The Feasibility of Using Precast Concrete Panels To Expedite Highway Pavement Construction
The Feasibility of Using Precast Concrete Panels To Expedite Highway Pavement Construction
The Feasibility of Using Precast Concrete Panels To Expedite Highway Pavement Construction
9. Performing Organization Name and Address 10. Work Unit No. (TRAIS)
Center for Transportation Research
The University of Texas at Austin
3208 Red River, Suite 200 11. Contract or Grant No.
Austin, TX 78705-2650 9-1517
12. Sponsoring Agency Name and Address 13. Type of Report and Period Covered
Texas Department of Transportation Research Report (9/99 – 2/00)
Research and Technology Implementation Office 14. Sponsoring Agency Code
P.O. Box 5080
Austin, TX 78763-5080
15. Supplementary Notes
Project conducted in cooperation with the Texas Department of Transportation and the U.S. Department of
Transportation, Federal Highway Administration.
16. Abstract
As the number of vehicles on America’s roadways continues to grow at an unprecedented rate, pavements continue
to deteriorate faster and require more frequent replacement. Construction, however, causes traffic delays, which further
compound the problem. Traffic delays increase user costs, which are costs incurred by the users of the roadway but are
directly caused and attributable to the presence of construction activities. Therefore, a method for expediting pavement
construction in order to reduce user costs is needed.
This report describes a method for expediting highway pavement construction through the use of precast concrete
panels. Precast concrete panels can be assembled quickly, allowing traffic back onto the pavement almost immediately.
This kind of assembly will allow pavement construction to be carried out in overnight or weekend operations, when
traffic volumes are low. The result will be a tremendous savings in user costs.
The concept for a precast concrete pavement presented in this report should have the same, if not better, durability as
conventional cast-in-place concrete pavements currently being constructed. Also, by incorporating prestressing, it is
possible to achieve increased load repetitions and design life, with a significant reduction in pavement thickness over
conventional pavements. This is especially important for removal and replacement applications, where pavement
thickness is constrained by existing conditions. Although the initial construction costs may at first be higher for a precast
pavement, the savings in user costs far outweigh any additional construction costs.
David K. Merritt
B. Frank McCullough
Ned H. Burns
Anton K. Schindler
February 2000
Implementation Recommendations
This report presents a concept for expediting highway pavement construction through the use
of precast concrete panels. Included in this concept are recommendations for panel fabrication,
base preparation, panel placement, and prestressing. In addition, basic design tools and
procedures are presented.
Implementation of the proposed concept should proceed in a staged process. Preliminary
laboratory testing and development of features requiring additional investigation should be
carried out prior to actual construction. Small-scale pilot projects should then be constructed to
work out construction details and procedures. A larger-scale project should then be constructed
in a rural area to further streamline the construction process under actual construction time
restrictions. The final stage should be a project constructed in an urban area where there are very
stringent construction time restrictions and where issues such as curbs and gutters can be
addressed. This staged implementation procedure will allow for development and refinement of
the proposed concept with a minimal impact on traffic.
Disclaimers
The contents of this report reflect the views of the authors, who are responsible for the facts and
the accuracy of the data presented herein. The contents do not necessarily reflect the official
views or policies of the Federal Highway Administration or the Texas Department of
Transportation. This report does not constitute a standard, specification, or regulation.
There was no invention or discovery conceived or first actually reduced to practice in the
course of or under this contract, including any art, method, process, machine, manufacture,
design or composition of matter, or any new and useful improvement thereof, or any variety of
plant, which is or may be patentable under the patent laws of the United States of America or any
foreign country.
Acknowledgments
The researchers acknowledge the invaluable input and assistance provided by all those who
participated in the expert panel meetings in December 1998 and in November–December 1999.
Also appreciated is the assistance provided by Gary Graham (TxDOT), Steve Forster (FHWA),
Suneel Vanikar (FHWA), and Mark Swanlund (FHWA), project directors for this project. The
assistance of K. Fults (DES), who served as project coordinator, is also appreciated.
Table of Contents
CHAPTER 1. INTRODUCTION AND BACKGROUND .......................................................1
1.1 Background .........................................................................................................1
1.1.1 Current Need/Interest with Regard to Expediting Construction............1
1.1.2 Problem Statement and Project Objectives............................................1
1.2 Project Methodology ...........................................................................................2
1.3 Scope of Report ...................................................................................................3
1.4 Report Objectives ................................................................................................3
vii
CHAPTER 4. EVALUATION OF STRATEGIES ................................................................45
4.1 Introduction .......................................................................................................45
4.2 Pavement Types ................................................................................................45
4.3 Design and Construction ...................................................................................46
4.4 Cross-Section Strategy ......................................................................................48
viii
6.3.4 Section Length .....................................................................................75
6.3.5 Section Width.......................................................................................75
ix
9.3.2 Prestressing ........................................................................................120
9.3.3 Joints ..................................................................................................120
9.3.4 Grouted Tendons................................................................................121
9.3.5 Anchorage ..........................................................................................121
APPENDIX .....................................................................................................................133
A.1 Void Effects on Pavement Life .......................................................................135
A.2 Handling and Erection of Precast Panels ........................................................136
A.3 Tolerances for Precast Panels..........................................................................140
A.4 Sheet Piles .......................................................................................................142
A.5 Precast Construction For Buildings.................................................................143
A.6 Lightweight Concrete ......................................................................................149
REFERENCES .....................................................................................................................151
x
Chapter 1. Introduction and Background
1.1 BACKGROUND
Precast concrete construction methods have now become feasible alternatives in such
applications as buildings and bridges. The primary benefit of precast construction is the speed of
construction. Precast elements can be cast in controlled conditions at a precasting yard far in
advance of when they will be needed, stockpiled, and transported to the construction site. The
structure can then simply be assembled like a puzzle using the precast elements. Allowing time
for the concrete to cure before construction progresses, which is a critical operation in terms of
operational time and long-term performance, particularly for portland cement concrete
pavements, is no longer a factor. The use of precast elements eliminates the operational step and
optimizes the curing time.
1.1.1 Current Need/Interest with Regard to Expediting Construction
As the population continues to grow rapidly, so does the number of vehicles on
America’s roadways. This increasing number of vehicles is beginning to push many roadways
far beyond their designed capacity. When a roadway that is near or above capacity is closed for
rehabilitation or expansion, major traffic congestion occurs. This congestion results in, among
many other things, lost work time and increased fuel consumption. A method for expediting
construction/rehabilitation time is, therefore, needed to minimize or even eliminate these effects.
Under these circumstances, and given the success of precast concrete construction in the
building and bridge industries, the Federal Highway Administration (FHWA) contracted the
Center for Transportation Research (CTR), through the Texas Department of Transportation
(TxDOT), to investigate the use of precast concrete technology to expedite pavement
construction. Precast panels have been used previously for repair of jointed and continuously
reinforced concrete pavements. However, precast concrete construction has seldom been used
for large-scale pavement construction. This project was undertaken to develop a concept for
using precast methods for large-scale pavement construction.
1.1.2 Problem Statement and Project Objectives
The problem statement for this feasibility project is as follows:
The goal of this project, therefore, was to develop a concept for a precast concrete
pavement — one that meets the requirements for expedited construction and that is feasible from
the standpoint of design, construction, economics, and durability. The proposed concept should
have a design life of 30 or more years to make it comparable to conventional cast-in-place
pavements currently being constructed. To meets these objectives, the tasks undertaken as a part
of this project were as follows:
1
CHAPTER 1. INTRODUCTION AND BACKGROUND
2nd Expert
Panel
(Chapter 3)
Prior
Experience
(Chapter 2) Feasibility
Analysis:
Design
Literature Strategy Proposed Design (Chapter 7) Recommendations
Review Evaluation Concept Considerations Construction & Implementation
(Chapter 2) (Chapter 4) (Chapter 5) (Chapter 6) (Chapter 8) (Chapter 10)
Economics &
Durability
(Chapter 9)
1st Expert
Panel
(Chapter 3)
Benefits
(Chapter 11)
Figure 1.1 Flow diagram of the precast pavement feasibility project methodology
After the feasibility analysis was completed, a second expert panel meeting was used to
evaluate the proposed concept from a practical point of view — that is, a view based on the
opinions of professionals in the precast and concrete pavement industries. The proposed concept
was then further refined from the recommendations of the second expert panel. Finally, after
2
1.4 Report Objectives
3
CHAPTER 1. INTRODUCTION AND BACKGROUND
4
Chapter 2. Literature Review
2.1 INTRODUCTION
An essential part of the precast pavement feasibility project was the literature review.
The literature review was used in conjunction with the expert panel meetings to determine the
current state of the art in the precast and concrete paving industries. It was also used to
investigate any previous precast concrete pavements that have been constructed.
There were three main aspects of the literature review. The first was an identification and
evaluation of the experience of the Center for Transportation Research (CTR) in this area. This
evaluation involved reviewing several reports previously generated by CTR. The second aspect
of the literature review was a search for precast concrete pavement literature elsewhere. This
search involved not only a computer assisted search, but also input from professionals at the first
of two expert panel meetings. A TRIS (computer-assisted) search was first utilized to find
published precast experience through a search of a transportation literature database. An
Engineering Index (EI) Compendex (computer-assisted) search was then undertaken through The
University of Texas library system.
A synthesis of the current state of the art of precast concrete pavement was the final
aspect of the literature review. This synthesis required sorting through all of the information
obtained from CTR experience and from the computer-assisted searches. What follows is a
summary of information from relevant articles/reports obtained from the literature review.
Aspects of many of these projects were applied to the proposed concept for a precast
concrete pavement presented in Chapter 5. Some of these projects are discussed in depth in this
chapter and in the appendix.
5
CHAPTER 2. LITERATURE REVIEW
investigated the viability of cast-in-place prestressed pavements, resulting in one such pavement
being constructed in McLennan County, Texas, in 1985. Although not a precast pavement, this
project provided several useful concepts for a precast pavement. The relevant aspects of each of
these projects will be discussed below.
2.3.1 Precast Pavement with AC Overlay in South Dakota
Research by South Dakota State University and the South Dakota Highway Department
in the 1960s led to the development of a precast pavement with an asphaltic concrete overlay
(Ref 1). The pavement consisted of 6 ft x 24 ft x 4½ in. thick prestressed panels that were placed
on a 1½ in. thick sand bedding over an 8 in. granular base. After all the panels were set in place,
they were overlaid with 1½ in. of asphaltic concrete. Figure 2.1 shows a cross section of the
pavement and slab layout.
The panels were interconnected with “tongue and fork” connections. A steel wedge was
used to interlock the tongue and fork. A grout key was cast into the panel edges for grouting the
joints after the panels were set in place. Figure 2.2 shows the tongue and fork connections and
grout keys. The transverse panel joints were staggered, as shown in Figure 2.1, to provide
rigidity in the transverse direction.
6
2.3 Previous Projects
Figure 2.2 Precast slab with tongue and fork connections (Ref 1)
One of the main problems experienced with this pavement was the appearance of
reflective cracks in the AC overlay only 1 month after the asphalt surface was applied (Ref 2).
In addition, it was found to be difficult to insert the steel wedges into the tongue and fork
connectors when joining the panels.
In a recent conversation, the South Dakota State University principal investigator for the
project stated that, although the pavement is still in place, it has been overlaid with asphalt since
it was constructed in the 1960s.
7
CHAPTER 2. LITERATURE REVIEW
stabilized subbase and were not prestressed either transversely or longitudinally. In addition,
there were no load transfer devices incorporated in the joints between the panels. After 1 month
of exposure to traffic, neither faulting, cracking, nor excessive joint opening was observed.
Another project in Japan investigated a method for prestressing the joints of precast
concrete pavements (Ref 4). The purpose of developing such a joint was to make the joints in
precast pavements more continuous, providing a tight fit between panels and complete
transmission of the shear loads. The joint detail developed is shown in Figure 2.4.
Non-shrinkage Mortar
For this joint, 17 mm (0.67 in.) threaded bars were inserted through holes cast into the
slab edges at 50 cm (19.7 in.) intervals. Adjacent slabs were prestressed together by tightening
anchorage nuts on either end of the prestressing bar by way of pockets cast into the slab at the
bar ends. After the joint was prestressed, the pockets and joint were filled with nonshrinkage
mortar. Laboratory testing revealed that this prestressed joint had 3 times the shear resistance of
a conventional bar dowel joint. The layout of the actual test section consisted of the slabs set on
a vinyl sheet (to reduce base friction) that was placed over a cement-treated base. Testing
revealed favorable results, with no faulting of the prestressed joints up to a failure load of 250 kN
(28.1 kip). No faulting was observed at the joints of the precast prestressed concrete pavement in
situ for 6 months after construction.
A third project in Japan examined the long-term performance of precast prestressed
concrete pavements (Ref 5). Seven pavements were examined ranging in size from 170 mm to
200 mm (6.7 to 7.9 in.) thick, 1.3 m to 2 m (4.3 to 6.6 ft) wide, and 4 m to 10 m (13.1 to 32.8 ft)
long. The precast panels were prestressed in the longitudinal direction and reinforced with
nonprestressed bars in the transverse direction. Two types of dowel bars were used to provide
load transfer between panels: straight bars and curved “horn-shaped” bars. Figure 2.5 shows the
two different joints used. The panels were laid out in a grid and interconnected with dowel bars,
as shown in Figure 2.6. For the straight bar joints (Figure 2.5a), the dowel bars were inserted
into a shaft cast into the panel. After the adjoining panel was set in place and leveled, the dowel
bars were slid from the first panel into a larger shaft cast in the adjoining panel. The dowel bar
was then grouted in place by way of small holes cast into the top of the slab.
For the horn-bar joints (Figure 2.5b), curved slots were cast into the panels. After the
panels were set in place, the horn-shaped bars were inserted into the slot to connect the panels.
The dowel bars were then grouted in place (filling the slots) and mortar was used to seal the slot
openings. For both joint details, spiral reinforcement was cast around the slots for increased
bearing strength and support. At the time of the report, the precast pavements examined ranged
in age from 9 to 13 years old; the overall pavement performance was reported as quite good.
8
2.3 Previous Projects
(a) (b)
Central Stressing
Probably the most significant technique developed for prestressed pavements was central
stressing. With this technique, the post-tensioning strands are anchored at the ends of the slab
and extend into stressing pockets cast into the pavement, as shown in Figure 2.7. The strands
9
CHAPTER 2. LITERATURE REVIEW
coming from each side of the slab into the stressing pocket are coupled in the pocket with a
device similar to that shown in the plan view of a stressing pocket in Figure 2.8.
CL
Post-tensioning Strand Expansion Joint
Stressing Pocket
A stressing ram, similar to that used for post-tensioning circular concrete tanks, is used to
stress both strands coming into the pocket at the same time. The stressing pockets are then filled
with concrete after stressing is complete. The advantage of using this technique is that access to
the end anchorage is not needed in order to post-tension the slab. This technique allows for a
more continuous pavement placement operation, avoiding as it does the use of “gap slabs”
between prestressed slabs.
Figure 2.8 Plan view of central stressing pocket and coupler device (Ref 6)
10
2.3 Previous Projects
to secure the joint to the pavement. A neoprene seal, which can accommodate the joint
openings, is used to prevent incompressible material from falling into the joint. Stainless steel-
plated dowels, which will not corrode or seize up in the dowel sleeve, are used for load transfer
across the joint.
Friction-Reducing Medium
In prestressed pavements, which feature particularly long slabs, a significant amount of
expansion and contraction occurs owing to daily and seasonal temperature cycles. The friction
between the bottom of the slab and the base material resists these movements, thereby causing
tensile stresses in the pavement (during contraction movement). To reduce this frictional
resistance, CTR incorporated a friction-reducing membrane placed beneath the slab. Extensive
testing revealed that a single layer of polyethylene sheeting was the best membrane material
available for meeting the requirements of constructibility, effectiveness, and economics.
Neoprene Seal
1/2" Ø Nelson
Deformed Bars
(~ 3' in length)
6" Weld
11/4" Ø Stainless
Steel Dowel
Existing Pavement
11
CHAPTER 2. LITERATURE REVIEW
Adjacent
pavement slabs
(cast at different times)
PSCP2 Program
A computer program dubbed “PCP1” was developed for analyzing prestressed
pavements. This program computes stresses and slab movements for prestressed pavements
based on given temperature conditions, support conditions, concrete properties, and steel
properties. This program proved valuable for estimating slab movements and for determining
the required prestress and maximum allowable slab length in the McLennan County prestressed
pavement. PCP1 was later calibrated, using actual data from the McLennan County pavement,
and renamed “PSCP2.”
Overall, this project revealed many benefits of prestressed pavements. Among these
benefits are reduced pavement thickness (only 40–50% of a conventional pavement thickness),
fewer joints (slab lengths of up to 440 ft), less maintenance, and enhanced durability (cracks are
pulled closed by prestressing). In 1985, a cast-in-place prestressed overlay was constructed on a
section of southbound Interstate 35 in McLennan County, Texas. This overlay incorporated all
of the ideas that had been generated throughout the project. The pavement was subsequently
monitored for several years after construction to investigate the performance of the pavement.
Over the 15 years the pavement has now been in service, under very high traffic volumes and
truck traffic, it has required only minimal maintenance and shows virtually no signs of distress.
12
2.4 Related Literature
1) A female-to-female type shear key, similar to that shown in Figure 2.11, should be
used between precast panels. This joint should have a ½ in. opening at the bottom to
allow for panel irregularities. A foam or polyethylene compression seal can also be
used at the bottom of the joint to prevent grout from leaking and to provide flexibility.
A tongue-and-groove-type joint, as shown in Figure 2.12, is not practical because of
difficulties encountered with the grouting process. A direct contact type joint, or butt
joint, is not recommended because it may result in leakage through the joint when the
deck panel is under tension.
2) The precast panels should be post-tensioned longitudinally to ensure a tight joint, to
keep the joint in compression, and to prevent leakage of the joint.
3) Precast panels should be designed with a sufficient amount of transverse prestress to
prevent cracking during handling.
4) An overlay should be used to provide a smooth ride and keep the bridge deck in good
condition. The most common overlay used was found to be latex-modified concrete.
In addition, a waterproofing membrane system may be used to prevent penetration of
water into the joints.
13
CHAPTER 2. LITERATURE REVIEW
A 1983 report by Martin (Ref 9) on connections for modular precast concrete bridge
decks addresses various concepts, details, and problems experienced. This report documents a
research project conducted in 1969 at Purdue University on the feasibly of precast, prestressed
concrete deck members supported by steel beams. The test specimen consisted of narrow
precast, pretensioned planks placed perpendicular to the traffic flow. The planks were
interconnected with a tongue and groove joint and post-tensioned longitudinally, as illustrated in
Figure 2.13.
14
2.4 Related Literature
Three different joint shapes were investigated, as shown in Figure 2.14. The flat joint in Figure
2.14(a) proved to be superior to the other joints. The specimens were post-tensioned to 40 psi
and tested with repetitive loads through 2.25 million cycles. The report further mentions that for
a tight fit, extremely tight tolerances are required. In the first set of slabs produced, the joints did
not fit with sufficient precision and, consequently, severe spalling occurred at the joint after very
few loading cycles. To reduce the stress concentrations, a 1/16 in. neoprene sheet was placed in
the joint, which seemed to provide nearly full composite action between the deck and the
supporting stringers.
a)
b)
c)
This report further documented a research project on Indiana State Road 140 south of
Knightstown. In this project, deck panels 38 ft/4 in. long by 4 ft wide were positioned on steel
beams. The panels had keyed joints as shown in Figure 2.15. Problems were encountered as
cracks formed, perpendicular to the joints, during post-tensioning of the deck panels. This
cracking was attributed to poor joint fit that led to local bending stresses. Upon inspection,
irregularities in the width of the joints were found. There were numerous locations where the
joint widths were less than 1/8 in., and approximately half of the defective joints were
completely closed. A few months after the bridge was opened to traffic, the concrete in the
vicinity of the closed joints began to spall. The cause of the joint irregularity was determined to
be irregularities in the forms used to cast the slabs.
15
CHAPTER 2. LITERATURE REVIEW
Figure 2.15 Panel elevation and shear key details, Knightstown Bridge (Ref 9)
The New York State Department of Transportation used precast deck panels for
rehabilitation purposes on the suspension bridge over Rondout Creek near Kingston, New York
(Ref 9). The deck panels were 9 ft wide by 24 ft long, with a simple V-shaped male-female
joint. No grouting was done except at the connections to the steel stringers. The details of this
project can be seen in Figure 2.16. No major problems were reported with these bridge deck
panel details.
Martin (Ref 9) summarized the discussion about integral deck bridge connections by
stating that “… tongue-and-groove joints have been tried, but an exact fit between units is nearly
impossible without match-casting. This is not practical for plant cast products, especially if they
are pretensioned.”
Figure 2.16 Details used at the Kingston Bridge, New York (Ref 9)
Although these studies focused on full-depth bridge deck panels, the findings presented
will be helpful for the investigation of these aspects as they relate to full-depth precast pavement
panels.
16
2.4 Related Literature
1) necessity for a high degree of geometry control during fabrication and erection of
sections,
2) potential joint weakness owing to a lack of mild steel reinforcement across the joint,
3) temperature and weather limitations regarding the mixing and placing of epoxy joint
material, and
4) frequent loading and unloading of segments, with the risk of damage.
Web keys in segmental bridge construction serve two main functions. The first is to align
the segments during erection. The second is to transfer the shear force between segments during
that period while the epoxy, applied to the joint, is still plastic and acts only as a lubricant.
Experimental tests were conducted at The University of Texas at Austin on segmental
bridge specimens consisting of combinations of joining methods. Configurations using no key,
single-key, and multiple keys, together with either no bonding material (dry) or epoxy in the
joint, were evaluated. These joining methods were then compared to the performance of a
monolithically constructed joint. Figure 2.17 summarizes the behavior of the different joints
considered. From the testing, Kosiki and Breen concluded that the effect of epoxy on
performance of precast segmental joints was phenomenal. All three specimens with epoxied
joints, including the keyless joint, acted monolithically, carrying loads as high as the monolithic
no-joint specimens. It was further recommended that, if nonepoxied joints are to be used, the use
of multiple keys improves the overall performance of the joints. However, application of an
epoxy bonding agent provides much better total assurance; it is, therefore, highly desirable (Ref
11).
17
CHAPTER 2. LITERATURE REVIEW
In a paper on the use of precast components (Ref 15), the joint details shown in Figure
2.18 were presented. The combination of a contact joint and a thin concrete-filled joint was
shown to provide adaptability to any possible geometry change (vertical/horizontal curves) in the
structure. A sealing ring around longitudinal tendons, passing through the precast units, prevents
leakage during pressure grouting of the tendons.
18
2.4 Related Literature
A large number of precast segmental bridges use an epoxy resin joint material between
precast segments. Specifications are provided in the American Association of State Highway
and Transportation Officials (AASHTO) Load and Resistance Factor Design (LRFD) Bridge
Design Specification (Ref 10), which pertains to joints in precast segmental bridges. In the
AASHTO Guide, cast-in-place concrete, fresh concrete, and epoxy joints between precast units
are defined as Type A joints. It is specified that in Type A joints, the prestressing system shall
provide a minimum compressive stress of 30 psi and an average stress of 40 psi across the joint
until the epoxy has cured. The commentary further states that this temporary stress is required to
ensure full bond and to prevent uneven epoxy thickness. Such variations could lead to a
systematic accumulation of geometric error.
The commentary to the AASHTO guide (Ref 10) states that the epoxy serves as a
lubricant during placement of the segments, prevents water intrusion, provides a seal to prevent
crossover during grouting, and provides some tensile strength across the joint. Dry joints are
susceptible to freeze-thaw damage and cannot prevent intrusion of water, which may lead to
corrosion of internal tendons. If tendons pass through the joints, then the joint detail must have
sufficient durability to protect the tendons against corrosion. In CTR Research Report 248-1
(Ref 11), a concern is expressed that “…improper use or choice of the epoxy can be critical with
respect to shear strength of the joint.” Kashima and Breen (Ref 12) have pointed out that many
epoxies furnished as suitable for joining concrete segments in fact are unsuitable. The suitability
19
CHAPTER 2. LITERATURE REVIEW
of specific formulations should be checked using simple tests, but with surface conditions and
ambient factors typical of the proposed application.
The epoxy application process must be planned carefully to ensure that all the necessary
tasks are completed within a required time frame. The epoxy pot-life serves as a maximum time
limit for completion of epoxy measuring and mixing, application of the epoxy to both surfaces of
a match-cast joint, joint closure, temporary post-tensioning, and cleaning of the epoxy from the
surrounding concrete and equipment. Time studies should be conducted to estimate the
necessary manpower and the staging of the various tasks. Bruggeling (Ref 13) describes the
function of any bonding agent between precast panels as stated by the AASHTO guide.
Bruggeling lists, however, the following requirements to be met by the bonding agent placed
between adjacent precast panels (Table 2.2):
20
2.4 Related Literature
Raft units are usually set on a mechanically compacted granular subbase, preferably in
excess of 250 mm (9.8 in.) thick. No load transfer devices are incorporated in the joints between
raft units. Joints are usually not filled or sealed either, as this allows water to percolate and drain
through the subbase. When a high riding quality and a smooth finish are desired, the joints can
be filled with a fast-curing mortar. Filling the joints, however, inhibits removal and replacement
of the unit.
a)
b)
Figure 2.19 Inverted V-shaped edge detail for raft units (Ref 16)
21
CHAPTER 2. LITERATURE REVIEW
Figure 2.20 Loader placing raft units at a “nose-up” angle (Ref 16)
22
2.4 Related Literature
1) Lifting connections in the panel should not be made more than 1/4 to 1/5 of the total
length from the edges of the panel.
2) For panels longer than 7 ft, a bond breaker should be used in the middle of the panel
to form a weakened plane so that the concrete fractures before steel stresses become
too great.
3) The repair panel should be set on a screeded bed of grout in the repair area.
4) A polymer or fast-setting portland cement concrete should be used in the gaps
between the repair panel and the existing pavement.
In a paper by Meyer and McCullough (Ref 19), the actual fabrication and installation of
CRCP repair panels along I-30 near Mt. Pleasant, Texas, is discussed. The theory and design
procedures presented in the report previously mentioned were used for this project. One of the
interesting aspects of this project, which may have applications to a large-scale precast
pavement, was the use of leveling beams to set the precast panel to the proper height. With this
method, the precast panel is set on a screeded grout bed, slightly higher than the surrounding
pavement. Leveling beams are then used to press the panel down so that it is at the same level as
the surrounding pavement. This process is illustrated in Figure 2.22.
Precast Repair Panel Leveling Beams
Figure 2.22 Precast repair panel before and after leveling beams are used to set it into place
23
CHAPTER 2. LITERATURE REVIEW
8'
Ducts for
longitudinal
post-tensioning
24
2.6 SUMMARY
4' 4'
Duct for
transverse
post-tensioning
Ducts for
longitudinal
post-tensioning
Dowel Pretensioning
between Strands
sections
8'
Duct for
transverse
post-tensioning
Ducts for
longitudinal
post-tensioning
Pretensioning
Strands
Joint Panel Base Panel C.S. Panel Base Panel Joint Panel
(multiple) (multiple)
25
CHAPTER 2. LITERATURE REVIEW
2.6 SUMMARY
The literature review provided an extensive amount of information on the current state of
the art in precast pavements and precasting in general. Although there was a very limited
amount of information on actual precast pavements, some of the ideas presented, particularly the
new concepts described in Section 2.5, and the bridge deck joint details described in Section 2.4,
proved very beneficial for the development of a concept for a precast concrete pavement.
26
Chapter 3. Documentation of Expert Panel Meetings
3.1 INTRODUCTION
Expert panel meetings were held at the beginning and end of the project to both help
determine the current state of the art in the precast concrete and concrete paving industries and to
generate and refine concepts for a precast concrete pavement. The first expert panel meeting,
held at the beginning of the project, primarily provided ideas and recommended areas of further
investigation for the development of preliminary concepts. The second expert panel was used to
evaluate and refine the original concepts developed by the researchers.
The expert panels were made up of professionals from the precast concrete industry,
construction industry, concrete paving industry, and transportation agencies. The panel members
represented several regions of the United States. Overall, the panel members had a great degree
of experience in their respective fields.
• Determine the current state of the art in precasting and concrete pavement
construction.
• Discuss the practicality of various methods proposed by the researchers.
• Discuss feasible techniques for using precast panels in highway construction.
• Recommend areas of further investigation and possible sources of relevant
literature.
The feedback from this expert panel was crucial for the development of the proposed
concept for a precast concrete pavement. The panel members tended to focus on ideas that
would be economically feasible and easily adaptable to current practices.
3.2.1 Panel Members
Of the thirteen members who were invited, seven were able to attend the first expert
panel meeting. The members were selected to provide a balance of input from transportation
agencies (DOT and FHWA), consultants, contractors, and suppliers — in short, to ensure a
feasible final product relevant to all aspects of the transportation industry. The following is a list
of those who attended the first expert panel meeting. The “Expert Panel” consists of the various
professional members, including the project directors from TxDOT and the Federal Highway
Administration. The “Researchers” include the three principal investigators and graduate student
researchers from the Center for Transportation Research.
27
CHAPTER 3. EXPERT PANEL MEETINGS
Researchers
• Dr. Frank McCullough
• Dr. Ned Burns
• Dr. David Fowler
• Mr. Anton Schindler
• Mr. David Merritt
Expert Panel
• Mr. Mark Swanlund - FHWA Representative
• Mr. John Dick - Precast / Prestressed Concrete Institute (PCI)
• Mr. Gene Marter - American Concrete Paving Association,
(Texas chapter)
• Mr. Burson Patton - Texas Concrete Incorporated
• Mr. Tom D’Arcy - The Consultant Engineers Group
• Mr. Doug Huneycutt - Texas Department of Transportation (TxDOT),
(Waco District)
• Mr. Andrew Wimsatt - Texas Department of Transportation (TxDOT),
(Dallas District)
3.2.2 Presentation of Scope
The scope of this project is limited to full-depth pavement construction. With this in
mind, two variations of a full-depth precast pavement were presented to the expert panel. The
first variation is that of full-depth precast panels. With this application, the panels would be
constructed to be the full pavement depth, as shown in Figure 3.1. The top surface of the panel
would serve as the riding surface.
One advantage of this application is that once the panels are placed in position, traffic can
almost immediately be turned onto the pavement. However, problems could be experienced
during alignment of adjacent panels.
D Precast Panel
D = Pavement Thickness
The second variation is precast panels with a bonded concrete overlay. With this
application, panels would be constructed to be about 2 in. thinner than the final pavement
thickness. The final 2 in. of the pavement would consist of a bonded concrete overlay, as shown
in Figure 3.2. The bonded concrete overlay would, thus, provide the final riding surface of the
pavement and should provide good riding quality.
28
3.2 First Expert Panel
2"
BCO*
D
Precast Panel
The advantage of this application is that the panels can be placed with less tolerance, as
their alignment does not affect the final ride quality. However, a bonded concrete overlay adds
an additional operation to the construction process. Additional time will be required to allow the
BCO to gain strength before traffic is turned back onto the pavement.
3.2.3 Discussions
The main discussions of the first expert panel meeting were concentrated in three
sessions. During the first session the current state of the art was discussed. In the second and
third sessions, new concepts were discussed for the two different applications presented above.
During each session, certain aspects were discussed as they came up; these discussions are
documented below under the appropriate heading.
29
CHAPTER 3. EXPERT PANEL MEETINGS
General Strategy
One statement made was that the current methods (rules) for concrete paving do not
necessary apply to precast — for example, the requirement for not allowing polishing of the
aggregate on the surface of the pavement. For precast, it may be economically feasible to cast
the panels in two lifts, with the last lift being the riding surface, which has the necessary
polishing resistance. Another example is maximum aggregate size. A maximum 2 in. aggregate
size is required because it gives better aggregate interlock when joints open up. If post-
tensioning is incorporated in a precast pavement, the joints will be prevented from opening up
and it may be possible to use smaller aggregate. The focus should be on what is needed for this
particular application, and not on trying to shoehorn this new technology into an old paradigm.
Design Strategy
The consensus seemed to be that the recommended concept should start on the safe side
and then back off. If corners are cut from the start, and a bad job results, it may be impossible to
overcome the poor results. It is better to start with some good jobs, then back off the
requirements until a combination is found that works and minimizes costs.
Match-Casting
The issue of match-casting the pavement panels was also discussed. If 10 ft wide panels
are match-cast, a 20 ft wide bed will be needed, which could be fairly difficult to attain. It was
felt the match casting process could be too slow and that the tolerance achieved by a modern
precast plant could provide the necessary precision for tight joints between the panels. Tongue-
and-groove joints, commonly used for sheet piling, have been used very successfully. Also, if
the panels are match-cast, and one of them is damaged somehow, that could delay construction.
The use of epoxy in the joints would help with fitting the panels together and match
casting would then probably be unnecessary. Epoxy aids with sealing of the joint and it also
develops tensile strength between adjacent panels. The characteristics of modern day epoxies
can be tailored to meet various needs.
30
3.2 First Expert Panel
poured concrete or welded connection joint that forces the panels to work together, rather than
creating a hinge.
Compressible Material
i.e. Polystyrene
Void to be Filled
With Concrete
Reinforcement Bars
Void to be Filled
With Concrete
Prestressing
The comment was made that prestressing would probably be very similar to that used in
bridge deck panels. Pretensioning could be used for the transverse prestress, and post-tensioning
for longitudinal prestress. Typical minimum levels of prestressing in wall panels range from
200–250 psi, which is sufficient to cover stripping, handling, and erection. The panels could also
be stressed concentrically so that camber will not be a problem.
Storage/Handling
Various options, such as lift loops, “dog-bones,” and “swift-lifts,” were suggested for
handling the panels. Recesses created by these devices can easily be patched with a nonshrink
concrete.
31
CHAPTER 3. EXPERT PANEL MEETINGS
The question was raised as to whether it would be possible to drive a transport truck over
the assembled panels. This ability could make access easier under situations where working
space is limited, owing to the presence of traffic. It was concluded that this might be feasible,
provided the panels are supported sufficiently.
Leveling of Panels
The use of shim stacks was recommended for leveling the panels. Enough shim stacks
would be needed in order to support the panels sufficiently, particularly if construction vehicles
would be passing over them. If the shim stacks are too tall, they can be tack-welded together.
Surface Preparation/Finishing
It was agreed that a macrotexture must be obtained on the riding surface of the panels. A
tined finish could be obtained in the prestress plant by simply dragging steel wires through the
top surface at the appropriate time.
It was suggested that the panels could be cast face down, with the tined surface then cast-
in. This could create a regular pattern, however, which could lead to harmonic problems on the
pavement. Irregular patterns were suggested, but the precasters agreed that the surface of the
panel would probably be too smooth for highway purposes anyway. Casting the panels face
down would also require that the panel be turned over, which could cause handling problems.
For the panel with BCO application, the surface of the panels should be prepared so that
sufficient bond can be developed to prevent delamination. A “turf drag” or a rough broomed
finish can easily produce the required surface texture.
Concrete Strength/Aggregates
The precast industry produces concrete with very high strengths on a daily basis. The
order of concrete strengths required for highway pavements should, therefore, easily be obtained.
Less expensive aggregates could be used in the bottom of the panel and more expensive
aggregate in the top to achieve the necessary skid and abrasion resistance. This process would
permit the use of local, softer fine aggregates and limit the use of the harder fines that are in short
supply in many areas. The comment was made that since the implementation of Superpave by
the asphalt industry, there has been a change in the usage of fine aggregates, and there are a lot
of fines around that can be used, which could even reduce the material cost.
Maximum aggregate in a precast plant is about 1 in., with the average being around ¾ in.
Checks will have to be performed to determine whether the smaller aggregates will be a problem,
especially since post-tensioning will most likely be incorporated.
Curing Conditions
Typically, in a precast plant, the application of curing compound is followed by a tarp
placed over the application. Mat curing is also possible. The expert panel was encouraged by
the fact that problems that arise from strength differentials in traditional cast-in-place pavements
would not occur in a precast pavement, as improved curing methods can be applied.
32
3.2 First Expert Panel
panels. Whether the panels could be placed along a curve also depends on the joint detail used
between the panels. The comment was made that it should not be a problem to skew the side
forms for casting “curve-panels.” For interstate applications, the horizontal and vertical curves
should be gradual enough not to present a problem, especially if the panel widths are only 12 ft.
However, problems could occur with superelevation. Allowance for geometrical eccentricities
should also be made when calculating the required post-tensioning. The length of the post-
tensioned sections might have to be shortened around curves.
Strand Size
It is likely that 0.6 in. diameter prestressing strands will be used for post-tensioning, as
they provide 40% more force per strand compared to 0.5-inch diameter strand. The majority of
precast panels are pretensioned with 3/8 in. diameter strands. Half-inch strands are also
sometimes used, depending on the panel thickness. The smaller strands have the advantage of
having shorter bond lengths.
Anchorage
It was stated that anchorage is available for 0.5 in. and 0.6 in. diameter strand. If there
are exposed end anchorages, however, encapsulation is necessary to prevent corrosion and
provide a more durable pavement. It was recommended that the anchorage could be bolted to
the steel bearing structure in the expansion joint. This procedure proved very successful in the
McLennan County prestressed pavement project in 1985.
33
CHAPTER 3. EXPERT PANEL MEETINGS
mean that construction joints would occur every 10 ft, making proper leveling of the panels
essential. It may be difficult to have a panel layout where panels are joined longitudinally and
transversely.
Leveling
During the presentation, two different leveling concepts were presented. The first
involved screw levels, whereby the elevation of the panels would be adjusted by a three- or four-
point screw level. The second concept used air bags at the corners of the panels to adjust the
elevation. With each of these concepts, the pavement would be kept about 0.5 in. off the base
surface. After leveling is completed, a thin liquid-like grout would be pumped under the slab to
fill the void beneath the slab. The advantage of the air bags is that they could be removed and
reused.
The use of shim stacks, as described earlier, was again mentioned as an alternative
method of leveling the panels. This method would be simpler and more economical than the two
methods described in the preceding paragraph.
34
3.2 First Expert Panel
leveling devices would be needed. Shims would be required only where the subbase is not
sufficiently level. A planer could even be used to smooth out the asphalt layer in areas where it
might not be sufficiently level. The asphalt layer could be placed as a separate operation,
allowing traffic onto it prior to panel placement. Planing could be performed just prior to
placement of the panels.
Longitudinal Prestress
A sleeved, monostrand could be threaded through an enlarged duct cast into the precast
panels for longitudinal post-tensioning. Investigation should be undertaken to determine whether
the protective coating around the strand is damaged during the threading process. A special
fitting or a trumpeted end might be required where panels are joined.
Construction Rate
The question was posed as to how many panels a contractor could place to be competitive
with regular construction. It was stated that this would be dependent on the size of the job and
on the location of the project with respect to the precast plant. The production rate achieved in
parking structures for double-tee sections is about 20–25 sections per day. For typical double-tee
sections of 20 ft x 60 ft, this results in about 24,000 to 30,000 sq ft per day. Pavement panel
placement should be competitive with this estimate.
Precast Contractors
The success of a precast pavement will be dependent on the contractors who will be
producing the precast panels. Concern was expressed that the level of sophistication involved is
probably above the ability of the average highway contractor. The feeling was that the general
contractor might want to do his/her own precasting, as this is where most of the profit for this
type of project can be achieved.
For this application, however, there might be reasons to prohibit the general contractor
from setting up his/her own precasting facility. Durability and long life are essential and can
easily be achieved in an established precast plant with a controlled environment, permanent
employees, onsite concrete batch plants, and a high level of quality control. These essential
qualities probably cannot be achieved by a temporary job-site operation.
35
CHAPTER 3. EXPERT PANEL MEETINGS
36
3.2 First Expert Panel
Precast Panels
• Panels should not exceed a weight of 20 tons each, as anything greater could be
difficult to handle on site.
• Panel width should be limited to 10–12 ft.
• Match-casting of the panels may be unnecessary and will slow down production.
• A tined surface texture could be provided for the riding surface of the panels.
• Lightweight concrete could be used to minimize the weight of the panels.
• Less expensive aggregates could be used in the bottom of the panel, and more
durable, more expensive aggregates in the top.
Leveling of Panels
• It may be possible to place the panels on a thin layer of asphaltic concrete so that no
additional panel leveling will be required. If needed, a planer could be used to
smooth out the AC layer even further.
• The riding surface could be smoothed out by grinding the pavement at the joints.
This operation could be done as a separate phase after traffic is turned back onto the
pavement.
• If necessary, shim stacks could be used for leveling panels.
• Grout or urethane injection could also be used to level the pavement.
Post-Tensioning
• If unbonded tendons are used, the new Post-Tensioning Institute (PTI) specification
on strand protection should be used.
• Bare post-tensioning strands could be used. These strands could be grouted in the
ducts in a subsequent operation even after traffic has been allowed back onto the
pavement.
• If end anchorages are used, encapsulation of these anchorage devices is highly
recommended.
Precast Contractor
• Durability and high quality concrete probably can be attained only in an established
precast plant, where a controlled environment, permanent employees, on-site concrete
batching plants, and a high level of quality control exist. Therefore, there might be
justification not to permit the general contractor from setting up his/her own
precasting facility.
37
CHAPTER 3. EXPERT PANEL MEETINGS
Many of these issues were resolved prior to the conclusion of the feasibility project.
However, some issues will not be resolved until actual implementation is undertaken. This will
be discussed further in Chapter 10.
38
3.3 Second Expert Panel
The purpose of the four-state pooled fund meeting was to provide a forum for
transportation officials from four different states to discuss common problems and issues with
the express intent of developing pooled funded research projects. The four states that
participated in this meeting were Texas, California, Minnesota, and Washington. Receiving
feedback from researchers and transportation officials from other areas of the country was very
important for the development of a precast pavement concept. It is hoped that this concept will
be implemented nationwide in the future, especially in states such as California, where expedited
construction is a very important issue.
The meeting with Bill Garbade, the district engineer for the TxDOT Austin District,
provided feedback on the practicality of construction of the proposed concept. The district
engineer is involved in various pavement and bridge construction projects throughout the Austin
District.
The meeting with precast suppliers/consultants provided feedback on the ideas the
researchers had come up with from the perspective of the precasting industry. Burson Patton is a
precast concrete fabricator with Texas Concrete, Inc., which fabricates structural and
nonstructural precast elements for buildings, bridges, garages, etc. Tom D’Arcy is a consultant
with The Consulting Engineers Group, Inc., which specializes in precast concrete construction.
Both have had many years of experience with precast concrete and are aware of the intricacies of
precast concrete fabrication and construction.
3.3.2 Discussions
As mentioned previously, the discussions from the second expert panel tended to focus
on the actual application and constructibility of the proposed concept. The intent was to refine
the proposed concept to make it appealing to contractors and transportation agencies. The
discussions from each of the meetings are summarized below.
39
CHAPTER 3. EXPERT PANEL MEETINGS
Meeting with the TxDOT District Engineer for the Austin District
The main issues that were discussed in this meeting regarded alternative methods to
simplify construction of the proposed concept. Alternatives to using epoxy in the panel joints (as
was part of the original concept) were discussed. Applying epoxy has been found to be a
cumbersome and time-consuming process in segmental bridge construction. The use of a thin
liquid sealant, soaked or injected into the joint after post-tensioning, was suggested.
The possibility of orienting the post-tensioning tendons at an angle, rather than parallel to
the length of the pavement, was also discussed. Skewed tendons would eliminate the need for
separate transverse and longitudinal prestressing. It would also eliminate the need for the
stressing pockets in the middle of the pavement, since the tendon anchorage would be placed
along the edges of the pavement.
Concern was expressed over how smooth the finished pavement would be, especially at
the panel joints and where the stressing pockets are located. The possibility of diamond-grinding
the pavement after placement and post-tensioning was presented as an option. Diamond-grinding
the pavement would give the pavement a very smooth and flat riding surface. Diamond-grinding
has been used successfully around the United States and has become much more cost-effective in
recent years. It may require, however, casting the panels at least 1/8 in. thicker so that they will
be flush with the expansion joints after they have been diamond-ground.
The requirements for base preparation when placing a precast pavement under a bridge
were also discussed. Because clearance will be an issue when paving under a bridge, it may be
necessary to gouge out or rotomill the existing pavement under a bridge to accommodate the
thickness of the precast pavement. The researchers noted that it may be possible to use thinner
precast panels with increased prestress for applications under a bridge.
The district engineer also recommended that a pilot section be constructed where it will
not have adverse effects on traffic if it is not finished as quickly as desired. The possibility of
constructing the pilot section on a ramp or a “comfort station” road was suggested so as to
expose the pavement to significant traffic, particularly truck traffic.
40
3.3 Second Expert Panel
The precasters estimated that a typical placement rate for double-tee beams in a parking
garage is between 20 and 30 pieces per day. If 10 ft wide precast panels were used for the
pavement, up to 300 ft of pavement could be placed each night at this rate. If more than one
crew were working, however, more could be placed. It would be ideal to have the precast panels
on-site ahead of time, instead of hauling them to the site at the time of placement.
The precast consultants felt that vertical curves that must be accommodated by the
precast panels are probably gradual enough that the keyed edges could accommodate the slight
angle created between the panels. For horizontal curves, the side forms of the precasting bed
could be angled to create skewed panel edges.
It was recommended that the transverse prestress be designed for the handling stresses
generated when the panels are handled from the ends. A type of lifting device, which clamps
onto the keyed panel edges, with a strongback for support, could be used to lift the panels, so that
lifting anchors do not have to be cast into the panels. Accommodation of this lifting device will
have to be considered when placing the panels in the field.
The precasters agreed that a thin liquid sealant should be used in the panel joints to
expedite construction. A small notch could be cast into the panels to receive the sealant material.
They recommended the possibility of using keyed ducts to protect the strands crossing the joints,
as shown in Figure 3.6. They also recommended the use of ducts with trumpeted or flared ends
to make inserting the strands easier where they cross panel joints.
Figure 3.6 Keyed duct across a panel joint for a precast pavement
41
CHAPTER 3. EXPERT PANEL MEETINGS
The idea of skewing the tendon ducts was discouraged by the precasters. Skewed ducts
would greatly complicate the casting process and would make it difficult to ensure that the ducts
are lined up exactly across the panel joints. In addition, pretensioning is necessary for
accommodating handling stresses.
3.3.3 Recommendations and Conclusions
Input from the second expert panel was essential for evaluating the proposed concept
from a practical standpoint. The information from the second expert panel led to the refinement
of the original proposed concept to maximize the efficiency of fabrication and construction of a
precast pavement. The significant recommendations for the final proposed concept and
recommendations for further investigation from the second expert panel are summarized below.
Fabrication
• Long-line fabrication will greatly increase the production rate and decrease the cost of
fabrication.
• A continuous shear key along the panel edges will simplify the casting process over
using discrete match-cast keys.
• Skewed strand ducts would greatly increase the complexity of fabrication.
• Pretensioning will provide the necessary prestress to withstand handling stresses.
• Ducts with trumpeted or flared ends will make threading post-tensioning tendons
through the ducts easier.
Construction
• The shear keys in the panel edges should be able to accommodate vertical curves.
The side forms on the casting bed can be angled to accommodate horizontal curves.
• A thin, liquid sealant soaked/injected into the panel joints after post-tensioning will
protect the post-tensioning strands from water penetrating the joint. It will also
greatly increase the construction rate over applying epoxy to the panel edges. Keyed
ducts will provide further protection for the strands.
• Diamond-grinding the pavement, after placement is completed, will ensure a much
smoother pavement, particularly at the joints.
• When the pavement is placed in an area where overhead clearance is a problem,
either the base/existing pavement can be rotomilled down, or the thickness of the
precast pavement can be decreased by increasing the prestress in the pavement.
Implementation
• A pilot section should be constructed before large-scale implementation on a major
project. The pilot section should be constructed on a rest area or “comfort station”
42
3.3 Second Expert Panel
road where delays in construction will not have adverse effects on traffic. Ramps or
weigh station roads will also work for a pilot section but may have construction time
restrictions.
Many of these issues will not be resolved until a pilot project is undertaken. This pilot
project will be discussed further in Chapter 10.
43
Chapter 4. Evaluation of Strategies
4.1 INTRODUCTION
Before a concept for a precast concrete pavement can be established, a rational evaluation
of precast construction strategies will be used to determine the pavement type to be constructed.
Four types of precast panels will be evaluated for use in construction. Three of these panel types
correspond to pavement types exclusively constructed in the U.S. For each of the four pavement
types considered, three construction applications will be considered. The first application is that
of a new pavement placed over prepared base material. The second type of construction
application is that of an unbonded concrete overlay to be used to overlay an existing pavement
requiring rehabilitation. The final construction application is that of removal and replacement.
This type of construction entails breaking up and removing the existing pavement and replacing
it with a new pavement on the existing subbase.
For each of the three construction applications, the use of full-depth precast panels or
partial-depth panels with a bonded concrete overlay (BCO) will be considered. The advantage of
using a bonded concrete overlay is that a smooth, controlled riding surface can be attained over
the top of the precast panels. This chapter will first evaluate each of these precast concrete
pavement strategies with respect to design and construction, narrowing the choices down to a
final precast panel type; it will then present a cross-section strategy for determining precast panel
sizes.
45
CHAPTER 4. EVALUATION OF STRATEGIES
46
4.3 Design and Construction
Speed of Construction
The design of conventional pavement panels is such that the panels can stand alone,
allowing traffic back onto the pavement almost immediately after placement. The strength of a
prestressed concrete pavement, however, is reliant upon the prestress provided by post-
tensioning after the entire pavement (all precast panels) is in place. This additional post-
tensioning operation for a prestressed pavement will significantly reduce the speed of
construction of a prestressed concrete pavement.
With these considerations in mind, the researchers constructed a decision matrix to
evaluate the different pavement types with respect to design and construction. Table 4.1 shows
the evaluation chart used for this purpose. Each pavement type was rated on a scale of 1 to 3,
with “1” representing a poor rating, “2” representing a fair rating, and “3” representing an
excellent rating. All design and construction considerations were given equal weight, although
different weights would not have affected the results.
Based upon this evaluation, PCP has the largest score, and thus the conventional
pavement types (JCP, JRCP, and CRCP) are eliminated from consideration for use in a precast
concrete pavement. This elimination leaves prestressed concrete pavement as the most feasible
method for precast construction. Although PCP rated low with respect to speed of construction,
which is one of the most important criterion for this feasibility project, it is believed that the
benefits of prestressed concrete panels will far outweigh the additional construction time.
Methods for further expediting prestressed construction can be developed later on.
47
CHAPTER 4. EVALUATION OF STRATEGIES
Table 4.1 Evaluation chart for design and construction considerations for each pavement type
Speed of Construction 3 3 3 1
Total 8 9 9 16
The focus of the remainder of this report, therefore, will be on the use of full-depth
precast, prestressed concrete panels for pavement construction in new, overlay, and removal and
replacement applications.
48
4.4 Cross-Section Strategy
Partial-width construction is not considered for new or overlay applications. If only one
section of the pavement is placed for an overlay application, prior to allowing traffic back onto
the pavement, there will be a drop-off from the new pavement down to the existing pavement.
For a new pavement, traffic most likely will not be allowed onto the new pavement until the full
width of the pavement is constructed.
Type of Construction
Application
Full Width Partial Width
Number of Lanes 2 3 4 2 3 4
Based on the cross-sectional strategies and selected pavement type given here, a concept
for a precast concrete pavement will be presented in the following chapter. The feasibility of
design, construction, economics, and durability will then be evaluated in subsequent chapters.
49
Chapter 5. Proposed Concept: Full-Depth Panels
5.1 INTRODUCTION
The proposed concept for a precast concrete pavement has evolved from several key
aspects of the feasibility project. The flow diagram below demonstrates the evolution of the
proposed concept. Possible concepts for a precast concrete pavement were first developed from
the literature review (Chapter 2), from the first expert panel meeting (Chapter 3), and from the
experiences of the researchers. These possible concepts were then presented to the second expert
panel for evaluation. The input from the second expert panel led to a refinement of the original
concepts to a final proposed concept.
Literature
Review
Experience
The proposed concept for a precast concrete pavement focuses on the use of full-depth
precast panels. It is believed that a smooth enough riding surface can be obtained with proper
alignment of individual panels and with occasional diamond grinding or bump cutting. The
pavement will be prestressed so as to maximize the effective thickness of the slabs. The proposed
concept consists of base panels, central stressing panels, and joint panels, similar to those items
presented in Section 2.5. The panels are placed on a single layer of polyethylene sheeting over
an asphalt leveling course. The panels are all pretensioned in the transverse direction during
fabrication and will be post-tensioned together in the longitudinal direction after placement.
Post-tensioning will not only provide a means for tying the individual panels together, but will
also prestress the pavement in the longitudinal direction as well.
The details of this concept will be discussed over the course of this chapter. The
discussion includes a description of the panels that will be used, the expansion joint and
intermediate joint details, panel assembly process, post-tensioning anchorage and post-tensioning
procedures, and base preparation. This concept applies to all of the pavement applications
discussed previously, including new pavements, unbonded overlays, and removal and
replacement applications.
51
CHAPTER 5. FULL-DEPTH PANELS
side of the panel. These keys will interlock the panels together, such that there is a tight fit and
exact vertical alignment between adjacent panels.
All of the panels will be the same length (transverse pavement direction) to simplify the
casting and assembly processes. The length of the panels will depend on the application of the
pavement, as discussed in Chapter 4. The panel width (longitudinal pavement direction) will
depend on the panel type and on the limitations of the fabrication and handling equipment. A
panel width of 10 ft will probably be the maximum width owing to precasting bed size and
transportation limitations.
Based on experience with prestressed concrete pavements, prestress in the transverse
direction is essential. Previously constructed prestressed concrete pavements, which did not
have transverse prestressing, experienced extensive longitudinal cracking and premature failure
(Ref 6). Transverse prestress will be incorporated by pretensioning the panels in the transverse
direction during fabrication.
Ducts for the longitudinal post-tensioning strands will be cast into the panels during
fabrication. Tight tolerances on the side forms of the casting bed will ensure that the post-
tensioning ducts will line up along the length of the pavement. Single- or multiple-strand ducts
may be used for post-tensioning.
5.2.1 Base Panels
Base panels are the “filler” panels between the central stressing panels and joint panels.
The number of base panels between the central stressing panel and joint panels will depend on
the slab length. Figure 5.1 shows a typical base panel. As described above, the base panels will
be pretensioned in the transverse direction during fabrication and will contain ducts for the
longitudinal post-tensioning strands. Male and female continuous shear keys will be cast into the
edges of the panels to ensure continuity and to provide proper alignment of the panels when they
are assembled. The width of the base panels will depend on the application of the pavement and
on limitations of the fabrication and handling equipment.
5.2.2 Central Stressing Panels
The central stressing panels will be similar to the base panels, though with the addition of
pockets for stressing the post-tensioning tendons, as shown in Figure 5.2. The pockets in the
central stressing panel will need to be staggered across the panel, so that the panel will have
sufficient rigidity for handling purposes and will not be susceptible to a perforation weakness
effect when the slab is post-tensioned. The idea of central stressing is one that was developed for
the cast-in-place prestressed pavement constructed in McLennan County and discussed in
Chapter 2 (Ref 6). Central stressing allows for the post-tensioning strands to be anchored at the
ends of the slab and post-tensioned from pockets at the middle of the slab. The advantage of
using this technique is that access to the end anchorage is not needed in order to post-tension the
slab. This advantage allows for a more continuous pavement placement operation.
52
5.2 Precast Concrete Panels
Ducts for
Post-tensioning
Pretensioning Strands
Ducts for
Post-tensioning
Stressing Pockets
Pretensioning Strands
53
CHAPTER 5. FULL-DEPTH PANELS
Ducts for
Post-tensioning
54
5.2 Precast Concrete Panels
55
CHAPTER 5. FULL-DEPTH PANELS
between the panel shown in Figure 5.5 and the base panel, shown previously in Figure 5.1, is the
additional post-tensioning duct for transverse post-tensioning. Most likely, this duct will be a
flat duct that can accommodate differential movement and placement offset of adjacent slabs.
Longitudinal
Post-tensioning
Ducts
Pretensioning Strands
The other primary difference with a removal and replacement application is the additional
post-tensioning process required during the panel assembly. Once an adjacent slab is placed, the
slabs will be post-tensioned together using the transverse post-tensioning ducts. To ensure that
the ducts will line up between adjacent slabs, any new slabs should be placed from the center out
(starting with the central stressing panel[s]), since the center of the slab will not move.
56
5.3 Pavement Joint Details
loads. This requirement will necessitate hardware and a structure that is not susceptible to
fatigue; constructibility and economic feasibility must also be maintained.
5.3.2 Joints from Previous Projects
Several different joint details have been developed for previously constructed precast
pavements, as described in Chapter 2. One such joint detail, developed in Japan, used straight
and “horn-shaped” dowel bars (inserted after the panels are placed) to provide the load transfer
between adjacent panels. Another joint detail used in a precast pavement in South Dakota
consisted of a tongue and fork type joint. The tongue and fork connectors were cast into the
panels and locked together with a steel wedge after the panels were set in place.
Information on expansion joint details from previous projects came from the four cast-in-
place prestressed pavements constructed prior to the prestressed pavement in McLennan County,
Texas, in 1985 (Ref 6). The information from these previous projects led to the development of
an expansion joint detail for the McLennan County project. The final joint detail used for the
McLennan County project is shown in Figure 5.6. This joint detail utilizes a steel bearing
structure for durability and a neoprene seal to prevent material from falling into the joint. Two
rows of ½ in. Nelson deformed anchor bars, approximately 3 ft long, tie the joint structure to the
pavement and reduce “rocking” of the joint as traffic passes over it, thereby reducing fatigue on
the welds in the joint. The upper and lower anchor bars are alternated over the length of the joint
so that there is only one bar every space. Dowel bars provide load transfer across the joint and
are plated with stainless steel to prevent corrosion. One of the primary advantages of this joint is
that it can be assembled as a single piece, reducing the chance that bars or dowels will be
improperly positioned. This joint detail was found to be very constructible and has performed
very well under heavy traffic loading (high truck volume) after 15 years in service.
Neoprene Seal
1/2" Ø Nelson
Deformed Bars
(~ 3' in length)
6" Weld
11/4" Ø Stainless
Steel Dowel
Existing Pavement
Figure 5.6 Expansion joint detail for the McLennan County prestressed pavement (Ref 6)
57
CHAPTER 5. FULL-DEPTH PANELS
panels, will be cast into the joint panel during fabrication. The steel flanges at the top of the joint
will be tack-welded together, prior to casting the concrete for the joint panel, to ensure that the
joint remains parallel during fabrication and placement of the panel. The weld will be removed
prior to post-tensioning and once the panel is set in place.
The anchors will be positioned in the joint panel so as not to interfere with the dowels or
bars from the joint detail. The anchors will be bolted to the joint structure to ensure that they are
correctly positioned during fabrication of the joint panel. This joint detail should be able to
accommodate the expected expansion and contraction movements of the pavement slabs while
also withstanding repeated wheel loading. In order to ensure good ride quality, however, the
joint width design should never exceed 3½–4 in.
5.3.4 Intermediate Panel Joints
The intermediate panel joints will be similar to “dry joints” used extensively in segmental
bridge construction. These joints consist of continuous keys cast into the edges of the panels, as
shown in Figures 5.1–5.3. A thin liquid sealant will be applied to the joints after assembly and
post-tensioning of the panels. This sealant will be soaked or injected into the joints to protect the
post-tensioning strands crossing the joints from water penetration.
Alignment of the keys will be ensured through strict tolerances on the casting bed and
side forms. The primary purpose of the keys is to aid with alignment of the panels during
assembly. However, the keys will also provide some degree of load transfer across the joints,
even though the prestress in the pavement provides most of the load transfer.
58
5.5 Longitudinal Post-Tensioning
The slab-base interface between precast pavement panels and the asphalt leveling course
will be different from that of a cast-in-place pavement. Precast panels will have a smooth
surface in contact with the leveling course, and will also span small voids, thereby reducing the
contact area with the leveling course. These factors will serve to further reduce the friction
between the pavement and the leveling course. Push-off tests quantifying these effects should be
conducted prior to construction of a precast pavement. However, with the present lack of data on
these effects, a friction reducing medium such as polyethylene sheeting should still be used for
precast pavement construction. At minimum, the plastic sheeting will serve as a bond breaker
between the leveling course and precast panels, allowing the finished pavement to expand and
contract with reduced frictional resistance. Additionally, assuming a frictional resistance
coefficient similar to that for a cast-in-place pavement will result in a conservative design for
precast pavements.
59
CHAPTER 5. FULL-DEPTH PANELS
Prestress
Force
fps
Joint Panel
t Prestressing Strand
Figure 5.7 Transfer length for transfer of prestress from the strand to the precast panel
The modified anchor will be bolted to the bearing plates in the expansion joint to ensure
that the anchor is properly positioned and stays in place while the concrete is cast in the joint
panel. Bolting the anchor to the bearing plates will also cause the bearing plates to contribute to
transferring the prestress to the concrete. A schematic diagram of what the expansion joint detail
60
5.5 Longitudinal Post-Tensioning
will look like with the modified anchor is shown in Figure 5.9. The anchors should be spaced
such that they to not coincide with the dowel bars in the joint detail (Figure 5.6).
An alternative to using the modified tendon anchor is the use of a standard post-
tensioning anchor. With a standard anchor, access to the anchor will be required in order to set
the wedges after the strands are inserted. One way to accomplish this will be to anchor a short
piece of the strand to the joint panel when the panel is fabricated, as discussed in Section 5.2.5.
Like the modified anchor, the standard anchor will be bolted to the bearing plates in the
expansion joint. A schematic of this concept is shown in Figure 5.10.
Holes/slots for anchor bolts
Spring
Strand
Wedges
Bearing Surface
Grout Inlet/Vent
Tendon Duct
Tapered End
Anchor Bolt
Spring-loaded Anchor Strand
Figure 5.9 Spring-loaded post-tensioning anchor cast into the joint panel
61
CHAPTER 5. FULL-DEPTH PANELS
Grout Inlet/Vent
Tendon Duct
Figure 5.10 Standard post-tensioning anchor cast into the joint panel
Post-tensioning Strands
Figure 5.11 Gap left between joint panel and base panel for inserting strands
into the anchors
62
5.5 Longitudinal Post-Tensioning
Post-tensioning Strands
Figure 5.12 Strands inserted into the anchors from pockets in the base panel
If the standard post-tensioning anchor is used, short lengths of strand will be anchored to
the joint panel during fabrication and will extend into pockets in the coupler panel, as discussed
previously. The strands will then be threaded though the ducts from the central stressing pockets
to the pockets in the coupler panel, where they will be spliced or coupled to the short lengths of
strands. Strand stressing will then be performed in the usual manner.
5.5.4 Post-Tensioning
Post-tensioning must be performed prior to allowing traffic onto the pavement. If the
pavement is not post-tensioned prior to exposure to traffic, the pavement will act as a
nonprestressed pavement. Because the thickness of the prestressed panels is significantly less
than that of an equivalent nonprestressed pavement, failure to post-tension could result in
substantial damage to the pavement after only a small amount of exposure.
The post-tensioning strands will be stressed from the central stressing pockets at the
center of the pavement slab. A portable hydraulic jacking device, similar to that used for circular
tanks and which essentially stresses both strands coming into the central stressing pockets at the
same time, may be used for the post-tensioning operation. The full post-tensioning force will be
applied after all of the panels are set in place and have been pulled together. Stressing the
strands should start with the tendons at the center of the slab and should alternate out to the
tendons at the slab edges.
A coupler device, similar to that shown in Figure 5.13, will be used for stressing and
coupling the strands in the central stressing pockets. This coupler device grips both strands
coming into the pocket simultaneously. The stressing ram is used to pull one of the strands by
reacting against the other strand, thus stressing both strands at the same time through the coupler
device. This same coupler device can also be used to splice or couple the strands in the coupler
pockets; alternatively, standard coupler chucks can be used. After all of the strands have been
stressed, the stressing pockets and coupler pockets will be filled with a fast-setting concrete that
will have attained to adequate strength by the time traffic is allowed onto the pavement. The
pockets do not have to be filled immediately after the panels are post-tensioned; however, it
should be possible to place temporary steel cover plates over the pockets until the pockets can be
filled at a later time.
63
CHAPTER 5. FULL-DEPTH PANELS
Figure 5.13 Plan view of a strand coupler used in the central stressing pockets (Ref 6)
64
Chapter 6. Design Considerations
6.1 INTRODUCTION
There are several design considerations that must be accounted for in order to develop a
precast concrete pavement that maximizes performance during its design life. These factors
affect both the durability and constructibility of a precast pavement. Durability is critical for
ensuring a high-performance pavement that has a design life equivalent to, if not longer than,
that of conventional pavements currently being constructed. Constructibility is a critical factor,
as expedited construction is the main reason for using precast pavement. The methods used for
construction must meet these expedited construction requirements.
Section 6.2 presents factors affecting the design of a precast pavement. These factors
will primarily influence the durability of the pavement. In Section 6.3, design variables used to
characterize the design factors are discussed. These variables will primarily influence the
constructibility of the pavement and will differ for each job.
65
CHAPTER 6. DESIGN CONSIDERATIONS
Compression
Tension
The continual repetition of wheel loads, especially those from heavy trucks, tends to
fatigue concrete pavements over time. Several factors, including the foundation strength and
magnitude and number of wheel loads, will dictate the effects of these factors. However, these
effects are fairly well understood for conventional concrete pavements, making it possible to
design a pavement for a specified life based on given conditions.
To determine wheel load repetition effects, the magnitude and occurrence of various
traffic loadings are converted to the total number of passes of the equivalent standard axle
loading, usually the equivalent 18-kip single-axle load (ESAL). One of the most difficult aspects
of quantifying the effects of load repetitions is predicting the number of ESALs the pavement
will experience over its design life. This number is not a constant, as the volume of vehicles has
been increasing exponentially on most major roadways each year. Methods do exist, however,
for forecasting these numbers.
6.2.2 Temperature Effects
Temperature has a significant effect on any concrete pavement, but particularly on
prestressed concrete pavements, where much longer slabs are generally constructed. Of primary
concern are two effects of temperature on prestressed concrete pavement: horizontal slab
movements (expansion and contraction) and slab curling. Expansion and contraction movements
of prestressed pavement slabs are resisted by friction between the bottom of the slab and the base
material. This frictional resistance causes stresses in the slab, which can be detrimental to the
pavement. Expansion and contraction also affects the expansion joint widths between pavement
slabs, which affects the ride quality of the pavement.
Slab curling is caused by temperature gradients across the depth of the slab. When a heat
source is acting on the top of the slab (i.e., the sun), the ends of the slab tend to curl downward,
as shown in Figure 6.2(a). However, the weight of the slab tends to counteract the curling
movement, causing tensile stresses to form in the bottom of the slab. Conversely, when a heat
source is acting on the bottom of the slab (i.e., the subbase), the ends of the slab tend to curl
upward, as shown in Figure 6.2(b). Again, however, the weight of the slab counteracts the
curling movement, causing tensile stresses to form in the top of the slab. The first condition
66
6.2 Factors Affecting Design
occurs during the warmest part of the daily temperature cycle, usually in the late afternoon. The
second condition occurs during the coolest part of the temperature cycle, usually at night and
during the early morning hours when the subbase, which acts like a “thermic battery,” is warmer
than the surrounding air owing to heat absorbed during the day. Therefore, a thorough analysis
of the slab stresses resulting from daily and seasonal temperature cycles is required to ensure that
the stresses generated from temperature effects do not exceed limiting values.
Heat
Source
Slab Weight
Tensile Stress
(a)
Slab Weight
Slab Weight
Tensile Stress
Heat
Source
(b)
67
CHAPTER 6. DESIGN CONSIDERATIONS
68
6.2 Factors Affecting Design
Figure 6.3 Three components of frictional resistance under concrete pavements (Ref 23)
Numerous experiments over the years have shown that the relationship between frictional
resistance and horizontal slab movement is inelastic (Ref 25). The resistance force versus
movement curve for most subbase materials is defined by two major factors: (1) the elastic
properties of the material beneath the slab and (2) the condition of the sliding plane and the
nature of the materials at the interface. The first factor defines the slope and shape of the curve
before sliding. The second defines the peak resistance and the shape of the curve after sliding is
reached. This relationship is shown in Figure 6.4.
The relationship between slab movement and subbase resistance can be categorized in
three ways:
• Movements partially restrained by subbase resistance: movements produced by
daily temperature changes
• Movements unrestrained by subbase resistance: concrete swelling, shrinkage, and
creep
• Movements temporarily restrained by subbase resistance: elastic shortening,
which is diminished by the friction when the prestress force is applied, but which
affects the full slab length shortly after prestressing
69
CHAPTER 6. DESIGN CONSIDERATIONS
Figure 6.4 Frictional resistance versus movement for concrete pavements (Ref 25)
Because long-term movements from seasonal temperature changes occur at minute daily
rates, as compared to daily temperature movements, they therefore take place without significant
frictional resistance. Frictional resistance to movements from daily temperature changes,
however, produces stresses in the slab. Compressive stresses will develop when the slab
expands, while tensile stresses will develop when the slab contracts. The latter situation is more
critical, as these tensile stresses may be additive to those tensile stresses caused by wheel loads
and curling to such an extent that the slab may crack (Ref 25).
Movement of concrete pavement slabs caused by temperature variation decreases from a
maximum at the slab ends to zero movement at the center. Likewise, frictional resistance also
decreases from a maximum at the ends to zero at the center. The result is tensile stresses (for
slab contraction) increasing from zero at the ends to a maximum at the center. This relationship
is illustrated in Figure 6.5(a).
In a prestressed (post-tensioned) pavement, frictional resistance has another effect.
Frictional resistance causes a decrease in the amount of compressive stress transferred to the
concrete from post-tensioning. This effect is illustrated in Figure 6.5(b). The reduction of post-
tensioning force along the slab requires that a higher post-tensioning force be applied at the ends
of the slab.
70
6.2 Factors Affecting Design
(a) (b)
To reduce the effect of subbase frictional resistance, which causes tensile stresses in the
pavement and reduces the amount of prestress transferred to the concrete during post-tensioning,
a friction-reducing membrane is placed beneath prestressed pavements to lower the coefficient of
friction between the pavement slab and supporting base.
The three main considerations in selecting a friction-reducing medium are the following
(Ref 23):
Previous research and experience have found a single layer of polyethylene sheeting to be
a very practical friction-reducing medium for meeting these requirements. The use of this
material will be discussed in more detail in Chapter 8.
An additional consideration, with regard to subgrade restraint, is that the bottom of
precast panels will be very smooth, unlike that of a cast-in-place prestressed pavement, in which
the concrete conforms to the roughness of the base surface. The precast panels will also be very
rigid, spanning small voids in the leveling course, thereby reducing the contact are between the
bottom of the slab and supporting layer. These effects will result in a reduction of the shear
effect, described previously, at the slab-base interface.
71
CHAPTER 6. DESIGN CONSIDERATIONS
Extensive testing and experience in the prestressed concrete practice have produced
methods to reliably predict the effects of these factors. A detailed discussion of the relationships
that have been developed through research and experience for each of these factors can be found
elsewhere (Ref 6).
6.2.6 Transverse Prestress
Transverse prestress is an essential component of any prestressed (precast) concrete
pavement. An extensive investigation of four prestressed pavements constructed in the United
States, prior to the development of the prestressed pavement constructed in McLennan County
(Chapter 2), found that a lack of transverse prestress in those pavements resulted in extensive
longitudinal cracking after exposure to traffic (Ref 6). Therefore, it is essential that transverse
prestress be incorporated in a precast pavement.
Owing to the relatively short width of prestressed pavements (transverse direction), as
compared to the length, the effects of prestress losses, particularly subgrade restraint and slab
curling, are minimal, as compared to the longitudinal direction. One of the advantages of a
precast concrete pavement is that the prestress for the transverse direction can be obtained
through pretensioning, during fabrication of the panels. In addition, pretensioning will prevent
cracking from occurring during handling of the panels, as mentioned in Chapter 4. In general,
the handling stresses will usually govern the magnitude of the required transverse prestress.
6.2.7 Joint Movement
Horizontal slab movements, owing to expansion and contraction of prestressed (precast)
concrete pavement slabs caused by daily and seasonal temperature cycles, result in movement of
the expansion joints between slabs. These joint movements can become fairly substantial,
depending on the length of the slabs. As the slab length increases, so too does the amount of
horizontal slab movement (and, hence, the expansion joint movement). In general, the expansion
joint width requirements usually govern the permissible slab length.
In order to prevent damage to the expansion joint and the possible crushing of the
concrete at the joint, the expansion joints should never be fully closed. Thus, an initial joint
opening must be provided when the pavement is constructed. This initial joint width will be
different, depending on the design slab length and the time of year that the pavement is
72
6.3 Design Variables
constructed. For example, a pavement constructed in the winter will experience more expansion
than a pavement constructed in the summer and will consequently require a larger initial joint
width during construction. To ensure good ride quality, it is desirable to ensure that the
maximum joint width will be less than 4 in. As with the minimum joint width, this maximum
joint width will depend on the slab length and time of year when the pavement is constructed.
Expansion and contraction movements are well understood and can be fairly accurately
predicted for given conditions. Conditions that affect expansion and contraction movements
include the amount of prestress in the pavement, type of friction-reducing medium beneath the
slab, coefficient of thermal expansion of the concrete, and the length of the slab. It is essential
that these movements be calculated prior to slab construction using given conditions so that the
limiting joint width requirements are met.
6.2.8 Site Geometry
Another important design consideration for precast pavements is ensuring that
rectangular precast concrete panels will be able to conform to the geometry of a roadway with
vertical and horizontal curves. In order to determine the effects of horizontal and vertical curves,
the 1994 AASHTO publication, “A Policy on Geometric Design of Highways and Streets,” may
be used to determine the minimum expected horizontal and vertical curves for a given design
speed. The angle created between the adjacent precast panels can then be computed by using
geometric relationships, as will be demonstrated in Chapter 7.
1) The stress in a pavement for a given load is inversely proportional to the strength of
the supporting foundation.
2) The ability of the pavement to withstand repetitive loads is proportional to the
strength of the supporting foundation.
The first relationship implies that, as the supporting foundation becomes weaker, the
stresses generated in the pavement by wheel loads will increase. This action will result in
cracking and failure of a pavement on a weaker supporting foundation earlier than it will on a
pavement on a stronger supporting foundation. The second relationship implies that a pavement
with a weaker supporting foundation will fatigue and eventually fail faster than a pavement with
a stronger supporting foundation.
73
CHAPTER 6. DESIGN CONSIDERATIONS
Methods such as cement stabilization have been developed and used extensively for
increasing pavement foundation strength. However, since the main purpose of using precast
concrete panels is to expedite construction of pavements, it may not be practical to strengthen the
existing foundation during precast construction. Fortunately, the prestress level can be adjusted
to account for lower foundation strengths.
6.3.2 Pavement Thickness
Thickness of conventional concrete pavements is generally governed by foundation
strength, concrete strength, and the number and magnitude of wheel load repetitions. For a
prestressed (precast) concrete pavement, however, there is more flexibility with the pavement
thickness. In most cases, it is possible to simply select a desired pavement thickness and adjust
the amount of prestress in the pavement to meet the design criteria. Although the relationship
between foundation strength and pavement performance is not very well understood for
prestressed (precast) concrete pavements, these design criteria will be assumed to be the same as
that mentioned above, for conventional pavements.
A reasonable limit for precast pavement thickness seems to be a thickness not less than
50 to 60% of the thickness that would be used for a conventional concrete pavement. At the
same time, the thickness should be such that sufficient cover is provided for all of the
reinforcement and other hardware (such as anchorage) contained in the pavement. As the
thickness is reduced, stresses should be evaluated in the lower layers of the pavement structure to
ensure that they are at acceptable levels.
6.3.3 Magnitude of Prestress
The magnitude of prestress refers to the prestress force applied to the pavement from
pretensioning or post-tensioning. The magnitude of prestress varies along the length of the
pavement owing to prestress losses, as described earlier in this chapter. The magnitude of
prestress must be such that the compressive stress at all points along the length and width of the
pavement is greater than or equal to the minimum compressive stress required to meet the fatigue
requirements over the life of the pavement. The fatigue requirements are a function of the
number of load repetitions and foundation strength. These requirements will be discussed further
in Chapter 7.
The compressive stress at any point along the length of the pavement can be expressed as
a critical stress combination, which accounts for the magnitude of the applied prestress, stress
generated by applied wheel loads, curling stress resulting from temperature differential over the
depth the slab, and friction stress caused by subbase resistance. This critical stress combination
is given by Equation 6.1 below:
σ CR = σ P + σ W + σ C + σ F (6.1)
74
6.3 Design Variables
Stresses are different in the top and bottom of the slab, requiring both the top and bottom
to be analyzed. Curling stresses are assumed to be equal and opposite (tensile [+] versus
compressive [-]) in the top and bottom of the slab. Stresses caused by applied wheel loads are
assumed to be tensile (+) in the bottom of the slab, and zero in the top (although compressive
stresses would actually be expected). Friction, from slab-base interaction, causes both tensile (+)
and compressive (-) stresses, depending on the movement of the slab, and is assumed to be
uniform over the pavement depth. Although these stresses vary along the length of the
pavement, essentially the only two points at which the stresses must be evaluated are at the ends
of the slab and at mid-slab.
6.3.4 Section Length
Section length is the length of the pavement slab between expansion joints. Each section
will consist of several precast panels tied together through post-tensioning, as described in
Chapter 5. As mentioned earlier in this chapter, the section length will be primarily governed by
the expansion joint width requirements. As the section length is increased the amount of slab
expansion and contraction (caused by temperature cycles) also increases, causing wider (or
narrower) expansion joint widths.
There are several factors to consider with regard to the section length. The first factor is
that the cost of the expansion joints is inversely proportional to the slab length. As the slab
lengths are decreased, the number of expansion joints, which are a significant cost component of
prestressed (precast) concrete pavements, increases. Another factor is that the magnitude of
prestress, and hence the cost of prestressing, increases as the section length is increased. In
conjunction with this consideration is the fact that as the section length is increased, the
maximum expansion joint widths also increase, thereby affecting the ride quality of the
pavement. Therefore, a compromise must be sought between economics and quality of the final
product, in order to select the optimal section length.
6.3.5 Section Width
Section width refers to the distance between the exterior edges of the finished pavement
(transverse direction). Section width is governed by several factors including:
• pavement application
• equipment limitations
• public traffic accommodation
Pavement application refers to the type of pavement that will be constructed. This could
be a single-lane or multi-lane pavement. If a one- or two-lane pavement is to be constructed, it
may be possible to use precast panels that are the full width of the pavement. If more than two
lanes are to be constructed, multiple precast panels may be required to cover the full section
width, as described in Chapter 4.
Equipment limitations refer to the size of precast panels that can be accommodated. It
will be advantageous to use precast panels that are the full width of the pavement, to eliminate
longitudinal joints. However, this may result in the use of very large precast panels, and
equipment limitations may be encountered during fabrication, transportation, or placement of
these panels.
75
CHAPTER 6. DESIGN CONSIDERATIONS
76
Chapter 7. Feasibility Analysis: Design
7.1 INTRODUCTION
This chapter is the first of three chapters in which the recommended concept presented in
Chapter 5 is evaluated. The proposed concept utilizes full-depth, precast concrete panels that are
pretensioned in the transverse direction during fabrication, and post-tensioned in the longitudinal
direction after they have been set in place on a single layer of polyethylene sheeting over a thin
asphalt leveling course. Three types of panels are used between consecutive expansion joints in
order to form a continuous slab when they are all post-tensioned together. These panel types
consist of joint panels at the ends of the slab, a central stressing panel in the center of the slab,
and base panels between the joint and central stressing panels.
Although precast pavement construction will have many advantages over conventional
pavement construction, such as speed of construction, increased durability, and reduction in user
costs, in order for a precast concrete pavement to truly be a feasible alternative to conventional
concrete pavement it must have a design life at least equivalent to that of conventional pavement.
Incorporated in this equivalent design is elastic design for fatigue loading, and elastic design for
environmental stresses and wheel loads. Ultimately, the pavements must be constructed side-by-
side to compare their performance under the same conditions. For now, however, this analysis
will show that it is possible to design a precast concrete pavement using accepted design
procedures so that the pavement has a design life equivalent to that of a conventional pavement
but which requires a significantly reduced pavement thickness.
7.1.1 Equivalent Pavement
The primary basis for developing a precast pavement having a design life equivalent to
that of conventional pavements is through the elastic design for fatigue. Fatigue loading design
takes into account the effect of repeated load applications on the pavement over its design life. A
continuously reinforced concrete (CRC) pavement was selected as the control pavement for
comparison. A CRC pavement was selected primarily because CRC pavements are commonly
being constructed on major highways, including one designed by CTR currently under
construction on I-35 in TxDOT’s Waco District. It should be noted, however, that the same
procedures can also be used to develop a precast pavement with a design life equivalent to that of
a jointed reinforced concrete pavement (JRCP).
The control CRC pavement was designed with the following design parameters, using the
existing base conditions along a section of I-35 in the Waco District:
A design life of 30 years is typical for pavements currently being constructed and is
essential for pavements constructed on heavily trafficked roadways. The number of ESAL
applications, for the 30 year design life, was determined from regression models developed at
CTR for forecasting the expected number of 18-kip ESALs in the design lane, given an expected
77
CHAPTER 7. FEASIBILITY ANALYSIS: DESIGN
growth rate (Ref 26). The concrete tensile strength and modulus of elasticity are 28-day values
typically used for concrete pavement design.
Based on the design criteria and on the existing base conditions where the pavement is
being constructed, a pavement thickness of 14 in. was selected for the control CRC pavement
(Ref 27). Under the same design criteria and base conditions, a pavement thickness of 15 in.
would be required for a JRCP.
7.1.2 Design Procedure
The first step in the design procedure was to determine the prestress requirements for a
precast pavement of varying thickness, based upon the elastic design for fatigue loading. The
fatigue loading design criteria were determined from an equation developed by Taute (Ref 28),
which relates the number of 18-kip ESALs to the ratio of the concrete flexural strength over the
tensile stress at the bottom of the pavement. This relationship will be discussed in more detail in
Section 7.2.
The second step in the design procedure was to determine, for a selected pavement
thickness and slab length, the prestress force (to be applied from post-tensioning) needed to meet
the prestress requirements from fatigue loading, taking into account environmental stresses and
wheel loads. This step was carried out for both minimum and maximum expected slab lengths to
get an upper and lower bound on the prestress requirements. This step was also performed for
various weather (summer versus winter) conditions to determine under which conditions the
critical stress combination (Eq. 6.1) would occur.
The third step was to select a slab length to meet the expansion joint width requirements.
For a selected slab thickness and corresponding prestress, the length of the slab was varied
(between the minimum and maximum expected slab lengths) to determine the minimum and
maximum expansion joint widths. From this, an optimal slab length was selected based on the
weather condition at the time of placement.
78
7.2 Elastic Design for Fatigue Loading
from a falling weight deflectometer (FWD). For this analysis, the elastic moduli of the subbase
layers were based on the results obtained during the backcalculation of the resilient modulus.
The resulting support structure and loading, used for the elastic layered theory analysis of
the control CRC pavement, are shown in Figure 7.1. The pavement structure was assumed to be
loaded by a 20 kip ESAL with a tire pressure of 125 psi. Two slightly different support
structures were analyzed in order to account for the variability in the support conditions where
the CRCP control section is being constructed. The difference in the two pavement structures is
the elastic modulus of the asphaltic concrete pavement (ACP) layer. A moderate elastic modulus
of 1,042 ksi was selected for one analysis, and a low elastic modulus of 780 ksi was selected for
the second analysis. The layered structure below the ACP represents the worst conditions that
were found where the CRC pavement is being constructed. Such conditions will provide
somewhat conservative results.
Figure 7.1 CRC pavement structure analyzed using elastic layered theory
The tensile stress, σT, generated at the bottom of the 14 in. CRC control pavement, for the
given support structure and loading, was determined through the use of the elastic layered theory
computer program BISAR (Bitumen Structures Analysis in Roads). The stress was computed
directly beneath the loads and at the midpoint between the loads to determine the highest stress
for the loading condition. The amount of slip between the ACP layer and the CRCP was varied
to represent the presence of a friction-reducing membrane between the two layers (for the precast
concrete pavement). The different slip conditions analyzed were: frictionless slip, half slip, “1/4
slip” or 75% cohesion, and no slip. Table 7.1 shows the different values for the tensile stress in
the bottom of the 14 in. CRC control pavement for these different conditions.
79
CHAPTER 7. FEASIBILITY ANALYSIS: DESIGN
Table 7.1 Bottom fiber tensile stress (σT) at the bottom of the 14 in. CRC pavement for various
support conditions
The same pavement structure, shown in Figure 7.1, was used to determine the tensile
stress at the bottom of an equivalent precast concrete pavement of varying thickness for the same
loading conditions. Only the “frictionless slip” condition was analyzed, however, as this was
shown to be the critical case from the analysis of the 14 in. control pavement. This analysis will
result in somewhat conservative results, as there will always be some amount of friction between
the actual pavement and the supporting structure. Figure 7.2 shows the tensile stresses versus
pavement thickness that resulted from this analysis. These stresses will be used to determine the
prestress requirements for the fatigue loading design.
140
f t = 700 psi
120
100
Tensile Stress (psi)
80
60
40
20
0
5 6 7 8 9 10 11 12 13 14 15
Precast Pavement Thickness (inch)
Figure 7.2 Bottom fiber tensile stress versus precast concrete pavement thickness as
determined from elastic layered theory
80
7.2 Elastic Design for Fatigue Loading
3.00
f
N18 = 46,000 (7.1)
σT
To determine the fatigue stress ratio, Re, for a precast pavement, the required prestress
(σPR) was subtracted from the bottom fiber tensile stress, obtained from layered theory, as shown
below:
σ − σ PR
R e = T (7.2)
f
Using a flexural strength of 700 psi, the required prestress, (σPR), was backcalculated
using the fatigue stress ratio from the CRC control pavement and the tensile stresses, calculated
using layered theory, for each precast pavement thickness. The results of this analysis are shown
in Figure 7.3 (EACP = 1,042 ksi) and Figure 7.4 (EACP = 780 ksi).
81
CHAPTER 7. FEASIBILITY ANALYSIS: DESIGN
70
f= 700 psi
E(ACP)=1042 ksi
60
50
Required Prestress (psi)
40
30
20
10
0
5 6 7 8 9 10 11 12 13 14 15
Precast Pavement Thickness (inch)
Figure 7.3 Required prestress for various precast pavement depths for EACP = 1,042 ksi
80
f = 700 psi
E(ACP)=780 ksi
70
60
Required Prestress (psi)
50
40
30
20
10
0
5 6 7 8 9 10 11 12 13 14 15
Precast Pavement Thickness (inch)
Figure 7.4 Required prestress for various precast pavement depths for EACP = 780 ksi
The required prestress (σPR) shown in Figures 7.3 and 7.4 is, therefore, the minimum
compressive stress required at every point along the pavement to produce a precast concrete
pavement with a design life equivalent to that of the 14 in. CRC (15 in. JRC) control pavement.
The actual applied post-tensioning force, as determined from the elastic design for environmental
82
7.3 Elastic Design for Environmental Stresses and Wheel Loads
stresses and wheel loading (discussed below), will be significantly higher than the required
prestress (σPR), however, owing to prestress losses that occur within the pavement.
Geometric Properties
The geometric inputs for the PSCP2 program include the slab (section) length (between
expansion joints), slab (section) width, and slab thickness.
Concrete Properties
The concrete properties include the coefficient of thermal expansion, the ultimate
shrinkage strain, unit weight, Poisson’s ratio, creep coefficient, and age-compressive strength
relationship. As mentioned previously, it is necessary to “trick” the program to account for the
differences of a precast pavement. This trick can be accomplished by specifying a very low
ultimate shrinkage strain and a very high early-age strength (age-compressive strength
83
CHAPTER 7. FEASIBILITY ANALYSIS: DESIGN
relationship) to account for the fact that the concrete will already be cured and up to full strength
by the time the precast panels are placed.
Steel Properties
The steel properties include the strand cross-sectional area, yield strength, elastic
modulus, and thermal coefficient. The spacing of the strands, which dictates the amount of
prestress applied to the slab, is also specified. The strand spacing is varied to adjust the amount
of prestress in the pavement (to meet the fatigue requirements).
Prestress
The PSCP2 program allows for multiple-stage post-tensioning. This process is essential
for cast-in-place prestressed pavements for which it is essential to apply an initial prestress
within the first several hours after concrete placement to prevent shrinkage cracking. For a
precast concrete pavement, however, only one stage of post-tensioning is required. The program
allows for specification of the amount of prestress (per strand) and the number of hours after
placement at which the prestress is applied. Prestress is specified by varying the spacing of the
post-tensioning strands and the prestress force applied to each strand.
Slab-Base Interaction
The slab-base interaction inputs include the friction-displacement relationship and the
stiffness of the slab support. The friction-displacement relationship can be specified as either a
linear, multi-linear, or exponential relationship between the coefficient of friction between the
slab and the base, and the corresponding displacement.
Analysis Period
The analysis period input specifies the number of days after placement the pavement is to
be analyzed. The program automatically analyzes the pavement for the first 24 hours. It also
allows for specification of multiple analysis periods beyond the first 24 hours in order to
examine the stresses and end movements occurring during the pavement design life. An analysis
period near the end of the expected design life should be specified, at minimum.
Temperature
Temperatures are usually specified for the first 24 hours after placement and for any
future analysis periods. Mid-depth slab temperature, top-bottom temperature differential, and the
time of day are all specified. The concrete setting temperature is also specified. For a precast
concrete pavement, the setting temperature will be the temperature of the concrete at the time the
precast panels are placed.
84
7.3 Elastic Design for Environmental Stresses and Wheel Loads
Table 7.2 Minimum compressive stress from the fatigue loading design for a typical precast
pavement for two different asphalt support layer conditions
The preliminary analysis also focused on using two different concrete coefficients of
thermal expansion, one corresponding to that of siliceous river gravel and the other
corresponding to that of limestone. The final analysis, however, focused on only one thermal
coefficient and one pavement thickness. The following inputs were used for these PSCP2
analyses to determine stresses and horizontal end movements, given these analysis parameters.
85
CHAPTER 7. FEASIBILITY ANALYSIS: DESIGN
Geometric Properties
For the preliminary analysis, 6 and 8 in. pavement thicknesses were analyzed for slab
lengths of 240 ft and 440 ft. The slab width was set at 38 ft, which corresponds to a typical four-
lane interstate pavement width with two 12 ft lanes, a 10 ft outside shoulder, and a 4 ft inside
shoulder. For the final analysis, the slab length was varied from 100 ft to 440 ft and slab
thickness was set at 8 in.
Concrete Properties
In order to “trick” the PSCP2 program into accounting for the differences of a precast
concrete pavement, the age-compressive strength relationship was specified such that the
concrete had reached its full compressive strength of 4,000 psi at 0.01 days. The 3, 7, 14, and 28
day compressive strengths were specified at 4,000 psi also. The ultimate shrinkage strain was
specified at 0.0001 in./in., which is what might be expected from precast concrete.
Two different values were used for the coefficient of thermal expansion during the
preliminary analysis, the first (α = 9.18 x 10-6 in./in./ºF) corresponding to that of a typical
siliceous river gravel aggregate and the second (α = 6.57 x 10-6 in./in./ºF) corresponding to that
of a typical limestone aggregate. These values, which were obtained from a coarse aggregate
project conducted at CTR (Ref 29), correspond to 28 day concrete at 100 oF and 40% humidity.
Since it was decided that limestone aggregate would most likely be used for actual construction,
a value of 6 x 10-6 in./in./ºF was used for the final analysis. For the remaining inputs, a value of
150 lb/ft3 was specified for the unit weight of the concrete, a value of 0.2 was specified for the
Poisson’s ratio, and a value of 2.1 was specified for the creep coefficient.
Steel Properties
Six-tenths (0.6 in.) diameter strand was specified for the prestressing (post-tensioning)
steel, with a corresponding cross-sectional area of 0.216 in.2, a yield strength of 230 ksi, an
elastic modulus of 30 x 106 psi, and a thermal coefficient of 7 x 10-6 in./in./ºF.
Prestress
The pavement was assumed to be post-tensioned in the longitudinal direction, in one
stage, 6 hours after placement. The strands were assumed to be stressed to 70% of their ultimate
strength, corresponding to 189 ksi, which is probably somewhat conservative.
Slab-Base Interaction
Two different values were used for the slab support for the preliminary analysis. Values
of 500 psi/in. and 2,000 psi/in. were used, corresponding to weak and moderate slab support,
respectively. The preliminary analysis revealed, however, that slab support had no effect on the
environmental design stresses or on horizontal movements. Therefore, a single value of 500
psi/in. was used for the final analysis. The slab support value specified for the PSCP2 analysis
does not correlate with the slab support values used for the elastic layered theory analysis
described previously.
The friction-displacement relationship was assumed to be a linear relationship with a
maximum coefficient of friction of 0.2 and corresponding displacement of 0.02 in. at sliding.
Although extensive testing has found that the maximum coefficient for slabs placed on a single
layer of polyethylene sheeting is around 0.92, the value used for this analysis was obtained from
actual measurements of the cast-in-place prestressed pavement in McLennan County. As
86
7.3 Elastic Design for Environmental Stresses and Wheel Loads
mentioned previously, the frictional resistance for precast panels will be different than that for
cast-in-place pavements, but due to a lack of data on these differences, the values obtained from
the McLennan County prestressed pavement were assumed, providing conservative results.
Analysis Period
The precast concrete pavement is expected to have a design life of at least 30 years. At
30 years, the prestress will be at a minimum, owing to relaxation of the post-tensioning strands.
Therefore, the number of days after placement for the final analysis was specified at 10,950. In
addition, another analysis period at 1 year was specified to ensure that the critical stress
combination was not occurring earlier than 30 years. For determining maximum horizontal
movements, a third analysis period of 90 days was also specified.
Temperature
Temperature data was specified for the first 24 hour period after placement and for a 24
hour period at the specified final analysis periods (90 days, 1 year, 30 years). The temperature
data used in the analysis was actual temperature data collected from the McLennan County
prestressed pavement project (Ref 30). Six sets of temperature data were collected for the
McLennan County project. From these six sets, one set representing a typical summer condition
and one set representing a typical winter condition were selected. The temperature data and the
dates on which they were collected are shown in Table 7.3.
Table 7.3 Temperature data from McLennan County cast-in-place prestressed concrete
pavement used for PSCP2 program
For purposes of analysis, four temperature condition cases were considered. For each
case, one set of temperature data was specified for the initial 24 hour period after placement, and
another set of temperature data was specified for the final analysis periods. The first case
87
CHAPTER 7. FEASIBILITY ANALYSIS: DESIGN
considered placement of the pavement in the winter and final analysis period(s) (at 90 days, 1
year, and 30 years), also in the winter. The second case considered placement in the winter and
final analysis in the summer. The third case considered placement of the pavement in the
summer and final analysis in the summer, while the final case considered placement in the
summer and final analysis in the winter. The slabs were assumed to be placed at 2:00 p.m. for all
four cases.
The setting temperature, or the temperature of the precast panels at the time of placement,
was calculated from a relationship between the ambient temperature and concrete temperature
given by (Ref 31):
For the temperature sets given above, a setting temperature of 95 oF was specified for
summer placement and 60.4 oF for winter placement.
Table 7.4 Wheel load stresses from layered theory for interior slab loads
88
7.3 Elastic Design for Environmental Stresses and Wheel Loads
was met. The critical stress combination was checked only at two critical locations along the
length of the slab — at the ends of the slab and at mid-slab.
The required strand spacing, as determined from this analysis, is shown in Figures 7.5 –
7.8 for 6 in. and 8 in. thick pavements. Figures 7.5 and 7.6 show the required strand spacing for
slabs with a thermal coefficient corresponding to siliceous river gravel (SRG) aggregate for the
weak and moderate asphalt support layers, respectively. Figures 7.7 and 7.8 show the required
strand spacing for slabs with a thermal coefficient corresponding to limestone (LS) aggregate for
the weak and moderate asphalt support layers, respectively. As mentioned previously, the
analysis was performed for both the 240 ft and 440 ft slab lengths.
-20
Stress in Pavement (psi)
6" x 240'
-40 6" x 440'
8" x 240'
-60 8"x 440'
6" Min Prestress
-80
8" Min Prestress
-100
-120
-140
12 14 16 18 20 22 24
Strand Spacing (in.)
Figure 7.5 Required strand spacing for slabs with siliceous river gravel (SRG) aggregate and
weak asphalt support layer (EACP = 780 ksi)
0
Stress in Pavement (psi)
6" x 240'
-20
6" x 440'
8" x 240'
-40
8"x 440'
6" Min Prestress
-60 8" Min Prestress
-80
-100
12 14 16 18 20 22 24 26
Strand Spacing (in.)
Figure 7.6 Required strand spacing for slabs with siliceous river gravel (SRG) aggregate and
moderate asphalt support layer (EACP = 1,042 ksi)
89
CHAPTER 7. FEASIBILITY ANALYSIS: DESIGN
-100
-120
16 18 20 22 24 26
Strand Spacing (in.)
Figure 7.7 Required strand spacing for slabs with limestone (LS) aggregate and weak asphalt
support layer (EACP = 780 ksi)
0
Stress in Pavement (psi)
-20
6" x 240'
6" x 440'
-40
8" x 240'
-60 8"x 440'
6" Min Prestress
-80 8" Min Prestress
-100
-120
16 18 20 22 24 26 28 30
Strand Spacing (in.)
Figure 7.8 Required strand spacing for slabs with limestone (LS) aggregate and moderate
asphalt support layer (EACP = 1,042 ksi)
For all slabs with a coefficient of thermal expansion corresponding to siliceous river
gravel, the critical stress combination was found to occur at the 30 year (after placement) winter
analysis period for slabs placed during the summer. The critical stress occurred in the top of the
slab at the mid-slab location at 6:00 a.m. For the 8 in. slabs with a limestone thermal coefficient,
the critical stress combination was found to occur at the 30 year winter analysis period for slabs
placed in the winter. The critical stress occurred in the top of the slab at mid-slab at 6:00 a.m.
For the 6 in. slabs with the limestone thermal coefficient, the critical stress combination occurred
at the 30 year summer analysis period for slabs placed in the winter in the bottom of the slab at
the slab end at 6:00 p.m.
90
7.3 Elastic Design for Environmental Stresses and Wheel Loads
Table 7.5 Transverse prestress requirements for 38-ft x 10-ft precast panels
91
CHAPTER 7. FEASIBILITY ANALYSIS: DESIGN
joint widths for winter placement of the pavement on weak and moderate asphalt support layers,
respectively. The shaded regions in Figures 7.9 through 7.12 represent the required strand (0.6
in. diameter) spacing for the different slab lengths, as determined from Figures 7.7 and 7.8.
Minimum
5
Maximum
Joint Opening (in.)
0
100 200 300 400
Slab Length (ft)
Figure 7.9 Minimum and maximum joint widths for summer placement
on weak asphalt support layer (EACP = 780 ksi)
Minimum
5
Maximum
Joint Opening (in.)
0
100 200 300 400
Slab Length (ft)
Figure 7.10 Minimum and maximum joint widths for summer placement on moderate
asphalt support layer (EACP = 1,042 ksi)
92
7.3 Elastic Design for Environmental Stresses and Wheel Loads
Figure 7.11 Minimum and maximum joint widths for winter placement
on weak asphalt support layer (EACP = 780 ksi)
3.0
2.5
2.0
1.5
1.0
0.5
0.0
100 200 300 400
Slab Length (ft)
Figure 7.12 Minimum and maximum joint widths for winter placement
on moderate asphalt support layer (EACP = 1,042 ksi)
For both summer and winter slab placement, the maximum joint width was found to
occur at 8:00 a.m. at the 30 year winter analysis period. For winter pavement placement, the
minimum joint width was found to occur at 4:00 p.m. within the first 90 days after placement
under summer conditions. For summer pavement placement, the minimum joint width occurred
at 2:00 p.m., 12 hours after the pavement was placed. As summer and winter placement
represent extreme conditions, placement of the pavement under fall or spring temperature
conditions will result in joint widths somewhere between those given by this analysis.
93
CHAPTER 7. FEASIBILITY ANALYSIS: DESIGN
The results of this analysis show that, for an 8 in. limestone aggregate, precast concrete
pavement, the expansion joint will never fully close for slab lengths up to 440 ft (with an initial
width of 1½ in.). For winter placement of the pavement, there is no restriction on the slab length
(up to 440 ft) to meet the maximum joint width requirement of 4 in. For summer placement,
however, the slab length should be limited to 340 ft to meet the maximum joint width
requirement.
As stated previously, it should be noted that the frictional resistance between the slab and
base, which affects the amount of slab movement, will be different for a precast pavement than a
cast-in-place pavement. However, due to a lack of data on these differences, the same slab-base
interaction was assumed. Push-off tests conducted prior to construction of a precast pavement
will help to quantify these differences for future projects.
94
Chapter 8. Feasibility Analysis: Construction
8.1 INTRODUCTION
This chapter is the second chapter in which the recommended concept, presented in
Chapter 5, is evaluated. This chapter focuses on the feasibility of precast concrete pavement
construction. Issues discussed include fabrication of the precast panels, installation/placement of
the panels, and estimated production rates for pavement placement. Some of the major
differences between precast concrete construction and conventional pavement construction
become apparent in this analysis.
There are several advantages to precast concrete pavement construction over
conventional pavement construction. The most notable advantage is the speed with which a
precast concrete pavement can be assembled and exposed to traffic. Although it may not be
possible to place as much precast pavement during one day’s construction as can be placed using
conventional pavement, it will be possible to assemble the pavement piecewise, allowing traffic
back onto the pavement between construction sequences. This provides the option of
constructing during “off peak” periods, such as at night and on weekends. The primary emphasis
in this chapter is the use of a precast pavement for a new pavement or unbonded overlay. In
Section 8.7, however, the removal and replacement application is also discussed.
8.2 FABRICATION
Based on discussions with precast consultants, the most effective method for fabrication
appears to be through the use of a “long line” process, as described in Chapter 3. There are
essentially two options for fabricating the precast concrete panels. The first option is on-site
fabrication, whereby the panels are cast at or near the construction site. The second option is off-
site fabrication, whereby the panels are cast at an existing precasting plant and transported to the
construction site. Each of these options will be discussed in this section.
8.2.1 On-Site Fabrication
On-site fabrication will probably be feasible only for large pavement jobs located in
remote areas. On-site fabrication requires setting up a precasting bed at or near the job site.
Depending on the size of the precasting bed, this setup may require a large section of land. Land
will also be required for storage of the panels after they are cast. The precasting bed itself will
require large pretensioning abutments to be constructed (to very strict tolerances). Consideration
must also be given to who will supply the concrete. Most likely, it will be necessary to set up a
small concrete batch plant on-site to supply the concrete, mainly to ensure that a consistent,
proper concrete mixture is used for each pour. Transporting concrete to the site could be very
costly, depending on the location of the job site.
Although on-site fabrication seems cost-prohibitive at first, it may actually be more
economical, depending on the size and location of the paving job. The more precast panels that
are needed, the more the unit-cost of fabricating the panels decreases. Transporting the panels
from an existing precasting plant could be very expensive, while on-site fabrication would
require the panels to be transported for only very short distances.
95
CHAPTER 8. FEASIBILITY ANALYSIS: CONSTRUCTION
96
8.3 Pavement Placement
placed (void volume will be discussed in Section 8.6). Profile data was obtained from the Texas
Department of Transportation for a 500 ft section of newly placed asphaltic concrete pavement
along FM 812 in Austin, Texas. The data was obtained using a van equipped with a laser
profiler. The profiler collected data approximately every 5 in. over the 500 ft length. Six passes
were made (using two lasers) over the pavement section, generating eleven profiles (one profile
repeated), each spaced 1 ft apart. This procedure produced a 10 ft wide by 500 ft long section of
pavement for analysis. Figure 8.1 shows a plot of the profile data for the 500 ft section. Each of
the eleven lines represents one of the profiles. Attention should be given to the scales on the plot,
as the horizontal scale is in feet and the vertical scale is in mils, or thousandths of an inch. The
length of the plot, 500 ft, represents the leveling course beneath fifty 10 ft wide panels. To
reduce the amount of data to be analyzed, only the first 250 ft of the profile data was analyzed.
The easiest way to evaluate the smoothness of the AC pavement was by visual inspection
of the plotted profile data. The data was analyzed in 10 ft segments, representing 10 ft wide
panels. Figure 8.2 shows the profile data (eleven profile lines) for a typical 10 ft section. The
difference in elevation between the two outermost lines can be attributed to the overall slope of
the pavement (for drainage). Considering the scale, however, this difference is only about 400
mils or 0.4 in. The difference in elevation between the ends of the lines can be attributed also to
the slope, or grade, of the pavement. There are only a few areas with noticeable irregularities. In
particular, between 235 ft and 236 ft, there is a sharp peak. This peak is greatly exaggerated by
the scale, however, as it is less than 0.1 in. in height.
Overall, there do not appear to be any major imperfections in this 10 ft section that would
compromise the evenness of the leveling course. Visual inspection of the profile data for the rest
of the 10 ft sections lead to similar conclusions. Although this pavement is thicker (6 in.) than
that which would be used for a leveling course (1–2 in.), this analysis has shown that an AC
pavement can be placed that is sufficiently smooth to work as a leveling course for a precast
pavement. If obvious imperfections were found in the leveling course, techniques such as
diamond-grinding could bring the leveling course to within required tolerances.
1000
800
600
Difference in Elevation (mils)
400
200
-200
-400
-600
-800
-1000
0 50 100 150 200 250 300 350 400 450 500
Distance (ft)
Figure 8.1 Profile data from a newly placed AC pavement in Austin, Texas
97
CHAPTER 8. FEASIBILITY ANALYSIS: CONSTRUCTION
800
700
600
Difference in Elevation (mils)
500
400
300
200
100
-100
-200
230 231 232 233 234 235 236 237 238 239 240
Distance (ft)
Figure 8.2 Profile data for a 10-ft-wide section, representing the width
of a single precast panel
Extensive research has been conducted over the years on the effects of various types of
friction-reducing media. The predominant media that have been investigated include
polyethylene sheeting, spray-applied bond breaker, and granular layers. Figure 8.3 shows the
relationship between displacement and coefficient of friction obtained from push-off tests
performed at The University of Texas at Austin for concrete slabs on three different types of
friction-reducing media (Ref 33).
98
8.3 Pavement Placement
Figure 8.4 shows the results of push-off tests performed by Transtec, Inc., on aircraft
pavement slabs in Las Vegas, Nevada. For these tests, a granular material was tested along with
other materials.
120.00
North Slab (No Curing Compound)
South Slab (With Curing Compound)
3 mm Sand
100.00
2 mm Sand
Polyethylene Sheeting
Petromat
80.00 Slurry Seal
Load (kPa)
60.00
40.00
20.00
0.00
0.000 1.000 2.000 3.000 4.000 5.000 6.000 7.000 8.000 9.000
Displacement (mm)
99
CHAPTER 8. FEASIBILITY ANALYSIS: CONSTRUCTION
Both of these tests revealed that polyethylene sheeting is the best material for reducing
subbase frictional restraint. A single layer of polyethylene sheeting was found to have a
maximum coefficient of friction between 0.57 and 0.92 (Ref 33). Tests performed at The
University of Texas at Austin showed that a double layer of polyethylene sheeting (maximum
coefficient of friction between 0.47 and 0.70) reduced friction more than a single layer did.
However, it was felt that a double layer reduced the friction too much. It is desirable to have
some friction beneath prestressed pavement slabs to keep expansion joints from opening
excessively and to prevent the slabs from sliding transversely off the base material. In addition,
previous experience revealed that it was difficult to walk on the surface during construction.
An added benefit of polyethylene sheeting, or virtually any friction-reducing medium, is
the prevention of adhesion between the subbase and the bottom of the pavement. This benefit is
especially important for pavements whose construction makes use of an asphalt base, as asphalt
tends to adhere to concrete.
A single layer of polyethylene sheeting was used successfully beneath the cast-in-place
prestressed pavement constructed in McLennan County, Texas, in 1985 (Chapter 2). The
polyethylene sheeting proved to be constructible, economical, and effective as a friction-
reducing medium (Ref 20). Polyethylene sheeting can be purchased in large rolls and simply
rolled out and temporarily pinned down over the leveling course. Based on its success in
previous projects, a single layer of polyethylene sheeting should prove viable for use with a
precast pavement as well.
8.3.3 Placement of Panels
Placement of the precast panels will follow the sequence presented at the beginning of
this section. The panels will, most likely, be lifted off the truck and set in place using a crane.
The panels will be handled using either lifting devices embedded in the panels, or using a strong-
back with clamps that lock onto the shear keys in the edges of the panels. The latter method
eliminates the need to fill holes in the panels, left by the lifting devices, after the panels are in
place.
A gap will intentionally be left between the joint panel and its adjacent base panel so that
the post-tensioning strands can be pushed into the anchors. Inevitably, there will also be gaps
left between each of the other panels when they are set in place, particularly if a strong-back
lifting device is used. It will be necessary to close these gaps as much as possible before post-
tensioning to minimize the amount of wasted strand. In order to prevent the polyethylene
sheeting from bunching up between the panels as they are pulled together, thicker strips of
plastic can be placed beneath the panels where they come together.
8.3.4 Installation/Stressing of Post-Tensioning Tendons
As described in Chapter 5, the post-tensioning strands will be threaded through the panels
starting at the stressing pockets and terminating at the joint panel. Although ½ in. or 0.6 in.
diameter strands are fairly rigid, it may be necessary to pull the strands through the ducts, rather
than pushing them from the stressing pockets. This maneuver can be accomplished by first
threading wire or rope through the ducts and pulling the strand through. The strand can then be
pushed into the self-locking anchor from the gap left between the joint panel and adjacent base
panel. As an alternative, a coupler panel can also be used, as described in Chapter 5.
After all of the strands are anchored in the joint panels, they are stressed from the central
stressing pockets, as described in Chapter 5. Post-tensioning the pavement will cause the
pavement to contract significantly, owing to the gaps between the panels closing up. Because
100
8.3 Pavement Placement
each joint panel is part of two different slabs, the expansion joint will need to be temporarily
clamped to prevent it from opening during the stressing operation. Otherwise, when one slab is
post-tensioned, it will try to pull the expansion joint open, which is attached to a slab that has
already been post-tensioned. With the expansion joint clamped, the slab being post-tensioned
will, essentially, contract in one direction, toward the expansion joint.
8.3.5 Mid-Slab Anchor
Once a slab has been post-tensioned, it will be necessary to anchor the center of the slab
to the subbase. The purpose of this mid-slab anchor is to restrict movement of the center of the
slab so that the slab will expand and contract outward from the center, ensuring uniform
expansion joint widths over the length of the pavement. Otherwise, some expansion joints may
open up or close more than others.
For the cast-in-place prestressed pavement constructed in McLennan County, Texas,
described in Chapter 2, vertical dowel bars were embedded in the supporting layers beneath the
prestressed overlay, prior to casting the concrete, to provide the mid-slab anchor. For a precast
pavement, it may be possible to drive dowel bars into the supporting layers at the central
stressing pockets. When the stressing pockets are filled, the central stressing panel will then be
anchored to the subbase. It may even be necessary to use a core drill to drill a small shaft into
the subbase layers at the stressing pockets, which will subsequently be filled when the stressing
pockets are filled. It is important, however, that the mid-slab anchor is not set (or drilled) until
the slab has been post-tensioned. This delay will ensure that the slab is in its final position
before being anchored.
8.3.6 Grouting of Post-Tensioning Tendons
After the post-tensioning strands have been threaded through ducts and stressed, they can
then either be bonded to the pavement by means of grouting the tendon ducts, or they can be left
unbonded. Although leaving the strands unbonded simplifies construction by eliminating the
extra grouting process, there is less corrosion protection for the strands, even if greased and
polyethylene-sheathed strands are used. Corrosion can cause a strand to eventually lose part or
all of its prestress. Another disadvantage of unbonded tendons is the lack of continuity between
the steel and concrete, which requires the use of additional nonprestressed reinforcement. There
is also the risk of the tendon being inadvertently cut some time during the life of the pavement,
which could result in damage to the pavement and which could pose a safety hazard.
The alternative to unbonded tendons is grouting the ducts after the strands have been
stressed. Grouting the ducts bonds the strands to the pavement, ensuring continuity between the
concrete and the strands, thereby reducing, if not eliminating, the amount of nonprestressed
reinforcement required in the pavement. In addition, there will not be any damage or loss of
prestress if a tendon is inadvertently cut. Most importantly, however, is the corrosion protection
that the grout provides to the strands. If grouting is done properly, the grout will provide
protection from water penetrating the concrete and reaching the strands. This protection is
especially important at the panel joints, where the duct is not continuous across the joint. The
grout will help seal the duct across the joint, thereby protecting the strands.
Grout will be pumped into the tendon ducts through grout inlets near the expansion joint,
as shown in Figure 5.10. One or more grout vents will be cast into the pavement, along the
length of the slab, to provide an outlet for the displaced air when grout is pumped through the
duct.
101
CHAPTER 8. FEASIBILITY ANALYSIS: CONSTRUCTION
It is very important that proper procedures be followed for grouting. Proper procedures
include the use of the proper grout mixture, materials, and methods for grouting. Improper
grouting can result in air voids in the ducts caused by water separation in the grout and by
incomplete grouting of the duct. These voids can collect water and contribute to the corrosion of
the strands, which cannot be replaced. As there is no easy way to inspect the tendons after the
ducts have been grouted, it is important to ensure that the proper procedures be followed during
construction.
Neither grouting the tendons nor filling the stressing pockets must be completed before
traffic is allowed back onto the pavement. For example, if a section of pavement is placed and
post-tensioned one night, traffic could be allowed back onto the pavement the next day. Steel
cover plates could simply be used to temporarily cover the stressing pockets. The tendons can
then be grouted and the stressing pockets filled during placement of another section on the
following night. This practice will serve to further expedite the construction process.
8.3.7 Traffic Control/Temporary Ramps
Traffic control will be determined by the scope of each project. The scope of the project
entails the type of pavement to be constructed, such as a new pavement, overlay, or removal and
replacement, as well as the time frame allotted for construction. Traffic can be diverted to
frontage roads or to opposing lanes of traffic.
A precast pavement can either be constructed piecewise, in separate overnight operations,
or all at once. Separate overnight operations will allow traffic back onto the pavement during the
daytime, when traffic volumes are higher. For a new or overlay application, temporary precast
ramps can be placed at the ends of the precast pavement to provide a transition from the existing
pavement to the new pavement. These temporary ramps can be reused as each successive
section of pavement is placed.
8.3.8 Ride Quality
Ultimately, an actual determination of ride quality cannot be ascertained until a precast
pavement is actually constructed. However, ride quality of a precast pavement should be
comparable to that of conventional concrete pavements. Because the panels are cast under
controlled conditions, there is a high degree of control over the smoothness and evenness of the
precast panels. The continuous shear keys in the edges of the panels will interlock adjacent
panels so that tight, flush joints are created. If necessary, uneven areas of the pavement can be
diamond-ground smooth using existing techniques and equipment to improve ride quality. Areas
that may require diamond-grinding are at the stressing pockets and at panel joints. Any ridges
created at the panel joints by the sealant material or misalignment of adjacent panels should be
ground smooth.
The expansion joints should not affect the ride quality, as long as the maximum
expansion joint width requirements are met. Data collected from the cast-in-place prestressed
concrete pavement in McLennan County (Chapter 2) has shown that the expansion joint widths
can be predicted accurately using the PSCP2 program for design (Ref 20).
8.3.9 Estimated Production Rates
It is essential that the construction sequence be carefully planned so that a precast
pavement can be placed quickly and efficiently. This planning is especially critical when a
precast concrete pavement is constructed during an overnight operation. Careful planning entails
ensuring that all of the materials and equipment necessary for construction are at the job site
102
8.4 Vertical and Horizontal Curves
before construction begins. These materials include all of the post-tensioning materials and the
precast panels themselves.
The actual production rate of a precast pavement will be dependent on how fast the
panels can be placed and post-tensioned. The asphalt leveling course can be placed well in
advance of panel placement and can be exposed to traffic between nightly construction
sequences. It is imperative, however, that the pavement be post-tensioned prior to exposure to
traffic.
Based on estimates of production rates for parking garage construction using precast
double-tee beams, at least thirty panels can be placed in an 8 hour period. It should be possible
to increase this amount, however, so that at least 500–1,000 ft of pavement is placed during a
construction sequence. Although this is substantially less than a typical placement rate for
conventional pavement (~2,000 ft/day), the savings in user costs (discussed in Section 9.1)
associated with overnight pavement placement will far outweigh the additional time required for
construction.
One advantage of precast pavement, with respect to actual construction, is that weather
conditions will not impact precast pavement placement as they do conventional pavement
placement. Precast pavement can be placed under moderate and possibly even heavy
precipitation, whereas conventional pavement cannot. Precast pavement placement also will not
be inhibited by concreting temperature requirements. For example, in Texas, concrete pavement
cannot be placed when the ambient temperature is below 5 ºC (41ºF) and falling or when the
concrete temperature is above 35 ºC (95 ºF) (Ref 47). Because the panels will be cast under
controlled conditions at a precast yard and set in place after the concrete has already hardened to
full or near-full strength, weather conditions will have little effect on a precast pavement when it
is placed.
103
CHAPTER 8. FEASIBILITY ANALYSIS: CONSTRUCTION
most cases, be around 120 km/h (75 mph), with corresponding recommended K-value limits of
50 and 73.
L
0.5L
In order to find the percent change in angle in the parabolic curve over the width of each
panel, the panel width (in meters) was divided by the K-value. Depending on the panel
thickness, the gap width between panels will vary. For this analysis, a panel thickness of 8 in.
was used. The angle created between adjacent panels for the maximum sag curve is shown in
Figure 8.6 for varying panel widths. The corresponding gap between adjacent panels, created by
this angle, is shown in Figure 8.7.
7.0
Angle change between panels (degrees)
6.0
5.0
4.0
3.0
Stopping Sight Distance = 203m
Stopping Sight Distance = 286m
2.0
Panel thickness = 8 inches
1.0
8 10 12 14 16 18 20
Panel Width (ft)
Figure 8.6 Angle created between adjacent panels on vertical sag curves
104
8.4 Vertical and Horizontal Curves
0.9
0.8
0.7
0.6
0.5
0.4
Stopping Sight Distance = 203m
Stopping Sight Distance = 286m
0.3
Panel thickness = 8 inches
0.2
8 10 12 14 16 18 20
Panel Width (ft)
Figure 8.7 Gap width between adjacent panels on vertical sag curves
In the design of horizontal curves, it is necessary to establish the relationship between the
design speed and curvature, superelevation, and side friction. The AASHTO guide recommends
limiting values for the rate of roadway superelevation, e, and also for the side friction factor, f.
Using the maximum superelevation (emax) value with a conservative side friction (f) value, a
minimum curve radius for various design speeds can be determined. The AASHTO guide lists
various minimum radii based on various design speeds, super elevation rates, and side-friction
factors. The AASHTO guide recommends a super elevation of 8% as a reasonable value for
design, though the maximum that may be used is 12%. Based on this recommended design value
for superelevation, on a design speed of 120 km/h, and on a side-friction factor of 0.09, the
minimum curve radius (R0) is given as 665 m.
The minimum curve radius was used to compute the angle and gap width between
adjacent panels using geometric relationships. For the purpose of analysis the total panel length
was taken as 38 ft, which is probably the largest panel size that will be used. This geometric
relationship is illustrated in Figure 8.8.
105
CHAPTER 8. FEASIBILITY ANALYSIS: CONSTRUCTION
/2
R0
0 +L
/2
R
-L
R0
L = panel length
Figure 8.9 shows the angle created between adjacent panels, for the minimum curvature,
for varying panel widths. Figure 8.10 shows the corresponding gap width created by the
maximum expected horizontal curve for varying panel widths.
0.6
Angle between panels (degrees)
0.5
0.4
0.3
Maximum superelevation = 8%, R = 665m
Panel Length = 38 ft
0.2
8 10 12 14 16 18 20
Panel Width (ft)
106
8.5 Cross-Slope (Superelevation) Criteria
5
Maximum superelevation = 8%, R = 665m
4
Panel Length = 38 ft
3
8 10 12 14 16 18 20
Panel Width (ft)
This analysis has shown that horizontal and vertical curves can cause significant angles
between adjacent rectangular precast panels. For example, with 8 in. thick panels that are 10 ft
wide and 38 ft long, a ½ in. gap will be created by a maximum vertical curve and a 4.2 in. gap
will be created by the maximum horizontal curve.
Based on the second expert panel meeting with precast consultants, it is believed that
precast panels will be able to accommodate these angles. The shear key in the panel edges
should be able to accommodate the angle created by vertical curves. For a sag curve, there will
simply be a small gap between the panels in the bottom of the pavement. For a crest curve, it
may be necessary to fill the gap created in the top of the pavement with a rubberized sealant
material, if the gaps are found to be significantly wide. To accommodate the angles created by
horizontal curves, the side forms on casting bed can be angled slightly to create panels with
slightly tapered sides to accommodate horizontal curves.
The scenarios presented here represent extreme situations and will probably not be
encountered in an actual precast concrete pavement. However, this analysis has shown that the
angles and gaps created are not extremely large and that measures can be taken to accommodate
vertical and horizontal curves.
107
CHAPTER 8. FEASIBILITY ANALYSIS: CONSTRUCTION
µs (8.1)
= TAN (θ )
FS
Figure 8.11 shows the relationship between the superelevation cross-slope angle and
factor of safety. As this figure shows, even with a factor of safety of 4, the permissible cross
slope is still nearly 5%. The AASHTO guide for geometric design of highways and streets (Ref
34) recommends a maximum cross slope of 2% for most high-surface-type pavements, and 4%
for pavements with three or more lanes that receive intense rainfall. For intermediate surface
types, the AASHTO guide recommends a range of cross slope between 1.5% and 3%. These
values, which might be expected for a precast pavement application, are all well below the
maximum calculated value of 5%, for a safety factor of 4. Therefore, for typical roadway
construction, there should not be a problem with the precast panels sliding laterally off the base.
25
20
Superelevation Criteria
10
0
1.0 1.5 2.0 2.5 3.0 3.5 4.0
Safety Factor
Figure 8.11 Cross-slope criteria for precast panels assuming a coefficient of friction of 0.2
108
8.6 Voids Beneath Pavement
To get a general idea of expected void volumes, the profile data presented in Section
8.3.1 was analyzed to determine the approximate volume of voids beneath the section of
pavement panels 250 ft long by 10 ft wide. Two different methods were used to fit 10 ft wide
rigid “panels” on the profile data to represent precast pavement panels placed on an asphalt
leveling course. For both methods the data was divided up into 10 ft segments to match the 10 ft
wide panels.
The first method involved finding the least slope between any two data points in the 10 ft
section and assuming that the panel would sit at this slope, resting on the high points of the
profile. The second method used a trendline, or a best fit line, through the profile data to
represent the 10 ft wide panel. Figure 8.12 shows a typical 10 ft segment of profile data with the
“panels” superimposed using both methods. The area between the “panel” and the profile was
used to determine the volume of voids beneath the pavement. The trendline method provided a
lower bound estimate of the actual void area, as the “panels” tended to cut through, rather than
rest on top of, the profiles, whereas the least slope method provided an upper bound estimate, as
the panels tended to sit on top of the profile data. Adjoining panels were assumed to connect to
each other at the ends, as would be expected in the actual pavement.
600
500
400
300
Trendline Method
200
100
0
0 1 2 3 4 5 6 7 8 9 10
Distance (width of panel)
To calculate the volume, the area between the “panel” and the profile was determined,
averaged over the eleven profiles, and then multiplied by the 10 ft width. As a check of a
reasonable estimate of the void volume, a section of the profile was plotted on paper, and a
straight line, representing a panel, was fit over the profile by hand. The area between the “panel”
and the profile was then measured and calculated by hand. The area calculated by hand was very
close to the value obtained by averaging the values from the two methods mentioned above.
Therefore, the volume of voids beneath the pavement was taken as the average of the values
found from the least slope and trendline methods.
109
CHAPTER 8. FEASIBILITY ANALYSIS: CONSTRUCTION
Upon plotting the “panels” from least slope method superimposed on the profile data, it
was found that the voids were significantly overestimated on some parts of the 250 ft section. To
obtain a more reliable estimate, each profile was plotted, and the values from any part of the plot
clearly in error were thrown out. The new values were then used as the upper bound estimate.
The results from the void volume analysis are shown below in Table 8.1. Void volume
was determined for each 10 ft by 10 ft section of pavement for both the least slope and trendline
methods. The values were then averaged over the 25 sections (250 ft of profile data) to give an
overall average value for a 10 ft by 10 ft section. The values were then added to give the total
volume for a 250 ft long by 10 ft wide section. As mentioned previously, the plots for the least
slope method were checked and any clearly errant data was thrown out. This value was then
averaged with the trendline volume to give an average for a 10 ft by 10 ft section. This value of
0.157 ft3 is approximately 30% less than the value obtained before data was thrown out (0.228
ft3) — and probably more reliable.
This analysis has shown that the volume of voids beneath a precast pavement may be
fairly significant. Using the final value (highlighted in Table 8.1) for the void volume beneath a
10 ft by 10 ft segment (0.157 ft3), a 10 ft by 38 ft panel would average 0.6 ft3 of voids, while a
250 ft section of panels would average 150 ft3 of voids. However, this analysis does not show
how the voids are distributed. Judging from the smoothness of the profile data, this void volume
estimate represents mostly very small voids, which can be bridged by the panels. In essence, this
analysis has given a worst case estimate of the void volume.
Void detection may require the use of special techniques, such as ground-penetrating
radar. If it is determined that significant voids are present beneath a precast pavement, there are
two options for addressing this problem. The first option is to fill the voids using either grout
injection or an expansive urethane foam (described in Chapter 3). Either method will require
drilling small holes through the pavement, which will require special attention so that the
transverse or longitudinal prestressing strands are not affected. The second option is to simply
increase the post-tensioning force to account for the increase in stresses caused by the voids.
110
8.7 Removal and Replacement
111
Chapter 9. Feasibility Analysis: Economics and Durability
113
CHAPTER 9. ECONOMICS AND DURABILITY
4
Reduced Capacity
3
0
6:00 10:00 2:00 6:00 10:00 2:00 6:00
AM AM PM PM PM AM AM
Hour of Day
7
Percent of Daily Volume
4
Reduced Capacity
3
0
6:00 10:00 2:00 6:00 10:00 2:00 6:00
AM AM PM PM PM AM AM
Hour of Day
Figure 9.2 Overcapacity created by overnight precast pavement construction
In order to quantify the difference in user costs resulting from the reduction in
overcapacity through precast construction, the computer program QUEWZ, which was
developed by the Texas Transportation Institute (College Station, Texas) and later modified by
Transtec, Inc. (Austin, Texas), was used to calculate expected delay time, which can be
expressed as a cost to the user in dollars per day (Ref 35).
For the purposes of analysis, the following general assumptions were made:
114
9.1 Life Cycle Cost
The 5 mile work zone was chosen as a possible average work zone length for medium-
sized projects. The median-separated, four-lane freeway with frontage roads was chosen because
it is a type of urban freeway commonly found in Texas. The ADT range of 50,000 – 105,000
vpd (both directions) is a likely range for urban principal arterial interstates in Texas. The
vehicle mix of 25% trucks is very common as well, since NAFTA trade with Mexico is
increasing the number of heavy trucks traveling on Texas highways.
In addition to those assumptions applicable to both construction methods, certain
assumptions were needed for each of the methods. First, for precast construction:
For conventional concrete pavement construction, only one assumption was needed:
Conventional pavement construction will require 24 hour traffic diversion, since the concrete
requires time to reach strength before traffic can be allowed back onto the pavement. The actual
work might only occur for 10–12 hours a day, but the traffic diversion (one lane open in each
direction) must be in place 24 hours a day.
Several runs were made using QUEWZ for varying ADT values and for the three traffic
diversion strategies discussed previously. The first run corresponded to using precast
construction with one lane open in each direction from 8:00 p.m. to 6:00 a.m. daily. The second
run focused on precast construction with traffic diverted to the frontage road, also from 8:00 p.m.
to 6:00 a.m. Finally, the third run corresponded to conventional pavement construction, with one
lane open in each direction 24 hours a day. Table 9.1 and Figure 9.3 show the results from this
analysis. Note the log scale for daily user costs in Figure 9.3.
Table 9.1 Daily user delay costs for precast and conventional pavement construction
Precast
Precast
Construction Method 2-1 Conventional
1-1
(frontage road)
115
CHAPTER 9. ECONOMICS AND DURABILITY
1,000,000
100,000
Daily User Cost ($/day)
10,000
Precast 1-1
Precast 2-1 (frontage road)
Conventional Pavement
1,000
40,000 50,000 60,000 70,000 80,000 90,000 100,000 110,000
Average Daily Traffic - Both Directions (vpd)
Figure 9.3 User costs for precast versus conventional pavement construction on an urban
principal arterial for varying ADT (Note: Log scale on the ordinate axis)
Table 9.1 and Figure 9.3 clearly demonstrate that the overnight precast pavement
construction process results in a significant reduction in traffic delays, which in turn results in
substantially lower user costs. This, again, is a consequence of being able to allow traffic back
onto the pavement between construction sequences, when traffic volumes are highest. Although,
as mentioned before, it may not be possible to place as much precast pavement as conventional
pavement in one day, the savings in user costs are still very substantial. Considering the example
presented above, if a placement rate of 2,000 ft per day is assumed for conventional pavement
and 500 ft per day for precast pavement, it will take approximately 20 days to place 5 miles of
conventional pavement (including an additional 7 days of set time after placement of the final
2,000 ft), and approximately 53 days to place 5 miles of precast pavement. However, as Table
9.2 shows, even under a worst case ADT scenario of 105,000 vehicles per day, the total user
costs are still more than twice as much for conventional pavement construction as that for
overnight precast pavement construction.
116
9.2 Economic Analysis
Table 9.2 Total user delay costs for precast and conventional pavement construction for a 5
mile pavement with an ADT of 105,000 vehicles per day
Daily Total
Placement
Construction Method User Construction Total User Cost
Rate
Cost Time
Conventional Pavement 2,000
(CRCP, JRCP) ft/day
$680,610 20 days $13,612,200
For a removal and replacement application, it may be necessary to divert traffic over a
full weekend, owing to the additional construction time required for removal of the existing
pavement. To quantify the user delay costs for this scenario, QUEWZ was again used following
the general assumptions given above. However, for this analysis, traffic was only assumed to be
diverted to the opposite side of the roadway, providing one lane in each direction. Traffic
diversion was assumed to occur from 8:00 p.m. Friday night to 6:00 a.m. Monday morning.
Based upon these assumptions, the total user delay cost for weekend construction was found to
range from $713,700 (for the entire weekend) for an ADT of 50,000 vehicles per day, to
$1,527,540 for an ADT of 105,000 vehicles per day. This delay cost, however, is not dependent
on whether precast or conventional (using fast-setting concrete) pavement construction is used.
The difference in cost will be realized only through the material and construction costs.
Another consideration with regard to user costs, discussed previously in Section 8.3.9, is
the fact that precast pavement placement should not be affected by adverse weather conditions
(as are conventional pavement placements). Precast pavement can be placed under moderate
precipitation and under extreme temperature conditions that would restrict the placement of
conventional pavement. This option will allow for much more flexibility with precast pavement
placement and can eliminate construction delays, commonly experienced during conventional
pavement placement, caused by inclement weather conditions.
Although the examples presented here are simplified, this analysis has shown that user
delay costs resulting from construction can be very substantial, depending on when traffic is
diverted. Clearly, overnight construction is desirable, as it greatly reduces any delays caused by
overcapacity. Weekend construction, which will result in fairly substantial user delay costs, may
be necessary for removal and replacement applications.
117
CHAPTER 9. ECONOMICS AND DURABILITY
Conventional concrete pavements require several days or weeks for the concrete to reach
sufficient strength for traffic to be allowed back onto it. Because of this, traffic must be diverted
24 hours a day during construction. As shown in Table 9.1, this diversion can result in
substantial user delay costs for heavily trafficked roadways. It is possible to use high-early-
strength concrete in conventional pavements so that the concrete will reach adequate strength in
less than 24 hours. High-early-strength concrete, however, will substantially increase initial
construction costs.
9.2.2 Precast Pavement Construction
Precast concrete pavement construction will, invariably, cost more than conventional
pavement construction owing to the additional materials and procedures required. Some of the
major cost components of precast pavement construction are listed below:
118
9.3 Durability
9.3 DURABILITY
Durability is essential for ensuring that a pavement will achieve its full design life with
minimal life cycle maintenance. Most pavements are constantly subjected to aggressive
environments. In particular, pavements in colder regions are subjected to freeze-thaw cycles and
to such corrosive agents as deicing salts. Precast (prestressed) concrete pavements are
particularly susceptible to aggressive environments owing to the nature of the reinforcement in
the pavement.
There are several measures that can be taken to ensure the durability of precast concrete
pavements. These measures include using a suitable aggregate and concrete mix, protection of
the prestressing steel and anchorage, and using durable expansion joints. These measures will be
discussed below.
9.3.1 Concrete/Aggregate
The use of a suitable aggregate and concrete mix can greatly enhance the durability of
concrete pavements. Research conducted at the Center for Transportation Research has shown
that pavements consisting of concrete with a low (< 5 x 106 in./in./ºF) coefficient of thermal
expansion (COTE) tend be more durable, showing less cracking and overall failures than
pavements with a high (> 5 x 106 in./in./ºF) COTE (Ref 50). Lower COTE concrete reduces the
amount of expansion and contraction movement of precast pavement slabs, thereby reducing the
stresses generated from frictional resistance to slab (contraction) movements at the slab-base
interface.
It is also desirable to use a concrete mix with a very low permeability. Such a mix will
prevent chlorides and other corrosive agents from penetrating the concrete and reaching the
prestressing steel in the pavement. Low permeability will also reduce moisture gradients in the
pavement (moisture gradients can lead to warping, as discussed in Chapter 6). The use of
mineral admixtures, such as silica fume or fly ash, in the right proportions will significantly
reduce the permeability of concrete. The requirements for water-cementitious materials (which
include silica fume and fly ash) should conform to the limits given in Chapter 4 of the ACI
Building Code (Ref 21) and Chapter 1 of the PCI Design Manual (Ref 32). These requirements
are specific to the exposure conditions of the pavement, which include freeze-thaw exposure,
sulfate exposure, and deicing chemical exposure.
Air entrainment will also increase the durability of concrete exposed to freezing and
thawing or to deicing chemicals. The requirements for air content should conform to the
119
CHAPTER 9. ECONOMICS AND DURABILITY
recommendations of Chapter 4 of the ACI Building Code and Chapter 1 of the PCI Design
Manual.
Durability and abrasion resistance of the pavement surface should also be criteria for
selecting the aggregate/concrete mix for a precast pavement. As discussed in Section 3.2.3.2,
harder fine aggregates, which are in short supply in many areas, could be used at least in the top
of the precast panels to provide the necessary abrasion resistance, while local softer aggregates,
which are more readily available, could be used in the bottom of the panels. Precasting also
allows for the use of smaller aggregates. While larger (2 in.) aggregates are required in
conventional pavements to ensure aggregate interlock at cracks and joints, smaller aggregates
can be used in precast pavement, as the prestress in the pavement will prevent cracks from
opening up. Precasting in a controlled environment allows for this sort of flexibility in varying
concrete mixes — a flexibility not possible with conventional pavement.
One inherent advantage of a precast concrete pavement with respect to durability,
discussed previously in Chapter 6, is the fact that the precast panels will have a very low
moisture gradient over the depth of the panels. This is due to the fact that both sides of the
panels will be exposed and allowed to “dry out” after they are stripped from the casting bed. A
low moisture gradient will reduce stresses generated in the panels from moisture curling and
warping, which can be very significant.
9.3.2 Prestressing
Prestressing strand is made from high strength steel generally specified as Grade 270,
meaning a minimum guaranteed breaking stress of 270 ksi. Seven-wire strand is currently used
almost exclusively for precast and prestressed concrete structures in the United States (Ref 36).
Low relaxation strand has also progressively replaced the use of stress-relieved strand.
Prestressing strand is also somewhat flexible, thus facilitating the threading of the post-
tensioning strands through the ducts in a precast pavement.
Protection of the prestressing strands and hardware — the anchorage, couplers, and both
the pretensioning and post-tensioning strands — is essential for maintaining a durable precast
concrete pavement. Protection of reinforcement is primarily provided by embedment in the
concrete. A protective film forms on the surface of the steel as a result of the high alkalinity of
the cement paste. However, this high alkalinity can be lost in the presence of oxygen, moisture,
and chlorides (Ref 32). To protect the steel from these agents, concrete having a low
permeability should be used. Corrosion inhibitors can also be added to the concrete mix to
reduce or prevent corrosion of embedded metals. In addition, sufficient cover should be
provided over the reinforcement. The Precast and Prestressed Concrete Institute provides
minimum cover requirements in Section 1.3.4 of the PCI Design Handbook (Ref 32). Epoxy-
coated strand and anchorage is also available but can be cost-prohibitive. In particularly
aggressive environments, however, the use of epoxy-coated strand may be required.
9.3.3 Joints
Joint durability is critical for prestressed (precast) concrete pavements. Replacing
expansion joints can be very costly, particularly when the prestressing tendons are anchored at
the expansion joint. The four cast-in-place prestressed concrete pavements projects that were
constructed prior to the development of the McLennan County prestressed pavement (Chapter 2)
all experienced durability problems with expansion joint details (Ref 6). The expansion joint
detail developed for the McLennan County pavement, shown in Chapter 5, was a refinement of
some of the ideas borrowed from these previous pavements. At the time of this report, this
120
9.3 Durability
expansion joint detail has shown virtually no signs of distress after 15 years in service. Minimal
maintenance, such as cleaning debris out of the expansion joint, has been the only maintenance
required. Based on these observations, this expansion joint detail should perform just as well for
a precast concrete pavement.
Using galvanized steel in the expansion joint detail will protect the steel joint from
corrosion, particularly when it is used in an aggressive environment. The dowel within the
expansion joint should be stainless-steel plated, as shown in Chapter 5. Corrosion could cause
the dowels to seize up in the dowel sleeve, preventing the expansion joint from opening or
closing.
9.3.4 Grouted Tendons
Grouted tendons have been found to enhance the durability of prestressed concrete
structures. Grouting the strands in the ducts ensures continuity between the concrete and steel
strands. More importantly, however, grouting provides an additional layer of protection from
corrosion. In order for grouting to be effective, proper procedures must be followed, including
the use of a suitable grout, proper materials, and sound construction methods.
The requirements for a suitable grout mixture include minimal bleed, good flowability,
and minimal expansion and shrinkage. Bleed occurs when water comes out of solution with the
grout (owing to the higher density of the grout material), leaving air voids in its place when the
water evaporates or seeps out of the duct. Good flowability is important for ensuring that the
grout fills the entire duct and completely surrounds the strand. Minimal expansion and shrinkage
is important so that the pavement is not damaged by expansion of the grout and air voids are not
left from shrinkage of the grout. The grouting material predominantly used for bonded post-
tensioning tendons has a water-cement ratio of 0.45 or less, and a combination of mineral and
chemical admixtures (Ref 37). The purpose of the admixtures is to tailor the grout to the
flowability, bleed, and shrinkage requirements for the job.
Extensive research on grouted post-tensioned tendons was carried out at the Ferguson
Structural Engineering Laboratory at The University of Texas at Austin. This research revealed
that, for horizontal applications (such as a precast pavement), the optimal grout mixture has a
water-cement ratio of 0.35, contains 4 ml/kg of a superplasticizer chemical admixture, and has
30% fly ash mineral admixture (Ref 38). This grout mixture was found to have good flowability
characteristics, with low bleed and, essentially, no shrinkage.
Adequate venting is another important factor for grouting. Venting should be provided at
the ends of continuous sections of the duct to allow the air displaced by the grout to escape.
Grout should continue to be pumped into the duct until there are no visible slugs of air or water
ejected from the duct and the efflux time of the ejected grout is no less than the injected grout
(Ref 22). This precaution will ensure that all of the air and any water that may have come out of
solution has been removed from the duct. Air and water left in the duct tend to create voids that
may collect water and contribute to strand corrosion. By following simple, standardized
procedures, grouting the post-tensioning tendons should significantly increase the durability of
precast concrete pavements.
9.3.5 Anchorage
The proposed post-tensioning anchorage is a modified version of standard post-
tensioning anchorage. The durability of the anchorage should be just as good as that of standard
post-tensioning anchorage. Protection of the anchorage from corrosion will be provided by
embedment in the concrete. If the pavement is placed in a particularly aggressive environment,
121
CHAPTER 9. ECONOMICS AND DURABILITY
it may be necessary to use encapsulated anchorage. However, the anchorage is required only to
sustain the full prestress force until the strands are grouted in the ducts. After grouting, transfer
of prestress to the pavement will be provided by bond between the strand and grout.
122
Chapter 10. Recommendations
for Additional Investigation and Implementation
10.1 INTRODUCTION
Looking to the future, the researchers recommend that implementation be carried out in
two phases: preliminary and full-scale implementation. During the preliminary implementation
phase, the features requiring additional investigation should be resolved and details worked out
in pilot projects. The findings from the preliminary implementation should then be incorporated
in the full-scale implementation.
Table 10.1 (at the end of this chapter) summarizes the tasks that must be carried out
during each of the implementation phases. Preliminary implementation includes any lab testing,
such as that of the self-locking anchor and strand placement (pushing the strands into the
anchors), and pilot projects, which will investigate many of the items presented in the following
section. Full-scale implementation will apply all of the techniques, tested and refined during
preliminary implementation, to large-scale projects in rural and urban areas.
During each of the three implementation projects (pilot, rural, and urban), the design
methodology described in Chapter 7 will be applied to determine slab thickness, slab length,
prestress levels, and joint details for each of the site-specific projects. In addition, the three
different applications (new pavement, unbonded overlay, and removal and replacement) will be
examined during each of the implementation projects. As mentioned previously, the majority of
the investigation will take place prior to and during the pilot project. However, certain items of
investigation, such as void treatment, and performance monitoring, which will be described in
Section 10.4, will be considered through both preliminary and full-scale implementation.
123
CHAPTER 10. ADDITIONAL INVESTIGATION AND IMPLEMENTATION
124
10.2 Additional Investigation
will reduce the cost of the concrete mix, thus reducing the cost of the pavement. In addition,
precast plants typically use only smaller aggregates (less than 1 in.), and may not be equipped to
handle larger aggregates.
The type of fine aggregate used affects the skid resistance of a pavement surface.
Concrete pavements with softer fine aggregate are susceptible to surface polishing, which greatly
reduces skid resistance in wet — and even dry — conditions. Therefore, from the standpoint of
skid resistance, a harder fine aggregate is desirable for use in a concrete pavement. A
combination of the two aggregates could provide a practical solution. Softer, more readily
available fine aggregate could be used in the bottom half of the pavement where skid resistance
is not an issue. Harder fine aggregate, which may be limited in supply, could then be used in the
top half of the pavement (the riding surface) to provide better skid resistance.
In order to provide a smooth riding surface, grinding the pavement surface may be
required. This is typically done using a “bump-cutter” or diamond-grinding machine. The
harder the aggregate in the concrete, however, the harder and more expensive it is to grind the
pavement. Therefore, it is more desirable to use a softer aggregate in the top of the pavement
where grinding is done.
Lightweight aggregate will greatly reduce the weight of the precast panels, which will
result in cost savings because more lightweight panels than normal-weight panels can be
transported on each truck. This lighter weight may also allow larger panels to be used.
Lightweight aggregates have been studied extensively and have proved to be just as durable as
normal-weight aggregates. Casting the panels in a controlled environment should provide the
necessary quality control required for lightweight concrete. Further investigation of each of
these four issues will help determine the most viable solution for the optimum aggregate to be
used in a precast pavement.
10.2.6 Performance of Joints
The proposed expansion joint detail has proved to be durable and effective in the cast-in-
place prestressed concrete pavement in McLennan County, Texas. The joint has required
minimal maintenance over the 15 years it has been in service. The specifications for this joint
detail, however, should be investigated for use in a precast concrete pavement. Such a
specification should include the length of the Nelson deformed bars, the size of steel angles to be
used, the type of dowel bars, and the type of neoprene seal.
In addition to the expansion joints, the intermediate joints should also be investigated,
including the type of sealant material for use in the joint, the type of ducts (whether keyed or
flared at the joint), and any other provisions, such as a strip of heavier plastic under the joints and
accommodation of vertical curves.
10.2.7 Filling Voids with Grout/Urethane Products
The most effective method for filling large voids beneath precast concrete pavements
should be investigated. A method for detecting voids, such as ground-penetrating radar, can be
used to determine the magnitude of any voids beneath the pavement. From that point, either
grout or urethane can be injected to fill those voids. Although grouting is a fairly standard
method, expansive urethane foam can be just as effective. Uretek USA, Inc., of Sugar Land,
Texas, has developed a controlled and efficient method for injecting an expansive polyurethane
foam beneath concrete slabs through a ½ in. diameter hole to fill voids.
125
CHAPTER 10. ADDITIONAL INVESTIGATION AND IMPLEMENTATION
126
10.4 Performance Monitoring
Fabrication Conditions
Fabrication conditions will affect the quality of the precast concrete panels. Conditions
that should be monitored include concrete strength (at removal from forms and at 28 days),
casting/curing conditions (temperature, humidity, method for curing), applied prestress, and
storage conditions.
Temperature
Ambient temperature will have an effect on the expansion and contraction movements of
the pavement. Ambient temperature should be monitored at the time of placement and at any
other time slab movement is measured. Pavement temperature at the bottom, top, and mid-depth
should also be monitored. Pavement temperature differentials will affect curling movements and
stresses in the pavement.
Cracking/Distresses
Any cracking or obvious distresses, such a spalling, should be recorded and carefully
monitored. The width and length of any cracks should be continually monitored, particularly if
they develop soon after placement. Weaker areas, particularly around the stressing pockets and
at the joints, should be constantly checked.
Joints
Expansion joints should be continually monitored to ensure that there are no signs of
distress and that the joints are behaving properly. The neoprene seal and the cavity below the
seal should be checked regularly for debris trapped in the joint. The intermediate joints should
also be checked to ensure that the sealant material remains intact and properly seals the joints.
Performance monitoring, according to the variables just discussed, will provide
information for calibrating the models used for design, as well as information on the durability of
the proposed concept. Precast concrete pavements should be monitored closely during
127
CHAPTER 10. ADDITIONAL INVESTIGATION AND IMPLEMENTATION
construction and over the first several months after construction. Monitoring should continue
over the design life of the pavement, though to a lesser extent.
Slab Length ✔ ✔ ✔
Prestress Level ✔ ✔ ✔
Joint Details ✔ ✔ ✔
Panel Alignment ✔
AC Leveling Course ✔
Self-locking Anchor ✔ ✔
Strand Placement ✔ ✔
Mid-slab Anchor ✔
Expansion Joint Clamp ✔
Investigation
Aggregates ✔
Filling Voids/
Adding Prestress ✔ ✔ ✔
Performance Monitoring ✔ ✔ ✔
New or Overlay ✔ ✔ ✔
Application
Removal & Replacement ✔ ✔ ✔
128
Chapter 11. Conclusions and Recommendations
11.1 SUMMARY
This feasibility project has demonstrated that it is possible to expedite the construction of
portland cement concrete pavements through the use of precast concrete panels. While the
construction process is quite different from that of conventional pavements, the concepts should
be easily adaptable to current practices. The following is a summary of the important aspects of
a precast concrete pavement presented in preceding chapters.
In Chapter 2, the results of the literature review were presented. The literature review
proved very beneficial for examining previous precast pavements constructed around the world,
and for determining the current state of the art in the precast industry. Some of the concepts
from the literature, particularly from the cast-in-place prestressed pavement constructed in
McLennan County, Texas, were incorporated in the final proposed concept. The literature
should also be beneficial for future implementation.
Chapter 3 presented the significant findings and recommendations from the two expert
panel meetings. These meetings were very beneficial for generating and refining the proposed
concept to make it practical for construction and appealing to contractors and transportation
agencies.
Chapter 4 discussed and evaluated the different pavement types that could be used for
precast concrete pavement construction. The pavement types were evaluated on the basis of
design and constructibility. In addition, cross-section strategies for each of three common
applications (new pavements, unbonded overlays, and removal and replacement) were also
presented.
In Chapter 5, the proposed concept for a precast concrete pavement was presented. The
concept consists of base panels, joint panels, and central stressing panels placed on a thin
asphalt-leveling course with a single layer of polyethylene sheeting provided as a friction-
reducing medium. The panels have continuous shear keys cast into the edges to aid with
alignment of the panels during assembly. The panels are all pretensioned during fabrication in
the transverse direction, and post-tensioned together in the longitudinal direction, after they are
all set in place. The post-tensioning strands are inserted through the stressing pockets and
threaded through ducts to self-locking, post-tensioning anchors embedded in the joint panels.
The pavement is post-tensioned from the stressing pockets, which are subsequently filled with
fast-setting concrete. The post-tensioning ducts are then grouted to bond the strands to the
pavement.
In Chapter 6, design considerations for a precast concrete pavement were discussed. The
design considerations include factors affecting the design, such as load repetitions, subgrade
restraint, prestress losses, and joint movement, as well as design variables, such as foundation
strength, pavement thickness, and magnitude of prestress. The design variables are adjusted to
accommodate the factors affecting design, which will be job-specific.
Chapter 7 presented a feasibility analysis for design. For the sake of comparison, a
precast concrete pavement was designed for a design life equivalent to that of a conventional
CRC pavement. From the design analysis, it was found that an 8 in. precast concrete pavement
can be designed to be equivalent to a 14 in. thick CRCP (15 in. JRCP), which is a significant
savings in concrete. The computer program PSCP2 was introduced as a design/analysis tool for
129
CHAPTER 11. CONCLUSIONS AND RECOMMENDATIONS
precast concrete pavements. Based on the example design, it was determined that expansion
joints can be spaced up to 440 ft for winter pavement placement, and up to 340 ft for summer
pavement placement, in order to meet the expansion joint width requirements.
In Chapter 8, the feasibility of construction of the proposed concept was discussed.
Feasibility of construction is very important for gaining acceptance among contractors and
transportation agencies. This chapter evaluated the feasibility of some of the proposed methods
for construction, such as the use of an asphalt-leveling course and polyethylene sheeting. Issues
raised during the expert panel meetings, such as accommodation of horizontal and vertical
curves, were also discussed.
Chapter 9 focused on the feasibility of the proposed concept from the standpoint of
economics and durability. It is important that precast concrete pavement construction be
economically feasible, as compared to conventional concrete pavement construction, with
comparable, if not enhanced, durability characteristics. The feasibility analysis showed that the
major economic advantage of precast pavement construction will be realized through savings in
user costs. Since precast concrete pavements can be exposed to traffic almost immediately after
placement, they can be constructed in short segments, minimizing the effects on traffic. In
addition, the high degree of quality control that can be achieved with precast concrete panels will
ensure outstanding durability of the pavement.
In Chapter 10, recommendations for additional investigation and implementation were
presented. Several aspects of the proposed concept, such as the self-locking strand anchor and
the asphalt-leveling course will need to be investigated further through actual implementation of
the proposed concept. A staged implementation strategy was recommended as the most effective
method for achieving this. Staged implementation involves first conducting laboratory tests and
constructing pilot sections, where any details or possible problems can be worked out without
having an impact on the motoring public. A rural section will then be constructed to implement
the proposed concept on a larger scale, under actual construction time constraints. Finally, an
urban project will provide the ultimate test of the speed, efficiency, and adaptability of precast
construction.
11.2 CONCLUSIONS
This project has demonstrated that the construction of a precast pavements is feasible and
provides numerous benefits.
11.2.1 Feasibility
The project objectives set forth in Chapter 1 ensured a thorough feasibility analysis of
precast concrete pavement construction. As revealed through the literature review, many of the
aspects of the proposed concept, such as the keyed panel joints, expansion joint details, and post-
tensioning, have been used successfully in the past and should also prove viable for precast
pavement. From the expert panel meetings, feasible techniques for panel fabrication and
construction were incorporated into the proposed concept. Such incorporation will ensure that
the proposed concept meets the expedited construction requirements and will be easily adaptable
to existing precasting and pavement construction techniques.
Based on the evaluation of different pavement types, prestressed concrete panels were
determined to be the most practical pavement type to use for precast pavement construction.
Prestressing greatly reduces the required thickness of the pavement and enhances the durability
130
11.2 Conclusions
of the pavement, which is particularly important for handling considerations and pavement
applications in areas where overhead clearance is restricted.
The feasibility analysis for design revealed that a precast pavement can be designed to
have a design life equivalent to that of conventional pavements, with a significant savings in
pavement thickness. The feasibility analysis for construction reveled feasible methods for rapid
construction, such as the use of an asphalt leveling course, as well as solutions for job-specific
considerations, such as site geometry.
Finally, the feasibility analysis for economics and durability showed the economic
advantages of a precast pavement, such as reduced user costs, as well as advantages in terms of
durability, which have been proven through prior experience with prestressed pavements.
Further investigation, future implementation, and performance monitoring will, ultimately,
demonstrate the feasibility of the proposed concept, as discussed in Chapter 10.
11.2.2 Benefits of Precast Pavement Construction
The most obvious benefit of precast concrete pavement construction, the attraction to
which is the reason this project was originally undertaken, is the speed of construction. By using
precast panels, additional time is not required to allow the concrete to cure before traffic can be
allowed back onto the pavement. This quick opening to traffic allows for precast concrete
pavements to be placed during separate (overnight or weekend) operations. Construction can
take place when traffic volumes are low, while the pavement will be open to traffic when traffic
volumes are higher.
The economic benefits of precast construction will be realized through savings in user
costs. As was demonstrated in Chapter 9, by limiting construction to an overnight time frame,
user delay costs are significantly reduced (from approximately $680,610/day to $124,500/day for
the example presented). Although it may not be possible to place as much precast pavement as
conventional pavement in a daily operation, the user cost savings far outweigh the additional
time needed for construction.
The proposed concept has many aspects that are favorable for separate overnight
construction operations. First, the asphalt leveling course can be placed well in advance of the
precast panels, allowing traffic onto the leveling course prior to panel placement. Second, the
post-tensioning tendons do not have to be grouted before traffic is allowed back onto the
pavement. Grouting can be done at a later time, during a subsequent operation. The stressing
pockets, also, do not have to be filled before traffic is allowed onto the pavement. Finally, the
use of prefabricated ramps will provide an efficient method for transitioning traffic onto the new
pavement from the existing pavement.
Other major advantages of precast construction include increased slab lengths (fewer
joints), material savings (less concrete and reinforcement), and increased durability. The cast-in-
place prestressed concrete pavement in McLennan County, Texas, which formed the basis for
many of the aspects of the proposed precast pavement concept, is evidence of these advantages.
The McLennan County pavement had expansion joints spaced at only 240 ft and 440 ft. The
thickness of the pavement was only 6 in., as compared to 14 in. CRC pavements currently
constructed in the same region. Also, the pavement, which has been in place for nearly 15 years,
shows virtually no signs of distress.
Precast concrete pavements can be used for any application where expedited construction
is required. They can be used for new pavement applications, for unbonded overlay applications,
and for removal and replacement applications. The ability to place several adjacent slabs at
131
CHAPTER 11. CONCLUSIONS AND RECOMMENDATIONS
different times and tie them together through post-tensioning makes precast concrete pavement
ideal for applications where only one or two lanes can be replaced at a time, such as is the case in
a removal and replacement application.
11.3 RECOMMENDATIONS
The proposed concept should meet the requirements for expedited pavement
construction. The feasibility of precast concrete pavement construction, however, will ultimately
only be realized through actual implementation. Further development of some of the conceptual
ideas should also be completed prior to actual implementation. As discussed in Chapter 10, a
staged implementation strategy is recommended. This strategy allows for small-scale
implementation at first (to work out the minor details), followed by larger-scale implementation,
and ultimately, urban implementation, which will present the greatest challenges to precast
pavement construction.
As implementation proceeds, the proposed concept will continually be refined. Since the
purpose of using precast concrete pavement is to expedite construction, it is important to
streamline the production and placement processes as much as possible to increase efficiency. In
the end, a simple concept, which is appealing to contractors and transportation agencies, is
desirable. A concept that is easily adaptable to existing techniques, but yet not restricted by
current practices, will ensure the viability of precast concrete pavements.
132
Appendix
133
A.1 VOID EFFECTS ON PAVEMENT LIFE
CTR Research Report 249-3 (Ref 39) describes an investigation into the effects of voids
beneath concrete pavement slabs on the life of pavements. When voids are present, the
pavement must span the voids, causing a significant increase in pavement stresses. These
increased stress levels reduce the fatigue life of pavements considerably. In this project, slab
stresses were determined through analytical techniques for three different void size conditions.
Using these stresses, the fatigue life under these conditions was computed using the following
fatigue equation developed for Texas (Ref 28).
3.0
f
N = 46,000 (A.1)
s
The parameters for the project are shown in Table A.1. These conditions pertain to
conventional concrete pavements. Under conditions where prestressing is applied to the slab, the
pavement fatigue life should be less affected by the presence of voids. In Figure A.1, the results
of this project show that increasing void size results in a significant pavement life reduction.
Parameter Value(s)
1) Slab size 24 ft x 12 ft
2) Void size 2 ft x 6 ft
4 ft x 12 ft
6 ft x 18 ft
3) Pavement thickness 8 in, 10 in, 12 in
4) K-value 100 pci, 300 pci
5) Wheel load 18-kip single axle with dual tire
32-kip tandem axle
6) Load position 0.5 ft from edge
1.5 ft from edge
2.5 ft from edge
7) Concrete: Modulus of Elasticity 5,000 ksi
8) Poisson’s ratio 0.20
9) Concrete: Flexural strength 650 psi
135
APPENDIX
6.6
6.2
5.8
5.6
8-inch Slab
5.4
5.2
5.0
0 5 10 15 20
Void Size, square feet
Figure A.1 Effect of void size on fatigue life of pavement (Ref 39)
When precast slabs are used for pavements, there is a high probability that voids will be
present under the slab after it is in place. These voids could be caused by:
Depending on the supporting layers beneath the precast concrete panels, the amount of
prestress applied to the pavement, and the method used to level the panels, the reduction in
pavement fatigue life caused by the presence of voids should be less severe than that for
conventional pavements.
136
A.2 Handling and Erection of Precast Panels
before making the lift. A bushing on the lifting hardware fits into the hole left by the plastic
sleeve and a steel locking hook engages the insert. The hardware is then adjusted by hand, and
the crane hook is attached to the bail to make the lift. The lifting hardware on all of these units is
reusable, and the insert holes can be filled with mortar.
Waddell further recommends that inserts be sized to set back 3/8 in. from the top face of
the panel. The Precast Concrete Institute (PCI) Handbook (Ref 41) also warns against the thread
connector protruding from the face, as this could possibly be damaged during handling.
One of the simplest anchorage elements consists of a spiral or threaded unit embedded in
the concrete, as shown in Figure A.3. This element forms a “nut” into which a special bolt can
be threaded. To increase the pullout resistance of the anchor, a wire loop is welded to the coil
(Figure A.3), thus increasing the depth of embedment. The loop may be single or multiple,
straight or flared. Some are designed with a loop through which a short bar of reinforcing steel
can be inserted.
Figure A.2 Several basic items of lifting hardware for precast panels (Ref 40)
137
APPENDIX
Figure A.3 Straight coil loop insert, flared coil loop insert, and attachment bolt (Ref 40)
Selection of the correct insert depends on a number of factors associated with the type,
weight, configuration, thickness, and strength of the precast member. It is recommended that the
insert selection be based on the manufacturer’s recommendations and on an engineering analysis
of the proposed installation. Many conditions of loading should be considered, depending on the
type of handling operation involved. It is also recommended that the strength, as controlled by
the steel, can be taken from manufactures’ catalogs. The PCI Handbook (Ref 41) contains
design tables for inserts such as those shown in Figure A.3.
Waddell (Ref 40) also presents vacuum lifting devices, as shown in Figure A.4, that have
been used to successfully handle flat precast elements. One advantage of vacuum lifters is the
reduction in handling time. It takes only a few seconds to attach or release the lifter. Also, the
panel is not disfigured by holes for inserts that have to be patched later. A fail-safe period of an
hour is built into the equipment in case of power failures.
138
A.2 Handling and Erection of Precast Panels
Figure A.4 Vacuum lifters come in a variety of sizes and capacities and are adaptable to a
variety of precast units (Ref 40)
Waddell (Ref 40) also addresses issues regarding the transportation of precast concrete
members. It is recommended that the loading of any type of unit be done in a way that provides
adequate support and cushioning to minimize damage while the unit is in transit. Adequate
padding must be provided between chains, cables, or ropes and the members to prevent chipping
or other damage, especially around edges and corners. Most precast panels can be supported by
an A-frame positioned on the bed of a truck, trailer, or rail car to hold the panels in nearly
vertical position, with the panels loaded in such a manner to minimize the weight of one unit
bearing on another. The use of an A-frame to support a panel is shown in Figure A.5.
139
APPENDIX
Positioning of Tendons
It is common practice to use 5/8 in. diameter holes in end dividers (bulkheads or headers)
for 3/8 in. to ½ in. diameter strands, since it is costly to switch end dividers for different strand
diameters. Thus, better accuracy is achieved when using larger diameter strands. The PCI
Handbook recommends that individual tendons be positioned within ±1/4 in. of the design
position.
140
A.3 Tolerances for Precast Panels
Bowing differs from warping in that two opposite edges of a panel may fall in the same
plane, but the portion between is out of plane, as shown in Figure A.7. The PCI bowing
tolerance is L/360, where L is the length of bow. The maximum tolerance on differential bowing
between panels of the same design is ½ in.
141
APPENDIX
considered in design of the panel and its connections to minimize bowing and warping. Pre-
erection storage might also affect warping and bowing. Because thin panels are more likely to
bow, tolerances should be more liberal (Ref 41). Table A.2 gives the thickness, related to panel
dimensions, for which the given warping and bowing tolerances should apply. It is stated that
more rigid tolerances can be set, but this could lead to significant increases in cost and should not
therefore be specified unless absolutely necessary.
142
A.5 Precast Construction for Buildings
Figure A.8 Typical cross sections used for prestressed concrete sheet piles (Ref 42)
Figure A.9 Polyethylene interlock for prestressed sheet piles (Ref 42)
1) Overlap: If Øs is made less than 14Ø, more of the tension force has to be transferred by bond
in the straight side of the loop. This means that the overlap of the bars must be increased. A
simple rule of thumb is that when diminishing the diameter Øs below 14Ø, add the difference
to the overlap length, as shown in Figure A.10.
143
APPENDIX
2) Concrete Cover: The loops must be far enough, at least 5Ø, from the edges. If the concrete
cover to the outer loop is less than this, then failure could occur owing to spalling of the top
cover.
3) Provision of Lateral Reinforcement: The effect of the lateral tensile stresses is evident in
the splitting of the outer concrete zone and the cracking of the slabs. To withstand these
tensile forces, lateral reinforcement should be provided. The reinforcement, however, will
not come into action before the cracks are already visible and, therefore, will not
substantially reduce the rotation at the joint. The recommended lateral reinforcement layout
is also shown in Figure A.10.
Figure A.10 Recommended joint type to connect precast panels (Ref 43)
An article by Despeyroux (Ref 44) presents the detail, shown in Figure A.11, used to join
wall panels. It is stated that this detail successfully provides continuity between two panels.
Despeyroux recommends the use of indentations (see Figure A.11), as they reduce sliding
between panels and provide a better key.
144
A.5 Precast Construction for Buildings
Figure A.11 Vertical joints between panels with auxiliary spiral (Ref 44)
In a publication on structural connection details for precast concrete elements (Ref 45),
the detail in Figure A.12 is presented for connecting adjacent floor units. In this connection, the
sides of the floor panels have large chamfers from which looped reinforcing bars protrude,
overlapping those of the adjoining panel. Reinforcement bars are then inserted through the
loops, along the full length of the joint, around which concrete is then cast. It is noted that,
depending on the design of the looped splice connections and the quality of the in-situ concrete,
the connection is able to transmit large compressive and tensile forces, large horizontal and
vertical shear forces, and a fairly large negative and fairly small positive moment.
145
APPENDIX
Figure A.12 Floor unit to floor unit connection by looped bars (Ref 45)
146
A.5 Precast Construction for Buildings
The PCI Handbook (Ref 41) presents the groove joint details shown in Figure A.14.
These grooved joints are continuous and usually filled with grout. It is recommended that the
minimum groove dimension be 1½ in. deep and 3 in. wide. The PCI Handbook addresses
methods to design the capacity of such keyed connections. The capacity of such a connection
can be limited by:
Figure A.15 illustrates the types of joints recommended by the PCI Handbook for
segmental precast construction. Two types of joints are defined: “open,” designed to permit
completion by a field-placed grout, or “closed,” designed such that the joint is either dry or
bonded by a thin layer of adhesive.
147
APPENDIX
148
A.6 Lightweight Concrete
The use of lightweight aggregate would also reduce the weight of the precast concrete
panels, which would make handling, transportation, and placement of the panels easier.
An article by Despeyroux (Ref 44) also addresses the use of lightweight concrete in order
to reduce the weight of precast members. Regarding the use of lightweight aggregates, it was
stated that various structural problems present themselves because of the following factors:
(a) Shrinkage is 50 to 60% greater than that of ordinary concretes.
(b) Creep is likewise 50 to 60% greater than that of ordinary concretes.
Because of the shrinkage, it may be necessary to specify rather longer periods of storage
(maturing) in the storage yard before the components are allowed to be used.
149
References
3. Nishizawa, T., E. Noda, and T. Fukuda. “Study on the Mechanical Behavior of Precast
Concrete Pavements,” International Symposium on Concrete Roads, Vienna, 1994, pp.
93–98.
5. Hara, Chisato, Takuya Ikeda, Saburo Matsuno, and Tatsuo Nishizawa. “Long Term
Performance of Prestressed Concrete Pavements in Japan,” Purdue Conference on
Concrete, Indiana, 1997.
7. Issa, Mohsen A., Alfred A. Yousif, Mahmoud A. Issa, Iraj I. Kaspar, and Salah Y.
Khayyat. “Analysis of Full Depth Precast Concrete Bridge Deck Panels,” PCI Journal,
January–February 1998, pp. 74–85.
8. Issa, Mohsen A., Alfred A. Yousif, Mahmoud A. Issa, Iraj I. Kaspar, and Salah Y.
Khayyat. “Field Performance of Full Depth Precast Concrete Panels in Bridge Deck
Reconstruction,” PCI Journal, May–June 1995, pp. 82–108.
9. Martin, L. D., and A. E. N. Osborn. Connections for Modular Precast Concrete Bridge
Decks, Report Number FHWA/RD-82-106, Office of Research, Development, and
Technology, Federal Highway Administration, Washington, D.C., August 1993.
10. AASHTO. AASHTO LRFD Bridge Design Specification, American Association of State
Highway and Transportation Officials, Washington, D.C., 2nd ed., 1998.
11. Koseki, K., and J. E. Breen. Exploratory Study of Shear Strength of Joints for Precast
Segmental Bridges, Research Report 248-1, Center for Transportation Research, The
University of Texas at Austin, September 1983.
151
REFERENCES
12. Kashina, S., and J. E. Breen. Construction and Load Tests of a Segmental Precast Box
Girder Bridge Model, Research Report No. 121-5, Center for Highway Research, The
University of Texas at Austin, February 1975, 261 pp.
13. Bruggeling, A. S. G., and G. F. Huyghe. Prefabrication with Concrete, A.A. Balkema
Publishers, Rotterdam, Netherlands, 1991, 380 pp.
14. Zech, U. I. Joints in Large Panel Precast Concrete Structures, Seismic Resistance of
Precast Concrete Panel Buildings, Report No. 1, Department of Civil Engineering,
Massachusetts Institute of Technology, January 1976, 174 pp.
16. Bull, John W. Precast Concrete Raft Units, Van Nostrand Reinhold, New York, NY,
1991, 193 pp.
17. Bull, John W., and Salim H. Salmo. “Fatigue Characteristics of Precast Concrete Raft
Pavement Units Used for Heavy Duty Pavements,” Fatigue and Fracture in Steel and
Concrete Structures — ISFF ‘91 Proceedings, December 19–21 1991, Oxford and IBH
Pub. Co. Pvt. Ltd., New Delhi, India, pp. 565–578.
18. Elkins, Gary Eugene, B. F. McCullough, and Ronald W. Hudson. Precast Repair of
Continuously Reinforced Concrete Pavement, Research Report 177-15, Center for
Transportation Research, The University of Texas at Austin, May 1979.
19. Meyer, Alvin H., and B. F. McCullough. “Precast Repair of CRC Pavements,” Journal
of Transportation Engineering, Vol. 109, No. 5, September 1983, pp. 615–631.
20. Mandel, Elliott, Jose Tena-Colunga, Kenneth Hankins, Ned H. Burns, and B. Frank
McCullough. The Performance of a Prestressed Concrete Pavement, Research Report
No. 556-4F, Center for Transportation Research, The University of Texas at Austin,
November 1989.
21. American Concrete Institute. Building Code Requirements for Structural Concrete and
Commentary (ACI 318-95), American Concrete Institute, Farmington Hills, MI, 1995.
23. Wesevich, James W., B. F. McCullough, and Ned H. Burns. Stabilized Subbase Friction
Study for Concrete Pavements, Research Report 459-1, Center for Transportation
Research, The University of Texas at Austin, April 1987.
152
REFERENCES
24. Rozycki, Dan K., and Robert Otto Rasmussen. Assessment of Slab-Base Interaction in
PCC Airfield Pavements, research paper, Transtec, Inc., Austin, Texas, 1998.
25. Mendoza Diaz, A., B. F. McCullough, and Ned H. Burns. Behavior of Long Prestressed
Pavement Slabs and Design Methodology, Research Report 401-3, Center for
Transportation Research, The University of Texas at Austin, September 1986.
27. Schindler, Anton K., Tony S. Krauss, and B. F. McCullough. The Design
Documentation of a High Performance Concrete Pavement Located on IH-35 in the
Waco District, Texas, Research Report 98-0215-1F, Center for Transportation Research,
The University of Texas at Austin, May 1999.
29. Green, William J., Ramon L. Carrasquillo, and B. F. McCullough. Coarse Aggregate for
PCC — Pilot Study Evaluation, Research Report 422-1, Center for Transportation
Research, The University of Texas at Austin, September 1987.
32. Precast and Prestressed Concrete Institute. PCI Design Handbook, Precast and
Prestressed Concrete Institute, Chicago, Illinois, 5th ed., 1999.
33. Chia, Way Seng, B. F. McCullough, and Ned H. Burns. Field Evaluation of Subbase
Friction Characteristics, Research Report 401-5, Center for Transportation Research,
The University of Texas at Austin, September 1986.
153
REFERENCES
35. Wilde, James W., Steve Waalkes, and Rob Harrison. Life Cycle Cost Analysis of
Portland Cement Concrete Pavements, Research Report 1739-1, Center for
Transportation Research, The University of Texas at Austin, September 1999.
36. Lin, T. Y., and Ned H. Burns. Design of Prestressed Concrete Structures, 3rd ed., John
Wiley and Sons, Inc., 1981.
37. Schupack, Morris. “Bonded Tendon Debate,” Civil Engineering, August 1993, pp. 64–
66.
39. Torres, F., and B. F. McCullough. Void Detection and Grouting Process, Research
Report 249-3, The Center for Transportation Research, The University of Texas at
Austin, April 1983.
40. Waddell, J. J. Precast Concrete: Handling and Erection, ACI Monograph Number 8,
The American Concrete Institute, Detroit, Michigan, 1974, 127 pp.
41. PCI. PCI Design Handbook, Prestressed Concrete Institute, Chicago, Illinois, 3rd ed.,
1985.
42. Gerwick, B. C., Jr. Construction of Prestressed Concrete Structures, John Wiley and
Sons Incorporated, New York, 2nd ed., 1992.
44. Despeyroux, J. “Structural Connection Problems and the Use of Special Materials in
Precast Concrete Construction,” Proceedings of a Symposium held at Church House,
London SW1, International Association for Bridge and Structural Engineering, May
1967.
45. Stupré — Society for Studies on the Use of Precast Concrete. Kraftschüssige
Verbindungen im Fertigteilbau: Deckenverbindungen, Precast Concrete Connection
Details: Floor connections, Beton-Verlag GmbH, Düsseldorf, Netherlands, 1981, 133
pp.
46. Munch-Petersen, J. F. “Floor, Wall and Façade Joints in Danish Precast Housing,”
Proceedings of a Symposium held at Church House, London SW1, International
Association for Bridge and Structural Engineering, May 1967.
154
REFERENCES
48. McCullough, B. F., and Robert Otto Rasmussen. Fast-track Paving: Concrete
Temperature Control and Traffic Opening Criteria for Bonded Concrete Overlays,
Volume I: Final Report, Report No. FHWA-RD-98-167, U.S. Department of
Transportation, Federal Highway Administration, October 1999.
155