000

Total 0000
Rate per square
104. 5/3” thick plastering to wall in lime cement and
sand 1:1:5 finished smooth with lime putty
floating.
Materials
0.80 cwt cement (50 Kg bags)

0.60 cwt slaked lime

0.07 cubes sand

Water (10 gals)

Labour
1 ½ days mason

1 ½ days U/Sk labourer

Scaffolding –Add 3% 0000


Total - 0000

Rate per square Ra

90
Item Description Rate Amount
105. ½” thick rendering in cement and sand 1:3
finished smooth.
Per square

Materials

1.07 cwt cement (50Kg bags)

0.05 cube sand

Water 10 gals

Labour

1 day mason

1 ½ days U/Sk labourer (curing)

¼ day U/Sk labourer (Curing)

Rate per square


106. ½” thick rendering in cement and sand 1:2 in
floors, finished sooth.
Per square

Materials

1.50 cwt cement (50 kg bags)

0.05 cubes sand

Water 10 gals.

Labour

1 day mason.

1 ½ days U/Sk labourer

¼ day U/Sk labourer (curing)

Rate per square

91
Item Description Rate Amount
107. ¾” thick rendering in cement and sand 1:3
finished smooth.

Per square

Materials

1.75 cwt cement (50 kg bags)

0.08 cube sand

Water 10 gals

Labour

1 ¼” days mason

2 days U/Sk labourer

¼ day U/Sk labourer (curing)

Rate per square


108. ¾” thick rendering in cement and sand 1:2 in
flooring finished smooth.
Per square
Materials
2.25 cwt cement (50 kg bags)
0.08 cubes sand
Water 10 gals

Labour
1 ¼ days mason
2 day U/Sk labourer
¼ day U/Sk labourer (curing)

Rate per square

92
Item Description Rate Amount
109. ¾” thick rendering in cement and sand 1:2 in
coloured cement floors finished smooth.
Per square
Materials
2.25 cwt cement (50 kg bags)
0.08 cubs sand
5 lbs powdered pigment
Water 10 gals

Labour
1 ¼ days mason
2 day U/Sk labourer
¼ day U/Sk labourer (curing)

Rate per square

110. ½” 6” skirting in cement and sand 1:3 projected


or flush to walls finished with floating including
forming groove.
Per 10.l.ft
Materials
0.10 cwt cement (50Kg bags)
0.003 cube sand
0.25lbs powdered pigment

Labour
3/8 day mason
5/16 U/Sk labourer

Total per 10 l.ft


Rate per l.ft.

NOTE: Where coloured skirting is not required,


delete provision for powdered pigment.

93
Item Description Rate Amount
111. Prepare and apply one coat of preservative (oil
type) to structural timber including touching up
cut ends etc. after fixing.
Per one square
Materials
2.75 ltr. wood preservative (oil type)
3” brush (1/10 use)

Labour
¾ day painter
½ day U/Sk labourer

Rate per square

112. Prepare surface of steel truss and apply two


coats of anti-corrosive primer.
Consider one square
Materials
2 ¼ ltr. Anti-corrosive primer 0.15 ltr. Mineral
turpentine or thinner.
1 wire brush
2” brush (1/3 use)

Labour
1 ½ day painter
1 ½ day U/Sk labourer

Rate per square

94
Item Description Rate Amount
113. Apply one coat of anti-corrosive primer and two
coats enamel paint on already shop primed and
erected steel roof truss.
Consider one square
Materials
0.20 ltr. anti-corrosive primer
1 1/3 ltr. enamel paint
0.20 ltr. Mineral turpentine or thinner.
2” brush (1/5 use)

Labour
2 ½ days painter
1 day U/Sk labourer
Scaffolding –Add 3% 0000
Total 0000

Rate per square


114. Prepare and apply two coats primer and finishing
coat of enamel paint to mild steel (angle/ flat)
gate.
Consider 50 sq.ft
Materials
1 ½ ltr. anti-corrosive primer
2/3 ltr. enamel paint
0.20 ltr. mineral turpentine or thinner
½ wire brush
2” brush (1/5 use)

Labour
½ day painter
¾ day U/Sk labourer
Total per 50 sq.ft

Rate per square

95
Item Description Rate Amount
115. Painting steel on new work with 2 coats of anti-
corrosive paint
Per square
Materials
2/3 ltr. anti-corrosive paint
2” brush (1/5 use)

Labour
1 ½ days painter

Rate per square


116. Painting new timber work with two coats wood
preservative.
Materials
½ gal wood preservative
2” brush (1/5 use)

Labour
½ day painter

Rate per square


117. Preparing and painting wood work with primer
and 2 coats enamel paint.
Per square
Materials
¾ ltr. primer
2.50 ltr. enamel paint (2 coats)
2” brush (1/10 use)
2 sand papers

Labour
1 ½ days painter
½ day U/Sk labourer
Rate per square

Item Description Rate Amount

96
118. White or colour washing two coats in single
storey.
Per 10 squares
Materials
0.50 cwt. boiled lime
2 lbs salt
½ lb yellow ochre
2 oze blue
6” brush (1/3 use)
Water 10 gals

Labour
2 ½ days painter
2 ½ days U/Sk labourers
Scaffolding –Add 3%

Total per 10.00 squares 000


Total 000

Rate per 10.00 squares

119. White or colour washing two storied building.


Per 10 squares
(As per 10 squares)
Add ½ day painter
½ day U/Sk labourers

Scaffolding –Add 3%
000
Total 000

Rate per 10.00 squares

97
Item Description Rate Amount
120 Prepare and apply one coat of Alkali resistant
primer and two coats of emulsion paint to walls.
Per square
Materials
Primer 90 ltr. primer
1.40 ltr. emulsion paint
Water 0.10 gals
6” brush(1/10 use)
2 sand papers

Labour
1 ¼ day painter
scaffolding -Add 3% 000
Total 000

Rate per 10.00 squares


121. Cement washing to walls of single storied
building 2 coats
Per 10 square
Materials
5/8 cwt cement
1-6” coir brush
Water 5 gals

Labour
2 days painter
2 days U/Sk labourer
Scaffolding-Add 3 %
Total per 10.00 sqrs. 0000
Total 0000
Rate per 10.00 squares

98
Item Description Rate Amount
122. Painting walls with emulsion paint (2 coats)

Per square

1st Coat – 1/6 gal emulsion paint


2nd Coat - 1/7 gal emulsion paint
6” brush – (1/10 use)
0.10 gals water

Labour
¾ day painter
Scaffolding –Add 3% 0000
Total 0000

Rate per squares

123. Prepare and apply one coat alkali resistant


primer and two coats of emulsion paint to soffit
of slabs.
Consider 100 sqrs.
Materials
.90 ltr. primer
1.50 ltr. emulsion paint
6” brush (1/10 sue)
Labour
1 ¾ days painter
scaffolding –Add 3% 0000
Total 0000
Rate per square

99
Item Description Rate Amount
124. Varnishing two coats with copal varnish after
sandpapering.
Per square
0.40 gals (1.80 ltr.) varnish
3” brush (1/3 use)
2 No sand paper

Labour
½ day painter
½ day U/Sk labourer

Rate per square

125. Wax polishing to timber in panels & floors.


Per square
Materials
¾ lb. wax polish
½ doz. sheets sandpaper
1/10 floor brush
½ yards flannel cloth

Labour
3hrs. U/Sk labourer

Rate per square

100
Item Description Rate Amount
126. PLUMBING – PVC PIPES
½” diameter PVC pipes fixed to walls (specials
paid separtely)
Per 10 L.ft
Materials
13 L.ft pipes
3 clips and rails
2 grams solvent cement

Labour
1 hr. plumber
1 hr U/Sk labourer
Total per 10. CO L.ft

Rate per L.ft

127. ¾” dia meter PVC pipes to walls (specials paid


separately)
Per 10 L.ft
Materials
13 L.ft pipes
3 clips and nails
3 gram. solvent cement

Labour
1 hr. plumber
1 hr. U/Sk labourer

Total per 10 L.ft

Rate per L.ft

101
Item Description Rate Amount
128. 1” dia meter PVC pipes fixed to walls (specials
paid separately)

Per 100 L.ft


Materials
100 L.ft pipes
Add 5% for wastage
8-1” dia sockets
32 grms. solvent cement
35 clips and nails

Labour
½ day plumber
½ day U/Sk labourer
Total per 100 L.ft

Rate per L.ft


129. 1 ¼” dia meter PVC fixed to walls (specials paid
separately)
Per 100 Lft
Materials
100 L.ft pipes
Add 5% for wastage
8-1 ¼” dia sockets
48 grms solvent cement
35 clips and nails

Labour
¾ day plumber
¾ day U/Sk labourer
Total per 100 L.ft

Rate per L.ft

102
Item Description Rate Amount
130. 1 ½“ dia meter PVC pipes laid to walls (specials
paid separately)
Per 100 L.ft
Materials
100L.ft pipers
Add 5% for wastage
8- 1 ½” dia sockets
64 grms solvent cement
35 clips and nails

Labour
¾ day plumber
¾ day u/Sk labourer
Total per 100 L.ft

Rate per L.ft


131. 2” dia motor PVC pipes laid to walls (specials
paid separately)
Per 100 L.ft
Materials
100 L.ft pipes
Add 5% for wastage
8 – 2” dia sockets
35 clips and nails
112 grams solvent cement

Labour
¾ day plumbers
¾ day U/Sk Labourer
Total per 100 L.ft

Rate per L.ft


Item Description Rate Amount
132. 3” dia meter PVC pipes fixed to walls (specials
103
paid separately)
Per 100 l/ft
Materials
100L.ft pipe
Add 5% for wastage
8-3” sockets
200 grms. solvent cement
35 clips and screws

Labour
1day plumber
1 day U/Sk labourer
Total per 100 L.ft

Rate per L.ft

133. Excavation for laying ½” to 3” dia meter PVC


pipes in ground not less than 1”-6” deep, back
filling & compacting.
Per 100 L.ft
Labour
2 ¼ days U/Sk labourer
Total per 100 L.ft

Rate per L.ft

104
Item Description Rate Amount
134. Chasing brick for laying ½” to 1 ½” dia PVC
pipes and making good average depth 2” (pipes
and specials paid separately)
Per 100 l.ft
Materials
0.10 cwt cement
0.01 cubes sand

Labour
3 days mason
3 days U/Sk labourer
Total for 100 L.ft

Rate per L.ft


135. Chasing brickwork for laying 1 ½” to 3” dia PVC
pipes in ground or floor and making good.
Average depth 3” (pipes & specials measured
separately)
Per 100 L.ft
Materials
0.20 cwt cement
0.03 cubes sand

Labour
3 ½ days mason
3 ½ days U/Sk labourer
Total per 100 L.ft

Rate per L.ft

105
Item Description Rate Amount
136. ½” dia PVC specials viz-elbows/ bends/sockets.
Per 10 specials
Materials
10-1/2” elbows/bends/socket
20 grms solvent cement

Labour
2 hrs plumber
Total per 10 No.

Rate per No.


137. ¾“dia PVC specials viz elbows/ bends/sockets.
Per . . . .. .
Materials
10 -3/4” dia elbows/bends/sockets
30 grms solvent cement.

Labour
2 hrs. plumber
Total per 10 No.

Rate per No.

106
Item Description Rate Amount
138. 1“ dia PVC specials viz elbows/ bends/sockets.
Per 10 specials
Materials
10 -1” dia elbows/bends/sockets
40 grms solvent cement.

Labour
2 hrs. plumber
Total per 10 No.

Rate per No.

139.
1 ¼” dia PVC specials viz-elbows / bends
/sockets.
Per 10 specials

Materials

10 No. 1 ¼” dia elbows/bends/sockets.

60 grms solvent cement.

Labour

2 hrs plumber

Total for 10 No.

Rate per No.

107
Item Description Rate Amount
140. 1 ¼” dia PVC specials viz-elbows / bends
/sockets.
Per 10 specials

Materials

10 No. 1 ¼” dia elbows/bends/sockets.

60 grms solvent cement.

Labour

2 hrs plumber

Total for 10 No.

Rate per No.

141.
2” dia specials viz-elbows / bends /sockets.
Per 10 specials

Materials

10 -2” dia elbows/bends/sockets.

140 grms solvent cement.

Labour

½ day plumber

Total for 10 No. specials

Rate per No.

108
Item Description Rate Amount
142.
2” dia PVC specials viz-elbows / bends /sockets.
Per 10 specials

Materials

10 -2 1/2” dia elbows/bends/sockets.

200 grms solvent cement.

Labour

½ day plumber

Total for 10 No. specials

Rate per No.


143.
3” dia PVC specials viz-elbows / bends /sockets.
Per 10 specials

10 - 3” dia elbows/bends/sockets.

240 grms solvent cement.

Labour

½ day plumber

Total for 10 No. specials

Rate per No.

109
Item Description Rate Amount

144. ½” dia PVC specials viz. tees.

Per 10 Tees

Materials

10- ½” tees

30 grms solvent cement

Labour

½ day plumber

Total for 10 No. tees

Rate per No.


145.
¾” dia PVC specials viz. Tees
Per 10 Tees

Materials

10 No.3/4” dia tee

45 grms solvent cement

Labour

½ day plumber

Total for 10 No. Tee

Rate per No.

110
Item Description Rate Amount
146.
1” dia PVC specials viz-Tees
Per 10 Tees

Materials

10 -1” dia Tees

60 grms solvent cement

Labour

½ day plumber

Total for 10 No. Tees

Rate per No.

147.
1 ¼” dia PVC specials viz Tees
Per 10 Tees

Materials

10-1 ¼” dia Tees

go grms solvent cement

Labour

½ day plumber

Total for 10 No. Tees

Rate per No.

111
Item Description Rate Amount
148.
1 ½” dia PVC specials viz Tees
Per 10 Tees

Materials

10 - 1 ½” dia Tees

120 grams solvent cement

Labour

1 day plumber

Total for 10 No. Tees

Rate per No.

149.
2” dia PVC specials viz Tees
Per 10 Tees

Materials

10 – 2” dia Tees

210 grms solvent cement

Labour

1 day plumber

Total for 10 No. Tees

Rate per No.

112
Item Description Rate Amount

150. 2 ½” dia PVC Specials viz Tees


Per 10 Tees

Materials

10- 2 ½” dia Tees

300 grms solvent cement

Labour

1 ½ days plumber

Total per 10 No. Tees

Rate per No.

151. 3” dia PVC specials viz Tees


Per 10 Tees

Materials

10-3” dia Tees

360 grms solvent cement

Labour

1 ½ days plumber

Total for 10 No. Tees

Rate per No.

113
Item Description Rate Amount

152. 4” dia glazed earthenware pipes laid on 6” thick


bedding in cement concrete 1:3:6

(1 ½”) including excavation average 2’0” depth,


back filling with selected excavated materials and
concrete hunching to joints.
Per100 L.ft

Materials

50 – 4 “ dia EW pipes

0.75 cubes cement concrete – 1:3:6 (1 ½”)

2 lbs yarn

0.50 cwt cement (jointing)

4.00 cubes excavation

Labour

Laying concrete bedding

1 ½ day U/Sk labourer

Laying and testing pipes

2 days plumber

2 days U/Sk labourer

Backfilling –

2 ½ days U/Sk labourer

Total for 100 L.ft

Rate per L.ft

114
Item Description Rate Amount

153. 4” dia C.I. soil/vent pipe fixed vertically to walls


jointed with cement caulking. (Specials measured
separately)

Per 6’ 0” length

Materials

6’ 0” L.ft 4” dia C.I. pipe

Add 10% for wastage

5/16 lbs yarn

1- timber plug 6” x 6” x 2”

2- 3” iron screws

2lbs cement

Labour

¼ day plumber

¼ day U/Sk labourer

Scaffolding – Add 5%

Total for 6 L.ft 0000

Total 0000

Rate per L.ft

115
Item Description Rate Amount

154. 4” dia C.I. pipes fixed to walls jointed with lead


caulking. (Specials measured separately)

Per 6’ 0” length

Materials

6’ 0” L.ft 4” dia C.I. pipe

(Add 10% for wastage)

6 lbs lead

5/16 lbs yarn

1 wood plug 6” x 6” 2”

2-3” iron screws

1/16 cwt firewood

Labour

¼ day plumber

¼ day U/Sk labourer

Add 10% for sundries in cement and sand

Scaffolding – Add 5% 0000

Total 0000

Rate per L.ft

116
Item Description Rate Amount

155. 4” dia stoneware gulley with 6” x 6” x 6” gulley


box including excavation, 4” cement concrete 1:
2: 4 (3/4”) base, surrounded by 4 ½” thick
brickwork in cement and sand 1:5 extended 6”
above top of gulley box including making
connection, ½” cement and sand 1:2 rendering
internally and exposed faces finished smooth
with neat cement floating and providing G.I.
grating on top of gully.

Per No.

Materials

1-4” S.W. gulley

4.00 cu.ft. excavation

5.50 sq.ft 4 ¼” brickwork

0.80 cu.ft cement concrete

1:2:4 (3/4”)

1.00sq.ft ½” cement rendering 1:2

1-4” G. I. grating.

Labour

¼ day mason

¼ day U/Sk labourer

Rate per L.ft

117
Item Description Rate Amount

156. Manhole 2’ 0” x 2’ 0” internally with invert depth


not exceeding 2’0” including excavation,
backfilling 6” cement concrete 1:2:4 (3/4”) base
with 3/8” dia meter mild steel rods at 4” centres
both ways, forming channels and benching in
similar concrete, 4 ½” walls in brick in cement
1:5, ½” thick cement and sand 1:2 rendering
internally and exposed surfaces including
channels, benching and 2” thick RCC removable
cover slab 2’3”x2’3” inlet and outlet connection
all complete to working order.

Materials

35.00 cu.ft excavation

7.00 cu.ft cement concrete

1:2:4:(3/4”) in base & channels

33.00 sq. ft 4 ½” brickwork in cement 1:5

28.00 sq.ft ½” cement rendering 1:2

1-Rcc cover slab.

Labour

1 ½ days mason

2 ½ days U/Sk labourer

Rate per No.

118
Item Description Rate Amount

157. 22” x 16“ glazed fireclay wash basin with ½” dia


chromium plated pillar tap, waste plug,
chromium plated waste chin and stay, including
fixing wash basin on brackets, (water supply and
waste water connection measured separately)

Per No.

Materials

1 wash basin complete with brackets

1-1/2” tap

Waste plug and chain

4 wooden plugs

6 – 1 ½” brass screws

2 lbs cement

Labour

½ day mason

1 day U/Sk labourer

Rate per No.

119
Item Description Rate Amount

158. Sink 24” x 15” X 7” overall vitreous China with


rubber plug and chromium plated chain waster
carried on iron brackets painted and fixed to
walls. (water supply and waste water connection
measured separately)

Per No.

Materials

1 sink 24”x 15” x 7”

2 L iron brackets

2 lbs cement

2 tapered wooden blocks 2” thick

8-1 ½” dia brass screws

Labour

½ day mason

½ day U/Sk labourer

Rate per No.

120
Item Description Rate Amount

159. Closet pedestal type with L/L flushing cistern,


flush pipe double plastic seat cover, ½” dia stop
cock, trap supplied & fixed complete to working
order

Per No.

Materials

1 low level suite complete

1- ½” dia stop cock

2 lbs cement

¼ cu.ft sand

2-1 ½” brass screws

Labour

¼ day mason

1 day plumber

1 day U/Sk labourer

Rate per No.

121
Item Description Rate Amount

160. Closet squatting type with trap including high


level cistern fixed complete with flush pipe and
½” dia stop cock, all complete to working order

Per No.

1 squatting pan with trap

2 gals C.I. cistern with 1 ¼” flush,

pipe, chin and overflow pipe

1 clip

5 wooden plugs

1dos. 1 ½” brass screws

1-1/2” stop cock

¼ cwt cement

½ cu.ft metal

¼ cu.ft sand

Labour

½ day mason

1 day plumber

1 day U/Sk labourer

Rate per No.

122
Item Description Rate Amount
161. Vitreous China bidet suite fixed complete to
working order
Per No.
Materials
1 bidet

Labour
1 day plumber
1 day U/Sk labourer

Rate per No.


162. 4 No. Bowl type urinal with trap and 2 gals
capacity automatic flushing cistern and spreaders
complete to working orders.
Materials
4 Urinal Bowls
1 – 2 gal. cistern
8 rawl plugs
1 spreader
4 wooden plugs (for cistern)
4 – 1 ½” brass screws
4 lbs cement
1/8 cu.ft sand

Labour
¼ day mason
1 day plumber
1 day U/Sk labourer
Total per 4 No.
Rate per No.

Item Description Rate Amount

163. 6” dia half round PVC eaves gutter fixed to

123
timber valance board including gutter joiner and
brackets fixed at 18” centres. (Other specials
paid separately)

Consider 24.00 L.ft

Materials

2-6” dia eaves gutter lengths

1 joiner

17 gutter brackets

34-3/4” brass screws

20 grms solvent cement

Labour

½ day plumber

½ day U/Sk labourer

Scaffolding Add 5% 0000

Total per 24.00 L.ft Total 0000

Rate per 24.00 L.ft

124
Item Description Rate Amount

164. 6” dia PVC gutter head

Consider 1 No. gutter head

Materials

1 PVC gutter head

2 gutter joiners

2 gutter brackets

12 grams solvent cement

4-3/4” brass screws

Labour

1/8 day plumber

1/8 day U/Sk labourer

Scaffolding Add 5% 0000

tt Total 0000

Rate per No.

125
Item Description Rate Amount

165. 6” dia PVC mitres consider 1 No. mitre

Materials

1 mitre hand

2 gutter joiners

2 brackets

12 grms solvent cement

4-3/4“ brass screws

Labour

1/8 day plumber

1/8 day U/Sk labourer

Scaffolding – Add 5% 0000

Total 0000
Rate per No.

166. 6“ dia PVC and caps consider 1 No. end cap.

Materials

1 No. end cap

12 grms solvent cement

Labour

1/16 day plumber

1/16 day U/Sk labourer

Scaffolding – Add 5 % 0000

Total 0000

Rate per No.

Item Description Rate Amount


167. 3 ½” dia PVC rain water down pipe fixed to brick
126
wall with wooden plugs buried in wall.
(Specials measured separately)
consider 24 L.ft pipe length
Materials
2-3 ½” dia pipe lengths
1-3 ½” joiner
4 PVC straps
8 brass screws 1” long
30 grms solvent cement

Labour
1/3 day plumber
1/3 day U/Sk labourer
Scaffolding- Add 5% 0000
Total 0000
Rate per 24” 0’ L.ft
Rate per L.ft
168. 3 ½” dia PVC elbow
Materials
1-600 /800 elbow
32 grams solvent cement
Labour
1/16 day plumber
1/16 day U/Sk labourer
Scaffolding – Add 5% 0000
Total 0000
Rate per No.

127
Item Description Rate Amount

169. 3 ½” dia PVC shoe

Materials

1-600 /800 shoe


15 grms solvent cement

Labour
1/16 day plumber
1/16 day U/sk labourer

Rate per No.

128

You might also like