The daily checklist provides instructions for plastering work at a construction site. It outlines key steps to check (1) before plastering such as reviewing drawings and safety measures, (2) during plastering like platform setup, thickness measurements, and material quality controls, and (3) after plastering like curing and crack/hollowness inspections. The checklist aims to ensure the plastering work meets quality standards at various stages from preparation through completion.

Uploaded by

byleekk
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
400 views2 pages

Checklist

The daily checklist provides instructions for plastering work at a construction site. It outlines key steps to check (1) before plastering such as reviewing drawings and safety measures, (2) during plastering like platform setup, thickness measurements, and material quality controls, and (3) after plastering like curing and crack/hollowness inspections. The checklist aims to ensure the plastering work meets quality standards at various stages from preparation through completion.

Uploaded by

byleekk
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 2

Daily Checklist for Plastering

Project : Doc. No. : QA/CL-MSN/


Client : Project Location :

SITE LOCATION DATE

YES NO NA
BEFORE PLASTERING

Check Drg./ Number/ Date & Revision for all other service like electrical,
1 plumbing etc.,

2 Safety access platform

3 Check for hacking/ Button marking / Mortar thickness

4 Provision of chicken mesh for conduits, column brick work joints & other

5 Preparation of Surface - Remove moss/ efflorescence & Dampen Surface

6 Material stacked - Cement, sand at various locations

7 Prewetting of surface

8 Quality of Sand - screening silt

9 Check the Beam, B/W joints packing with Nito Bond AR

10 check for Door Frame Projections


DURING PLASTERING
1 Platform for mortar mixing on tray

2 Check for thickness/ level & line & right angle

3 Proportion of mix

4 Addition of water proofing compound

5 Proper roughing of first coat

6 Check for collection of mortar spills

7 Cleaning of dead mortar

8 Check for waviness

9 Check for grooves/ drip moulds


Application of cement slurry on concrete surface/Space for tile area, cutting
10 for skirting area

11 Check for loft thickness and top surface in dead level W/Robe size

AFTER PLASTERING
1 Curing water distribution for various locations

2 Check for hollowness

3 Check for cracks

4 Check of plastering date for curing

Remarks of Quality Assurance Engineer:

Signature Date Remarks/ Comments


Checked By:
Approved By:
B
Daily Checklist for Masonry

Project : Doc. No. : QA/CL-MSN/


Client : Project Location :

SITE LOCATION DATE

YES NO NA

1 Availbility of MATERIAL AS PER Daily requirement & test report

2 Cleaning work area off loose material/ concrete

3 Proper stacking of bricks/ blocks

4 Quality of bricks/ Sand. Test performed and ok? Note supplier.

5 Wetting of bricks. When?

6 Door frames if any erected in position?

7 Line out rechecked? Room dimension, diagonals, alignment with one


layer of bricks work, door opening position & verticality, etc

8 Check mortar preparation & provision platform.

9 Check mortar thickness

10 Check plumb

11 Check finished level, Rt angle/ Proportion of mix

12 Check hacking/ conduit/ silt contect in sand

13 Check cleaning of dead mortar

14 Check curing/ raking

15 Check for any addition & alterations

16 Check roof height front……….. & rear ………...

Remarks of Quality Assurance Engineer:

Signature Date Remarks/ Comments