Subdivision Construction Plan Overview and Review Procedures
Subdivision Construction Plan Overview and Review Procedures
Subdivision Construction Plan Overview and Review Procedures
General Information
The procedures for review and approval of construction plans are based on Volume III, Chapter 25 of
the City of Austin Land Development Code. The process is summarized below:
Step I: Development Assessment (Optional)
Typically, the general scope of subdivision construction is resolved schematically during the
subdivision preliminary plan and plat process. A development assessment is not done prior to the
subdivision construction process. However, a person may request an assessment of a proposed
development prior to formal submittal by contacting the Development Assistance Center (DAC).
City of Austin | Subdivision Construction Plan Overview and Review Procedures 07/30/2015 | Page 1 of 4
Contact:
City of Austin
Development Assistance Center
505 Barton Springs Road
Austin, Texas 78704
Phone: (512) 978-4000
Step 2: Completeness Check
In order to submit a subdivision construction plan for review, an application for Completeness Check
must be submitted to the Intake staff. No appointment is necessary. Intake reviews the application
and pertinent information to determine if all required administrative items have been submitted. Intake
then forwards it to the completeness check team, which determines whether the technical items
needed for review have been submitted.
An application for completeness check must include:
• Subdivision Construction Plan Application
• Subdivision Review - Completeness Check fee (check, cash, money order, or credit card): see
http://www.austintexas.gov/department/fees
• 2 copies of the Subdivision Construction Plans, associated engineer’s drainage reports and
environmental site assessment (when applicable) sealed by professional engineer as required
by state licensing regulations
• All Items listed on the completeness checklist, located in the Intake Office and available online
at http://www.austintexas.gov/page/land-use-applications#sub
The completeness check review takes a maximum of 10 business days from the date of submittal.
The applicant will be notified via email or fax whether the application is approved or additional
information is required for submittal. When the application is approved, the plans can be formally
submitted for a detailed review. The application must be submitted formally within 45 calendar
days of the initial completeness check or it will expire and a new completeness check will be
required.
Contact:
City of Austin and Travis County
Land Use Review – Intake Section
505 Barton Springs Road
Austin, Texas 78704
Phone: (512) 978-4000
City of Austin | Subdivision Construction Plan Overview and Review Procedures 07/30/2015 | Page 2 of 4
A Case Manager with Land Use Review is assigned to coordinate interdisciplinary reviews and
provide guidance on code requirements and procedures. A review team is also assigned to the
project. The team reviews the plans and prepares a Master Comment Report that contains specific
areas of non-compliance. The initial review of the plans by the team can take up to 28 days from the
date that the plans were formally submitted. If the subdivision construction plan complies with the
provisions of the code and other applicable state and federal regulations and Commission approval is
not required, the subdivision construction plan will be approved administratively. The Master
Comment Report will be sent to the applicant electronically or by fax. The Master Comment Report
can also be viewed on the City of Austin website at
http://www.austintexas.gov/page/interactive-development-review-permitting-and-inspection.
Step 4: Update
If it is determined that the subdivision construction plan does not comply, after the initial review, the
applicant must file an update in order to bring it into compliance. Contact Intake staff to schedule
an appointment to submit the update. Staff reviews the updates within 14 days of receipt, and the
Case Manager will issue additional Master Reports identifying remaining items to be addressed.
Updates will be required until the subdivision construction plan is in compliance or the subdivision
construction plan expires.
Under current code, subdivision construction plan applications do not expire unless the corresponding
plat expires, is not approved or not recorded. Updates filed later than 180 days after the initial
submittal may require an adjustment to review fees as determined by the Director.
Step 5: Subdivision Construction Plan Approval and Release
Once all code requirements have been met, the Case Manager will notify the applicant that the
subdivision construction plan can be approved administratively.
Please note that prior to subdivision construction plan approval, all construction inspection fees and
fiscal requirements identified during the review process must be paid.
Prior to release of the subdivision construction plan, one reproducible full-size copy of the plans must
be provided which will be signed by the Case Manager. The engineer will reproduce three full- and
one half-size plan sets and return them to the Case Manager for internal distribution at which time the
subdivision construction permit will be provided to the engineer by the Case Manager. A final version
of the plans and reports incorporating all changes made during the review process must be
submitted electronically prior to release of the site plan as described in Exhibit V (Subdivision
Construction Plan Application Instructions).
During the punch list phase of the subdivision construction process, the engineer will be required to
furnish one full-size 4 mil non-degradable mylars to the Site and Subdivision Inspection Division.
These mylars will become the permanent City record of the as-built condition of public infrastructure
which will be kept on permanent file in the City’s Public Works Engineering Division File Room.
Revisions to Released Construction Plans
As described in Section 25-5-21 of the City of Austin Land Development Code, major revisions to a
released construction plan shall be processed as a new application. Minor revisions require a 14-day
review time.
Fiscal Surety Information
The applicant is responsible for posting adequate fiscal surety for all proposed erosion and
sedimentation controls, and for permanent restoration of all disturbed areas.
City of Austin | Subdivision Construction Plan Overview and Review Procedures 07/30/2015 | Page 3 of 4
An Engineer’s Cost Estimate for erosion/sedimentation controls and restoration must be submitted.
When the Case Manager has approved the estimate, fiscal surety in a form approved by the Director
of Financial Services shall be submitted.
Contact the Fiscal Officer (512-974-2771) to post cash in an interest-bearing escrow account. If a
letter of credit is to be posted, the Fiscal Officer will ensure the proposed financial institution is
acceptable under the City’s policies and the proper form is utilized.
Ethics and Financial Disclosure Information
If you or your agent/representative were City employees or officials within the past 24 months, you
may be subject to the Ethics and Financial Disclosure Ordinance (860717-X). Copies of the ordinance
are available from the City Clerk’s Office.
City of Austin | Subdivision Construction Plan Overview and Review Procedures 07/30/2015 | Page 4 of 4