The first process in MRP is the checking of the planning file entry.
The planning run and the scope of the planning run (which materials are planned in which
planning run) are controlled by the planning file.
The planning file contains a list of all materials relevant to the planning run. As soon as a
material master record is created with MRP data and a valid MRP type, this material is then
automatically included in the planning file.
During MRP run at plant level system checks for the materials which are having indicator
activated in planning file and plans those materials and will not plan the materials for which this
indicator is not activated….this reduces the run time of the MRP..
Entry in planning file is again activated when there is change to material with respect to MRP…
like below.
Change in stock
Change in requirement
Now check for the planning file entry again….now indicator will be activated