Integration Between PP Module and QM Module

na

Uploaded by

srinivasa varma
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 10

Integration between PP module and QM module

It is a common question faced by PP consultants in the interviews about integration between


PP and QM modules…

PP-QM

Inspection lot generation as production order is released.


When GR is made, material posting to inspection stock.
Assignment of inspection characteristics in routing.
Assigning inspection work center in operation for scheduling.

This document explains the integration points between PP and QM modules…


Integration Points…
1. In process inspection during Production
2. Inspection after Goods Receipt for Production order
In process inspection during Production:
During production it is required to check the product at once or at regular intervals like for
every one hour or after producing certain qty like 100 KG or after changing the equipment part
etc.. for this In process inspection during Production functionality is used..
we will see the settings needed for this…
First activate Inspection type 03 in material master in Quality management view as shown
below….
Now go to routing and select the operation for which inspection is done and click on the
button Inspection characteristics

Now assign the Master Inspection Characteristics as shown below

Now save the routing…


Now create Production order for material as shown below.
Now save the order

Now release the Production order. during release system, will generate the inspection lot as
shown below
Now for this inspection lot you can carry out Results recording and Usage decision…. there is no
stock posting in this case…
If it is required to carry out inspection at some regular intervals check the below document for
the settings and flow….
Inspection after Goods Receipt for Production order:
It is required to check the product after completion of production process. for this inspection at
GR for production order functionality is used…
Activation of Inspection Type 04 in the quality management view in the material master of the
Material (mm02) as shown below…

We need to maintain the below QM relevant master data after this…


Master Inspection Characteristics.
Sampling Procedures
Inspection Plans – QP01

Now create the Production order and release the order….


Now do the goods receipt for the Production Order through MB31…
Now check in MMBE Stock will be in quality inspection and inspection lot is generated….
check for the inspection lot as shown below in QA32…
after completion quality transaction Results Recording, Usage decision and stock posting, stock
is transferred to unrestricted use if approved or to blocked stock if rejected…

You might also like