Load Estimation Methods
Load Estimation Methods
Paper 0664
Paper 0664
have found it relatively easy to match the active power demand allocation was updated for each month in
component of the power flow to measured results. Of the simulation. This would be similar to a
course, the line and transformer impedances must be technique that allocates loads based on a
sufficiently accurate to account for the losses. It is often customer’s billing information from the previous
more difficult to calibrate the model to the measured year. The substation load is allocated to each
reactive power flow, particularly on feeders in the US customer in proportion to the specified monthly –
where it is common to have multiple switched power or other period – kWh usage. This technique
factor capacitor banks. Fortunately, it was straightforward distributes the kW loading more heavily to those
to match the reactive power characteristic for the test customers using more energy regardless of
circuit because it serves mostly residential loads. The service transformer size. One assumption inherent
power factor of each load was estimated to be 0.95 in this approach is that the heavier users will be
lagging and was assumed to be invariant for the duration the heavier users throughout the billing period,
of the simulation. By switching on local current the which is obviously not always true.
capacitor switching occurs quite naturally in the Class Loadshape Allocations – This is a method
simulation. Simulation difficulties with reactive power used in some distribution state estimation tools as
can arise when capacitors are controlled remotely or by well as distribution planning tools. It uses a
less deterministic quantities. combination of the transformer kVA size along
With a full 3-phase circuit model, all MV/LV with historical information about the type of load
transformers, and one LV line modelled for each of the being served. The historical load type information
metered loads, there are a total of 3107 electrical nodes in consists of various class loadshapes for customers
the test circuit. For the AMI case, there were 1779 unique based on season of the year, day of week, and
loadshapes, each with 16416 intervals. A full simulation
holidays. The class loadshape is used along with
requires approximately 4.5 min to execute on a typical
the measured substation demand data to develop
Windows-based modern laptop computer. Thus, this type
the loading level for each load. Knowledge of the
of analysis is not onerous when the data are available.
load class is required.
LOAD ALLOCATION METHODS
RESULTS
The load allocation methods used in this study were:
AMI Allocation – This is the reference method. The four load allocation methods were compared for
accuracy in the following three types of predictions:
It uses the actual kW demand interval
measurements for each customer. Each customer
1. Prediction of equipment loading
has a unique loadshape.
2. Prediction of service voltage magnitudes
For each of the loads with AMI, the 15-minute 3. Prediction of losses
average kW measurements were used directly to
define the demand value for each interval of the Equipment Loading Evaluation
simulation. The unmetered load values (1% of the Loading evaluations of power delivery equipment were
total load points) were estimated from the conducted by comparing the load current ratings of each
substation kW measurements while compensating line and transformer with calculated operating conditions.
for system losses. The evaluation status for each component was flagged as
Transformer kVA Allocation – This technique a “exceeds normal rating” when the loading exceeded
is commonly used when better data are 110% of user-defined normal limits. The evaluation
unavailable. It uses the total feeder load status was flagged as “exceeds emergency rating” when
measurements taken at the feeder head and then loading exceeds 150% of user-defined normal limits. This
allocates a portion to each load point based on the allows the feeder operator to determine the extent of the
kVA rating of the service transformer. In the test overload and the location of the overloads on the system.
circuit, a transformer often has multiple loads, The test circuit model showed overloads only with
respect to the normal rating and all of the overloads
individually metered. The load allocated to a
occurred on MV/LV transformers. No overloads were
transformer is allocated to the individual loads for
reported on lines and cables.
the simulation. The loadshape assumed for each Table 1 shows the number of overloads identified with
load is the same as the total feeder load. each allocation method. The reference method, the AMI
Monthly Usage Allocation – This method uses simulation, reported a total of 51 instances of overloads.
the monthly kWh billing to allocate loads to each Of the other methods, the monthly usage allocation
of the customers and then uses the substation load method reported 27 instances of overload, which was the
measurements develop a loadshape that is closest to the AMI method. The substation allocation, the
assigned to all loads. Each customer’s kW common method that allocates loads based on
Paper 0664
transformer kVA rating, identified only 5 instances of cases match closely; however, only the AMI model
overload. None of the overloaded transformers found causes the capacitor bank farthest downstream to change
with the kVA rating allocation method were found to be state due to current exceeding the ON setting. This can
overloaded with the AMI simulation, which is assumed to become a critical modeling issue when performing
be accurate. Not only are few overloads identified, but distribution state estimation.
they are misidentified. Note that in the kVA allocation
model each customer was modeled separately; therefore, Table 3. Minimum customer voltage at feeder peak
the loading on each transformer was proportioned to the demand.
total number of customers connected to it.
Table 1. Number of transformers that exceeded their Minimum Customer Voltage At Peak
normal rating.
AMI kVA rating Monthly Usage Class
Allocation Loadshapes
Number of Transformers Identified that Exceeded their 119.95 121.85 119.86 121.40
Normal Rating
AMI kVA rating Monthly Usage Class
Allocation Loadshapes 126
51 5 27 4 125.8
Capacitor Switching on AMI Allocation
125.6
Paper 0664
particularly important for those circuits with long LV overloads are reported because all transformers
lines such as are often encountered in European have the same percentage of loading. The test
distribution systems. circuit actually resulted in a few transformer
overloads due to the way load was allocated for
70
63.86 64.31 transformers with numerous loads. However, the
60
61.02
59.64 predicted overloads did not correlate with the
transformers found to be overloaded from the
50 AMI data.
40
The under loading of transformers can be
identified with proper load allocation and
kWh
80
example because 99% of the loads were
60 residential.
40
24.81 REFERENCES
20 13.32 12.03 11.21