List of activities:
Document number
BEE\LAM\303\001\06
B-b. Transportation of new pipes to be used for partial replacement from
Ebocha or Port Harcourt pipe rack to the site. Contractor shall provide the
means of transportation.
B-c. Bush clearing and excavation of the flowline right of way where
necessary.
B-e. Pressure testing of the laid flow-lines before hooking up to the manifold
B-f. Wrapping the pipes with polyken tapes (white and black) after cleaning
and priming, in case of road crossing or where deemed necessary by
Company Representative
B-l. Fabrication and installation of flow-line supports and lifting the laid lines
on the installed iron supports. Contractor is to supply the old flow-line
pipes for the fabrication of the supports. Paint the installed supports with
black epoxy paint. (Ref: AGIP SPEC.2000.VAR.PAI.FUN) All the supports
should be piled at 1meter to the ground level and Teflon shall be placed
on the supports in order to avoid direct contact with the fabricated support
Document number
BEE\LAM\303\001\06
B-o. Number the flow-lines at an interval of 100m, using white coloured anti-
corrosion paint
SECTION 3
(C) GENERAL
The following are to be considered as part of the general condition for the
execution of the project:
C.1. Reporting
C.1.a The Contractor will submit a comprehensive work program
detailing all work items shown in the scope of work including
procedures for their execution.
C.3. Standards
C.3.a All constructions have to be executed according to the latest
International and Agip Standards, which have to be made available
to Company for approval by the Contractor for the activity
concerned.
Date
TECHNICAL SPECIFICATION 27-Sep-10
Document number
BEE\LAM\303\001\06
C.3.b Contractor shall complete all works included in the punch list
prepared by company representative and eliminate any fabrication
or installation defects.
NOTE: Only brand new materials shall be acceptable for the following activities:
fabrication and installation of final wellhead hook-up, arrival manifold hook-up
Date
TECHNICAL SPECIFICATION 27-Sep-10
Document number
BEE\LAM\303\001\06
and casing vent line hook-up. All required materials should be the contractor’s
responsibility.
SECTION 4
(D) HSE REQUIREMENTS.
Document number
BEE\LAM\303\001\06
SMALL& NON-TECHNICAL PROJECTS.
Items 3, 4, 5 & 8 may not apply.
SHORT & LONG TERM TECHNICAL PROJECTS.
All items listed apply
CASHES* Manual is equivalent to NAOC HSE Manual