0% found this document useful (0 votes)
359 views5 pages

Quality Record Control Procedure

This document provides a master list of quality records for China International Water & Electric Corp., including 47 numbered records related to requests, reports, plans, and other documents for inspection, non-conformance, materials, testing, and training. The records are grouped and referenced according to the quality procedure they relate to.

Uploaded by

Gomathyselvi
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
359 views5 pages

Quality Record Control Procedure

This document provides a master list of quality records for China International Water & Electric Corp., including 47 numbered records related to requests, reports, plans, and other documents for inspection, non-conformance, materials, testing, and training. The records are grouped and referenced according to the quality procedure they relate to.

Uploaded by

Gomathyselvi
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 5

China International Water & Electric Corp.(S) No.

JIMT-C02-Q-04-20008
Pte.Ltd.
Date: 22 Feb 2017
Revision: 3
Quality Record Control Procedure
Page 1 of 5

1.1 Master list of quality record

Attached-In
No. Record No. Plan/Procedure Record Title
Document No.
Request for inspection
1 JIMT-C02-Q-13-20000-ZZZ JIMT-C02-Q-04-20001
master list

2 JIMT-C02-Q-13-20001-ZZZ JIMT-C02-Q-04-20001 Request for inspection

3 JIMT-C02-Q-13-20002-ZZZ JIMT-C02-Q-04-20002 Non-conformance report

Non-conformance report
4 JIMT-C02-Q-13-20003-ZZZ JIMT-C02-Q-04-20002
master list
Corrective and preventive
5 JIMT-C02-Q-13-20004-ZZZ JIMT-C02-Q-04-20003
action request
Corrective and preventive
6 JIMT-C02-Q-13-20005-ZZZ JIMT-C02-Q-04-20003
action request master list
Monitoring and measuring
7 JIMT-C02-Q-13-20006-ZZZ JIMT-C02-Q-04-20011
devices master list
Certified and qualified,
8 JIMT-C02-Q-13-20007-ZZZ JIMT-C02-Q-04-20001 registered personnel master
list
Summary of welding
9 JIMT-C02-Q-13-20008-ZZZ JIMT-C02-Q-04-20015
consumable materials

10 JIMT-C02-Q-13-20009-ZZZ JIMT-C02-Q-04-20015 Welding material request

Welding material return


11 JIMT-C02-Q-13-20010-ZZZ JIMT-C02-Q-04-20015
record
Welding electrode storage
12 JIMT-C02-Q-13-20011-ZZZ JIMT-C02-Q-04-20015
and drying record
Welding procedure
13 JIMT-C02-Q-13-20012-ZZZ JIMT-C02-Q-04-20013
specification
Procedure qualification
14 JIMT-C02-Q-13-20013-ZZZ JIMT-C02-Q-04-20013
record

15 JIMT-C02-Q-13-20014-ZZZ JIMT-C02-Q-04-20013 WPS and PQR master list

16 JIMT-C02-Q-13-20015-ZZZ JIMT-C02-Q-04-20013 Fit-up inspection record

Fit-up inspection record


17 JIMT-C02-Q-13-20016-ZZZ JIMT-C02-Q-04-20013
master list

18 JIMT-C02-Q-13-20017-ZZZ JIMT-C02-Q-04-20013 Visual inspection report


China International Water & Electric Corp.(S) No. JIMT-C02-Q-04-20008
Pte.Ltd.
Date: 22 Feb 2017
Revision: 3
Quality Record Control Procedure
Page 2 of 5

Attached-In
No. Record No. Plan/Procedure Record Description
Document No.
Visual inspection report
19 JIMT-C02-Q-13-20018-ZZZ JIMT-C02-Q-04-20013
master list

20 JIMT-C02-Q-13-20019-ZZZ JIMT-C02-Q-04-20013 Welder performance record

Welding joint traceability


21 JIMT-C02-Q-13-20020-ZZZ JIMT-C02-Q-04-20013
record
Summary of material
22 JIMT-C02-Q-13-20021-ZZZ JIMT-C02-Q-04-20010
stock/stores inventory
Material receiving inspection
23 JIMT-C02-Q-13-20022-ZZZ JIMT-C02-Q-04-20010
report

24 JIMT-C02-Q-13-20023-ZZZ JIMT-C02-Q-04-20010 Material issue record

Material return to stock


25 JIMT-C02-Q-13-20024-ZZZ JIMT-C02-Q-04-20010
record
Material receiving inspection
26 JIMT-C02-Q-13-20025-ZZZ JIMT-C02-Q-04-20010
report master list
Quarantine sticker or tag
27 JIMT-C02-Q-13-20026-ZZZ JIMT-C02-Q-04-20010
master list

28 JIMT-C02-Q-13-20027-ZZZ JIMT-C02-Q-04-20012 General inspection report

General inspection report


29 JIMT-C02-Q-13-20028-ZZZ JIMT-C02-Q-04-20012
master list

30 JIMT-C02-Q-13-20029-ZZZ JIMT-C02-Q-04-20012 Inspection and test plan

Summary of inspection and


31 JIMT-C02-Q-13-20030-ZZZ JIMT-C02-Q-04-20012
test plan

32 JIMT-C02-Q-13-20031-ZZZ JIMT-C02-Q-04-20018 Punch list form

Punch list summary status


33 JIMT-C02-Q-13-20032-ZZZ JIMT-C02-Q-04-20018
(Discipline)
Punch list summary status
34 JIMT-C02-Q-13-20033-ZZZ JIMT-C02-Q-04-20018
(System/subsystem)
Welding joint repair
35 JIMT-C02-Q-13-20034-ZZZ JIMT-C02-Q-04-20016
traceability record

36 JIMT-C02-Q-13-20035-ZZZ JIMT-C02-Q-04-20006 Annual training schedule

37 JIMT-C02-Q-13-20036-ZZZ JIMT-C02-Q-04-20006 Training attendance list

38 JIMT-C02-Q-13-20037-ZZZ JIMT-C02-T-01-20001 Tank fabrication data sheet


China International Water & Electric Corp.(S) No. JIMT-C02-Q-04-20008
Pte.Ltd.
Date: 22 Feb 2017
Revision: 3
Quality Record Control Procedure
Page 3 of 5

Attached-In
No. Record No. Plan/Procedure Record Description
Document No.
Material identification &
39 JIMT-C02-Q-13-20038-ZZZ JIMT-C02-Q-04-20017
traceability record

40 JIMT-C02-Q-13-20039-ZZZ JIMT-C02-Q-04-20025 Dimension inspection report

Dimension inspection report


41 JIMT-C02-Q-13-20040-ZZZ JIMT-C02-Q-04-20025
master list

42 JIMT-C02-Q-13-20041-ZZZ JIMT-C02-Q-04-20041 RT report

43 JIMT-C02-Q-13-20042-ZZZ JIMT-C02-Q-04-20042 UT report

44 JIMT-C02-Q-13-20043-ZZZ JIMT-C02-Q-04-20043 PT report

45 JIMT-C02-Q-13-20044-ZZZ JIMT-C02-Q-04-20044 MT report

Surface preparation
46 JIMT-C02-Q-13-20045-ZZZ JIMT-C02-Q-04-20039
roughness inspection report
Dry film thickness inspection
47 JIMT-C02-Q-13-20046-ZZZ JIMT-C02-Q-04-20039
report

48 JIMT-C02-Q-13-20047-ZZZ JIMT-C02-Q-04-20039 Adhesive test report

Summary of painting
49 JIMT-C02-Q-13-20048-ZZZ JIMT-C02-Q-04-20039
materials

50 JIMT-C02-Q-13-20049-ZZZ JIMT-C02-Q-04-20017 Surplus Material List

Welder performance
51 JIMT-C02-Q-13-20050-ZZZ JIMT-C02-Q-04-20014
qualification
Application form of welder
52 JIMT-C02-Q-13-20051-ZZZ JIMT-C02-Q-04-20014
qualification test
Welder qualification
53 JIMT-C02-Q-13-20052-ZZZ JIMT-C02-Q-04-20014
certificate

54 JIMT-C02-Q-13-20053-ZZZ JIMT-C02-Q-04-20014 Qualified welders master list

Visual inspection report for


55 JIMT-C02-Q-13-20054-ZZZ JIMT-C02-Q-04-20039
painting works
RC pile receiving inspection
56 JIMT-C02-Q-13-20055-ZZZ JIMT-C02-Q-04-20019
record

57 JIMT-C02-Q-13-20056-ZZZ JIMT-C02-Q-04-20019 Ultimate load test record

58 JIMT-C02-Q-13-20057-ZZZ JIMT-C02-Q-04-20019 Preliminary trial piling record


China International Water & Electric Corp.(S) No. JIMT-C02-Q-04-20008
Pte.Ltd.
Date: 22 Feb 2017
Revision: 3
Quality Record Control Procedure
Page 4 of 5

Attached-In
No. Record No. Plan/Procedure Record Description
Document No.

59 JIMT-C02-Q-13-20058-ZZZ JIMT-C02-Q-04-20019 Survey inspection record

60 JIMT-C02-Q-13-20059-ZZZ JIMT-C02-Q-04-20019 Pile driving inspection record

61 JIMT-C02-Q-13-20060-ZZZ JIMT-C02-Q-04-20019 Surveillance report

62 JIMT-C02-Q-13-20061-ZZZ JIMT-C02-Q-04-20019 Working load test report

63 JIMT-C02-Q-13-20062-ZZZ JIMT-C02-Q-04-20019 Pile cutting record

64 JIMT-C02-Q-13-20063-ZZZ JIMT-C02-Q-04-20019 Piling driving analyser report


Management review meeting
65 JIMT-C02-Q-13-20064-ZZZ JIMT-C02-Q-04-20005
attendance list
66 JIMT-C02-Q-13-20065-ZZZ JIMT-C02-Q-04-20005 Improvement plan
Minutes of meeting for
67 JIMT-C02-Q-13-20066-ZZZ JIMT-C02-Q-04-20005
management review
68 JIMT-C02-Q-13-20067-ZZZ JIMT-C02-Q-04-20004 Internal audit schedule

69 JIMT-C02-Q-13-20068-ZZZ JIMT-C02-Q-04-20004 Internal audit plan

70 JIMT-C02-Q-13-20069-ZZZ JIMT-C02-Q-04-20004 Internal audit checklist


Internal audit meeting
71 JIMT-C02-Q-13-20070-ZZZ JIMT-C02-Q-04-20004
attendance list
72 JIMT-C02-Q-13-20071-ZZZ JIMT-C02-Q-04-20004 Internal audit report
JIMT-C02-Q-04-20013
73 JIMT-C02-Q-13-20072-ZZZ Master list of welders sample
Rev.1
JIMT-C02-Q-04-20053
74 JIMT-C02-Q-13-20073-ZZZ Site backfilling record sample
Rev.0
JIMT-C02-Q-04-20012 Notification for inspection
75 JIMT-C02-Q-13-20074-ZZZ
Rev.1 sample
JIMT-C02-Q-04-20012 Notification for inspection
76 JIMT-C02-Q-13-20075-ZZZ
Rev.1 master list sample
Master list of driven pile
77 JIMT-C02-Q-13-20076-ZZZ
records
Master list of RC pile
78 JIMT-C02-Q-13-20077-ZZZ
receiving record
Concrete work inspection
79 JIMT-C02-Q-13-20078-ZZZ JIMT-C02-Q-04-20022
form
Record of inspection and
80 JIMT-C02-Q-13-20079-ZZZ JIMT-C02-Q-04-20022
approval for concreting
China International Water & Electric Corp.(S) No. JIMT-C02-Q-04-20008
Pte.Ltd.
Date: 22 Feb 2017
Revision: 3
Quality Record Control Procedure
Page 5 of 5

Note: With the project going on and quality procedure submission, the quality records shall be
added in the above master list of quality record.

You might also like