0% found this document useful (0 votes)
105 views18 pages

Superposition: DR Mostafa Ghasemi Email: Ext:7375 Room: No.8, 2 Floor, Block J3

The document discusses the principle of superposition in well testing. It can be applied in both space and time. Superposition in space states that the total pressure response at a point is equal to the sum of the individual pressure responses caused by each well. Superposition in time allows for the analysis of variable rate tests by treating each rate change as an individual test that is then summed. Examples are provided to demonstrate calculating pressure responses at a well under multi-well and variable rate conditions using the principle of superposition.

Uploaded by

hari6622
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
105 views18 pages

Superposition: DR Mostafa Ghasemi Email: Ext:7375 Room: No.8, 2 Floor, Block J3

The document discusses the principle of superposition in well testing. It can be applied in both space and time. Superposition in space states that the total pressure response at a point is equal to the sum of the individual pressure responses caused by each well. Superposition in time allows for the analysis of variable rate tests by treating each rate change as an individual test that is then summed. Examples are provided to demonstrate calculating pressure responses at a well under multi-well and variable rate conditions using the principle of superposition.

Uploaded by

hari6622
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 18

Superposition

Dr Mostafa Ghasemi
Email: [email protected]
Ext:7375
Room: No.8, 2nd floor, Block J3
Principle of Superposition
Lesson Content
Principle of superposition
Reservoir pressure response during buildup
Semilog plot of pws versus [(tp + ∆t)/∆t]
Determination of permeability and reservoir pressure
Computation of skin factor from last flowing pressure

CO1: To analyze drawdown and build up test using


analytical solutions.
CO3: To apply the concept of superposition in well
test.
Lesson Outcomes

Apply principle of superposition to multiwell and


variable rate systems.
Apply semilog straight line analysis method to
determine permeability, reservoir pressure, and skin
factor from the middle time buildup test data.
Estimate wellbore storage coefficient from early time
buildup test data.
CO1: To analyze drawdown and build up test using
analytical solutions.
CO3: To apply the concept of superposition in well
test.
Superposition in Space
 Superposition is summation of all individual parts (responses) that contribute
to the total system.

Superposition states that the pressure


drop at point X is equal to the sum of the
pressure drops owing to Well A, Well B,
and Well C. Mathematically,

∆ = ∆ + ∆ + ∆

Where, ∆ = − ( )
Superposition in Space

.
OR ( , )= +
.
+

.
+
Superposition in Space
If we have a well producing at a constant production rate, the
pressure in that well is a function of its own production as well
as the production from the surrounding wells.

− = − + − + −
Superposition in Space

 Similarly, the pressure drop at Well A becomes

70.6 −948ϕ
, = + −2

.
+

.
+
Example 1: Multiwell test
For the conditions shown in the figure below, estimate the pressure at Well 1 after 7 hours of
production. Well 1 is producing with a rate of 100 STB/D and Well 2 production rate is 25 STB/D.

= 100′

Well Well
1 2
+
= h=20 ft
= 1 = 0.2
=76 md = 10 × 10
=1 cp B=1.08 RB/STB
S (@well 1)=5
. . .
, = + −2 + +

= 100′

Well Well
1 2
Solution:
. .
, = + −2 +


,
70.6 ∗ 100 ∗ 1 ∗ 1.08 −948 ∗ 0.2 ∗ 1 ∗ 10 × 10 ∗1
= 2200 + −2∗5
76 ∗ 20 76 ∗ 7
70.6 ∗ 25 ∗ 1 ∗ 1.08 −948 ∗ 0.2 ∗ 1 ∗ 10 × 10 ∗ 100
+
76 ∗ 20 76 ∗ 7
Example 1 Solution cont’d

−948 ∗ 0.2 ∗ 10 × 10 ∗1
= −3.564 × 10 = ln 1.781 ∗ 3.564 × 10 = −11.968
76 ∗ 7
and
−948 ∗ 0.2 ∗ 10 × 10 ∗ 100
= −0.03564 = −2.7992
76 ∗ 7
Substituting the above calculation to the main equation gives
70.6 ∗ 100 ∗ 1 ∗ 1.08 70.6 ∗ 25 ∗ 1 ∗ 1.08
, = 2200 + (−11.968 − 2 ∗ 5) + −2.7992 = 2086.29
76 ∗ 20 76 ∗ 20
Superposition in Time

 The most important application of superposition is in modeling variable rate test (including
buildup test). Assuming the three
 Consider the case in the figure below: wells are located at the
same place, but
t produce at different
time as shown below:

q
= Well 1

0 t
( − )
+ Well 2

+0 Well 3
( − )
Superposition in Time Cont’d
 Using the concept of superposition in space, the pressure at the well with the rate change
shown before becomes:

70.6 −948ϕ
= + −2

. ( )
+ ( )
−2

. ( )
+
( )
−2
Superposition in Time
 For a general rate change case as shown in the figure below:

70.6( − ) −948ϕ
= + −2
ℎ ( − )
Or
70.6 −948ϕ
= + ( − ) −2
ℎ ( − )
Example 2: Variable rate test
A flowing well is completed in a reservoir that has the following properties.

= h=43 ft
= 0.35 = 0.16
= 25 md = 18 × 10
= 0.44 cp B=1.32 RB/STB
S =2
Calculate the pressure in the well after 11 days for the following rate history.

= 350

q, STB/D =250 =100

0 120 168 t, hrs


70.6 −948ϕ
Example 2 solution = +

( − )
( − )
−2

= 350

q, STB/D =250 =100 n=3

0 120 168 t, hrs

=
70.6 −948ϕ 70.6 −948ϕ
+ ( − ) −2 = + ( − 0) −2 +(
ℎ ( − ) ℎ −
−948ϕ −948ϕ
− ) −2 +( − ) −2
− ( − )
Example 2 solution
= 250
t=11*24=264 hrs
t1=120 hrs = 350
t2=168 hrs
= 100

70.6 70.6 ∗ 0.44 ∗ 1.32


= = 0.038
ℎ 25 ∗ 43

−948ϕ −948 ∗ 0.16 ∗ 0.44 ∗ 18 × 10 ∗ 0.35


= = −5.886 × 10
25
= 11
= 2500
−5.886 × 10 −5.886 × 10
+ 0.038 (250 − 0) − 2 ∗ 2 + (350 − 250) − 2 ∗ 2 + (100
264 264 − 120
−5.886 × 10
− 350) −2∗2
(264 − 168)
Example 2 solution cont’d

= 11
= 2500 + 0.038 250 −17.042 − 4 + 100 −16.436 − 4 + (−250) −16.03 − 4
= 2500 + 0.038 −5260.5 − 2043.6 + 5007.53 = 2500 − 232.856 = 2412.73

You might also like