Project Activity Plan (Updated till 31st May 2018)

Wk Plan Task Description (Outcome) Status Action Required /


No Date Remark
1 2 – 6 May Submission of IIR Completed
2 7-13 May Reading of Literature Completed
14-20
3 May Submission of Project Proposal Completed
(10 marks)
2 1– 27
4 May Literature Review Completed
28–3
5 May/June Developing Conceptual Completed
6 4-10 June Framework In progress
11-17 Data Collection primary and
7 June secondary, interviews and visit Pending
18-24
8 June
to banks. Pending
Submission of Interim Report
9 25-1
June/July & Industry Visit (40 marks) Pending
10 2-8 July Data Analysis and Pending
11 9-15 July Interpretation Pending
16-22 Submission of results and
12 July conclusion Pending
23-29 Submission of Final report to
13 July industry mentor Pending

30 – 31 Final Presentation and End of


14 July MIP 1 Pending
1-5
15 August Start of MIP 2 Pending
6-12
16 August Pending
13-19
17 August Pending
20-26
18 August Pending
19 27-2 Sept Pending
Final presentation and End of
20 2-8 Sept
MIP 2
Pending
Submission of Final Report
21 9-15 Sept
(40 marks) Pending
Presentation & Viva (60
TBA TBA
marks) Pending