Goldratt Simulation: Manufacturing Operations Management
Goldratt Simulation: Manufacturing Operations Management
Calculating Bottleneck
Utilisation Analysis
From the utilisation calculated we observed that blue is the most utilised resource as
for completion of all the order we have to achieve 94% [Exhibit 1] utilisation of Blue resource.
We also tried to calculate number of setups allowed for the blue resource which turns out to
be 14 [Exhibit 2]. Thus while deciding the production plan we have to ensure that blue resource
doesn’t remain idle.
Calculating Demand
Calculation for material required is shown in [Exhibit 3], After taking into account the
final demand for each of the material are as follows
MATERIAL REQUIRED
A 22
C 22
D 36
F 12
G 0
H 4
Strategy
Key idea in developing the strategy for successful completion of the demand
was as follows
Ensuring that blue resource never remains idle and setups involved in blue resource
are way less then 14 (As in our calculation we haven’t included any time loss that may
occur due to machine breakdown)
Blue resource has to be deployed in such a way that it keeps creating work for magenta
resource
As none of the other resources present any major constraints they are deployed to
support the production of blue and magenta resource.
At the start of the simulation, we focused on two objectives completing the demand of
Product 1 and Deploying magenta resource as soon as possible. To achieve this, we deployed
blue resource at F2, along with cyan resource to support the production. Production is
continued till 20 and then blue resource is deployed to D3 and later on to D4 till 20 units are
produced. After production of 20 units in both the lines is complete we move blue resource to
F3 to facilitate production of remaining raw material and introduce a magenta resource at E6
to complete the production of raw material we have just produced. As soon as blue resource
is finished with the production at line F it is moved to line D to use rest of the blue resource at
line D. For a detailed production plan of blue resource please refer to Exhibit 5
Mean while red and brown resource are deployed at A2, A3 and C2. Logic for this
decision as well is to deploy magenta resource in production. As soon as we move blue from
F2, cyan resources are shifted to line A and C. As soon as brown and red resource are finished
with the production they are moved to D and H line thus finishing the task of these resources.
Magenta resources is bought into production in line B as soon as cyan resource start
producing. Thus completing our objective of getting magenta resource into production as soon
as possible. When cyan resource are finished with the production in line A and C, they are
moved to line H. This is in align with our strategy of deploying resources such that production
of magenta resource is supported. We also move one of the magenta resource from line B to
line H to further allow the production of product 3. It is important here to note that taking
magenta resource out of a line in the middle of production won’t affect our utilisation as
magenta resource has zero setup time.
As soon as magenta resource is done with the task at line H and line E, they are
moved to line F and B to facilitate the rest of production. Followed by the deployment of
magenta resource at line D to complete the production.
All the decision and time at which these decisions were taken are
mentioned in [Exhibit 4]. Please note that actual time of decision may vary significantly as the
decision sheet does not include factor of machine breakdown or variability in the setup time
and production time.
Result
Using this production plan we were able to meet the demands completely for all the
product and reported a profit of 4050 with ROI of 40.21%
Exhibits
Setups Allowed
Blue 14
Green 71
Cyan 113
Red 16
Magenta Inf
Brown 17
Exhibit 2: Setups Allowed
Blue Resource
Position Logic
F2 Pushing Forward Production of product 3,
thus creating work for Magenta resource
D3 Same logic as above allowing Production
D4 of Product 3, to create work for Magenta
resource
F2 Using Blue Resource till 20 Production are
ready for production at G6
G6 Pushing 20 resource to create more work
for Magenta resource
F2 Finishing, what is left at F2
D3 Finishing remaining Production at D3 and
D4 D4
C5 Completing the Demand for Product 2
Exhibit 5: Detailed Production Plan for Blue Resource
Screenshot of “End of the Week Financial Statement