2 Civil Specs Final

Download as pdf or txt
Download as pdf or txt
You are on page 1of 222

SPECIFICATIONS

CIVIL WORKS

Table of Contents

1. CIVIL WORKS ............................................................................................. 1

1.1 Description and Design of Civil Works ........................................................ 1


1.1.1 Standards .................................................................................................... 1
1.1.2 Scope ........................................................................................................... 1
1.1.3 Extent of Works ........................................................................................... 1
1.1.4 On-Site Drainage System ............................................................................ 1
1.1.5 Roads and Parking ...................................................................................... 1
1.1.6 Fencing ........................................................................................................ 2
1.1.7 Landscaping ................................................................................................ 2
1.1.8 Water Retaining Structures ......................................................................... 2
1.1.9 Cable Ducts and Small Bore Pipelines ....................................................... 2
1.2 Site Investigation ......................................................................................... 3
1.2.1 General ........................................................................................................ 3
1.2.2 Scope ........................................................................................................... 3
1.2.3 Calculations ................................................................................................. 3
1.2.4 Design Parameters ...................................................................................... 3
1.2.5 Embankments .............................................................................................. 3
1.2.6 Foundations ................................................................................................. 4
1.3 Structural Concrete Design ......................................................................... 4
1.3.1 Design Principles and Analyses .................................................................. 4
1.3.2 Reinforced and Pre-stressed Concrete ....................................................... 5
1.3.3 Classification of Concrete Structures .......................................................... 5
1.3.4 Design Methods ........................................................................................... 6
1.3.5 Design Loadings .......................................................................................... 6
1.3.6 Grades of Concrete ..................................................................................... 6
1.3.7 Reinforcement ............................................................................................. 6
1.3.8 Cover ........................................................................................................... 7
1.3.9 Bond and Lap Length .................................................................................. 7
1.3.10 Water Stops and Sealants ........................................................................... 7
1.3.11 Joints in Concrete ........................................................................................ 7
1.3.12 Surface Finishes .......................................................................................... 8
1.3.13 Drawings ...................................................................................................... 9
1.3.14 Detailing shall be as follows ........................................................................ 9
1.4 Structural Steel Design .............................................................................. 11
1.4.1 General ...................................................................................................... 11
1.4.2 General Principles ..................................................................................... 11
1.4.3 Design Loadings ........................................................................................ 12
1.4.4 Deflection Limits ........................................................................................ 13
1.5 Protective Coating Design ......................................................................... 14
1.5.1 Scope ......................................................................................................... 14
1.5.2 Submissions .............................................................................................. 14
1.5.3 Design Generally ....................................................................................... 14
1.5.4 Systems ..................................................................................................... 14
1.6 Brickwork and Blockwork Design .............................................................. 15
1.6.1 Principles and Analysis.............................................................................. 15
1.6.2 Design ........................................................................................................ 15
1.6.3 Loadings .................................................................................................... 16
1.6.4 Joints ......................................................................................................... 16

GKW - Alliance i
SPECIFICATIONS
CIVIL WORKS

1.6.5 Drawings .................................................................................................... 17


1.7 Earthworks ................................................................................................. 17
1.7.1 General ...................................................................................................... 17
1.7.2 Definitions .................................................................................................. 17
1.7.3 Submissions by the Contractor ................................................................. 18
1.7.4 Materials .................................................................................................... 18
1.7.5 Workmanship ............................................................................................. 19
1.7.6 Testing ....................................................................................................... 32
1.7.7 Dewatering................................................................................................. 32
1.7.8 Particular Requirements ............................................................................ 34
1.8 Concrete .................................................................................................... 35
1.8.1 Scope ......................................................................................................... 35
1.8.2 Submissions by Contractor ....................................................................... 35
1.8.3 Materials .................................................................................................... 37
1.8.4 Workmanship ............................................................................................. 40
1.8.5 Testing ....................................................................................................... 56
1.8.6 Particular Requirements ............................................................................ 59
1.9 Concrete Jointing and Protection .............................................................. 59
1.9.1 Scope ......................................................................................................... 59
1.9.2 Submissions by the Contractor ................................................................. 59
1.9.3 Materials .................................................................................................... 60
1.9.4 Workmanship ............................................................................................. 64
1.10 Formwork and Reinforcement for Concrete .............................................. 66
1.10.1 Scope ......................................................................................................... 66
1.10.2 Submissions by the Contractor ................................................................. 66
1.10.3 Formwork ................................................................................................... 66
1.10.4 Reinforcement ........................................................................................... 70
1.11 Structural Steel .......................................................................................... 73
1.11.1 Scope ......................................................................................................... 73
1.11.2 Interpretation.............................................................................................. 73
1.11.3 Materials .................................................................................................... 74
1.11.4 Plant ........................................................................................................... 75
1.11.5 Construction............................................................................................... 75
1.11.6 Fabrication ................................................................................................. 76
1.11.7 Assembly ................................................................................................... 78
1.11.8 Setting-Out................................................................................................. 80
1.11.9 Erection...................................................................................................... 80
1.11.10 Grouting of Support ................................................................................... 81
1.11.11 Subcontracting ........................................................................................... 82
1.11.12 Tolerances ................................................................................................. 82
1.11.13 Tolerances on Dimensions, Accuracy of Erection, etc.............................. 82
1.11.14 Testing ....................................................................................................... 84
1.11.15 Schedules Items ........................................................................................ 86
1.12 Metalwork .................................................................................................. 86
1.12.1 Scope ......................................................................................................... 86
1.12.2 Submissions by Contractor ....................................................................... 86
1.12.3 Materials .................................................................................................... 87
1.12.4 Workmanship ............................................................................................. 91
1.12.5 Aluminium Ladders in Chambers .............................................................. 92
1.13 Pipelines for Water Supply ........................................................................ 92
1.13.1 Scope ......................................................................................................... 92
1.13.2 Submissions by Contractor ....................................................................... 93
1.13.3 Materials .................................................................................................... 94
1.13.4 Workmanship ........................................................................................... 110

GKW - Alliance ii
SPECIFICATIONS
CIVIL WORKS

1.13.5 Inspection and Testing ............................................................................ 125


1.13.6 Particular Requirements .......................................................................... 128
1.13.7 Design ...................................................................................................... 133
1.14 Pipelines for wastewater.......................................................................... 135
1.14.1 Scope ....................................................................................................... 135
1.14.2 Submissions by the Contractor ............................................................... 136
1.14.3 Materials and Equipment ......................................................................... 137
1.14.4 Workmanship ........................................................................................... 142
1.14.5 Inspection and Testing ............................................................................ 155
1.15 Painting and protective coatings ............................................................. 158
1.15.1 Submission by the Contractor ................................................................. 158
1.15.2 Specimen Schedule of Paint Systems and Protective Coatings............. 159
1.15.3 Materials .................................................................................................. 160
1.15.4 Workmanship ........................................................................................... 162
1.15.5 Inspection ................................................................................................ 170
1.16 Building Works ......................................................................................... 171
1.16.1 Scope ....................................................................................................... 171
1.16.2 Brickwork, Jointing and Pointing ............................................................. 171
1.16.3 Cavity Walls ............................................................................................. 174
1.16.4 Lintels, Ties, Miscellaneous .................................................................... 174
1.16.5 Grouting ................................................................................................... 175
1.16.6 Cleaning................................................................................................... 175
1.16.7 Damp Proof Course ................................................................................. 175
1.16.8 Waterproof Building Paper ...................................................................... 175
1.16.9 Corbelling................................................................................................. 175
1.16.10 Bonding to Concrete ................................................................................ 175
1.16.11 Underpinning ........................................................................................... 175
1.16.12 Centring and Lagging .............................................................................. 176
1.16.13 Exposed Concrete Block ......................................................................... 176
1.16.14 Concrete Blocks to be plastered ............................................................. 176
1.16.15 Fixing of Plasterboard.............................................................................. 176
1.16.16 Plastering ................................................................................................. 177
1.16.17 Flooring .................................................................................................... 179
1.16.18 Screeds.................................................................................................... 182
1.16.19 Tiling ........................................................................................................ 186
1.16.20 Suspended Ceilings................................................................................. 191
1.16.21 Roofing .................................................................................................... 193
1.16.22 Carpentry and Joinery ............................................................................. 195
1.16.23 Metal Windows, Louvres and Doors ....................................................... 204
1.16.24 Finish Hardware ...................................................................................... 205
1.16.25 Glass and Glazing ................................................................................... 206
1.16.26 Sanitary Installation ................................................................................. 208
1.16.27 Openings in Walls, Floors and Ceilings .................................................. 214
1.16.28 Tolerances for Building Works ................................................................ 214
1.17 Roadworks ............................................................................................... 215
1.17.1 Road Formations ..................................................................................... 215
1.17.2 Sub-Base Construction............................................................................ 215
1.17.3 Wet-mix Macadam Construction ............................................................. 216
1.17.4 Lean Concrete Construction.................................................................... 216
1.17.5 Laying Coated Macadam ........................................................................ 216
1.17.6 Laying Hot Rolled Asphalt ....................................................................... 216
1.17.7 Waterproof Underlay for Concrete Carriageways ................................... 217
1.17.8 Reinforcement of Concrete Carriageways .............................................. 217
1.17.9 Laying Concrete Carriageways ............................................................... 217
1.17.10 Laying Kerbs and Channels .................................................................... 217

GKW - Alliance iii


SPECIFICATIONS
CIVIL WORKS

1.17.11 Foundations for Footways ....................................................................... 217


1.17.12 Laying Concrete Paving Flags ................................................................ 218
1.17.13 Tolerances for Finished Carriageway Surfaces ...................................... 218
1.17.14 Fixing of Gullies ....................................................................................... 218

GKW - Alliance iv
SPECIFICATIONS
CIVIL WORKS

1. CIVIL WORKS

1.1 Description and Design of Civil Works

1.1.1 Standards

The following EN standards are the basis for the structural civil design and built:

 Eurocode 0: Basis of structural design (EN 1990)


 Eurocode 1: Actions on structures (EN 1991)
 Eurocode 2: Design of concrete structures (EN 1992)
 Eurocode 3: Design of steel structures (EN 1993)
 Eurocode 4: Design of composite steel and concrete structures (EN 1994)
 Eurocode 5: Design of timber structures (EN 1995)
 Eurocode 6: Design of masonry structures (EN 1996)
 Eurocode 7: Geotechnical design (EN 1997)
 Eurocode 8: Design of structures for earthquake resistance (EN 1998)
 Eurocode 9: Design of aluminium structures (EN 1999)

All material described in these Specifications, but not addressed in the various Eurocodes
above, shall comply with the relevant EN Reference Standards
(https://en.wikipedia.org/wiki/List_of_EN_standards), like ANSI, ASME, ISO, DIN, or
equivalent.

Equivalent Standards may substitute the Standards referred to in the Specifications,


provided that the Contractor has justified such substitution to the Engineer. These
Standards shall only be applied after written approval has been obtained from the Engineer.

1.1.2 Scope

This section describes the civil works to be built at the Katosi Water Treatment Plant project
and associated infrastructure works include roads, drainage and landscaping, etc.

1.1.3 Extent of Works

The limits of the works to be constructed at the Katosi Water Treatment Plant project area:

 The WTP construction works;


 The works at Nsumba Reservoir site;
 Works at transmission main;
 Works at access road.

1.1.4 On-Site Drainage System

At the work sites the Contractor shall also be responsible for all work necessary to discharge
all site overflows and drainage flows to an acceptable discharge point outside the
boundaries of the sites.

1.1.5 Roads and Parking

An access road, 5 m wide, shall be provided to the new intake structure and raw water
pumping station. Road areas shall contain ample space for parking and for manoeuvring
large vehicles.

GKW - Alliance 1
SPECIFICATIONS
CIVIL WORKS

1.1.6 Fencing

A temporary perimeter fence shall be provided around the site.

1.1.7 Landscaping

Landscaping shall be carried out at Katosi Water Treatment Plant project sites to soften the
visual impact of the works. Measures to be taken shall include earthworks and/or ground
level changes and the planting of suitable species of trees and shrubs. All flat areas within
the perimeter fence, which are neither planted nor paved, shall be grassed and irrigated.

1.1.8 Water Retaining Structures

Water retaining structures shall normally be reinforced concrete, unless stated otherwise.
Buildings shall generally be structural steel framed structures. Basement walls shall be
monolithic with adjacent floor slabs and shall be designed against soil and groundwater
loading. Walls shall generally be of brick infill between floors, columns and roofs or beams.

Expansion joints shall generally be provided at no more than 25 m spacing in plan through
roofs, floors and beams in order allow differential movement and to minimise temperature
effects. Columns and beam shall be duplicated on either side of expansion joints.

All basement and liquid retaining structures shall be tested for water-tightness. Each such
structure shall be filled and tested as soon as possible after the completion of construction
of the particular structure and prior to backfilling around the structure. The water level in the
structure shall be maintained at the maximum operational level for at least 72 hours during
which time the structure and underdrains shall be checked frequently for visible signs of
leakage. Thereafter the water level shall be lowered to 150 mm below that of any weir or
sill over which spillage might occur due to win action and the structure shall be left under
test in this condition with no water being added for 7 days during which time the water level
shall be recorded daily by a hook gauge.

Provided that the fall in water level during the 7-day test period does not exceed 10 mm
after allowing for rainfall and evaporation and that there are no visible signs of leakage or
damp patches, the structure shall be considered acceptable.

External water-tightness shall be checked by visual inspection of basement walls and flows
after backfilling of the structure shall be considered acceptable if no damp patches or
leakage are visible before the end of the Defects Liability Period.

Provision shall be made for all water retaining structure basements conduits, ducts etc. to
be drained completely. Floors shall be sloped or screeded at not less than 0.5% to drainage
channels and sumps. As far as possible, drainage shall be by gravity and where gravity
drainage is not possible sumps for the use of submersible pumps shall be provided.

Structures shall be designed to resist water loading due to external water level at ground
level. Uplift forces on reservoir, tanks and pipes shall be calculated assuming that they are
empty and the factor of safety against flotation in the condition shall be not less than l.1.

1.1.9 Cable Ducts and Small Bore Pipelines

Covered service ducts shall be provided outside the buildings for cables, small bore
pipework, dosing and sampling lines which shall be neatly arranged on racks to be visible

GKW - Alliance 2
SPECIFICATIONS
CIVIL WORKS

and easily accessible. Where several services run in parallel they shall normally be
grouped in a common duct with provision for man access, except that chlorine lines shall
not be run in the same duct as cables. Access room shall be provided in all ducts not
immediately accessible through removable covers.

1.2 Site Investigation

1.2.1 General

The Employer has carried out subsoil investigations in the area. The subsoil investigation
report is listed in Appendix 2 to the Specification, Part I - General, and is available for
inspection during the tender period in the offices of the Employer. The Contractor shall take
all such additional steps that he considers necessary to familiarise himself with the surface
and subsurface site conditions and shall obtain all necessary data that he may require to
analyse the water and soil environment at the site and to assure that, for example, the
components of dewatering systems will not perform as intended.

Soil investigation data is furnished for information only and it shall be expressly understood
that the Employer will not be held responsible for any interpretations or conclusions drawn
therefrom by the Contractor. If during construction the soil conditions prove to deviate from
those set out in the soil investigation data so that an effect may or will be experienced on
the work, the Contractor shall inform immediately the Employer.Earthworks and Foundation
Design

1.2.2 Scope

This specification covers the design methods to be used by the Contractor for the design
of earth embankments and foundations.

1.2.3 Calculations

Calculations shall take into account the worst conditions which will occur during
construction and the life of the works, including highest and lowest water levels and water
pressures, seepage, construction methods and their effects on the specified parameters.

Where not otherwise specified, calculations shall be made in accordance with the methods
set out in Terzaghi and Peck 1967, or with any other accredited and recognised design
method approved by the Engineer.

1.2.4 Design Parameters

Design parameters for geotechnical calculations shall be obtained from properties


measured in the site investigation. Where necessary, the Contractor shall extend or check
site investigations made by himself or others to satisfy himself and the Engineer that the
appropriate parameters are being used.

1.2.5 Embankments

Embankments shall be designed to be stable under all conditions to which they may be
subjected, including external vertical loads, lateral loads, water pressure, seepage and
drawdown and seismic effects, all where appropriate.

GKW - Alliance 3
SPECIFICATIONS
CIVIL WORKS

Calculations shall be made, using the specified parameters, of settlements expected as a


result of compression of the fill and of the foundations. Where appropriate, estimates shall
be made of the time to reach particular amounts of settlement.

For water retaining embankments, estimates of seepage and exit gradients shall be made
using the specified parameters. Corrections shall be made for differences between vertical
and horizontal permeability where necessary. Seepage quantities and exit gradients shall
not exceed the specified quantities. Where no exit gradient is specified, it shall not exceed
one eighth; that is to say, the head dissipated over the last section of soil considered
immediately before the seepage emerges from the soil shall not exceed one eighth of the
length of the seepage path over which it is dissipated. If not otherwise specified, the
Contractor shall take such length of seepage path in soil to calculate the exit gradient as
the Engineer shall direct.

1.2.6 Foundations

Foundations which are not piled shall be founded on suitable strata.

The factor of safety against shear failure in the soil beneath the foundations shall be as
specified. Where not otherwise specified, the factor of safety against shear failure shall not
be less than 3. Settlements of foundations shall not exceed values specified. Where not
otherwise specified, the total settlement of any unit shall not exceed 25 mm; differential
settlements shall not cause a gradient between two points originally level of more than 1 in
300.

Buried concrete and metal shall be protected in the manner specified against chemical
attack from corrosive materials in the ground. Where specified, buried concrete shall be
made using sulphate resisting cement of the quality specified, and tanked using asphalt
membranes in the manner specified. Where protection is damaged by construction
operations, it shall, before being covered up, be repaired to the satisfaction of the Engineer.

Water conditions including groundwater conditions shall be checked before placing


foundations. Uplift, shall, where necessary, be allowed for in foundation design.

1.3 Structural Concrete Design

1.3.1 Design Principles and Analyses

Calculations by the Contractor for the design of any structures shall be prefaced by a
statement explaining the principles of design and the type of analysis adopted. The
statement shall also indicate the codes of practice upon which the design is based and into
which category the structure, (or part of a structure) is placed for design purposes, i.e. class
l, 2 or 3 as described later under ‘classification of concrete structures’.

For a superstructure framework, a separate statement shall be included, explaining how


the overall stability is to be achieved and whether reliance is to be made on infill walls,
whether of brick, concrete or other material, to provide stability.

Any computer programs used in structural concrete design shall be fully described, and
details of input and print-out shall be presented in a manner which can be readily
understood. Program manuals and any instructions to program users shall be made
available to the Engineer upon request.

Where any such program cannot be demonstrated by the Contractor to have been fully
checked, or where the Engineer considers it necessary, the Contractor shall run such test

GKW - Alliance 4
SPECIFICATIONS
CIVIL WORKS

examples as the Engineer may choose, in order to verify the completeness and accuracy
of the program.

1.3.2 Reinforced and Pre-stressed Concrete

Plain concrete, reinforced and pre-stressed concrete shall be designed in accordance with
Eurocode 0, Eurocode 1 and Eurocode 2.

The thickness of reinforced concrete walls and slabs shall not be less than that derived
from the following constraints:

(a) Vertical walls and slabs inclined at angles more than 15 degrees above the
horizontal:

 where walls and slabs are ‘external’, i.e. bounding the outside of a water
containing space so that leakage, if it ever occurred, would pass through the
wall to or from foundations, drainage collection systems or places intended to
be dry and accessible, the thickness shall be not less than 350 mm;
 where walls and slabs, reinforced on both faces, are ‘internal’, i.e. dividing the
internal part of a structure so that leakage, if it ever occurred, would pass
through the walls from one water containing space to another water containing
space, the thickness shall not be less than 225 mm.

(b) All walls and slabs:

 The thickness shall nowhere be less than the structural thickness required by
the design procedures for Class 2 and 3 structures specified under ‘Design
methods’.

The Engineer will in any event reserve the right not to approve the design of any structure,
or individual structural member, if in the Engineer's opinion the design is either impractical
or not in keeping with good design practice.

1.3.3 Classification of Concrete Structures

This classification shall apply equally to parts of structures, where more than one case
exists within the overall framework of a particular structure. Structures are divided into
three classes as follows:

Class 1 those not normally subjected to hydrostatic pressure and not intended for the
purpose of storage, retaining, or transmission of liquids.
Examples include: building superstructures, supporting elements to elevated
tanks, foundations, shallow basements.

Class 2 do not function to store liquids, but may be subjected to hydrostatic pressure
and/or external soil pressure.
Examples include: culverts, spillways, water intakes, aqueducts, overflow
channels, dry pumping station basement areas.

Class 3 for storage or retaining of liquids.


Examples include: liquid storage tanks of all types, service reservoirs, filters,
clarifiers, pump sumps.

GKW - Alliance 5
SPECIFICATIONS
CIVIL WORKS

1.3.4 Design Methods

Class 1 structures shall be designed to Eurocode 2, part 1-1 and part 1-2.

Class 2 structures shall be designed to Eurocode 2, part 3. A limiting design crack


width of 0.2 mm shall be used for the serviceability limit state of cracking.

Class 3 structures shall be designed to Eurocode 2, part 3. A limiting design crack


width of 0.1 mm shall be used for the serviceability limit state of cracking.
Class 3 structures including storage tanks, services reservoirs, etc., should be
designed as to reduce any risk of areas of “dead” or “still” water within them.
This should be achieved by incorporating baffle plates, baffle walls, or by the
location of inlet diffusers and outlet pipes to eliminate shortcuts between inlet
and outlet pipes.

Where mass concrete beyond normal structural design needs is introduced for the purpose
of gaining weight to counter the effects of buoyancy, any such additional concrete shall, so
far as possible, be uniformly distributed among the sub-structure.

1.3.5 Design Loadings

Structures shall be designed to withstand the loads exerted by the plant and components,
including dynamic effects where these occur. Due to the tectonic active construction zone,
seismic effects have to be considered in structural calculations.

Other loadings shall be in accordance with Eurocode 0 and Eurocode 1. For ultimate limit
state analysis, water and soil pressures shall be considered as ‘imposed’ loadings.

All loads used in design, including those of plant and components, shall be clearly indicated
in the design calculations.

Wind pressures on structures shall be calculated using a basic wind speed of not less than
35 m/s.

The effects of air temperature and fluctuations in air temperature shall be taken into account
in the designs. Information on climatic condition is given in the ER.

1.3.6 Grades of Concrete

These shall generally be in accordance with Eurocode 2, part 3.

1.3.7 Reinforcement

Main reinforcement shall generally be high yield deformed (Type 2) steel bars. Links to
beams and columns shall be plain round mild steel bars.

The characteristic strengths be in accordance with Eurocode 2, part 3.

GKW - Alliance 6
SPECIFICATIONS
CIVIL WORKS

1.3.8 Cover

Concrete coverage has to follow strictly the requirements of Eurocode 2.

Where exposed aggregate finishes are used, the reinforcement covers specified above
shall be increased by 10 mm for concrete with a maximum aggregate size of 20 mm, and
15 mm for concrete with a maximum aggregate size of 40 mm. It shall be made clear on
the detailed structural drawings that the specified covers to exposed aggregate surfaces
are related to the original as-cast surfaces.

Where ribbed finishes are used, the reinforcement covers shall be increased by the
dimensions of the rib protection and the detailed structural drawings shall indicate that the
specified covers are to be measured from the outermost surface of the ribs.

1.3.9 Bond and Lap Length

The minimum ‘anchorage bond length’ and ‘lap length’ has to follow strictly the
requirements of Eurocode 2.

In no case shall the lap length be less than 25 times the bar diameter plus 150 mm for bars
in tension and 20 times the bar diameter plus 150 mm for bars in compression. Where
lapped bars are of two different diameters, the lap length shall be calculated using the
diameter of the smaller bar.

1.3.10 Water Stops and Sealants

Expansion and contraction joints in structures shall incorporate water stops or surface
sealers, or both, as specified in ‘Joints in concrete’.

In expansion joints and complete contraction joints, internal waterstops shall be of a centre
bulb type. Surface waterstops shall be of an expansion type.

In partial contraction joints, internal waterstops shall be of a ‘dumbbell’ type.

1.3.11 Joints in Concrete

Construction joints are introduced for convenience in construction. Reinforcement shall be


carried through the joints and special measures taken to achieve full continuity in the
concrete in accordance with the requirements of the specification for Concrete. The
Contractor’s proposed layout of construction joints shall also be in accordance with the
requirements of the specification for Concrete. In addition, the joint positions shall, wherever
possible, be located to avoid zones of high stress.

Expansion joints are permanent joints designed to prevent continuity in the concrete and
are primarily intended to control the effects of early thermal contraction and shrinkage in
the concrete.

Expansion joints shall be of two types:

(a) Complete Expansion Joints

In this type, concrete and reinforcement are completely discontinuous. Concrete


faces shall be painted with two coats of bituminous paint, to prevent continuity.

GKW - Alliance 7
SPECIFICATIONS
CIVIL WORKS

In Classes 2 and 3 structures, the joint shall be sealed on one or both faces and a
water stop provided.

A seal shall always be provided on faces in contact with water and on the dry side for
aesthetical reasons.

Slabs and walls in contact with soil or where protected from contact with soil by a
membrane tanking shall incorporate either a surface type waterstop or a centrally
placed waterstop. Where shear forces may occur across a joint, a suitable joggle
shall be provided to transfer the shear.

(b) Partial Expansion Joints

This type is similar to a complete contraction joint, except that the reinforcement is
stopped-off at each side of the joint such that only 50% of the reinforcement crosses
the joint. Transfer of shear forces across this type of joint will not be permitted.

Expansion joints are permanent joints provided with an initial gap between adjoining
parts of a structure to accommodate expansion and contraction.

A compressible joint filler shall be used to form the joint. Exposed edges of the filler
shall be protected by a sealer.

In Classes 2 and 3 structures, a waterstop shall be provided and, at all faces in


contact with water, a sealer shall be provided.

Slabs and walls in contact with soil, or protected from contact with soil by membrane
tanking, shall incorporate either a surface expansion type waterstop on the soil side
or a centrally placed dumbell type waterstop.

1.3.12 Surface Finishes

Finishes shall generally be provided as described below:

 Formed Surfaces

Class F.1:
Surfaces against which further concrete is to be placed and surfaces to be
permanently concealed by rendering, plastering, etc.

Class F.2:
All surfaces permanently exposed to view, except where Class F.3 is required.
Surfaces either permanently in contact with stored, retained or flowing liquids.
Surfaces against which a membrane tanking is to be applied.

Class F.3, ‘ribbed’ and ‘exposed aggregate’ finishes:


Surfaces prominently exposed to public view where good appearance is of special
importance. Class F3 is also known as ‘fairfaced’ finish.

 Un-formed Surfaces

Class U.1:

GKW - Alliance 8
SPECIFICATIONS
CIVIL WORKS

Surfaces of foundations, slabs and other structural members to be subsequently


covered by further stages of concrete construction, bonded concrete toppings
cement/sand screeds.

Class U.2:
All surfaces permanently exposed to view, except where Class U3 finish is required.
Surfaces including those of blinding concrete, against which a membrane tanking is
to be applied.

Class U.3:
For hard smooth surfaces to slabs, walls, parapets and other structural members,
where exposed to weathering.

1.3.13 Drawings

Drawings shall be prepared such that the details are presented in a clear, concise and un-
ambiguous manner. Written descriptions shall be as brief as possible, consistent with
completeness. Lettering shall be legible and clear, but not too small.

Special requirements associated with the design, e.g. details of chambers, sequence of
construction, position and type of joints and shall be described on the detailed structural
drawings.

Special consideration shall be given to the spacing of bars, to ensure that the concrete can
be placed and consolidated without difficulty.

Wherever possible, distribution (secondary) reinforcement in walls and slabs shall have
staggered laps.

The following scales shall be used:

 General arrangement drawings 1 to 50


 Walls and slabs* - plans and elevations 1 to 50 or 1 to 20
 Walls and slabs - sections 1 to 20
 Beams and columns - elevations 1 to 20
 Beams and columns - sections 1 to 20 or 1 to 10

* Where concrete profiles and/or reinforcement details are complex and liable to result in a drawing which
is difficult to read, the larger scale shall be adopted.

1.3.14 Detailing shall be as follows

Lines

 Main reinforcement - to be 0.6 mm thick


 Concrete outline and links, etc. - to be 0.4 mm thick
 Dimension lines, etc. - to be 0.2 mm thick

Note: When detailing reinforcement all bars shall be indicated by full lines. Where, for
clarity, bars which are detailed elsewhere are shown extending into the part of
the structure being details (e.g. from an adjacent span of a beam, or from a
support), they shall be indicated by broken lines.

GKW - Alliance 9
SPECIFICATIONS
CIVIL WORKS

Reinforcing Bar Notation

The following method, specifying bending dimensions and scheduling of reinforcement for
concrete, shall be used.

(a) Elevations of walls and plans of slabs (example)

20 T 12 - 63 - 150 NF, where:


20 indicates number of bars
T indicates type of steel - see note (c) below
12 indicates diameter of bars in mm
63 indicates the bar mark
150 indicates spacing centre to centre in bars in mm
NF indicates location if disposition of bars

Use one of the following abbreviations:


EW each way
EF each face
FF far face
NF near face
B bottom
T top

(b) Main reinforcement in beam and column evaluations (example)

4 T 25 - 39 where:
4 indicates number of bars
T indicates type of steel - see (c) below
25 indicates diameter of bars in mm
39 indicates the bar mark

(c) Type of Steel

R = round mild steel bars in the metric round range of areas


T = high yield bars having a high bond strength, in the metric round range of areas

Adequate information shall be given on the plan, elevations or sections for the
bending dimensions of all reinforcing bars.

All reinforcing bars shall be positioned by dimension to concrete faces.

Basic structural dimensions shall be specified on the drawings, e.g. slab depth, wall
thickness, beam length, width and depth, etc.

Slabs

Slab plans shall be drawn as viewed from above the slab and shall show any grid reference
and the beam and wall numbers.

GKW - Alliance 10
SPECIFICATIONS
CIVIL WORKS

A ‘run’ of bar reinforcement on plan shall have the limits of the run shown by short lines and
one intermediate bar only shown in full. The short lines at the limits shall be joined by a
thin collecting line.

Provided congestion does result, the description of bar reinforcement on the plan shall be
written on the collecting line; otherwise the description shall be written on an extension of
the collecting line.

Beams

Elevations shall give the full bar notation of main reinforcing bars and link reinforcement.

Cross sections shall show the individual position of each reinforcing bar, its bar mark, the
concrete cover and the shape of the link reinforcement.

Slab reinforcement and reinforcement in adjacent beams shall only be shown on the beam
details for their relationship with the reinforcing bars in the subject beam, and when shown
shall be indicated by broken lines.

1.4 Structural Steel Design

1.4.1 General

Calculations by the Contractor for the design of any structure shall be prefaced by a
statement explaining the principles of design and the type of analysis adopted. The
statement shall also indicate the codes of practice and specifications upon which the design
is based.

Any computer programs used in the design process shall be fully described, and details of
input and print-out shall be presented in an easily understandable form. Program manuals
and any instructions to program users shall be available to the Engineer upon request.
Where any such program cannot be demonstrated to have been fully checked or where the
Engineer considers it necessary, the Contractor shall run such test examples as the
Engineer may choose in order to verify the completeness and accuracy of the program.

1.4.2 General Principles

Structures may be designed either by the working stress approach, using unfactored loads
against a working stress (generally limited to 0.7  yield stress) as specified in the relevant
standard, or by the limit state method. Structures designed to the limit state methods shall
be designed by considering the limit state at which they would become unfit for the use for
which they are considered and applying appropriate safety factors to provide an adequate
degree of safety and serviceability.

The overall design concept shall give due regard to the fact that the structure as a whole
will be required to behave as one three dimensional entity. The layout of its constituent
parts, including the steel members, the other structural elements, the foundations and the
connections between each component, shall be such as to produce a strong and stable
structure.

The structures shall be checked for the effects of all possible vertical and horizontal loads,
acting both in conjunction and separately as appropriate, using factored loads when
checking strength and stability to a limit state analysis and unfactored loads when checking
deflections or strength and stability using a working stress approach.

GKW - Alliance 11
SPECIFICATIONS
CIVIL WORKS

The structure shall be designed to be capable of accepting without overstress a reasonable


amount of extra loading due to any cause including extra services, heavier cladding, or
other appurtenances that may reasonably be added during the life of the structure.

Structures shall be designed such that undue reliance is not placed on ‘key’ elements (a
key element is one whose removal tends to prejudice the ability of the whole structure to
survive). The removal or damage of such elements shall not entail collapse of more than
a limited part of the structure. Structures will not be considered to be adequate if, in the
event of abnormal loading, accident or misuse, the damage to the structure is out of
proportion to the magnitude of the event.

The design shall take account of the need for stability of both the framework and the
individual elements at all stages of erection. Where temporary bracing is required it shall
be checked for the effects of all loadings that may arise during erection including those due
to erection equipment and its operation. Such bracing shall be clearly indicated on the
drawings together with clear instructions as to the appropriate stage of removal.

The design of crane beams shall take due account of all factors relevant to the provision of
effective support to the crane under all conditions of loading including:

(a) Underslung cranes and monorail runway beams:

 combined flange stresses resulting from overall bending and local flange bending due
to wheel loads causing transverse stresses;
 lateral instability;
 torsional restraint;
 deflection limitations;
 joints, particularly local force concentrations due to loads passing across joints.

(b) Overhead, overslung cranes and gantry girders;

 lateral loading combined with vertical loads related to seismic effects;


 as above but related to coincident lifting, slewing, transversing actions of the
crane.
All cranes supporting structures shall be designed for the greater of:
- the design loadings, or
- the provided capacity of the crane.

1.4.3 Design Loadings

Structures shall be designed to withstand the loads exerted by the plant and components
including for dynamic effects where these occur.

All loads used in the design, including those of plant and components shall be clearly
indicated in the design calculations.

Wind pressures on structures, plant and cladding shall be calculated in accordance with
the applicable standard. A basic wind speed of not less than 40 m/s shall be used. The
Contractor shall submit global and local wind pressure coefficients to the Engineer for his
approval before commencing the actual design of clad structures.

GKW - Alliance 12
SPECIFICATIONS
CIVIL WORKS

The Contractor shall allow for temperature variations between components of structures as
well as in the structure itself. Due account shall be taken of the effects of direct sunlight on
structures which could cause high temperatures in exposed steelwork.

Information on climatic conditions is given in Specification - Part 1: General.

Crane loads shall be generally in accordance with the applicable standard.

1.4.4 Deflection Limits

When checking the deflections of a structure, the most adverse realistic combination and
arrangement of unfactored loads shall be assumed.

The deflection of a building or part of a building shall be limited so as not to impair the
strength or efficiency of the building or of its contents, nor be unsightly or cause damage to
the finish or inconvenience to the occupants.

Deflection of members listed in the table below shall not exceed the tabulated limits, unless
the Contractor can demonstrate to the Engineer's satisfaction that greater values would not
be detrimental to the performance of the structure.

Deflection Limit

A. Beams Deflection due to imposed loads

Cantilevers Length /180

Lintel beams supporting brickwork Span /360

Beams carrying plaster finish Span /360

Roof beams not carrying plaster finish Span /200

Purlins and sheeting rails To suit the characteristics of the


sheeting, roofing and cei1ing
materials

B. Columns Horizontal Deflection

Each storey, top of column, brick or plaster Height /300


cladding

Single storey portal framed structures, with Height /300


metal cladding

C. Crane girder Deflection at point of maximum span


moment

Vertical deflection due to static wheel loads Span /700

GKW - Alliance 13
SPECIFICATIONS
CIVIL WORKS

Horizontal deflection (calculated on Span /500


properties of top or bottom flange along as
applicable)

The relative lateral deflection of adjacent frames (including the end frames) of sheeting clad
structures shall be limited generally to frame centres/250 unless greater values can be
shown to have no detrimental effect on the structural performance of the sheeting.

1.5 Protective Coating Design

1.5.1 Scope

This section specifies design methods for the protective coating to be applied to structural
steel, metalwork and ironwork as corrosion protection systems. The systems designed as
specified here shall be applied as specified under Protective Coatings. Protective coatings
specified elsewhere for particular works such as pipes and cladding shall firstly be designed
in accordance with particular requirements specified elsewhere and secondly in
accordance with any requirements herein which are not over-ridden elsewhere.

1.5.2 Submissions

The Contractor shall design each protective coating system and shall submit details of each
system to the Engineer for approval. Submissions shall where possible be in the format of
which examples are given at the end of this section with such additional information and
samples as the Contractor may provide or the Engineer may require to enable the system
to be assessed.

1.5.3 Design Generally

Protective coatings shall be designed to have a long life, generally of at least 15 years to
first maintenance for metal surfaces and tank linings and 5 years of first maintenance for
building works. Protection systems shall be chosen to be easily maintained in the future
and to allow non-specialist on-site re-coating where necessary using single part paints.

1.5.4 Systems

Protective coating systems shall generally fall into one of the following basic systems:

 galvanising;
 galvanising plus painting;
 multi-coat painting;
 bitumen enamel;
 others as proposed by the Contractor and approved by the Engineer.

The Contractor shall submit to the Engineer details of his proposals for the corrosion
protection of each of the items requiring such protection, which will generally fall into the
above categories as follows:

 trash screens, flooring, ladders, access covers and frames, step irons and other
components which are inaccessible but subject to abrasion/damage;

GKW - Alliance 14
SPECIFICATIONS
CIVIL WORKS

 structural steelwork (including crane beams, monorails, crane structures and


chassis), bulkhead gates, stop-logs, grappling beams, steel tanks and other large
items readily accessible for maintenance;
 valves and other corrosion-susceptible items which may be buried and are not
covered by the provisions of other specifications;
 other components not covered by the above for which the Contractor may propose a
system which he considers to be more suitable for the duty.

1.6 Brickwork and Blockwork Design

1.6.1 Principles and Analysis

Calculations by the Contractor for the design of any brickwork and blockwork shall be
prefaced by a statement explaining the principles of design and the type of analysis
adopted. The statement shall also indicate the codes of practice (and other relevant
publications) upon which the design is based.

For walls forming infill panels between superstructure framework, a separate statement
shall be included, indicating whether reliance upon these panels is to be made for the
overall stability of any building.

All loads and structural wall sizes, including positions and sizes of any chases and
openings, shall be clearly indicated in the design calculations.

Any computer programme used in the brickwork and blockwork design shall be fully
described and details of input and printout shall be presented in a manner which can be
readily understood. Program manuals and any instructions to program users shall be made
available to the Engineer upon request. Where any such program cannot be demonstrated
by the Contractor to have been fully checked or where the Engineer considers it necessary,
the Contractor shall run such text examples as the Engineer may choose, in order to verify
the completeness and accuracy of the program.

The Engineer will in any event reserve the right not to approve the design of any wall, if in
the Engineer's opinion the design is either impractical or not in keeping with good design
practice.

1.6.2 Design

The limit state‚ and elastic methods shall not be used together in the same design.

The design of reinforced brickwork and blockwork shall be in accordance with the applicable
standard, using elastic methods.

As a minimum requirement, all walls shall also comply with the applicable standard.

The layout of walls shall, if designed to interact with the superstructure framework, be such
as to ensure a robust and stable design. Walls shall be designed to support loads caused
by normal function, allowing for corrosive environments, but in the event of misuse or
accident they must not collapse catastrophically or suffer damage disproportionate to the
original cause. This requirement is also applicable during construction of any element of
the works.

GKW - Alliance 15
SPECIFICATIONS
CIVIL WORKS

In addition, due to the nature of a particular occupancy or use of a building (e.g. chemical
house), consideration shall be given to the effects of a particular hazard and to ensure that,
in the event of an accident, there is an acceptable probability of the walls remaining after
that event, even if in a damaged condition. The design of the walls must include for
overturning, buckling and twisting caused by elastic or plastic instability, having due regard
to the effects of sway when appropriate.

When damp-proof courses in vertically spanning walls are required to transmit


compression, they must also combine adequate shear resistance with negligible
deformation under horizontal and vertical loads. Consideration shall be given to the use of
dpc bricks, slates and suitable metals.

Where walls act as infill panels between a structural framework, they shall, wherever
possible, be supported along at least three sides by one of the following methods:

 angle and/or channel sections fixed (not shot fired) or cast into the main structure;
 dovetail-ended wall ties inserted into dovetail slots cast into the structural framework,
where the latter is of concrete construction.

All fixings in (a) and (b) above shall be of stainless steel.

The design of the junction between infill wall panels and the structural frame, including the
fixings, shall take account of thermal movement, shrinkage and any other movements
associated with the walls and the structural frame. In addition, where an infill wall is used
to provide stability to a structural framework, the details including fixings at the junction of
the wall and the framework shall be sufficient to ensure that the design requirements
regarding stability are fully met.

Where an infill wall panel is designed to span vertically, e.g. as external wall cladding,
special consideration shall be given to the design of the fixings to the top horizontal edge,
where it joins the structure.

Wired butterfly and double triangle type wall ties will not be permitted in any wall. Wall ties
shall be stainless steel strip, but of a twist type for the leaves of cavity walls.

1.6.3 Loadings

Wind pressures on walls shall be calculated according to the applicable standard. “Wind
loads”, using a basic wind speed of not less than 40 m/s.

Other loadings shall be in accordance with the applicable standard. Where applicable, walls
shall also be designed to withstand any loads exerted, including plant and components,
dynamic effects, sway forces, having due regard to effects caused by air temperatures,
creep, moisture and shrinkage.

1.6.4 Joints

Without affecting the aesthetics and structural stability of any building (or part of building),
permanent joints shall be provided in brickwork and blockwork to allow for expansion and
contraction caused by temperature changes, shrinkage and moisture movement.

Unless there are specific requirements (e.g. stability of superstructure framework),


compressible joint fillers shall be used to form the joints, together with, protective sealers.

GKW - Alliance 16
SPECIFICATIONS
CIVIL WORKS

1.6.5 Drawings

Where applicable, the production of structural drawings shall be in accordance with the
requirements for Concrete.

Particular attention shall be made regarding the correct positioning and sizes of any chases
and openings for services. The methods and positions for supporting walls at their edges
shall be clearly indicated.

1.7 Earthworks

1.7.1 General

This Section contains requirements which, where relevant to this Contract, shall apply to
site clearance, general excavation, trench excavation, embankments, topsoiling and
landscaping.

1.7.2 Definitions

The following terms shall have the meanings hereby assigned to them:

"Topsoil" any surface material capable of supporting vegetation and


suitable for use in soiling areas to be grassed or cultivated.

"Rock" naturally occurring material which in the opinion of the Engineer


would normally have to be loosened either by blasting or by the
use of pneumatic tools (other than clay spades) or by other rock
quarrying methods or, if excavated by hand, by the use of
wedges and sledge hammers. An isolated solid boulder or
detached piece of rock shall qualify as Rock only if it exceeds
0.32 m3 in volume. For the purposes of determining the
boundary between rippable material and “Rock”, the Engineer
will alternatively require the Contractor to demonstrate that the
material below the boundary cannot be loosened and removed
by an excavator applying 0.11 kilowatts of flywheel power for
each mm of tined bucket width; the tined bucket width on the
machine being used shall be not less than 1.37 m measured
between the outsides of the outer tines.

"Bulk Excavation" excavation in open cut (excluding Trench Excavation) down to


levels specified on the Drawings or otherwise as being the
general levels after completion of excavation other than
Incidental Excavation.

"Trench Excavation" excavation, to levels and limits specified on the Drawings or


otherwise, of trenches into which pipes and the like are to be
laid.

"Incidental Excavation" excavation (generally in small quantities) below or outside the


limits of Bulk Excavation and Trench Excavation, but excluding
Excess Excavation.

"Excess Excavation" excavation outside the limits specified for Bulk, Trench or
Incidental Excavation.

GKW - Alliance 17
SPECIFICATIONS
CIVIL WORKS

1.7.3 Submissions by the Contractor

Submissions, which the Contractor is required to make in relation to earthworks shall be in


accordance with the ER.

1.7.3.1 Drawings, Survey Notes, etc.

 Contractor’s record drawings of the ground level survey prior to the start of any
earthwork.
 Information obtained from trial holes ordered by the Engineer.
 Contractor’s record drawings of any other level surveys taken for the purposes of
measurement of quantities of excavation or filling, e.g. Rock level surveys.
(Survey record drawings as specified above shall be submitted within 7 days of the
completion of the survey work recorded on them.)
 Survey notes on depths of Trench Excavation.
 Survey notes on Rock levels.
 Copies of designs for Temporary Works for supported and unsupported excavations.

1.7.3.2 Certificates

 Laboratory tests
 Field tests

1.7.3.3 Details of Proposed Methods

 Proposed methods of excavation, transport of materials, filling and compaction.


 Proposed source of free-draining fill and methods of selective excavation or
processing.
 Programme for quality control of earthworks and proposals for the use of off-Site
laboratories.
 Proposed methods of blasting rock, safety measures, hole patterns, blasting patterns
charges, permits, licences.

1.7.3.4 Samples

Materials proposed for filling and for geotextiles, where specified or where specifically
required by the Engineer.

1.7.4 Materials

1.7.4.1 Fill Material - General

Excavated material (including material excavated from borrow pits) selected by the
Contractor for use as backfilling to excavations, as filling around structures or as filling for
embankments shall be free from clods and lumps and shall be subject to the approval of
the Engineer.

GKW - Alliance 18
SPECIFICATIONS
CIVIL WORKS

Should the material selected as filling, while acceptable at the time of selection,
subsequently become unacceptable to the Engineer for any reason including exposure to
weather conditions, flooding, contamination by other materials or segregation during the
progress of the Works, the Contractor shall at no extra cost to the Employer remove such
damaged, softened or segregated material and replace it with fresh approved material.

1.7.4.2 Free-draining Fill

Free-draining fill material shall be formed of hard durable particles and shall be free from
clay, silt and organic matter and shall comply with any particular requirements specified
hereafter.

Material for free-draining fill shall be provided by the Contractor from an approved source.
The Contractor shall submit full details of the proposed source, certified test results and
samples for the approval of the Engineer. The Contractor may use material emanating
from excavations having first processed it so that it complies with the specified requirements
for free-draining materials fill.

1.7.5 Workmanship

1.7.5.1 Levels to be Recorded

Before the surface of any part of the Site is disturbed or the Works thereon are begun the
Contractor shall take and record levels and dimensions of any such part. The Contractor
shall also take and record such other levels and dimensions as are necessary during the
progress of excavation to allow accurate measurement of the different categories of
excavation.

All levels and dimensions shall be taken in the presence of the Engineer and recorded in
the manner specified or as agreed with the Engineer, and such levels when agreed with
the Engineer shall form the basis for measurement.

1.7.5.2 Notification of Rock

Any material in the excavations which the Contractor considers may be classified as rock
as defined herein shall be notified to the Engineer before excavation of the material is
begun. The quantities of rock or material alleged to be rock excavated from within the
nominal limits of excavation shall be recorded and the agreed record shall be signed by the
Engineer and the Contractor each day or at such shorter intervals as the Engineer may
require. Only such material so notified and agreed by the Engineer as rock shall qualify for
additional payment as rock. Overbreak (that is excavation in rock outside the nominal limits
of excavation) shall be kept to a minimum and shall be held to be excess excavation.

1.7.5.3 Explosives and Blasting

The Engineer shall have power to regulate, restrict or prohibit blasting if in his opinion it is
necessary to do so for the safety of persons or property or to safeguard the Works. No
blasting shall be carried out in any part of the Works without the permission in writing of the
Engineer. Such permission shall not absolve the Contractor from any of his obligations or
liabilities under the Contract. The Contractor shall take all necessary precautions including
the use of blasting nets to avoid damage, loss or injury to persons and to public or private
property.

GKW - Alliance 19
SPECIFICATIONS
CIVIL WORKS

Any work involved in the use of explosives, including storage and handling shall be carried
out in accordance with the applicable standard.

The Contractor shall obtain the necessary licenses for the storage, transport and handling
of explosives and shall provide a store or stores suitable for explosives in accordance with
local regulations.

The Contractor shall keep the Engineer fully informed at all times when blasting is proposed
to be carried out and of any details the Engineer may require concerning strength of charges
and their positions.

1.7.5.4 Excess Excavation (Backfilling)

Excess excavation may normally be backfilled with material emanating therefrom, but
where the Engineer has ordered such material to be removed from site as being unsuitable
the Contractor shall make good the excess excavation with such kind of fill material or in
such class of concrete as may be reasonably required by the Engineer having regard to the
circumstances.

1.7.5.5 Trial Holes

The Engineer may direct that trial holes shall be excavated in advance of other excavation
to such dimensions and depths as he shall order to obtain information required by him.

Any further trial holes required by the Contractor to determine the position of underground
services, sub-soil drains or for any other reason shall be excavated and reinstated at no
extra cost to the Employer.

The Contractor shall arrange for the refilling and reinstatement of trial holes to be carried
out immediately the required information is obtained. The reinstatement of the surfaces of
trial holes shall be carried out to the satisfaction of the Engineer.

1.7.5.6 Excavations - Support and Working Space

The Contractor shall provide effective support for the sides and ends of all excavations to
prevent any fall or run from any portion of the ground outside the excavation and to prevent
settlement or damage to structures adjacent to the excavation.

If, for any reason, any portion of the bottoms sides or ends of any excavations shall give
way the Contractor shall at no extra cost to the Employer take all necessary remedial
measures including the excavation and removal of all the ground thereby disturbed both
within and without the nominal limits of excavation and such extra excavations shall be held
to be Excess Excavation.

Where the Contractor proposes to carry out excavations with sloping faces and without
shoring, excavated faces shall be to stable slopes and heights and the resulting extra
excavation shall be held to be excess excavation. Full details of the Contractor’s proposals
shall be submitted to the Engineer for approval.

The Contractor shall be deemed to have made his own allowance for any working space or
support required, and any excavation outside the specified or nominal payment limits which
has not been ordered by the Engineer, whether it be excavated to suit the Contractor’s
method of working or unavoidable overbreak or due to his carelessness or error, shall be
held to be excess excavation.

GKW - Alliance 20
SPECIFICATIONS
CIVIL WORKS

1.7.5.7 Fossils, etc. found in Excavations

No requirement of the Specification regarding the disposal of material arising from site
clearance or excavation shall override any provision in the Conditions of Contract as to the
discovery, or ownership, of fossils, coins, articles of value or antiquity, or anything of
geological or archaeological interest found on the site.

1.7.5.8 Inspection by the Engineer

When the specified levels or limits of any excavation are reached, the Engineer will inspect
the ground exposed and if he considers that any part of the ground is by its nature
unsuitable he may direct the Contractor to excavate further. Such further excavation shall
be refilled to the specified levels or limits with concrete, selected excavated material or
selected imported material as directed but shall not be held to be excess excavation.

Should the material forming the bottom or side of any excavation, while acceptable to the
Engineer at the time of inspection, subsequently become unacceptable due to exposure to
weather conditions or due to flooding or have become puddled, soft or loose during the
progress of the Works, the Contractor shall remove such damaged, softened or loosened
material and excavate further to a sound surface. Such further excavation shall be held to
be excess excavation and material emanating therefrom shall be removed from the Site.

1.7.5.9 Site Clearance

All areas of the site earmarked for clearance or from which material is to be excavated or
upon which filling is to be deposited shall be cleared to the extent required by the Engineer
of all buildings, walls, gates, fences and other structures and obstructions and of all bushes,
hedges, trees, stumps, roots and other vegetation except for trees marked for preservation.
Material so cleared shall so far as suitable be reserved and stacked for the Employer’s use
but shall otherwise be burnt to ash or disposed of off the site as directed by the Engineer.

1.7.5.10 Trees

Where directed by the Engineer, trees shall be uprooted or cut down as near to ground
level as possible. Branches and foliage shall be removed and burnt to ash or disposed of
off the Site. Useful timber shall be deemed to be the property of the Employer and shall be
cut into suitable lengths and transported a distance not exceeding 5 km to a location
provided by the Employer where it shall be off-loaded and stacked.

1.7.5.11 Stumps

Stumps and roots whether existing or remaining after tree felling shall, where directed by
the Engineer, be grubbed out and disposed of off the Site. The resulting hole shall be filled
with approved material deposited and compacted in layers to the same dry density as the
adjoining soil.

GKW - Alliance 21
SPECIFICATIONS
CIVIL WORKS

1.7.5.12 Excavation Generally

For the purposes of this Sub-section the term ‘Excavation’ shall include excavation, whether
Bulk or Incidental, required for structures and roadworks and from borrow areas. It shall
not include excavation for pipe trenches and the like except for miscellaneous isolated
lengths of trenches beneath or adjacent to structures, such trenches being deemed to be
Incidental excavation.

The ground shall be excavated by such methods and to such dimensions and depths as
shall allow for the proper construction of the works.

1.7.5.13 Stripping Top Surface

Where ordered by the Engineer the top surface including topsoil if any shall be stripped, to
such depths and over such areas as he may direct, as a separate operation prior to any
further excavation which may be required.

1.7.5.14 Trimming Excavations

When excavating to specified levels for the foundation of any structure or to specified limits
for the face of any structures required to abut undisturbed ground the Contractor shall not
finally complete the excavation until immediately before commencing the constructional
work, except where the Engineer shall permit otherwise.

Before commencement of any constructional work all shattered and loose material shall be
removed from the excavations so as to ensure that the work rests on a sound and clean
foundation or where appropriate abuts against undisturbed ground.

1.7.5.15 Disposition of Excavated Material within the Site

Subject to any specific requirements of the Contract, the disposition of excavated material
within the Site shall be at the Contractor’s discretion but shall be so arranged as to suit the
overall requirements for the construction of the Works.

The Contractor shall ensure that no excavated material which is suitable for and is required
for reuse in the Works is disposed of outside the Site.

1.7.5.16 Spoil Tips on the Site

Only material which has received the approval of the Engineer shall be placed in the various
spoil tips. No tree trunks stumps roots branches or rubbish of any kind shall be placed in
spoil tips.

Temporary spoil tips may be used to store excavated material as required and shall be
arranged by the Contractor subject to the Engineer’s approval having regard to any
particular requirements of the Contract. Temporary spoil tips shall be so shaped as to
maintain stability and good drainage at all times. Where directed by the Engineer, topsoil
stripped from the site shall be stored in separate spoil tips for use in reinstatement or
landscaping.

The limits of permanent spoil tips shall be as may be ordered by the Engineer for
landscaping purposes. Permanent spoil tips shall be finished to shapes as required or as
directed by the Engineer.

GKW - Alliance 22
SPECIFICATIONS
CIVIL WORKS

1.7.5.17 Disposal of Excavated Material off the Site

Excavated material which is not required for or is unsuitable for re-use in the Works shall
be disposed of off the Site as directed either to locations to be found by the Contractor
(Contractor’s tip) or to locations designated by the Engineer (Employer’s tip).

Material ordered to be disposed-off to Contractor’s tip shall, as between the Employer and
the Contractor, be deemed to be the property of the Contractor and he shall be entirely
responsible for its removal from the Site and ultimate disposal.

Material ordered to be disposed-off to Employer's tip shall remain the property of the
Employer and shall be transported off the Site and deposited at places designated by the
Engineer. Material so deposited shall be shaped up or spread and levelled as directed by
the Engineer. Any necessary work to provide access to Employer’s tips or other preliminary
work in connection therewith shall be valued as additional work.

1.7.5.18 Field Drains

Should any existing sub-soil or field drains be uncovered during excavation the Contractor
shall either carefully replace them when backfilling or, if this is impracticable, shall divert
them to new drains or ditches or otherwise relay them as the Engineer may direct and all
work in this connection shall be valued as additional work.

1.7.5.19 Backfilling of Excavations

For purposes of this Sub-section the term ‘backfilling’ means replacing material into any
part of the excavations which the Contractor has needed for working space and which is
therefore deemed to be excess excavation. Backfilling shall be carried out using material
emanating from the excavations and complying with specified requirements. The backfilling
shall be properly compacted and where necessary the Contractor shall adjust the moisture
content of the material either by drying out or by adding water. After such drying out or
adding of water the material shall be thoroughly mixed until the moisture content is uniform.

1.7.5.20 Filling to Structures

Filling to structures means filling around or over completed structures (whether within
excavations or not) using such material as may be specified therefor. It does NOT include
‘backfilling’ as described in the preceding Clause.

Where the Contract requires the placing of different types of fill material in separate layers
or wedges the Contractor shall carry out the work so as to avoid mixing the different types
of material. Should there be any mixing of materials, such mixed materials shall be
removed from the Site and replaced with separate materials, all at no extra cost to the
Employer.

GKW - Alliance 23
SPECIFICATIONS
CIVIL WORKS

1.7.5.21 Backfilling etc. not to Endanger Structures

The Contractor shall arrange the timing and rate of placing of backfilling or of filling to
structures in such a way that no part of the Works is overstressed weakened, damaged or
endangered. The layers of material shall be so placed as to maintain adequate drainage
and to prevent accumulation of water. In particular, the placing of material around the walls
of basements reservoirs and tanks shall commence only after the walls and floor have been
completed and have attained their full specified strength. Material behind walls fixed at the
top to the roof shall not be placed until the roof has been completed and, if made of
concrete, has attained its full specified strength and had the temporary supports removed.
The material shall be placed uniformly around the walls of structures in such a manner as
to avoid eccentric or differential loads.

1.7.5.22 Trench Excavation Generally

Trench excavation means excavation of trenches into which pipes are to be laid and the
term ‘pipes’ shall mean pipes of all kinds and for whatever purpose, and shall also include
cables except where the context clearly renders this inapplicable.

The line and level of trenches shall be as specified or as may be directed by the Engineer.
Before commencing trench excavation, the route of the trench shall be set out accurately
and the natural ground levels shall be recorded and agreed with the Engineer. Strong sight
rails shall then be fixed and maintained at each change of gradient and at as many
intermediate points as may be necessary. On these rails shall be marked the centre line
and the level to which the excavation is to be carried out, such rails being not more than
40 m apart.

Trench excavation shall be carried out by such methods and to such lines dimensions and
depths as shall allow for the proper construction of the works.

Any rock in trench excavation shall be so excavated that the clearance between the pipe
when laid and the rock sides and bottom of the trench is kept to the minimum limits
necessary to provide for the specified thickness of bedding and surround to the pipe. Any
excavation outside these limits whether for working space or due to overbreak shall be held
to be excess excavation.

The sides of trench excavation shall be vertical unless the Engineer permits otherwise.

Any widening or deepening of trench excavations necessary to accommodate curves, joints


or bends in the pipe or to provide extra working space for the construction thereof shall be
held to be excess excavation.

No length of trench excavation shall be started until the pipes to be laid in that length are
available on the site.

1.7.5.23 Trench Excavation in Roads and Tracks

All trench excavation and other work carried out within the limits of any road shall be
completed as rapidly as possible and with every care for the safety of the public.

Unless the Contractor has made specific arrangements with the appropriate authority or
owner, the roads shall be kept open for normal traffic by the provision of suitable temporary
works. In roads where the width is sufficient to carry at least two lanes of traffic, not more
than half the width of the carriage way shall be obstructed at one time.

GKW - Alliance 24
SPECIFICATIONS
CIVIL WORKS

The Contractor shall take special precautions, which shall include the continuous support
of the side of the excavation, from the time of when excavation is begun until the refilling of
the trench is completed, to ensure that is there is no disturbance of the adjacent road or
road foundation.

Road drainage shall be maintained in operation without obstruction during the progress of
the work.

Any places on which material has temporarily been deposited shall on completion of refilling
be restored to their original condition.

1.7.5.24 Trench Excavation in Open Land

The term ‘open land’ includes fields, wasteland, bush, roadside verges, and all other like
land whether publicly or privately owned and whether or not open to the public. No length
of trench excavation located in open land shall be commenced until suitable temporary
fencing has been erected around that length unless the Engineer permits otherwise.
Temporary fencing shall not be removed without permission, which will not normally be
given until the trench excavation has been refilled and reinstated and, where relevant, until
sown grass has become established.

The Contractor shall have regard to the safety of livestock on open land, or which may be
introduced thereon, and shall ensure that all excavations, access routes and steep or loose
slopes arising from the Contractor’s operations are adequately fenced and protected.

After the erection of temporary fencing the Contractor shall first remove the top surface,
including Topsoil if any, to such depth and over such areas as may be necessary to provide
sufficient material to ensure adequate surface reinstatement of the working areas occupied
by the Contractor.

1.7.5.25 Trimming Trench Excavations

When excavating to specified levels for trench excavation or to specified limits for the face
of any structure therein required to abut undisturbed ground, the Contractor shall not finally
complete the excavation until immediately before commencing constructional work except
where the Engineer permits otherwise.

Where no bedding material is specified to be laid beneath the pipe the bottom of trench
excavation shall be carefully boned in and trimmed true to grade with the aid of a straight-
edge so as to ensure a continuous support for the pipes. The trench bottom shall then be
pricked over with a fork and any stones or flints likely either to cause the pipe to bed
unevenly, or to damage the pipe or its coating, shall be picked out of the pipe bed or any
holes so formed shall be filled in with soft material and trimmed to the correct level.

Where bedding material is specified, all shattered and loose material shall be removed from
the bottom of the Trench Excavation so that the bedding material rests on a sound and
clean foundation.

GKW - Alliance 25
SPECIFICATIONS
CIVIL WORKS

1.7.5.26 Disposition of Material from Trench Excavation

Subject to any specific requirements of the Contract, the Contractor shall make his own
arrangements for the temporary storage of any excavated material which is required for use
in refilling trench excavations, including any necessary double handling. In this connection
the Contractor shall have regard to the working areas available to him for the construction
of the pipeline, particularly where this is located in roads or in other places to which the
public has free access. Any temporary tips alongside the trench excavations shall be to
stable slopes and heights.

Top surface material and topsoil if any shall be stored separately from other excavated
materials.

Where the nature of the excavated material is suitable, the Contractor’s temporary storage
as aforesaid shall include for the separate storage as the Engineer may direct of suitable
material for the surface reinstatement of trench excavation.

Any excavated material not required for or not suitable for use as refilling as aforesaid or
for use elsewhere in the works shall, as between the Employer and the Contractor, be
deemed to be the property of the Contractor and he shall be entirely responsible for its
removal from the site and for its ultimate disposal.

1.7.5.27 Trenches not to be Left Open

Trench excavation shall be carried out expeditiously and, subject to any specific
requirements of the Contract, the refilling and surface reinstatement of trench excavations
shall be commenced and completed as soon as reasonably practicable after the pipes have
been laid and jointed.

Pipelaying shall follow closely upon the progress of trench excavation, and the Contractor
shall not permit unreasonably long lengths of trench excavation to remain open while
awaiting testing of the pipeline. The Contractor shall take precautions to prevent flotation
of pipes in locations where open trench excavations may become flooded, and these
precautions may include the partial refilling of the trench leaving pipe joints exposed while
awaiting tests of the joints.

If the Engineer considers that the Contractor is not complying with any of the foregoing
requirements he may prohibit further trench excavation until he is satisfied with the progress
of laying and testing of pipes and refilling of trench excavation.

1.7.5.28 Refilling Trench Excavations

Subject to any particular requirements specified hereafter, Trench Excavations shall be


refilled using suitable materials selected from nearby excavations.

After any specified concrete or granular bed haunch or surround has been placed the refill
material shall be deposited and properly compacted in layers, any coarse or hard material
being placed in the upper layers. Particular care shall be taken to avoid damage to the pipe
and any sheathing or surround.

Where necessary the Contractor shall adjust the moisture content of the refill material either
by drying out or by adding water to assist the compaction of the material.

Where directed by the Engineer, trench excavations shall be refilled with concrete.

GKW - Alliance 26
SPECIFICATIONS
CIVIL WORKS

1.7.5.29 Refill Material - Special Measures

Where in the opinion of the Engineer sufficient supplies of material suitable for trench
refilling cannot reasonably be obtained from nearby excavations without resorting to sieving
or other special means then he may order the Contractor

 to carry out such work as may be necessary to sieve or otherwise render the material
suitable, or
 to transport suitable material from excavations elsewhere (‘overhaul’), or
 to excavate material from suitable borrow areas and transport it to the length of trench
to be refilled, or
 to import suitable material.

1.7.5.30 Surface Reinstatement in Open Land

After he has refilled trench excavations in open land in the manner and to the level specified
the Contractor shall cultivate the surface of the affected area to a depth of at least 300 mm
and shall replace all top surface material, including topsoil if any, previously removed; such
replaced material shall be evenly distributed and levelled over the full extent of the stripped
area. Such of the working areas occupied by the Contractor as were originally down to
grass shall be sown with grass seed of equivalent quality and maintained until the new
grass is properly established.

Any agricultural land not originally down to grass shall be dressed with suitable fertilisers
harrowed in so as to restore the original level of fertility.

1.7.5.31 Surface Reinstatement in Roads and Tracks

Temporary or permanent surface reinstatement of trenches in roads and tracks shall


comply with any particular requirements specified hereafter.

1.7.5.32 Field Drains in Trench Excavation

Where field drains, mole drains or other drains are severed by trench excavation they shall
be kept in effective temporary operation during construction of the pipeline.

At the appropriate stage of refilling the trench excavation the drains shall be permanently
restored as specified below.

The drain shall be cut back into firm ground for at least 300 mm on each side of the
excavated trench and a suitable length and diameter of uPVC pipe, complying with the
applicable standard, shall be jointed to the existing drain and laid resting at the ends on
solid ground with clay or other stopping to prevent the subsequent run of water from the
drain into the pipe trench. During trench re-filling, earth shall be carefully placed and
thoroughly compacted under the uPVC pipes to give them adequate support.

GKW - Alliance 27
SPECIFICATIONS
CIVIL WORKS

1.7.5.33 Existing Services

Where trench excavation is carried out close to or across the line of sewers, pipes, cables
and other services whether underground or overhead the Contractor shall where necessary
provide temporary supports or slings and where such sewer, pipe, cable or other service is
temporarily disturbed it shall be replaced.

Where in the opinion of the Engineer construction of the pipeline cannot reasonably be
carried out unless the sewer, pipe, cable or other service is permanently severed or
permanently diverted or permanently supported he may order such permanent measures
as he considers necessary to be carried out by the Contractor or by others and in either
case at the cost of the Employer.

Notwithstanding any relevant information furnished by or on behalf of the Employer or


Engineer, the Contractor shall be responsible for ascertaining from his own inspection of
the Site and from the respective supply companies and public bodies, and by using cable
locators and excavating trial pits, the position of all mains, pipes and cables whether
underground or overhead, within or near the Site.

In any area where there may be buried power cables, the Contractor shall use a cable
locator:

 to survey the trench route before starting excavation, and


 to re-survey at the start of each day the length to be excavated during that day.

1.7.5.34 Hedges, Fences and Walls

Where the trench excavation crosses barriers such as hedges, fences and walls the
Contractor, as a temporary measure during construction, shall provide temporary fencing
in place of any parts of such barriers which have to be removed.

After trench excavation has been reinstated, the Contractor shall carry out such work as
the Engineer may order for permanent restoration of such barriers. In the case of a hedge
the section removed shall be replaced by rooted cuttings of the appropriate variety and
where ordered by the Engineer the rooted cuttings shall be protected from stock on one or
both sides by an adequate post and barbed wire fence. During the Period of Maintenance
all hedges replanted in the above manner shall be inspected and any dead cuttings
replaced by the Contractor.

1.7.5.35 Crossing Watercourses

Where the line of trench excavation crosses streams, ditches, culverts and other
watercourses the Contractor shall be deemed to have allowed for all the additional
measures necessary for the proper construction of the works at these crossings including
maintaining the full flow of water.

1.7.5.36 Geotextiles

Geotextiles shall be protected at all times against mechanical or chemical damage. Those
geotextiles which are susceptible to damage by light shall be stored under cover.

GKW - Alliance 28
SPECIFICATIONS
CIVIL WORKS

1.7.5.37 Laying of Geotextiles

Geotextiles shall be laid and lapped in accordance with the manufacturer’s


recommendations. The layer of material on which the geotextile is to be placed shall not
have protrusions or sharp projections which are likely to damage the geotextile during
installation or in service. The method of installation shall ensure that the geotextile is in
continuous contact with the surface on which it is to be placed and the geotextile shall not
be stretched or bridged over hollows or humps. Operation of construction plant directly on
the installed geotextile will not be permitted. Care shall be taken in placing fill material to
avoid damage to the geotextile.

1.7.5.38 Embankments Generally

The term ‘embankment’ includes, for example, the construction of embankments for
roadworks and for small lagoons. It does not include the construction of large earthfill dams
or reservoirs.

The forming of spoil tips and filling around or over completed structures are dealt with under
Excavation.

1.7.5.39 Material for Embankments

Material for embankments shall comply with the general requirements for fill material and
with any special requirements relevant to its particular kind or type.

1.7.5.40 Construction of Embankments

All embankments shall be constructed with selected materials obtained from the
excavations or from other sources approved by the Engineer.

Subject to any particular requirements specified hereafter, the approved materials shall be
placed in layers, and shall be compacted to a dry density not less than ninety-five per cent
of the maximum dry density obtained in the Compaction Test as described in the applicable
standard, Test 12. During compaction the fill shall have a uniform moisture content equal
to or not more than 2% above the optimum moisture content recorded in the Compaction
Test. Where necessary, the Contractor shall adjust the moisture content of the fill either by
drying out or by adding water. After such drying out or adding of water the fill shall be
thoroughly mixed until the moisture content is uniform. The layers of fill material shall be
so placed as to maintain adequate drainage and to prevent accumulation of water.

Where the Contract requires the placing of different types of fill material in separate layers,
the Contractor shall carry out the work so as to avoid mixing the different types of material.
Should there be any mixing of materials, such mixed materials shall be removed from the
Site and replaced with separate materials, all at no extra cost to the Employer.

1.7.5.41 Top soil

Parts of the site as may be ordered by the Engineer shall, as soon as practicable after the
completion of other earthworks, be covered with topsoil and sown with grass, all as
specified hereunder.

So far as is practicable, topsoil shall be obtained from material emanating from excavations
and separately stored in temporary spoil tips as specified. If in the Engineer's opinion the

GKW - Alliance 29
SPECIFICATIONS
CIVIL WORKS

Contractor cannot reasonably obtain sufficient topsoil in this way, he may order the
Contractor to provide extra material (‘Imported Topsoil’) from an approved source off the
site.

Topsoil shall be evenly spread and trimmed over embankments and other areas to the
slopes and levels specified or ordered by the Engineer. The depth after spreading and
trimming shall be 250 mm unless otherwise directed, measured perpendicularly to the
surface. All clods and lumps shall be broken up and any rubbish, large stones, roots and
weeds shall be removed.

1.7.5.42 Grassing

Areas to be grassed shall be covered with 100 mm topsoil. Areas to be grassed shall be
turfed using good quality locally produced turf.

Final Preparations

Areas to be turfed shall be cultivated. The surface shall be lightly and evenly firmed and
reduced to a fine tilth 25 mm in depth. Any stones exceeding 25 mm in any direction shall
be removed from the surface.

3:2:1 fertiliser shall be incorporated into the soil at a rate of 25 grams per square metre.
The preparation shall be inspected by the Engineer the prior to laying of any turves.

Grass Establishment: Turfing

The turf shall be laid when weather and soil conditions are suitable.

Turves shall be stacked on site on cleared ground to a maximum height of 1 metre. The
stacked turves should be laid as soon as possible to avoid deterioration. The imported turf
shall be good quality local grass and weed free, of average dimensions 900  450 mm,
trimmed to a thickness of not less than 25 mm. Samples shall be provided to the Engineer
prior to importation to site. Turves shall be laid in rows using planks over turves already
laid, with staggered jointing and be well butted together. They shall be lightly and evenly
rolled after laying and thoroughly watered.

Whole turves shall be laid round the perimeter of turfed areas and trimmed after laying to
give a well-cut edge. A dressing of finely sifted topsoil shall be applied to the surface after
laying, and brushed into joints. Any irregularities in finished levels owing to variations in
thickness of turves or uneven consolidation of the soil shall be adjusted by packing fine soil
under the turf. If shrinkage occurs and the joints open, fine topsoil shall be brushed into
the joints and the turves well watered.

Initial Cutting

About 48 hours before topping, any stones exceeding 50 mm in any direction shall be
removed and areas rolled to firm the grass and press in remaining stones. When the grass
has settled and is 60 mm in height, it shall be cut to a height of 40 mm. Grass arisings shall
be removed from site.

Following the first cut of grass areas, the grass should then be cut to a height of
approximately 25-30 mm.

GKW - Alliance 30
SPECIFICATIONS
CIVIL WORKS

Maintenance of Grass Areas

Cutting of grass:

All grass areas shall be cut regularly. Cuts may be utilised as a mulch on shrub areas or
removed from site.

Grass shall be maintained at a height suitable for the grass species, ensuring that the
blades are not set too low which may result in unsightly brown patches.

As a guide the following maintenance shall apply:

Local grass: 25-30 mm cutting height


 Cut once per week September to April
 Cut twice per month May and August
 Cut once per month June and July

Prior to cutting, all stones or other deleterious material on the surface shall be removed.

Top-dressing and Fertilising of Grass

Top-dressing of lawn areas shall be carried out if necessary to eliminate minor hollows.

Fertiliser shall be applied in September, December and March. 3:2:1 shall be applied at a
rate of 25 grams per square metre, evenly over all local grass areas.

Seeded areas shall be fertilised in Spring and autumn utilising Vitaflora 515 slow-release
at a rate of 50 grams per square metre.

Pest and Weed Control

Grass areas shall be kept weed free, and free of pests and diseases, by spraying or spot
treatment or hand weeding as necessary, in strict accordance with the manufacturer’s
instructions.

Edging

All grass areas shall be edged regularly according wherever the grass areas meet with
buildings, manholes, paving or other artefacts, around trees or against shrub areas. Edges
shall be carefully cut using an approved trimmer.

In the case of shrub beds, the Contractor shall ensure that the original shape of the beds is
maintained, and that edges are kept true to line and level. The Contractor shall be expected
to repair edging damaged due to careless trimming.

The Contractor shall operate the irrigating system in order to keep grassed areas watered
sufficiently.

GKW - Alliance 31
SPECIFICATIONS
CIVIL WORKS

1.7.6 Testing

1.7.6.1 Testing by the Contractor

The Engineer will perform the following testing:

 Compaction tests on each kind of filling material being used for embankments or
backfill.
 Particle size analysis and grading tests on fill materials and filter materials.
 Field density tests on backfilling and embankments at the rate of one test per layer
of embankment or backfill or one test per 250 m2 of an extensive single layer.

The Contractor shall be responsible for carrying out all other field and laboratory tests
required for the proper control of earthworks.

Laboratory tests shall be carried out at the site or in an off-site laboratory approved by the
Engineer.

Field density tests shall be performed to ensure that the specified density is being obtained.
Tests shall be in accordance with the applicable standard. Test results and copies of
calculations shall be submitted to the Engineer.

Tests on geotextiles shall be in accordance with the applicable standard and the Contractor
shall be responsible for carrying out such tests as required by the Engineer.

1.7.7 Dewatering

1.7.7.1 Scope of Work

The Contractor shall furnish all labour, materials and equipment, perform all work necessary
to lower and control the groundwater levels and hydrostatic pressures to permit all
excavations and construction to be performed in dry conditions.

The work shall include the testing, operation, maintenance, supervision, dewatering and
final dismantling and removal from the site of the dewatering system as described herein.

The Contractor will be responsible for the cost of dewatering. He will also be responsible
for all costs for claims and costs of any replacement or rehabilitation of the subgrade,
buildings, structures and services damaged during the process of dewatering. The
responsibility covers also all costs for damages due to dewatering system failures or
Contractor's negligence. The Contractor shall be responsible for compliance with all local
regulations relating to this work.

Dewatering shall include the diversion, collection and removal of all surface runoff from the
work areas; removal of groundwater from new excavations to permit construction in the dry.

1.7.7.2 General Information

Prior to any excavation, the dewatering system shall be placed in operation to lower the
water level, as required. Thereafter, the system shall be operated continuously twenty-four
(24) hours per day, seven (7) days per week until all structures have been satisfactorily
constructed, including placement of fill materials and dewatering is no longer required; all
as required by the Engineer.

GKW - Alliance 32
SPECIFICATIONS
CIVIL WORKS

Both primary and standby power for the dewatering system shall be provided by the
Contractor, including all costs for installation, energy and fuel. For any fuel powered system
the Contractor shall maintain adequate fuel supply on site. The Contractor shall make all
necessary arrangements for the temporary power service and provide all necessary
accessories required.

Prior to starting dewatering operations the Contractor and the Engineer shall make a joint
inspection of the condition of all existing structures on or adjacent to the site that is to be
dewatered to establish their present condition. Photographs shall be taken to record any
conditions that may become the subject of possible damage claims. The Contractor shall
include in his Tender the cost for adequate photo coverage of such existing structures. The
Contractor shall supply the Engineer with one set of all photographs taken which shall be
annotated with adequate reference details.

1.7.7.3 Submittals

The Contractor shall submit for the Engineer's approval a detailed description of the
sequence of dewatering operations.

The description shall include but not be limited to:

 Plans showing the methods and location of dewatering and discharge. The drawings
shall include sufficient details to clearly illustrate the work.
 Lists of materials and equipment to be used.
 Calculations for the design of the dewatering system. The Engineer's review shall be
made to verify that the general scope of work is adequate and that the Contractor is
qualified to perform the work as shown on the drawings. Review of the Contractor's
plans and methods of construction by the Engineer shall not be construed to relieve
the Contractor in any way from his responsibility for the successful performance of
the dewatering work.

The Contractor shall also submit daily operating logs which shall include results from water
quality tests for suspended matter at the discharge point including time of day and elapsed
times of tests, daily discharge rates, installation and removal of wells and general
observations on the system such as equipment running times and failure.

GKW - Alliance 33
SPECIFICATIONS
CIVIL WORKS

1.7.8 Particular Requirements

1.7.8.1 Free-draining Fill

Material for free-draining fill shall comply with the general requirements of Clauses 4.8.5.2.
Where material of Type 1 or Type 2 is specified, the particle size distribution, when
determined by the method described in the applicable standard, shall lie within the limits
given below:

Sieve Percentage of dry material passing by weight


size

Type 1 (fine)
mm µm Type 2 (coarse)

37.50 100 %

20.00 40 % - 100 %

10.00 100 % 25 % - 80 %

5.00 85 % - 100 % 5% - 50 %

1.18 15 % - 85 % 0% - 20 %

300 0% - 35 % 0% - 10 %

75 0% - 10 % 0% - 5%

1.7.8.2 Trench Width

Except by written permission of the Engineer, the overall width of trench excavations
(including any trench support) shall comply with the following:

Minimum width:

Trenches shall not be less than 750 mm wide, provided that trenches for small
diameter pressure pipelines and cables shall not be less than 500 mm wide subject
to there being a minimum of 150 mm clear on each side of the pipe barrel or cable.

Maximum with:

Trench widths shall not exceed those in the following table where ‘D’ is the external
diameter of the pipe: including any protective coating:

'D' Maximum trench width

not exceeding 400 mm 750 mm

exceeding 400 mm,


(D + 550) mm
not exceeding 1,100 mm

GKW - Alliance 34
SPECIFICATIONS
CIVIL WORKS

exceeding 1,100 mm,


(D + 550) mm
not exceeding 1,500 mm

These maximum widths shall generally apply throughout the whole depth range of
the trench. If the Engineer permits the excavation to be battered back or to be
stepped, e.g. to accommodate additional trench support such enlargement of the
trench shall not in any case extend below a line 500 mm above the crown of the pipe.

1.7.8.3 Compaction

Fill shall be compacted so as to achieve the following:

 Pipe trenches : 98 % Maximum dry density


 Structural embankments : 98 % Maximum dry density
 Landscaped areas : 90 Maximum dry density

1.8 Concrete

1.8.1 Scope

This Part contains requirements which, where relevant to this Contract, shall apply to the
supply of materials for concrete, design of mixes, quality control, mixing, transporting and
placing, and curing of concrete.

1.8.2 Submissions by Contractor

1.8.2.1 Submissions Generally

Submissions by the Contractor in relation to concrete work are described in the relevant
clauses of the Specification. These submissions are summarised hereunder, with cross-
references to the relevant sub-clauses.

1.8.2.2 Certificates

Manufacturers’ and suppliers’ certificates of compliance with relevant standards in respect


of the following materials:

 cement
 aggregates
 admixtures
 ready mixed concrete

Calibration certificates furnished by an approved person for:

 weighing devices
 dispensing devices
 batching plant

The results certified by an approved person for tests carried out subsequently on:

GKW - Alliance 35
SPECIFICATIONS
CIVIL WORKS

 aggregate
 moisture content of aggregate
 fresh concrete
 concrete test tubes
 hardened concrete

1.8.2.3 Samples

Samples of all the foregoing materials except concrete and water shall be submitted, and
those approved shall be kept in suitable containers, properly labelled and stored on site for
reference.

1.8.2.4 Concrete Mixes

Details of designed mixes for all grades of concrete required for the Works, together with
proposed methods of transportation, handling, placing and compaction.

1.8.2.5 Other Submissions

Proposals for the following, where relevant to the works:

 details of design mixes,


 details of construction jointing and lifts,
 construction details for the installation of water stops,
 special measures for dealing with particular circumstances (e.g. concreting in
hot/cold weather),
 methods for precast work,
 methods for pre-stressed work,
 methods of curing.

1.8.2.6 Records of Concreting

Daily returns in respect of all concrete placed during the previous day.

The returns shall detail:

(a) in respect of each grade of concrete:

 the number of batches mixed,


 the number of batches and the total volume of concrete placed,
 the number of batches wasted or rejected,
 the weight of cement used;

(b) in respect of work progress:

 the position of the pour (e.g. bay or lift reference number),


 the grade of the concrete placed,
 the total volume of concrete placed and the number of batches used.

GKW - Alliance 36
SPECIFICATIONS
CIVIL WORKS

In addition, the Contractor shall maintain an accurate and up to date record showing dates,
times, weather and temperature conditions when each part of the works was concreted.
The record shall be available for inspection by the Engineer at all times.

Results of all tests on concrete shall be recorded and identified with the parts of the works
to which they relate.

1.8.3 Materials

1.8.3.1 Cement

Cement used in the works shall be ordinary Portland cement unless otherwise specified or
agreed with the Engineer.

The Contractor shall provide from each consignment of cement delivered to the site such
samples as the Engineer may require for testing. Any cement which is, in the opinion of
the Engineer, lumpy or partially set shall be rejected and the Contractor shall promptly
remove such cement from the site. Cement which has been stored on the site for more
than forty days and cement which in the opinion of the Engineer is of doubtful quality shall
not be used in the works unless it is re-tested and the test results show that it complies with
the relevant Standard.

1.8.3.2 Storage of Cement

Immediately upon arrival at the Site, cement shall be stored in silos designed for the
purpose or in dry weather-tight and properly ventilated structures with floors raised 500 mm
above ground level with adequate provision to prevent absorption of moisture. All storage
facilities shall be subject to the approval of the Engineer and shall be such as to permit easy
access for inspection and identification. Each consignment of cement shall be kept
separately and the Contractor shall use the consignments in the order in which they are
received.

Cement of different types and from different sources shall be kept in clearly marked
separate storage facilities. Cement delivered to the Site in drums or bags provided by the
supplier or manufacturer shall be stored in the unopened drums or bags until used in the
Works. Any cement in drums or bags which have been opened on the Site shall be used
immediately or shall be removed from the Site.

1.8.3.3 Aggregates

Aggregates for concrete shall be obtained from an approved source, shall conform to the
grading and other requirements of the relevant Standards, and shall be washed clean.

Water absorption of aggregates when tested in accordance with the standard procedure
prescribed in the applicable standard, shall not exceed 3%.

Alkali-silica Reaction

The fine and coarse aggregates shall each consist of at least 95% of one or more of the
rock types tabulated below. Sources of aggregates shall not contain opaline silica or
quantities of flint, chert or chalcedony that could cause damage from alkali-silica reaction.

GKW - Alliance 37
SPECIFICATIONS
CIVIL WORKS

 Air-cooled blastfurnace slag  Limestone


 Andesite  Marble
 Basalt  Microgranite
 Diorite  Quartz
 Dolerite  Schist
 Dolomite  Sintered pfa
 Expanded clay / shale / slate  Slate
 Feldspar  Syenite
 Gabbro  Trachyte
 Gneiss  Tuff
 Granite

If the Contractor wishes to use aggregates other than those listed, he shall submit evidence
to the satisfaction of the Engineer from the previous performance of the coarse and fine
aggregates which he proposes to use that, when used with the proposed cementitious
constituents of the concrete mix in the proportions proposed there will be no cracking or
expansion due to alkali-silica reaction during the life of the structure.

If this requirement cannot be met, the Contractor shall adopt constituents for his concrete
such that either

(a) The cementitious material shall have a reactive alkali content not exceeding a
maximum value of 0.6% by mass when defined and tested in accordance with the
method prescribed,
or
(b) the total mass of reactive alkali in the concrete mix shall not exceed 3 kg per m 3 of
concrete when defined, tested and calculated in accordance with the method
prescribed.

The Contractor shall notify the Engineer of his proposals for complying with this requirement
at the time of tendering.

Soluble Chlorides

Chlorides content, expressed as chloride ion, shall be such that the concrete mix as a whole
complies with the limit of total chlorides specified. If necessary, the tests described in the
applicable standard shall be used to ensure compliance with this requirement.

Soluble Sulphates

Water-soluble sulphate contents of the aggregates shall be such that the concrete mix as
a whole complies with the limit of total water soluble sulphates specified later in this
document. If necessary the tests described in the applicable standard for acid-soluble
sulphates shall be used to ensure compliance with this requirement.

Coarse and Fine Low-shrinkage Aggregates

The coarse aggregates shall be capable of producing concrete having a drying shrinkage
of not more than 0.065 per cent, when listed in accordance with the method given in the
applicable standard.

GKW - Alliance 38
SPECIFICATIONS
CIVIL WORKS

The Contractor shall produce test sheets from the supplier certifying compliance with the
stipulated requirement. Where such test sheets are not available, tests shall be carried out
by the Contractor to establish the suitability of the proposed source of supply.

Where a source of supply produces coarse aggregates which do not satisfy the stipulated
shrinkage requirement, such a source shall not be used for the supply of fine aggregates.

1.8.3.4 Storage of Aggregates

The Contractor shall provide means of storing the aggregates at each point where concrete
is made such that (i) each nominal size of coarse aggregate and the fine aggregate shall
be kept separated at all times, (ii) contamination of the aggregates by the ground or other
foreign matter shall be prevented at all times, and (iii) each heap of aggregate shall be
capable of draining freely.

The Contractor shall ensure that graded coarse aggregates are tipped, stored and removed
from store in a manner that does not cause segregation.

Wet fine aggregate shall not be used until in the opinion of the Engineer it has drained to a
constant and uniform moisture content, unless the Contractor measures the moisture
content of the fine aggregate continuously and adjusts the amounts of fine aggregate and
added water in each batch of concrete mixed to allow for the water contained in the fine
aggregate. If necessary to meet the requirements of this clause, the Contractor shall
protect the heaps of fine aggregate against inclement weather.

1.8.3.5 Water

Water for washing aggregates, for mixing concrete and for curing shall be clean and free
from harmful matter and shall satisfy the recommendations in the applicable standard; the
concentration of sulphates and chlorides shall be such that the concrete mix as a whole
complies with the specified limits of salts content.

1.8.3.6 Admixtures

Admixtures shall mean material added to the concrete materials during mixing for the
purpose of altering the properties of the concrete mix.

Admixtures containing calcium chloride shall not be used.

The chloride ion content of admixtures shall not exceed 2% by weight of the admixture or
0.03% by weight of the cement when used in:

 concrete containing pre-stressing tendons, reinforcement, or embedded metal and


made with any type of cement; and
 concrete made with cement complying with the applicable standard.

Admixtures shall be used only if the Engineer has given his prior approval in writing, and
with due regard to the manufacturers’ instructions. Both the amount added and the method
of use shall be to the approval of the Engineer who shall also be provided in good time with
the following information:

 The typical amount added and any detrimental effects due to adding greater or
smaller amounts.

GKW - Alliance 39
SPECIFICATIONS
CIVIL WORKS

 The chemical name(s) of the main active ingredient(s) in the admixture.


 Whether or not the admixture leads to the entrainment of air when used at the
proposed rates of dosage.

Any approved admixture shall conform to the relevant applicable standard.

 water reducing admixtures


 retarding admixtures
 air entraining admixtures
 super-plasticising admixtures

When more than one admixture is used in a concrete mix the compatibility of the various
admixtures shall be established to the satisfaction of the Engineer.

1.8.4 Workmanship

1.8.4.1 Grades and Classes of Concrete

The Contractor shall design mixes for any or all of the grades of concrete in the table
overleaf as required for the Works.

Concrete Minimum Cement Maximum Free


Grade Content (kg/m³) Water / Cement Ratio

C 40/20 325 0.55


C 40/40 295

C 35/20 325* 0.55**


C 35/40 296*

C 35/20 325 0.55


C 35/40 270

C 30/20 325 0.55


C 30/40 245

C 25/20 250 0.65


C 25/40 220

C 20/20 230 0.70


C 20/40 200

C 15/40 180 0.70

C 10/40 150 --

* Maximum cement content 400 kg/m3 (or 450 kg/m3 where pfa forms a cementitious component).
** 0.50 where pfa forms a cementitious component.

Where a Class as well as a Grade (e.g. “Grade C25120/20/Class 4”) is required, the
minimum cement content and the maximum free water/cement ratio shall comply with the
applicable standard, as well as with the table shown above.

GKW - Alliance 40
SPECIFICATIONS
CIVIL WORKS

Concrete grade is that number which represents its characteristic strength at 28 days
expressed in N/mm2, followed by the maximum size of aggregate in mm.

Characteristic strength is that value of cube crushing strength below which not more than
5 per cent of all test results fall. This condition shall be deemed to be satisfied when the
results comply with the specified test requirements.

1.8.4.2 Free Water / Cement Ratio

In designing and establishing approved mixes of concrete for any part of the Works the
Contractor shall keep within any limitations on free water/cement ratios which may be
expressly stated in the Specification, as applying to concrete for particular parts of the
Works or (where not so stated) as given in the Table of concrete grades.

1.8.4.3 Limits of Salts Content of Mix

No concrete shall contain more than the following total quantities of the substances
expressed as percentages by weight of cement:

(a) For mixes containing ordinary Portland cement, or Portland-blastfurnace cement to,
or low-heat Portland cement, or low-heat Portland-blastfurnace cement, or a
combination of ggbfs and pfa.
The total chlorides expressed as chloride ions calculated whenever possible from the
mix proportions and the measured chloride contents of each of the constituents:
0.4%.
(b) For mixes containing Sulphate-resisting cements and Super-sulphated cement the
total chlorides expressed as chloride ions calculated as above: 0.2%.
(c) For mixes used for pre-stressed concrete or heat-cured concrete containing
embedded metal (all types of cement), the total chlorides expressed as chloride ions
calculated as above: 0.1%.
(d) For all mixes except where super-sulphated cement is used, total water-soluble
sulphates: 4.0% (as SO3 ions).

Tests for aggregates and mixing water shall be carried out in accordance with the applicable
standard.

Calcium chloride or chloride-based admixtures shall not be added to mixes intended to


contain reinforcement, pre-stressing tendons or other embedded metal.

Where it is required to verify the salt content of hardened concrete, tests shall be carried
out in accordance with the applicable standard.

1.8.4.4 Workability

The workability of the concrete mixes shall be defined by their compacting factors
determined by the method described in the applicable standard.

The workability of each concrete mix shall be such that satisfactory compaction can be
obtained when the concrete is placed and vibrated in the work and that there is no tendency
to segregate when it is handled, transported and compacted by the methods which the
Contractor proposes to use in the Works.

GKW - Alliance 41
SPECIFICATIONS
CIVIL WORKS

When, by trial mixes according to Clause 4.9.5.6 or otherwise, a mix has been verified as
complying with these requirements its workability shall be measured and, within the limits
given below, confirmed or amended as considered necessary by the Engineer.

For reinforced concrete and pre-stressed concrete, the compacting factor shall lie between
0.85 and 0.92. For un-reinforced concrete the compacting factor shall lie between 0.75 and
0.80. For concrete which is to be pumped, the compacting factor may be increased to 0.95.

1.8.4.5 Design of Concrete Mixes

Each mix design shall be such that:

(a) The aggregate shall comprise both fine aggregate and coarse aggregate. The
maximum size of coarse aggregate shall be either 20 mm or 40 mm as directed by
the Engineer. A separate mix shall be designed for each maximum aggregate size
for any grade of concrete.

(b) The maximum free water/cement ratio shall be the maximum water/cement ratio
when the aggregate is saturated but surface dry.

(c) The mixes shall be designed to produce a target mean concrete cube strength at 28
days after manufacture greater than the characteristic strength at 28 days by a margin
of at least 10 N/mm2 for grade 15 and a margin of at least 15 N/mm2 for grades
20,25,30 and 40.

(d) Where sufficient data demonstrate that a different margin is acceptable or necessary,
in order to maintain the standard of acceptance for characteristic strength, the mix
shall be redesigned to have such different margin. Sufficient data shall mean cube
test results from at least 40 separate batches of concrete produced over a period
exceeding 5 days but not exceeding 6 months by the same plant under similar
supervision. The different margin shall be 1.64 times the standard deviation of the
test results considered, but not less than 5 N/mm2 for grade 15 or 7.5 N/mm2 for
grades 20,25,30 and 40.

For any concrete containing admixtures, the strengths shall be not less than those specified
in the Table of concrete grades but the mixes shall be separately designed to take account
of the effects of the admixtures, and shall have separate trial mixes made and tested.

1.8.4.6 Trial Mixes

Laboratory Trials:

As soon as the Engineer has agreed the trial mix proportions for each grade of concrete,
the Contractor shall produce in the concrete testing laboratory on Site two batches from a
trial mix for each grade (except grade 10) using cement and surface dry aggregates known
to be typical of the proposed source of supply. Each batch shall contain the correct amount
of cement and have a free water cement ratio at or below the maximum value given in the
Table of concrete grades, and the workability of each batch shall be determined. Provided
that the compacting factors so obtained fall within the specified limits and the requirements
regarding cement content and free water cement ratio have been met, the Contractor may
proceed to carry out Site trials.

As an alternative to producing trial mixes in a laboratory as described above, the Contractor


may submit recent existing laboratory test reports from elsewhere. Such reports shall be
acceptable only if the Engineer is satisfied with the laboratory’s test procedures and that
the materials used were typical of the proposed source of supply.

GKW - Alliance 42
SPECIFICATIONS
CIVIL WORKS

Site Trials:

Trial mixes shall be made at the site of the proposed concreting under full scale production
conditions. The proportions of materials used, including the mixing water, shall agree with
the mix proportions determined by the laboratory trial mixes. Three batches of concrete for
each grade shall be produced, using the same plant and mixing time proposed by the
Contractor for use in the Works.

For each grade of concrete the following shall be carried out:

 The workability of each of the three batches shall be determined immediately after
mixing by the compacting factor method.
 Three 150 mm test cubes from each of the three batches shall be made by the
Contractor in the presence of the Engineer. The cubes shall be made, cured, stored
and tested at 28 days after manufacture in accordance with the method described in
the applicable standard.

A site trial mix for a particular grade of concrete shall be considered satisfactory provided
that:

(i) the compacting factors as under (a) above fall within the specified limits; and
(ii) the average value of the compressive strength of the nine cubes taken from the trial
mix is greater than the target mean strength used in the mix design.

If the requirements under (i) and (ii) above are not met for any mix the Contractor shall re-
design that mix and he shall make further Site trials as above.

Where re-design of any concrete mix becomes necessary, the making and testing of the
trial mix shall be repeated until the trial mix satisfies both requirements (i) and (ii) above.
Final approval will not be given to any trial mix which does not comply with the specified
requirements appropriate to that grade of concrete.

1.8.4.7 Mixes not approved

Approval of a mix may be withheld or withdrawn if (inter alia):

 the grading of the aggregate changes such that the fraction of aggregate
retained on any sieve differs from the corresponding fraction of aggregate in
the approved mix by more than 2% of the total quantity of fine and coarse
aggregate,
or
 the source of supply of aggregate or cement is changed.

If approval of a mix for any grade of concrete is withdrawn for any reason the Contractor
shall carry out such further trials as are necessary to achieve a satisfactory mix for that
grade of concrete.

1.8.4.8 Batching of Materials

Cement used in the production of concrete shall be measured by weight either with an
approved weighing machine or by making the size of each batch of concrete such as to
require an integral number of complete bags or drums of cement.

GKW - Alliance 43
SPECIFICATIONS
CIVIL WORKS

For concrete of grades 20, 25, 30 and 40 the fine aggregate and the several nominal sizes
of coarse aggregate shall be measured singly or cumulatively by weight using weigh-
batching machines.

For concrete of grades 10 and 15 the fine and coarse aggregate shall be measured
separately either by weight using weigh-batching machines or by volume in gauge boxes.

Weigh-batching machines shall provide facilities for the accurate control and measurement
of the aggregates either singly or cumulatively and shall be capable of immediate
adjustment by semiskilled operators, in order to permit variations to be made to the mix. All
weigh dials shall be easily visible from the place at which filling and emptying of the hoppers
is controlled.

Every concrete mixing machine shall be fitted with a device to measure added water by
weight or volume and shall be so constructed that the water inlet and outlet valves are
interlocked, so that neither one of them can be opened unless the other is fully closed. The
water-measuring device shall be provided with an overflow with a cross-sectional area at
least four times that of the inlet pipe, and with its discharge point clear of the mixing plant.
The entire water system shall be maintained free of leaks at all times and the measuring
device shall be fitted with a drain pipe which allows the full quantity of water being measured
to be drained off for checking the measurement. The outlet arrangement of the measuring
device shall be such that between five and ten percent of the water enters the mixer before
the other materials, and a further five to ten percent of the water enters the mixer after the
other materials. The remainder of the water shall be added at a uniform rate with the other
materials. The water measuring device shall be readily adjustable so that the quantity of
water added to the mixer can, if necessary, be varied for each batch.

Gauge boxes for use in volume batching shall be soundly constructed of timber or steel,
with closed bottoms. Each box shall be sized to contain exactly the volume of aggregate
required for one batch of any particular mix. In sizing up gauge boxes for fine aggregates,
the Contractor shall make an allowance for bulking due to moisture contained in the
aggregate stockpiles on Site. Each box shall be suitably identified by reference to the
aggregate and the mix for which it has been made.

Any admixtures which may be used shall be measured separately in calibrated dispensers.

All mixing and batching plants shall be maintained free of set concrete or cement and shall
be clean before commencing mixing. The accuracy of calibration of any weighing plant,
water measuring device and admixture dispenser shall be checked before carrying out trial
mixes, before the first mixing of concrete for inclusion in the Works, after each service or
adjustment to the mixing plant, and in any case at least once per week.

1.8.4.9 Mixing Concrete

Concrete shall be mixed in batches in plant, capable of combining the aggregates, cement
and water (including admixtures if any) into a mixture uniform in colour and consistency,
and of discharging the mixture without segregation.

On commencing work with a clean mixer, the first batch shall contain only half the normal
quantity of coarse aggregate to compensate for the adhesion of the other materials to the
drum.

The moisture contents of the aggregates shall be determined before the commencement
of each day’s concreting, and at such intervals during each day as may be necessary. The
Contractor shall make due allowance for water contained in the aggregates when

GKW - Alliance 44
SPECIFICATIONS
CIVIL WORKS

determining the quantity of water to be added to each mix, and shall adjust the amount of
water added to each mix to maintain the approved free water/cement ratio of the mixed
concrete.

1.8.4.10 Ready-mixed Concrete

Any concrete which is not prepared under the direct control of the Contractor and by plant
situated on or reasonably adjacent to the site, shall be classed as ready-mixed concrete.

Ready-mixed concrete shall not be used in any part of the works without the written
approval of the Engineer, which approval may be withdrawn at any time.

The Contractor shall satisfy the Engineer that ready-mixed concrete complies with the
Specification for concrete, and that the manufacturing and delivery resources of the
proposed supplier are adequate to ensure proper and timely completion of each concreting
operation. The proposed supply depot shall be open to inspection by the Engineer at all
times.

The specified requirements as to the sampling, trial-mixing, testing and quality of concrete
of various grades shall apply equally to ready-mixed concrete which shall furthermore be
made and delivered in accordance with the applicable standard.

The Contractor shall provide every additional facility which the Engineer may require for the
supervision and inspection of the batching, mixing and transporting of ready-mixed
concrete.

1.8.4.11 Preparing for Concreting

Before placing concrete, the Contractor shall remove from the surface of the foundations
or previously placed concrete all oil, loose fragments of rock, earth, mud, timber or other
debris and ( except as provided for in Clause 4.9.5.17) any standing water.

Where specified, and elsewhere as ordered by the Engineer, excavated surfaces on which
concrete is to be placed shall be covered with either blinding concrete not less than 75 mm
thick, or waterproof building paper, or polythene sheeting 0.1 mm in thickness, immediately
after completion of the final trimming of the excavation.

1.8.4.12 Transporting Concrete

Concrete shall be conveyed from the mixer to its place in the Works as rapidly as possible
by methods which will prevent segregation or drying out, and ensure that the concrete is of
the required workability at the time of placing. If segregation has nevertheless occurred in
any instance the materials shall be remixed or rejected.

1.8.4.13 Placing Concrete

Before placing concrete in any part of the Works, the Contractor shall satisfy himself by
inspection that that part is in all respects ready for the reception of concrete. He shall also
notify the Engineer so as to enable him to inspect the location if so required.

The temperature of concrete at placing shall not exceed 25C, except where requirements
of Clauses 4.9.5.14, 4.9.5.15 (as appropriate) are met.

GKW - Alliance 45
SPECIFICATIONS
CIVIL WORKS

Concrete shall be placed and, compacted before initial set has occurred and, in any event,
not later than forty-five minutes from the time of mixing.

Concrete shall be carefully placed in horizontal layers which shall be kept at an even height
throughout the work. Concrete shall not be allowed to slide or flow down sloping surfaces
into its final position but shall be placed directly in its final position from skip, truck, barrow,
down pipe or other placing machine or device or, if this is impossible, it shall be shoveled
into position with care being taken to avoid segregation. Concrete placed in horizontal
slabs from barrows or other tipping vehicles shall be tipped into the face of the previously
placed concrete.

Concrete dropped into place in the work shall be dropped vertically. It shall not strike the
formwork between the point of its discharge and its final place in the work. Concrete shall
not be dropped freely through a height greater than 1.5 metres. Chutes and conveyor belts
shall be so designed that there is no segregation or loss of mortar and shall be provided
with a vertical tapered down pipe, or other device, which ensures that concrete is
discharged vertically into place.

Where a lift of concrete is built up in layers, each layer shall be properly merged into the
preceding layer before initial set takes place. If necessary, the area of the pour will be
restricted to ensure that this is achieved.

When pneumatic placers are used, if the end of the placer pipe is not equipped with an
energy absorbing device, it shall be kept as close to the work as practicable. Mortar or
water used at the beginning or end of a run shall be discharged outside the formwork.

When pumps are used, the end of the supply pipe shall be kept immersed in the concrete
during placing to assist compaction. Mortar or water used at the beginning or end of a run
shall be discharged outside the formwork.

Where concrete abuts against earth or other materials liable to become loose or to slip, the
Contractor shall take steps to prevent any such loose material falling on to the surface of
the concrete. Subject to the approval of the Engineer, such steps may include leaving
timbering in place or cutting away and removing timbering in small lengths or depths at a
time.

1.8.4.14 Concreting in Hot Weather

Hot weather is defined as any combination of high air temperature, low relative humidity
and wind velocity tending to impair the quality of fresh or hardened concrete, or otherwise
resulting in abnormal properties.

In hot weather, the Contractor shall ensure that the temperature of the concrete as placed
shall not exceed 25C except in pipeline chambers where the temperature shall not exceed
30C, and that the maximum internal temperature attained during setting does not exceed
70C.

To that end the Contractor shall provide sun shades over stockpiles of aggregates, cement
silos, mixing water tanks and pipelines and, in addition, shall carry out one or more of the
following procedures which shall be submitted to the Engineer for approval:

(i) Cool the mixing water by methods approved by the Engineer.


(ii) Spray clean cool water over the aggregate stockpiles. The Contractor shall carry out
regular tests on the aggregates to ensure that concentrations of sulphates or
chlorides do not rise to unacceptable levels, and to ensure that moisture content
determinations allow for such spraying.

GKW - Alliance 46
SPECIFICATIONS
CIVIL WORKS

(iii) Shade or wet the outside of the formwork.


(iv) Apply a fine moisture (fog) spray of clean cool water in order to cool and moisten the
surrounding air and the sub-surface, to cool the formwork and reinforcement, and to
lessen rapid evaporation from unformed concrete surfaces.
(v) Pour concrete at night.
(vi) Change the mix to include retarding/plasticising admixtures, cement with a lower rate
of hydration, or cement replacements.

The Contractor shall provide the Engineer with details of the precautions he proposes to
take to protect the concrete from the effects of high temperatures. No concreting in hot
weather shall be put in hand until the proposed measures have received the approval of
the Engineer.

1.8.4.15 Concrete in Large Pours

A large pour is defined as a pour where the least dimension is greater than 1.5 metres.

Subject to the requirements for construction and movement, joint locations and the
requirements for the test blocks detailed in the following clause, the Contractor will not be
limited as to the size of a large pour, provided that adequate measures are taken to control
temperature differentials. Such measures will be evaluated with reference to the following:

(a) Temperatures:

 The temperature of the concrete at the time of placing shall not exceed 20C
and the peak hydration temperature shall not exceed 60C, except under hot
conditions, when the requirements of Clauses 4.9.5.14 shall apply.
 The difference in temperature between thermometers in the concrete near any
concrete face and the interior of the concrete at a distance of 1 m from that
face shall not exceed 20C at any stage after placing.

(b) Monitoring of temperature changes:

Sets of thermometers for recording concrete temperatures shall be placed at


positions in the concrete near to each exposed face at spacings not exceeding 5 m.
Further sets shall be placed at corresponding positions within the concrete at a
distance of 1 m from each face. The concrete temperatures shall be recorded at
intervals not exceeding 6 hours, or such other intervals as may be required by the
Engineer, for a period of at least 7 days.

Where the minimum dimension of a pour is between 1.5 m and 2.0 m, the internal
temperatures shall be recorded by thermometers placed at mid depth of the least
thickness.

(c) Insulation and protection of concrete surfaces:

 Formwork shall be plywood 19 mm thick, or such other combination of


materials having an equivalent insulation value. The formwork shall remain in
position for a sufficient time to ensure that the temperature control requirement
in (a-ii) above can be maintained after its removal.
 Unformed surfaces shall be protected, as soon as practicable after the initial
set has taken place, by either of the following means:
- by ponding the surface with at least 100 mm depth of water;

GKW - Alliance 47
SPECIFICATIONS
CIVIL WORKS

- by covering the surface with a layer of polythene sheet upon which shall
be placed a layer of sand of at least 50 mm thickness.

When the latter method of protection is adopted, the Contractor shall take appropriate
steps to ensure that no loss of sand is suffered through the action of wind; the
thickness of the sand layers shall be maintained at the specified minimum of 50 mm
at all times.

Whichever method of protection is adopted, the protection itself shall be kept shaded
from direct sunlight.

The Contractor shall provide the Engineer with details of the precautions he proposes to
take to protect the concrete from the effects of temperature build-up, and with details of the
methods he proposes to use to assess the correct timing at which such protection may be
removed. No concreting in large pours shall be put in hand until the proposed measures
have received the approval of the Engineer.

1.8.4.16 Test Blocks

Before commencing any large pour (as defined in the preceding clause) for a particular mix
of concrete, the Contractor shall construct three test blocks 2.0 m cube in size. The
temperature of the concrete at the time of casting the blocks shall not exceed 20C except
under hot conditions, when the requirements of Clause 4.9.5.14 will apply. The materials
used in making concrete for the test blocks, together with the reinforcement, formwork and
materials used for protecting the top surfaces, shall be of the same type and from the same
source as those intended for the large pour.

Two of the blocks shall be reinforced on two opposing sides and on the top face by 32 mm
diameter high yield reinforcing bars at 250 mm spacing in each direction. The cover to the
outer bars shall be 60 mm.

The Contractor shall ascertain the thermal characteristics of the cement and aggregates to
be used, from which he shall calculate the likely maximum rise in temperature of the
concrete. The data used shall be clearly indicated in the calculations which the Contractor
shall give to the Engineer before casting the blocks.

Thermometers shall be installed in the concrete near to the surface at the centre of each
face, with one placed centrally in the block. Temperatures shall be recorded at 6-hourly
intervals for a period of at least 7 days for each of the blocks.

Six 150 mm test cubes shall be taken during placement of concrete for each block, two for
testing at 7 days and four for testing at 28 days.

The test blocks shall be examined at regular intervals for cracks and a careful note shall be
made of any found during the first 28 days.

The test blocks shall be considered satisfactory if, for each of the blocks, all the following
conditions are met:

(i) The average strength of the four 28 day test cubes exceeds the specified 28 day
characteristic strength by at least 7.5 N/mm2;
(ii) The rise in temperature during hydration does not exceed 45C and the difference in
temperature between any face and the centre of the block does not at any stage
exceed 20C;

GKW - Alliance 48
SPECIFICATIONS
CIVIL WORKS

(iii) The nature of any cracks appearing is such that, in the opinion of the Employer’s
Representative, the cracks would not constitute a potential source of harm if they
were to occur in the Permanent Works.

If condition (i) above is not fulfilled, the Contractor shall redesign the concrete mix, construct
further test blocks, and repeat the testing as specified.

If condition (ii) is not fulfilled, or if under (iii) the Engineer is of the opinion that the cracks
as noted are potentially harmful, the Contractor may proceed with the casting of a large
pour only if he incorporates one or more of the following procedures in the concreting
operation:

 cool the mixing water/aggregate as set out in Clause 4.9.5.14;


 replace the 19 mm thick plywood formwork to formed faces with material having
better insulating properties;
 increase the surface protection to unformed faces.

If the Engineer so requires, the Contractor shall construct further test blocks to demonstrate
the efficacy of the measures which are being incorporated in the casting of the large pour.

1.8.4.17 Concrete Placed in Water

Where any concrete is to be placed in water, the Contractor shall submit detailed proposals
to the Engineer, and shall obtain his approval before commencing the work.

The quantity of cement in any concrete placed in water shall, if necessary, be increased so
that the free water/cement ratio of the mix is not more than 0.47.

Concrete shall not be placed in running water or be allowed to fall through water.

Concrete shall be placed in water only by means of a bottom-opening watertight box or a


tremie of a type approved by the Engineer. Bottom-opening boxes shall not be opened
until they are resting on the work, and the lower ends of tremies shall always be kept below
the surface of freshly placed concrete.

1.8.4.18 Compaction

Except as otherwise approved by the Engineer, concrete placed in situ shall be compacted
with power driven internal type vibrators supplemented by hand spading and tamping, and
shall be thoroughly worked around the reinforcement, tendons, duct formers and embedded
items, and into the corners of the formwork, so as to form a solid mass free of voids. The
vibrators shall at all times be adequate in number, amplitude and power to compact the
concrete properly and quickly throughout the whole of the volume being compacted. Spare
vibrators shall be readily on hand in case of breakdown.

Vibrators shall be inserted into the un-compacted concrete vertically and at regular
intervals. Where the un-compacted concrete is in a layer above freshly compacted
concrete, the vibrator shall be allowed to penetrate vertically for about 100 mm into the
previous layer. In no circumstances shall vibrators be allowed to come into contact with
the reinforcement or formwork nor shall they be withdrawn quickly from the mass of
concrete, but shall be drawn back slowly so as to leave no voids. Internal type vibrators
shall not be placed in the concrete in a random or haphazard manner nor shall concrete be
moved from one part of the work to another by means of the vibrators.

GKW - Alliance 49
SPECIFICATIONS
CIVIL WORKS

The duration of vibration shall be limited to that required to produce satisfactory compaction
without causing segregation. Vibration shall on no account be continued after water or
excess grout has appeared on the surface.

1.8.4.19 Attendance of Steel Fixer and Carpenter

The Contractor shall take adequate steps to ensure that reinforcement, ducts or duct
forming devices to house pre-stressing tendons, formwork and all embedded items are kept
in their correct position as concreting proceeds.

The Contractor’s arrangements for concreting shall include for a competent steel fixer and
a carpenter to be in attendance on the concreting gang, as and when required.

1.8.4.20 Curing of Concrete

Concrete shall be cured by being kept continuously moist throughout the curing period and
by protecting the newly cast surface from the effects of sunshine, drying winds, frost, rain,
running water or mechanical damage.

The curing shall be maintained for a continuous period of at least

 7 days when the cement used in the concrete is ordinary Portland cement;
 3 days when the cement used in the concrete is rapid hardening cement.

If, during the specified minimum period of curing, the average temperature of the concrete
falls below 10C, the period of curing shall be extended to allow for the concrete to reach
sufficient maturity. The period of extension shall be as directed by the Engineer.

The protection shall be applied as soon as practicable after completion of placing and shall
include one or more of the following methods, as may best suit the circumstances:

 by water sprays in continuous operation;


 by covering with hessian or similar absorbent material, or sand, kept constantly wet;
 after thorough wetting, by covering with a layer of waterproof fabric kept in contact
with the concrete surface;
 by the application of an approved coloured non-staining liquid curing membrane
which is either self-removing or easily removed following the curing period and which
has a 75% moisture retention standard. The liquid shall be applied to formed
surfaces immediately after stripping the formwork.

Liquid curing membranes shall not be used on Class U 1 surfaces, or where laitance is to
be removed and aggregate exposed to provide a satisfactory bond for placing further
concrete or mortar screeds, or where in the opinion of the Engineer the use of such a
membrane is likely to spoil the finished appearance of an exposed surface.

The Engineer may also prohibit the use of liquid curing membranes where their effect on
any retained liquid would make them unsuitable as curing agents.

Any concrete which, due to the Contractor’s failure to comply with requirements for curing,
is in the opinion of the Engineer likely to have been impaired shall forthwith be removed
from the Site and replaced.

GKW - Alliance 50
SPECIFICATIONS
CIVIL WORKS

1.8.4.21 Construction Joints

A construction joint is defined as a joint in the concrete introduced for convenience in


construction at which special measures are taken to achieve subsequent continuity without
provision for relative movement.

Construction joints shall be located so as not to impair the strength of the concrete.
Rebates, keys, or notches shall be formed and waterstops inserted as the Engineer may
require.

The position of construction joints and the size of the formwork panels shall be so co-
ordinated that, where possible, the line of any construction joint coincides with the line of a
formwork joint, and that in any case all construction joint lines and formwork joint lines
appear as a regular and uniform series.

For all exposed horizontal joints and purposely inclined joints, a uniform joint shall be
formed with a batten of approved dimensions to give a straight and neat joint line.

Concrete placed to form the face of a construction joint shall have all laitance removed and
the large aggregate exposed prior to the placing of fresh concrete. The laitance shall,
wherever practicable, be removed when the concrete has set but not hardened by spraying
the concrete surface with water under pressure, or brushing with a wire brush sufficient to
remove the outer mortar skin and expose the large aggregate without disturbing it. Where
the laitance cannot be removed due to hardening of the concrete, the whole of the concrete
surface forming the joint shall be treated by high pressure water jet, sand blasting, use of a
needle gun or a scaling hammer to remove the surface laitance. Before concreting is
resumed, all loose matter on the existing concrete surface shall be removed and the surface
slightly wetted.

Concrete shall not be allowed to run to a feather-edge and any vertical joints shall be formed
against a stop-end. If a kicker or stub-end is used it shall be at least 70 mm high.

No concreting shall be started until the Engineer has approved the positions and form of
the construction joints.

1.8.4.22 Dimensions and Surfaces of Finished Concrete

Workmanship in formwork and concreting shall be such that concrete shall normally require
no making good, surfaces being properly compacted and smooth. Concrete surfaces for
the various classes of unformed and formed finishes shall in any event never exceed the
maximum permitted tolerances stated in the Specification or, where not so stated, shown
in the Table below.

In the Table ‘line and level’ and ‘dimension’ shall mean the specified lines, levels and cross-
sectional dimensions.

Surface irregularities shall be classified as ‘abrupt’ or ‘gradual’. Abrupt irregularities include,


but shall not be limited to, offsets and fins caused by displaced or misplaced formwork,
loose knots and other defects in formwork materials, and shall be tested by direct
measurement. Gradual irregularities shall be tested by means of a straight template for
plane surfaces or its suitable equivalent for curved surfaces, the template being 3.0 m long
for unformed surfaces and 1.5 m long for formed surfaces.

GKW - Alliance 51
SPECIFICATIONS
CIVIL WORKS

Maximum Tolerance (mm) in:

Class Line Abrupt Gradual Dimensions


of Finish and Level Irregularity Irregularity

Ul  12 6 6 -

U2  6 3 3 -

U3  6 3 2 -

F1  12 6 6 + 12, - 6

F2  6 6 6 + 12, - 6

F3  3 3 3  6

1.8.4.23 Unformed Surfaces - Class of Finish

Finishes to unformed surfaces of concrete shall be classified as U1, U2, U3, ‘spaded’ or
‘bonded concrete’, or such other special finish as may be particularly specified. Where the
class of finish is not specified the concrete shall be finished to Class Ul.

Class Ul finish is the first stage for Class U2 and U3 finishes and for a bonded concrete
surface. Class Ul finish shall be a levelled and screeded, uniform plain or ridged finish,
which (unless it is being converted to Class U2, U3 or bonded concrete) shall not be
disturbed in any way after the initial set and during the period of curing, surplus concrete
being struck off immediately after compaction.

Where a bonded concrete surface is specified, the laitance shall be removed from the Class
Ul finish surface and the aggregate exposed while the concrete is still green.

A spaded finish shall be a surface free from voids and brought to a reasonably uniform
appearance by the use of shovels as it is placed in the Works.

Class U2 finish shall be produced by manual or mechanical floating of the concrete surface
after the initial set has taken place and the surface has hardened sufficiently. The concrete
shall be worked no more than is necessary to produce a uniform ‘sandpaper’ finish free
from screed marks.

Class U3 finish shall be a hard smooth steel-trowelled finish. Trowelling shall not
commence until the moisture film has disappeared and the concrete has hardened
sufficiently to prevent excess laitance from being worked into the surface. The surface shall
be trowelled under firm pressure and left free from trowel marks.

Cement, mortar or water shall not be added during any of the above operations.

1.8.4.24 Building in Pipes and Other Items

Pipes and other items passing through concrete structures shall, wherever practicable, be
built into the structure as work proceeds, having been installed and connected to the
remainder of the system to ensure proper fit before the start of any concreting.

GKW - Alliance 52
SPECIFICATIONS
CIVIL WORKS

Where this procedure cannot be adopted, holes shall be formed to allow such items to be
built in later, along with or after installation of the remainder of the system. Such holes shall
be of size and shape sufficient to permit proper placing and compaction of concrete or grout.
The surfaces of the holes shall be treated so as to bond with the later concrete.

All items to be built in shall be securely supported in their correct position so as to prevent
movement or damage during building-in. No pipe with flanged joints shall be concreted in
until its accurate fit with other pipework has been checked and it has been secured in
position.

Concrete used for building in shall be of the same grade as the surrounding concrete,
except that the mix shall incorporate an approved expanding agent used in accordance with
the manufacturer’s instructions. Cement/sand mortar or cement grout used for building-in
shall also incorporate an expanding additive. Concrete, mortar and grout shall be placed
and compacted by methods which will avoid moving or damaging built-in items.

1.8.4.25 Structural Precast Concrete

Structural units of precast concrete shall be manufactured in the required grade of concrete
and to the specified sizes. The concrete shall comply with the provisions of the
Specification whether such units are manufactured on the Site or obtained from
manufacturers approved by the Engineer.

Where the installation of precast concrete units in any structure is such that the faces or
the units are to be left exposed, either internally or externally, the exposed surfaces of the
units as finished shall be uniform in colour and in texture. All cement, aggregates and other
materials used in the manufacture of the units shall be obtained from the same approved
sources throughout the period of manufacture.

Formwork and unformed surfaces for precast concrete units shall comply with the
requirements for F3 formed surfaces and U3 unformed surfaces respectively.

The Contractor shall submit full details of his proposed method of carrying out all operations
connected with the manufacture and assembly of precast concrete structural members,
including:

 a description of the types of casting bed, mould and formwork for the various types
of members;
 the procedure for concrete casting and the method of curing the concrete;
 the procedure for transporting, handling, hoisting and placing of each type of precast
structural member;
 particulars of the temporary supports deemed necessary to ensure adequate stability
during erection and fully proof against the effects of construction loads, wind load and
other transient loads.

1.8.4.26 Dimensional Tolerances

Dimensions and shapes of precast concrete structural members shall comply with
tolerances given on the drawings or, when not so given, with those stated hereunder:

Length:

 not exceeding 3 m ± 6mm


 exceeding 3 mv, not exceeding 4.5 m ± 9 mm

GKW - Alliance 53
SPECIFICATIONS
CIVIL WORKS

 exceeding 4.5 m, not exceeding 6 m ± 12 mm


 additional for every subsequent 6 m ± 6 mm

Cross section (each direction):

 not exceeding 500 mm ± 6 mm


 exceeding 500 mm, not exceeding 750 mm ± 9 mm
 additional for every subsequent 250 mm ± 3 mm

Straightness or bow (deviation from intended line):

 not exceeding 3 m 6 mm
 exceeding 3 m, not exceeding 6 m 9 mm
 exceeding 6 m, not exceeding 12m 12 mm
 additional for every subsequent 6 m 6 mm

Squareness:

When considering the right angle of a corner the longer of the two adjacent sides being
checked shall be taken as the baseline, and a line perpendicular to the baseline shall be
taken as the check-line. The shorter side shall not vary in its distance from the check-line
so that the difference between the greatest and the shortest such distance exceeds the
following:

Length of shorter side:

 not exceeding 1.2 m 6 mm


 exceeding 1.2 m, not exceeding 1.8 m 9 mm
 exceeding 1.8 m 12 mm

For the purpose of this requirement, any error due to lack of straightness shall be ignored;
right angle shall be measured with respect to the straight lines which are most nearly
parallel with the features being checked. When the nominal angle is other than 90, the
included angle between the baseline and the check-line shall be varied accordingly.

Twist:

No corner of a nominally plane surface shall deviate from the plane containing the other
three corners by more than:

Surface Dimensions:

 not exceeding 600 mm wide an not exceeding 6 m long 6 mm


 exceeding 600 mm wide and for any length 12 mm

Flatness:

GKW - Alliance 54
SPECIFICATIONS
CIVIL WORKS

The deviation from a 1.5 m straight edge placed in any position on a nominally plane surface
shall not exceed 6 mm.

1.8.4.27 Installation of Precast Concrete Structural Members

At all stages and until completion of the Works, precast members shall be adequately
protected to preserve all permanently exposed surfaces, arises and architectural features.
The protection shall not mark or otherwise disfigure the concrete.

All units shall be laid, bedded, jointed and fixed in accordance with the detailed lines and
levels.

Dry-pack mortar jointing for packing shall consist of one part by volume of ordinary Portland
cement, and two parts by volume of fine aggregate passing a 1 mm sieve. The mortar shall
be mixed with only sufficient water to make the material stick together when being moulded
in the hands. The mortar shall be placed and packed in stages, where possible from both
sides of the space being filled, using a hardwood stick hammered until the mortar is
thoroughly compacted.

Any precast concrete structural member which is found to be cracked, damaged or


otherwise inferior in quality, either before or after erection, shall be rejected, and replaced
by the Contractor.

The Contractor shall submit for approval, his proposals for the following:

 Minimum time for handling and transportation;


 Position and design of lifting point;
 Method of lifting;
 Lifting equipment;
 Methods of supporting and stacking;
 Methods of assembly and erection;
 Accuracy of assembly and erection;
 Temporary support;
 Final structural connections;
 Method of protecting units from damage;
 Marking for identification;
 Preparation of contact surfaces;
 Removal of locating devices after erection.

1.8.4.28 Pre-stressed Concrete

Pre-stressed concrete work, whether precast or cast in situ, shall be as specified, and the
Contractor shall provide full details of his proposals for carrying out all operations connected
with pre-stressing including:

 Design of concrete mix;


 Description of concrete casting and curing operations;
 Procedure for pre-stressing and method of checking and recording the pre-stress,
wire extension and anchorage slip;
 Procedure for handling, hoisting and placing of any precast units;

GKW - Alliance 55
SPECIFICATIONS
CIVIL WORKS

 Grouting of ducts.

All tendons, duct forming devices, anchorages and other components shall be kept clean,
dry and free of oil (except for water soluble oil applied for protection). They shall be placed
with a tolerance of 3 mm in concrete dimensions of 300 mm or less or 5 mm in concrete
dimensions over 300 mm.

The bearing surfaces between anchorages and concrete shall be perpendicular to and
concentric with the tendons and the line of action of the pre-stressing force.

No grouting of ducts shall take place when the surface temperature of the member is below
5ºC, or is likely to fall below 5ºC during the 48 hours following placement.

1.8.4.29 No-fines Concrete

No-fines concrete shall be made using a coarse aggregate conforming with the applicable
standard and cement to the applicable standard. No fine aggregate shall be used. The
grading of the coarse aggregate shall be not less than 95% by weight passing a 20 mm
B.S. sieve; and not more than 5% by weight passing a 10 mm B.S. sieve. The proportion
of aggregate, cement and water shall be determined in trial mixes by the Contractor starting
with a cement - aggregate ratio of 1:8 by volume. The trial mix shall be considered suitable
when all the aggregate particles are coated with a film of cement grout. The water content
shall be just adequate to ensure that the cement paste completely coats the aggregate.
The concrete when placed shall contain no layers of laitance.

No-fines concrete shall not be mixed by hand.

Vibration shall not be used to compact the concrete. Three test cubes of no-fines concrete
shall be made of each trial mix. The minimum crushing strength of the chosen mix shall be
3N/mm² at 28 days.

1.8.4.30 Precast Concrete Products

Precast concrete products (kerbs, flags, window sills, masonry units, etc.) shall, where
appropriate, be manufactured in accordance with the applicable standard as follows.

Units shall be hydraulically pressed wherever possible.

The concrete shall comply with the Specification whether such products are manufactured
on Site or obtained from manufacturers approved by the Engineer.

1.8.4.31 Installation of Precast Concrete Products

Mortar for bedding and jointing units shall consist of one part by volume of ordinary Portland
cement, and two parts by volume of natural sand or crushed stone to the grading of the
applicable standard.

1.8.5 Testing

1.8.5.1 Sampling and Testing of Aggregates

GKW - Alliance 56
SPECIFICATIONS
CIVIL WORKS

The Contractor shall take samples of all aggregates and test them for grading, by the
methods described in the applicable standard, at least once in each week when concreting
is in progress and additionally as the Engineer may require.

Whenever the source of aggregate is changed and, in any case at least once per month,
the Contractor shall carry out tests on aggregates relating to water absorption, potential
alkali reaction, chloride content, sulphate content and shrinkage characteristics, all as
specified.

1.8.5.2 Sampling and Testing of Concrete

The Contractor shall provide the necessary equipment and shall determine the compacting
factor of the freshly mixed concrete by the method described in the applicable standard on
each occasion that a set of test cubes is made and at such other times as the Engineer
may direct.

For each grade of concrete (except Strength Class C8/10) works test cubes shall be made
whenever required by the Engineer, but not less frequently than as follows, unless
otherwise particularly specified:

 Strength Class C30/37 : one set of cubes per 50 m³, or part thereof,
concreted per day.
 Strength Class C25/30 : one set of cubes per 100 m³, or part thereof,
concreted per day
 Strength Class C 20/25 : one set of cubes per 100 m³, or part thereof,
concreted per day

Each set of cubes (three cubes per set) shall be made from a single sample taken from a
randomly selected batch of concrete. One cube shall be tested 7 days after manufacture
and two cubes 28 days after manufacture. The average of the two 28-day results shall be
taken as the test result.

Where concrete of a particular grade is likely to be placed infrequently, and the above rates
of sampling might not produce sufficient representative test cubes to enable the concrete
quality to be monitored properly, the Contractor shall increase the number of standard
samples taken during each day when concrete of that grade is being placed so as to ensure
that enough representative test cubes are obtained.

1.8.5.3 Compliance with Specified Requirements

The concrete shall be deemed satisfactory if the conditions given in both (i) and (ii) are met:

(i) The average 28-day strength determined from any group of four consecutive test
cubes exceeds the specified characteristic strength by not less than 2 N/mm 2 for
grade 15 concrete and 3 N/mm2 for grades 20 and above;
(ii) The strength determined from any test result does not fall short of the specified
characteristic strength by more than 2 N/mm2 for grade 15 concrete or 3 N/mm2 for
grades 20 and above.

If only one cube result fails to meet the second requirement, that result may be considered
to represent only the particular batch of concrete from which the cube was taken, provided
that the average strength of the group satisfies the first requirement.

GKW - Alliance 57
SPECIFICATIONS
CIVIL WORKS

If more than one cube in a group fails to meet the second requirement, or if the average
strength of any group of four consecutive test cubes fails to meet the first requirement, then
all the concrete in all the batches represented by such cubes shall be deemed not to meet
the strength requirements.

1.8.5.4 Action in the Event of Failure to Meet Requirements

When concrete of a particular design of mix does not meet the strength requirements set
out in Clause 4.9.6.3, no further concrete from that mix shall be placed in the work and the
Contractor shall establish the cause of the failure and apply such remedies as are
necessary. The Contractor shall revise the mix accordingly and demonstrate by trial mixes
and test cube results that the revised mix meets the specified requirements.

The Contractor shall within 24 hours of the date of test make proposals for approval by the
Engineer for action to be taken in respect of any concrete represented by test cubes which
fail to meet the foregoing requirements. These proposals may include, but shall not be
limited to, cutting and testing cores. In the absence of such approved proposals the
Engineer will instruct the Contractor regarding the action to be taken.

1.8.5.5 Cutting and Testing of Core Samples

For the examination and testing of hardened concrete, cylindrical core specimens of 150
mm nominal diameter shall be cut from it, as and where directed by the Engineer. They
shall be cut perpendicular to the face. The preferred ratio of length to diameter shall be 2.
The procedure for drilling, examination, measurement and testing for compressive strength
shall be in accordance with the applicable standard. Before preparation for testing, the
specimen shall be made available for examination by the Engineer. If the estimated in-situ
cube strength of the specimen determined in accordance with the applicable standard is
less than the specified characteristic strength at 28 days, or if in the opinion of the Engineer
the concrete fails to meet the Specifications in other respects, the concrete in that part of
the Works of which it is a sample shall be deemed not to comply with the Specification.

1.8.5.6 Action in the Event of Concrete not Complying

Concrete which is found not to comply with the Specification shall be rejected and shall be
broken out and replaced or otherwise dealt with as directed by the Engineer.

1.8.5.7 Contractor Responsible for Testing

In addition to any specific obligations for sampling and testing, the Contractor shall be
responsible for routine inspection sampling and testing of concrete, materials, measuring
devices and plant, in order to control the quality of work and to ensure compliance with the
Specification including conformity with approved samples.

If the Contract provides for a laboratory and testing equipment for the use of the Engineer's
staff, the Contractor shall be allowed reasonable opportunity to use them for quality control.
In the absence of such provision the Contractor shall himself provide all necessary test
equipment.

GKW - Alliance 58
SPECIFICATIONS
CIVIL WORKS

1.8.6 Particular Requirements

1.8.6.1 Testing of Concrete Structures Designed to Retain Aqueous Liquid

After cleaning, and as far as practicable and as far as design requirements permit, before
any earth or other filling is placed against the outside wall faces, concrete structures
designed to retain an aqueous liquid shall be filled with water at a uniform rate of not greater
than 2 m in 24 hours. A period of 21 days shall be allowed by the Contractor for stabilisation,
after which the water level shall be recorded by approved means at 24 hour intervals for a
test period of 7 days. During the test period the total permissible drop, after allowing for
evaporation and rainfall, shall not exceed 1/500 of the average water depth of the full tank
or l0 mm, whichever is the less.

Notwithstanding the satisfactory completion of the above test, any leakage visible on the
outside faces of the structure shall be stopped. Any caulking or making good of cracks in
the wall section shall, where practicable, be carried out from the inside face.

1.9 Concrete Jointing and Protection

1.9.1 Scope

1.9.1.1 Coverage

This Section includes requirements for joints in concrete and surface protection of concrete
by membranes against groundwater and the salts which may be dissolved therein.

1.9.1.2 Definitions

The following terms shall have the meaning hereby assigned to them:

Construction joint A joint in the concrete introduced for convenience in


construction at which special measures are taken to achieve
subsequent continuity without provision for further relative
movement.

Movement joint A joint in the concrete intended to accommodate relative


movement between adjoining parts of a structure.

Expansion joint A movement joint intended to accommodate expansion and


contraction of the concrete without restraint.

Contraction joint A movement joint intended to accommodate contraction of


the concrete without constraint, in the case of a complete
contraction joint, or with some constraint, in the case of a
partial contraction joint.

Induced contraction joint A contraction joint formed not by using a temporary stop end,
but by reducing the depth of the concrete section by at least
25%.

1.9.2 Submissions by the Contractor

Submissions which the Contractor is required to make in relation to concrete jointing and
protection include, where relevant, the following:

GKW - Alliance 59
SPECIFICATIONS
CIVIL WORKS

1.9.2.1 Data

 Types of material and their properties.


 Manufacturers’ catalogues.
 Manufacturers’ proposals for choice and application of products with details of the
joint geometry where applicable and the allowable movement accommodation factor.
 Manufacturers’ recommendations for storage handling, and installation of products,
including where relevant:
- extent of allowable movements of joints;
- design life, and
- method of fixing during installation.

When required by the Engineer, details of previous successful applications of the material
offered.

Submissions shall be in accordance with the Specification but, where the Contractor
considers that a departure from the Specification will benefit the work, he shall make an
additional submission, drawing attention to the points of departure. Such departures
require the express approval of the Engineer.

1.9.2.2 Drawings

Full-scale dimensioned drawings of waterstop cross sections.

1.9.2.3 Samples

Where required by the Engineer, samples of materials for inspection or independent testing
or both.

1.9.2.4 Certificates

Manufacturers’ and suppliers’ certificates of compliance with relevant standards. Such


certificates shall state the results of tests carried out.

1.9.3 Materials

1.9.3.1 Materials Generally

Materials for concrete jointing and protection shall be obtained from manufacturers
approved by the Engineer. Unless otherwise approved, all materials for concrete jointing
and protection which are in contact with each other or jointed together to form a jointing
and/or protective system shall be obtained from a single manufacturer.

All materials for concrete jointing and protection which may come into contact with one
another shall be compatible with each other. They shall not cause any change in properties
of the materials with which they are in contact which may make them unsuitable for use in
concrete jointing or protection, or which may reduce the working life of joints or protection.

The Contractor shall supply manufacturers’ test sheets to certify compliance of all jointing
and protection materials with relevant quality standards. Where there is no relevant quality
standard, the Contractor shall prove by demonstration tests or otherwise the suitability,

GKW - Alliance 60
SPECIFICATIONS
CIVIL WORKS

adequacy and performance of the material under Site conditions. Only such materials as
have been approved by the Engineer shall be used in the Works.

1.9.3.2 Materials in Contact with Potable Water

No substance or product which could impart toxicity, taste, odour or colour to water or be
otherwise objectionable on health grounds shall be used in the Works where it may be
applied to or introduced into water which is to be supplied for drinking, washing or cooking.

1.9.3.3 Materials in Contact with Sewage

Materials which may come into contact with sewage shall not be susceptible to chemical or
biological attack, and shall retain their specified properties.

1.9.3.4 Waterstop

Waterstop shall be of the following types, or as specified elsewhere:

 rubber or PVC waterstop for use within the thickness of the concrete member;
 PVC waterstop for use on the outer face of the concrete member.

Waterstop shall be dense, homogeneous and free of holes or other imperfections. The
cross section shall be uniform along the length and symmetrical transversely so that the
thickness at any given distance from either edge‚ will be uniform. Where not otherwise
specified:

 the width of the waterstop shall be not less than 80% of the thickness of the concrete
section and not less than 250 mm;
 the web thickness shall be not less than 9 mm in the case of waterstop for use within
the concrete thickness or 5 mm in the case of waterstop for use on the outer face;
 all waterstop shall incorporate a solid bulb or major rib at or near each edge;
 waterstop wider than 180 mm which is for use on the outer face shall incorporate a
total of at least two major ribs each side of the centreline;
 waterstop at movement joints shall incorporate a central hollow bulb;
 waterstop for use at induced contraction joints shall incorporate a crack inducer.

Rubber waterstop shall be of natural rubber, suitable synthetic rubber, or a blend of the two.
PVC waterstop shall be of an elastomeric plastic compound; no reground material shall be
used.

Waterstop shall have the following properties when tested at 25ºC:

PROPERTY RUBBER PVC

Minimum tensile strength (N/mm2) 20 13.75

Minimum elongation at break (%) 450 280

Hardness (Shore ‘A’) 60-70 70-80

Softness - 42º-52º

GKW - Alliance 61
SPECIFICATIONS
CIVIL WORKS

Specific gravity 1.05-1.15 -

All intersections and junctions in waterstop shall be factory produced by the manufacturer
of the waterstop, normally as moulded special pieces, so that the only joints remaining to
be made at Site shall be straight butt joints between straight lengths of waterstop of the
same section and material.

1.9.3.5 Joint Filler and Capping Strip

Joint fillers shall be preformed, compressible and resilient and shall comply with all relevant
requirements of this clause, except where alternative requirements are specified or
specifically approved by the Engineer.

Bitumen impregnated joint fillers of fibre or cork shall comply with ASTM D 1751.

Resin bonded cork or self expanding cork joint filler shall comply with ASTM D 1752.
Sponge rubber joint fillers shall also comply with ASTM D 1752 except that the load required
to compress the test specimen to 50% of its initial thickness shall not exceed 0.5 N/mm2.

Joint fillers of closed-cell polyethylene or polyvinyl foam shall, when tested in accordance
with ASTM D 545, have the following properties:

 the load required to compress the test specimen to 50% of its thickness before test
shall be no less than 0.13 N/mm2 nor greater than 0.3 N/mm2;
 10 minutes after release of the compressive load (or 1 hour if the re-test provision
applies) the test specimen shall have recovered not less than 80% of its initial
thickness.

Joint filler for use in joints which may be submerged shall be of closed-cell polyethylene or
self expanding cork.

Joint filler for use in joints across which little load needs to be transferred shall be of sponge
rubber, closed-cell polyethylene or polyvinyl foam.

Capping strip to joint filler shall be of grey plasticised PVC complying with Clause 4.10.4.4,
formed to shape and sized for use with the appropriate thickness of joint filler.

1.9.3.6 Joint Sealant

Joint sealant shall be one of the following types or as specified elsewhere:

 polysulphide-based sealant complying with the applicable standard, having a


movement accommodation factor of at least 25% and a minimum service life
expectancy of 15 years;
 synthetic rubber based on polysulphide, having a movement accommodation factor
of at least 10% and a minimum service life expectancy of 15 years;
 approved proprietary product formulated from chemically resistant elastomeric
polymers, having a movement accommodation factor of at least 20% and a minimum
life expectancy of 15 years;
 rubber-bitumen compound, having a movement accommodation factor of at least
10% and a minimum service life expectancy of 10 years;

GKW - Alliance 62
SPECIFICATIONS
CIVIL WORKS

 approved bituminous putty proprietary product, having a movement accommodation


factor of at least 10% and a minimum life expectancy of 10 years.

Where not otherwise specified herein, sealant shall be selected in accordance with the
applicable standard.

Sealant shall be non-degradable under the prevailing conditions. Where sealant will be in
contact with sewage, the Contractor shall submit for the Engineer's approval evidence that
the proposed product will resist aerobic and anaerobic attack.

1.9.3.7 Back-up Material, Bond Breaker and Primer

Back-up material inserted in a joint to limit the depth of sealant (where joint filler does not
serve this purpose) shall comprise closed-cell low-density compressible joint filler
preformed for the purpose or such other material as is recommended for this use by the
sealant manufacturer and approved by the Engineer.

Bond breaker installed behind joint sealant shall be thin self-adhesive polyethylene tape.
Where the sealant manufacturer recommends the use of primer before the application of
sealant, it shall be provided by the sealant manufacturer for the purpose.

1.9.3.8 Slip Membrane

Slip membrane for use in a two-layer separating membrane at sliding joints shall consist of
plastic sheet not less than 1.5 mm thick which shall have a coefficient of friction not
exceeding 0.2 between rubbing surfaces, when used in accordance with the manufacturer’s
instructions and subjected to a lead of 0.27 N/m2.

1.9.3.9 Bituminous Paint

Bond breaking paint for use on concrete or steel reinforcement shall be bituminous paint
complying with the relevant provisions, as appropriate.

1.9.3.10 Dowel Caps

Where dowels of steel reinforcement are used for bridge expansion joints, the dowel to one
side of the joint shall be painted with 2 coats of bituminous paint and the end of the dowel
shall be fitted with a dowel cap. The cap shall comprise a cardboard or plastic tube which
is a free fit on the dowel and which is filled with joint filler for a part of its length not less than
the thickness of the joint filler in the joint.

1.9.3.11 Protective Membrane Systems

Membrane for the protection of concrete from salts presents in groundwater shall be flexible
self-adhesive impervious composite sheeting of total thickness not less than 1.5 mm,
consisting of either:

 a sheet not less than 0.25 mm thick of cross-laminated polyethylene or PVC, and a
rubber-bitumen compound, or
 a bituminous sheet and a polyester surface film.

GKW - Alliance 63
SPECIFICATIONS
CIVIL WORKS

Membrane for the exclusion of groundwater or the retaining of an aqueous liquid shall
comply with the applicable standard and shall be flexible self-adhesive impervious
composite sheeting of total thickness not less than 1.5 mm, consisting of either:

 a sheet not less than 0.30 mm thick of cross-laminated polyethylene or PVC, and a
rubber-bitumen compound, or
 Polyester-reinforced bituminous felt.

Primer for membrane and other sundry materials for forming fillets, up-stands and chamfers
shall be fully compatible with the membrane material.

1.9.4 Workmanship

1.9.4.1 Storage of Materials

All materials for concrete jointing and protection shall be stored under weatherproof cover.
Any storage conditions recommended by the manufacturer of any materials for concrete
jointing and protection shall be observed.

Materials shall be used in order of delivery from the manufacturer and shall not be used
after the expiry of any storage life recommended by the manufacturer.

1.9.4.2 Waterstop

Each waterstop system shall be made up of straight lengths of waterstop and factory-
produced intersections and junctions, jointed together so as to form a continuous
impermeable barrier.

No joints shall be made at Site except straight butt joints between lengths of waterstop of
identical section and material, made by heat fusion or hot vulcar used in accordance with
the waterstop manufacturer's instructions and using jigs, tools and equipment provided by
him.

Waterstop shall not be stretched or kinked during handling or installation. It shall be fixed
using only such methods as are approved by the Engineer for the section being fixed. It
shall be positioned in accordance with the manufacturer’s recommendations and shall not
be in contact with reinforcement or built-in items. The concrete shall be properly compacted
around it so that no voids or porous areas remain.

Unless otherwise approved, waterstop shall not be bent more sharply than:

 a radius equal to its width, viewed ‘on edge’, or


 15 m radius in the plane of the waterstop.

1.9.4.3 Joint Filler and Capping Strip

Joint fillers employed to form and fill expansion joints, shall have the same nominal
thickness as the joint width specified, and shall extend through the full thickness of the joint
not occupied by other jointing materials.

The joint filler shall be fixed by dabs of adhesive to the surface of the first placed concrete
forming one side of the joint. Alternatively, the joint filler shall be placed against the
formwork on the concrete side of the first pour. The latter method shall be used when the

GKW - Alliance 64
SPECIFICATIONS
CIVIL WORKS

joint filler edge is to be finished with capping strip. In that case, joints between lengths of
capping strip shall be made by heat fusion and the capping strip pushed firmly over the
edge of the joint filler which shall be accurately pre-cut.

Where sealant is required, the recess or caulking groove to receive it may be formed by the
use of removable forms or where appropriate by cutting back the filler to the required depth,
the filler being incised upon installation to facilitate this.

1.9.4.4 Joint Sealing

The caulking groove to accept sealant shall be formed to the specified dimensions or
recommended by the sealant manufacturer and approved by the Engineer. After the
concrete has cured and dried out, the bonding faces of the caulking groove shall be first
grit blasted or wire brushed and then vacuum cleaned to remove all dirt, surface laitance
and dust. The adjacent areas shall also be thoroughly vacuum cleaned to reduce the risk
of cleaned caulking grooves becoming contaminated.

Any wet or damp areas shall be allowed to dry out, or where necessary, shall be dried out
before joint sealing materials are applied.

Where back-up material is required it shall be at least 20% wider than the joint and shall be
placed accurately in position to define the required depth of sealant.

The back of the caulking groove, whether of concrete or joint filler, shall be covered by bond
breaker tape except where the joint sealant is to be applied hot, or where the caulking
groove forms part of a structural hinge joint.

The sides of the caulking groove shall be primed where appropriate in accordance with the
joint sealant manufacturer’s instructions.

On permanently exposed areas of structures, joint sealing is to be carried out with the aid
of masking tape to form neatly defined surface limits to the seal.

Should sealant suffer any failure, it shall be replaced after the possible causes of failure
have been investigated and the appropriate remedial action has been taken.

1.9.4.5 Slip Membrane

Surfaces to receive slip membrane shall be smooth, plane and clean. Concrete surfaces
shall be Class U3 finish.

Two layers of slip membrane shall be cut to size and fastened together along all edges
using masking tape. The complete assembly shall then be placed and fixed in position in
accordance with the manufacturer’s instructions.

1.9.4.6 Bituminous Painting

Where specified, concrete surfaces or reinforcement shall be painted with two coats of
bituminous paint. Concrete surfaces to be painted shall be of Class F2 finish, smooth,
plane, clean and dry. New concrete shall not be placed against the painted surface until
the paint is dry.

GKW - Alliance 65
SPECIFICATIONS
CIVIL WORKS

1.9.4.7 Protective Membrane

All concrete to which protective membrane is to be applied shall be of Class U2 or F2 finish,


free from sharp protrusions and hollows. External angles shall be chamfered. All surfaces
shall be clean and dry. Except for horizontal blinding concrete, all concrete to receive
membrane shall be primed in accordance with the membrane manufacturer’s instructions.

One complete layer of protective membrane shall be applied in accordance with the
manufacturer’s instructions with laps of not less than 150 mm at all joints. All corners shall
receive two layers of membrane either by use of an additional reinforcing strip of membrane
not less than 300 mm wide or by carrying each overlapping membrane at least 150 mm
beyond the corner to provide an overlap not less than 300 mm wide. Internal angles shall
have approved fillets installed to facilitate proper dressing of the protective membrane with
the corner.

Chamfers and fillets shall be not smaller than 25  25 mm.

1.10 Formwork and Reinforcement for Concrete

1.10.1 Scope

This Section contains requirements which, where relevant to this Contract, shall apply to
formwork and reinforcement for concrete.

1.10.2 Submissions by the Contractor

Submissions required from the Contractor in relation to formwork and reinforcement shall
include the following, where relevant:

 calculations for, and design and layout of formwork;


 manufacturers’ data on accessories and mechanical couplings;
 manufacturers’ test certificates for each delivery of steel reinforcement and pre-
stressing steel tendons as required by the relevant quality standard;
 details of proposed welding procedures and welders’ qualifications;
 test certificates for mechanical couplings;
 samples of steel reinforcement for testing.

1.10.3 Formwork

1.10.3.1 Materials for Formwork

Formwork shall be constructed of timber, sheet metal or other approved material.

Ties shall be of the rod and cone or other approved proprietary type.

Ties for use in water-retaining structures 300 mm thick or less shall incorporate a diaphragm
not less than 50 mm dia. welded to the mid-point of the tie, designed to prevent water
passing along the tie.

1.10.3.2 Design and Layout of Formwork

GKW - Alliance 66
SPECIFICATIONS
CIVIL WORKS

The design and construction of formwork shall take account of safety and of the surface
finish required. The formwork shall be sufficiently rigid and tight to prevent loss of grout or
mortar from the fresh concrete or the formation of fins or other blemishes on the concrete.
The Contractor shall appoint a False-work Co-ordinator to carry out on behalf of the
Contractor the duties.

Formwork and its supports shall maintain their correct shape and profile, so that the final
concrete structure is within the limits of the specified dimensional tolerances. They shall be
designed to withstand the worst combination of self-weight, reinforcement weight, wet
concrete weight, concrete pressure, construction and weather loads, together with all
incidental dynamic effects caused by placing, vibrating and compacting the concrete.
Formwork shall not be tied to or supported by the reinforcement.

On formwork to external faces which will be permanently exposed, all horizontal and vertical
formwork joints shall be so arranged that joint lines will form a uniform pattern on the face
of the concrete. Where the Contractor proposes to make up the formwork from standard
sized manufactured formwork panels, the size of such panels shall be subjected to the
approval of the Engineer before they are used in the construction of the Works. The finished
appearance of the entire elevation of the structure and adjoining structures shall be
considered when planning the pattern of joint lines caused by formwork and by construction
joints to ensure continuity of horizontal and vertical lines.

1.10.3.3 Erection of Formwork

Faces of formwork in contact with concrete shall be free from adhering foreign matter,
projecting nails and the like, splits or other defects, and all formwork shall be clean and free
from water, dirt, or other foreign matter.

Except where the surface is subsequently to be rendered, formwork in contact with the
concrete shall be treated with a suitable non-staining release agent before the steel is fixed
or the concrete placed to prevent of the concrete adhering to it. Care shall be taken to
prevent the release agent from touching the reinforcement or concrete at construction
joints. Surface retarding agents shall not be used unless specified.

All exposed exterior angles on the finished concrete of 90º or less shall be given 20 mm
by 20 mm chamfers.

Formwork shall be provided for the top surfaces of sloping work where the slope exceeds
fifteen degrees from the horizontal unless otherwise specified, and shall be anchored so
that the concrete can be properly compacted and to prevent flotation. Care shall be taken
to prevent air being trapped.

Where ties are built into the concrete for the purpose of supporting formwork, part of any
such supports shall be capable of removal so that no part remaining embedded in the
concrete shall be within 50 mm off the surface in the case of reinforced concrete or 150 mm
in the case of un-reinforced concrete. Holes left after removal of such supports shall be
neatly filled with epoxy or well rammed dry-pack mortar.

Openings for inspection of the inside of the formwork, for the removal of water used for
washing down and for placing concrete shall be provided and so formed as to be easily
closed before or during placing concrete. Before placing concrete all bolts, pipes or
conduits or any other fixtures which are to be built in shall be fixed in their correct positions,
and cores and other devices for forming holes shall be held fast by fixing to the formwork
or otherwise. Holes shall not be cut in any concrete without prior approval of the Engineer.

GKW - Alliance 67
SPECIFICATIONS
CIVIL WORKS

1.10.3.4 Removal of Formwork

Formwork shall be so designed as to permit easy removal without resorting to hammering


or levering against the surface of the concrete.

The periods of time elapsing between the placing of the concrete and the striking of the
formwork shall have regard to the following factors:

 concrete strength;
 stresses in the concrete during construction including for precast units any
disturbance and handling stresses;
 curing;
 subsequent surface treatment requirements;
 the presence of re-entrant angles requiring early removal of formwork to avoid
thermal cracking.

The time shall be as approved by the Engineer, after consideration of the loads likely to be
imposed on the concrete, and shall in any case be not less than the periods shown in the
following table.

MINIMUM PERIOD BEFORE STRIKING FORMWORK (CONCRETE MADE WITH


ORDINARY OR SULPHATE-RESISTING PORTLAND CEMENT)
MINIMUM PERIOD BEFORE STRIKING
TYPE OF FORMWORK SURFACE TEMPERATURE OF CONTRETE (t°C)
Between 0°C and 15°C 15°C and above
Vertical formwork to
columns, walls and 300 hours 12 hours
large beams t + 10
Soffit formwork to slabs 100 days 4 days
t + 10
Soffit formwork to beams 250 days 10 days
and props to slabs t + 10
Props to beams 350 days 14 days
t + 10

Any time during which the temperature remains below freezing point shall be added to the
above times.

Notwithstanding the foregoing, the Contractor shall he held responsible for any damage
arising from removal of formwork before the structure is capable of carrying its own weight
and an incidental loading.

1.10.3.5 Formed Surfaces – Class of Finish

Finishes to formed surfaces of concrete shall be classified as F1, F2 or F3, or such special
finish as may be specified. Where the class of finish is not specified the concrete shall be
finished to class F1.

Formwork for Class F3 finish shall be lined with panels of non-staining material with a
smooth unblemished surface such as sanded plywood or hard compressed fibre board. The

GKW - Alliance 68
SPECIFICATIONS
CIVIL WORKS

panels shall be as large as possible, and shall be arranged in a uniform approved pattern
and fixed to back formwork by oval nails. Un-faced wrought boarding or standard steel
panels will not be permitted.

Formwork for Class F2 finish shall be faced with wrought tongued and grooved boards or
plywood or metal panels arranged in a uniform approved pattern and free from defects likely
to detract from the appearance of the surface.

Formwork for Class Fl finish shall be constructed of timber, sheet metal or any suitable
materials which will prevent loss of grout when the concrete is vibrated. Surfaces
subsequently to be rendered plastered or tiled shall be adequately roughened as soon as
the formwork is removed to reduce any irregularities to not more than half the thickness of
such rendering, plastering or bedding for tiles and to provide a satisfactory key.

1.10.3.6 Defects in Formed Surfaces

Workmanship in formwork and concreting shall be such that concrete shall normally require
no making good, surfaces being perfectly compacted and smooth.

An minor surface blemishes shall be repaired to the satisfaction of the Engineer


immediately after removal of formwork. Remedial measures may include, but shall not be
limited to, the following:

 Holes left by formwork supports shall be thoroughly cleaned out to remove all loose
material and the sides shall be roughened, if necessary to ensure a satisfactory bond.
They shall then be filled with epoxy or dry-pack mortar.
 Fins, pinhole bubbles, surface discolouration and minor defects may be rubbed down
with sacking and cement immediately the formwork is removed.
 Abrupt and gradual irregularities may be rubbed down with carborundum and water
after the concrete has been fully cured.
 Small defects and minor honeycombing shall be chipped out perpendicular to the
face of the concrete to a depth of at least 25 mm and filled with epoxy or dry-pack
mortar.

Where deeper or more extensive defects occur, the Contractor shall obtain the approval of
the Engineer to the methods of repair proposed which may include, but shall not be limited
to, cutting out to a depth of at least 25 mm with a diamond saw to give a regular edge to
the repair and further chipping to form a hole with undercut edges to sound concrete or to
a total depth of 75 mm whichever is the greater. If reinforcing steel is exposed, the concrete
shall be removed to a depth of 25 mm beyond the back side of the reinforcement. Steel
mesh reinforcement shall then be sprung into the hole, which shall be refilled with concrete
or suitable epoxy resin mortar.

The Contractor shall thoroughly clean any hole, pores or defective area that is to be filled
and break out any loose, broken or cracked concrete or aggregate.

Where the remedial work is to be carried out using dry-pack mortar or concrete, the
concrete surrounding the hole shall be thoroughly soaked after which the surface shall be
dried so as to leave a small amount of free water on the surface. The surface shall then be
dusted lightly with cement by means of a small dry brush until the whole surface that will
come into contact with the dry-pack mortar has been covered and darkened by absorption
of the free water by the cement. Any dry cement in the hole shall be removed.

Dry-pack mortar shall be mixed and placed as specified.

GKW - Alliance 69
SPECIFICATIONS
CIVIL WORKS

Where concrete is to be used, the concrete mix shall be subject to the approval of the
Engineer and shall be placed and compacted into the hole, using formwork as necessary.

Where the remedial work is to be carried out using epoxy resin mortar or other special
material, the surface of the cleaned hole shall be prepared and primed and the repair
material placed, compacted and finished in accordance with the manufacturer’s
instructions.

Where, in the opinion of the Engineer the defect is too extensive to permit satisfactory
repair, either from the point of view of structural integrity or appearance, the concrete
containing the defect shall be broken out and replaced.

1.10.3.7 Dry-pack Mortar

Dry-pack mortar for filling holes and repairing surface blemishes shall be made from one
part by weight of cement and three parts fine aggregate passing a 1 mm sieve. The colour
of the mortar shall match that of the surrounding concrete. The mortar shall be mixed with
just sufficient water to make the materials stick together when being moulded in the hands.

The dry-pack material shall be placed and packed in layers having a thickness not greater
than 15 mm. The compaction shall be carried out by use of hardwood stick and hammer
and shall extend over the full area of the layer, particular care being taken to compact the
dry-pack against the sides of the hole. After compaction the surface of each layer shall be
scratched before further loose material is added. Holes shall not be over filled and the
surface shall be finished by laying a hardwood block against the dry-pack fill and striking
the block several times. Steel finishing tools shall not be used and water shall not be added
to facilitate finishing.

1.10.4 Reinforcement

1.10.4.1 Steel Reinforcement

Steel for reinforcement shall be of the following kinds, as may be specified:

Type R - hot rolled plain round mild steel bars


Type T - Either hot rolled deformed high yield steel bars. Such bars shall be
of weldable quality with a cast analysis giving a carbon equivalent
not exceeding 0.51 per cent.
- Or cold worked deformed high yield steel bars.
Fabric - Welded hard drawn steel wire and other cold worked high bond bar
fabric.

1.10.4.2 Pre-stressing tendons

Pre-stressing steel wire or bar shall be of the following kinds as specified:

 Cold drawn wire or cold drawn and stress relieved wire conforming with the applicable
standard;
 Stress relieved seven-wire strand conforming with the applicable standard;
 Hot rolled and hot rolled and processed high tensile alloy steel bars conforming with
the applicable standard.

GKW - Alliance 70
SPECIFICATIONS
CIVIL WORKS

1.10.4.3 Accessories

Spacer blocks for maintaining concrete cover to reinforcement shall be of concrete of the
same strength, durability, porosity and appearance as the in-situ concrete. They shall be
cast in the form of a truncated cone or pyramid with the smaller face having a minimum
dimension of 50 mm.

Chairs and other accessories for maintaining reinforcement and pre-stressing tendons in
position shall be of steel.

Binding wire shall be No. 16 gauge (1.60 mm) soft iron wire.

1.10.4.4 Cutting and Bending of Reinforcement

Bars shall be bent in accordance with the provisions of the applicable standard. Bending
shall be carried out slowly, at a steady even pressure, without jerk or impact. The
temperature of the steel at the time of bending shall be not less than 5ºC. Hot bars shall
not be cooled by dowsing with water. Bent bars shall not be re-bent unless permitted by
the Employer’s Representative.

1.10.4.5 Storage of Reinforcing Bars and Steel Fabric

The Contractor shall stack separately and label different types of reinforcement for positive
identification.

Reinforcement shall not be subjected to mechanical damage or shock loading prior to


embedment.

Steel reinforcing bars shall be kept clean and shall be free from pitting, loose rust, mill scale,
oil, grease, earth, paint, or any other material which may impair the bond between the
concrete and the reinforcement.

All materials shall be stored under cover on wooden or concrete supports at least 150 mm
clear of the ground.

1.10.4.6 Storage of Pre-stressing Wire and Bars

In addition to complying with the above storage requirements, the Contractor shall ensure
that pre-stressing wire and bars are protected from mechanical damage by storing them on
timber supports above a concrete slab; he shall also ensure that during storage the wire
and bars are kept properly coated with water soluble oil inside protective wrapping.

1.10.4.7 Fixing of Reinforcement

All reinforcement shall be securely and accurately fixed in positions using approved plastic
spacers, spacer blocks or chairs. These shall be not more than 1 m apart and at closer
intervals if necessary. All intersections of bars shall be secured with soft iron wire, the ends
being turned into the body of the concrete. The Contractor shall ensure that all
reinforcement is maintained in correct position at all times, particular care being taken
during placing of the concrete.

GKW - Alliance 71
SPECIFICATIONS
CIVIL WORKS

Concrete cover to reinforcement shall be as detailed, and shall be maintained in


accordance with the tolerances specified in the applicable standard.

Top reinforcement in slabs shall be maintained in position by chairs, sized and spaced to
provide adequate support and fixity for the reinforcement.

No part of the reinforcement shall be used to support formwork, access ways, working
platforms or placing equipment, or for the conducting of an electric current other than as
part of an earthing system during the site welding of reinforcement.

1.10.4.8 Welding of Reinforcement

The Contractor shall not weld any reinforcement on site except where this has been
specified in the Contract or is approved by the Engineer in writing.

Reinforcement which is to be welded shall be welded in accordance with the requirements


of the applicable standard, and with the recommendations of the manufacturer. The
Contractor shall demonstrate by bend and tensile tests on specimen welds that the strength
of the parent metal is not reduced and that the weld possesses a strength not less than that
specified for the parent metal. The welding procedure established by successful test welds
shall be maintained and no departure from this procedure shall be permitted.

Following the establishment of a satisfactory welding procedure, each welder to be


employed on the Works, shall carry out welder performance qualification tests on
reinforcing bars of the same metal and size as those on the blocks.

Details of welding procedure and welder qualification tests shall be submitted for the
approval of the Engineer before welding of reinforcement commences.

Tack welds or other welds in positions shall not be permitted, unless specifically approved
by the Engineer.

1.10.4.9 Mechanical Couplings

Mechanical couplings shall be used and shall be obtained from an approved manufacturer.

The Contractor shall demonstrate by tensile tests on sample joints of all sizes rewired for
use in the Works that:

 the use of the couplings does not reduce the strength of the parent bars,
 completed couplings possess the strength required by the applicable standard, and
 there is no significant permanent set in the couplings as the bars are loaded.

Equipment used for making the couplings shall be supplied by the coupling manufacturer
and shall be operated in accordance with the manufacturer’s instructions.

1.10.4.10 Pre-stressing Operations

All operations regarding the placing of ducts, anchorages and tendons and the stressing
and grouting of tendons shall be carried out in full compliance with the requirements of the
applicable standard.

GKW - Alliance 72
SPECIFICATIONS
CIVIL WORKS

1.10.4.11 Testing of Samples of Reinforcement

The Engineer may require to witness routine testing of steel reinforcement at the
manufacturer’s works.

When required by the Engineer the Contractor shall take samples from reinforcement
delivered to site and shall arrange for the samples to be tested by an approved testing
agency. Test certificates from that agency shall be submitted to the Engineer.

1.10.4.12 Bar Schedules

Any bar schedules issued by the Engineer are for the assistance of the Contractor, who
shall nevertheless be entirely responsible for checking the correctness of such schedules
before arranging for the supply cutting and bending of steel reinforcement. In the event of
any information being apparently missing or incorrect the Contractor shall promptly refer to
the Engineer.

1.11 Structural Steel

1.11.1 Scope

This specification covers structural steelwork generally for buildings and other structures,
except portal cranes and road and rail bridges.

1.11.2 Interpretation

1.11.2.1 Supporting Specifications

Not applicable.

1.11.2.2 Definitions and Abbreviations

For the purposes of this specification the following definitions shall apply:

Normal temperature A temperature that is greater than 15ºC but not greater than
32ºC.

Grade (of a bolt) A strength designation consisting of two numbers (separated by


a dot), the first number being approximately one hundredth of
the minimum specified tensile strength in mega-pascals and the
second being approximately one-tenth of the ratio (expressed
as a percentage) between the stress at permanent set of 0,2%
(yield stress) and the minimum tensile strength. (For example,
Grade 4.6 indicates a nominal tensile strength of 400 MPa and
a nominal permanent set stress (0,2%) of 600 MPa. The letter
S, when added to the grade designation, e.g. Grade 8.8S,
denotes a metric high-strength structural bolt with a heavy
series hexagon head.)

GKW - Alliance 73
SPECIFICATIONS
CIVIL WORKS

1.11.3 Materials

1.11.3.1 Structural Steel

Subject to the provisions of 4.12.3.2 and 4.12.3.3, steel used in the fabrication of structural
steelwork shall comply with the requirements of the applicable standard for the grade of
steel specified.

Unless otherwise explicitly approved, and except where adequate resistance to brittle
fracture can be demonstrated, or where brittle fracture will not be a critical design
consideration, the material of welded elements subject to tensile stresses under any
combination of forces in the completed structure, or to tensile stresses exceeding 15% of
the specified minimum yield stress of the steel during erection, shall comply with the
following requirements:

(i) The thickness of steels of Grade 43A and 43B shall not exceed 40 mm.
(ii) The thickness of steels of Grades 50B and 55C used for universal beams, universal
plates, and normalised flats shall not be exceed 40 mm. In the case of universal
columns and other sections, the maximum thickness shall be 20 mm.
(iii) The thickness of steels of Grades 43C, 43D, 43E, 50C, and 55E shall not exceed the
following values:
Grade Plate Sections etc.
43C 50 mm 50 mm
43D 75 mm 50 mm
43E 75 mm 50 mm
50C 75 mm 40 mm (up to 75 mm in normalized conditions)
55E 65 mm 65 mm
(iv) For thicknesses in excess of those specified in (a) - (c) above the impact value
applicable in the impact test shall be at least 27 J at 0ºC.

Steel section profiles shall conform to the requirements given in the applicable specification:

 I- and H- sections
 Metric channels
 Imperial channels
 Angles
 IPE sections

1.11.3.2 Special Steels

Steel of a type not covered by the standards and used in structural elements shall be such
that it complies with the following requirements:

 The ratio of the tensile strength to the guaranteed yield strength, shall be at least 1.2;
 The elongation (on a gauge length of 5.65 √A0 mm), shall be at least 15%.
A0 = cross-sectional area of tensile test specimen, mm2.

1.11.3.3 Steel Used for Cold-Formed Sections

GKW - Alliance 74
SPECIFICATIONS
CIVIL WORKS

All steel used in the manufacture of cold-formed sections for use as structural members in
building shall, before fabrication, have a guaranteed minimum yield stress of at least 200
MPa.

1.11.3.4 Welding Consumables

(i) Electrodes:
Welding electrodes shall comply with such standard as may be agreed upon by the
Engineer and the Contractor.

(ii) Storage and Handling:


The storage and handling of all consumables shall be in accordance with the
requirements of the applicable standard.

(iii) Quality:
Welding consumables, in addition to complying with the requirements of (i) above,
shall be such that they produce weld metal which, when tested in accordance with
the applicable method, has a minimum yield stress and minimum tensile strength at
least equal to those of the parent metal.

1.11.3.5 Bolts, Nuts and Washers

Nuts shall be of at least the strength grade appropriate to the grade of bolt or other threaded
element with which they are used.

Friction-Grip Fasteners: High strength friction-grip bolts and associated nuts and washers
shall be capable of being reliably tightened.

1.11.3.6 Paints and Protective Coatings

Unless otherwise specified, paints and protective coatings shall comply with Part 4.18 of
this Specification.

1.11.4 Plant

The use of cranes, lifting devices, safety belts, harnesses, nets, and barricades shall
comply with the recommendations given in the applicable standard.

1.11.5 Construction

All shop drawings, fabrication, assembly and erection shall be produced/performed by an


Ugandan registered company which has at least five years sound experience in such works
in recent times.

1.11.5.1 Design Drawings

The Engineering drawings will include a general arrangement of the proposed structure
indicating all structural member sizes and special connections, and will be sufficiently
comprehensive to allow the detailing of all connections by the Contractor. Dimension

GKW - Alliance 75
SPECIFICATIONS
CIVIL WORKS

figures on the drawings shall be deemed to be correct even if the drawings are not to scale.
No dimension shall be obtained from a drawing by scaling.

1.11.5.2 Shop Details

The Contractor shall satisfy himself that the drawings contain all the information required
for the preparation of his own shop details, together with any other necessary drawings,
which shall be submitted in triplicate to the Engineer for approval at least one month before
commencement of fabrication. The Contractor’s drawings shall be complete in every
respect (including welding details which shall be fully described) and shall be checked by
the Contractor prior to submission. One copy of each drawing will be retained by the
Engineer and the other copy will be returned to the Contractor three weeks after the date
of receipt by the Engineer, with the Engineer's comments or written approval, as the case
may be.

When requested by the Engineer, calculations for the connection details are to be submitted
for the Engineer's approval.

Before the commencement of fabrication the Contractor shall obtain from the Engineer
approval of the shop details in writing. The approval given by the Engineer relates to
structural adequacy and does not absolve the Contractor from responsibility for dimensional
accuracy.

1.11.5.3 Variations from Drawings and Sections

Except where otherwise authorised in writing by the Engineer, the Contractor shall ensure
that the work is carried out strictly in accordance with the drawings supplied by the
Contractor and reviewed by the Engineer.

Steel sections shall be provided as specified except that substitution will be permitted with
the Engineer's prior approval. Where the Contractor wishes to make a substitution, he shall
state his reasons and alternative proposals in writing, along with supporting calculations.
The Contractor shall allow for a reasonable period for the Engineer to approve such
substitution.

1.11.6 Fabrication

1.11.6.1 General

All structural steel shall, before and after fabrication,

 be within the tolerances specified in Clause 4.12.13, and


 unless required to be formed to a particular shape, be flat, straight and free from
twists. Any necessary straightening or forming shall be carried out by methods that
neither weaken nor deface the material.

1.11.6.2 Identification

At all stages of fabrication, structural steel shall be positively identified as to grade, either
by colour marking or by another reliable system.

GKW - Alliance 76
SPECIFICATIONS
CIVIL WORKS

1.11.6.3 Cutting

Cutting may be done by sawing, shearing, cropping, or machine flame cutting. Manual
flame cutting is permissible only where authorised by the Engineer.

Edges shall be free from any defects or distortions that may adversely affect the strength
or serviceability of the member. All exposed burrs and similar defects shall be ground off
and smoothed.

The edges of flame-cut plates shall, where so required, be dressed to remove notches or
as much material as specified.

1.11.6.4 Holes for Fasteners

(a) The spacing between holes for fasteners and distances between holes shall comply
with the relevant requirements of the applicable standard.

(b) Except where otherwise provided for in C to K below, holes for fasteners shall be
drilled.

(c) Holes for fasteners of pins shall not be formed by flame-cutting, except that holes for
holding-down bolts may be flame-cut if specifically approved.

(d) Unless otherwise required, and provided that punching does not unduly distort the
material beyond the tolerances specified in Clause 4.12.13, holes for bolts, other than
fitted bolts (see H), may (subject to the provisions of E) be punched full size through
material not thicker than the diameter of the hole.

(e) Punching through material thicker than 12 mm shall be done only with prior approval.

(f) All burrs shall be removed from holes before assembly except where holes are drilled
in one operation through parts that would not otherwise be separated after drilling.

(g) The diameter of holes for bolts, other than fitted bolts and holding-down bolts, shall
be not more than 2 mm greater than the diameter of the fastener for fasteners of
diameter up to 24 mm and not more than 3 mm greater for fasteners of diameter over
24 mm, unless otherwise specifically required in terms of the design.

(h) The diameter of holes for fitted bolts or pins shall, subject to a tolerance of + 0,15 mm
and – 0 mm, be equal to the nominal diameter of the bolt or pin. Where practicable,
parts to be connected by fitted bolts or pins shall be tightly clamped or bolted together
and the holes drilled through all the thicknesses in a single operation and
subsequently reamed to size. Holes not so drilled shall be sub-drilled or sub-punched
to a diameter at least 2 mm under size and reamed to full size after assembly and,
where this is not practicable, the parts shall be drilled and reamed separately through
hard bushed steel jigs. Holes for fitted bolts or pins shall not be finally reamed until
welding and other fabrication procedures are complete.

(i) The details of holes for holding-down bolts shall be as specified.

(j) Slotted holes shall be formed by:

 drilling or, subject to the provisions of D and E above, punching a pair of holes
and flame-cutting between the holes or,
 slot punching in the case of material of thickness not-exceeding 12 mm.

GKW - Alliance 77
SPECIFICATIONS
CIVIL WORKS

(k) Where a sealed hollow member is holed for a fastener or pin, provision shall be made
to prevent ingress of moisture to the interior of the member.

1.11.6.5 Joints in Compressions

The abutting surfaces of a joint dependent on contact for the transmission of load shall so
butt that the areas necessary to transmit the load are, in the opinion of the Engineer, in
contact. A bearing face that is to be grouted direct to a foundation need not be machined
but such a face shall be true and parallel to the upper face of the foundation.

1.11.6.6 Structural Hollow Sections

The ends of hollow sections may not be flattened for welded or bolted connections.

Unless special protection against corrosion is provided by other means, the interior of any
hollow member, whether a structural hollow section or a fabricated member, shall be so
sealed as to prevent the ingress of moisture.

1.11.7 Assembly

1.11.7.1 General

The component parts shall be so assembled that:

 the whole and all parts of the finished structure are within the tolerances specified in
Clause 4.12.13;
 no member is bent, twisted, or otherwise damaged, and
 specified cambers are obtained.

1.11.7.2 Alignment of Holes

All matching holes for fasteners or pins shall register with each other so that the fasteners
can be inserted freely through the assembled members in a direction at right angles to the
faces in contact. Drifting to align holes shall be so done that the metal is not distorted and
the holes are not enlarged. Holes that cannot be aligned without enlargement shall be
cause for rejection unless enlargement by reaming is specifically approved.

1.11.7.3 Avoidance of Excessive Stresses during Construction

Structures, composite units, and bolted assemblies that comprise component parts shall
not be subject to excessive stresses during the assembly, fabrication, or erection process.

1.11.7.4 Welding

Welding shall be done in accordance with the relevant recommendations of the applicable
standard.

GKW - Alliance 78
SPECIFICATIONS
CIVIL WORKS

1.11.7.5 Bolting (other than Friction Grip)

(a) The parts to be joined shall be firmly drawn together. Mild steel (Grade 4.6) bolts
and high tensile (Grade 8.8) bolts in shear and bearing type connections shall be
tensioned by hand to the limit of the torque that can be applied by the use of a
standard spanner. High tensile (Grade 8.8) bolts for major tension and moment type
connections and where fatigue is a consideration, shall be tightened to a tension of
75% of the proof load stress of the bolt.

(b) Except in the case of fitted bolts, and unless required in terms of the project
specification or specifically ordered, where surfaces are flat and flanges are un-
tapered and holes have normal clearances washers shall not be used. On tapered
flanges tapered washers shall be used to give bolt heads and nuts a satisfactory
bearing. Where holes have greater than normal clearance, washers shall be used
under bolt heads and nuts.
The length of each bolt shall be such that after tightening, at least one thread projects
through the nut and at least one full thread (in addition to the thread run out) remains
clear between the nut and the unthreaded shank. Unless otherwise specified, the
threaded portion of the bolt shall be clear of the shear plane.

(c) Fitted bolts shall be long enough to ensure that no threads portion is within the
thickness of the connected parts required to develop the bearing load on the bolt and
shall be provided with a washer or washers, under the nut, of thickness such as to
ensure that at least one full thread (in addition to the thread run out) remains clear
between the nut and the unthreaded shank.
Where holes for fitted bolts are reamed after assembly, the parts to be connected
shall be accurately lined up with parallel drifts and a bolt shall be fitted and tightened
in each reamed hole before the next hole is reamed. All the bolts in each group shall
be re-tightened after the last bolt in the group has been fitted.

1.11.7.6 Friction-Grip Fastening

The use of friction-grip bolts shall be in accordance with the recommendations of the
manufacturer and the instructions of the Engineer.

1.11.7.7 Marking

Each piece of steelwork shall be distinctly marked before delivery, in accordance with a
marking diagram, and may bear such other marks as will facilitate erection.

1.11.7.8 Protective Treatment

Unless specified otherwise, all painting and protective treatments shall comply with Part
4.18 of this Specification.

Where friction-grip fasteners are used, protective treatment shall not be applied to the
contact (faying) surfaces unless so permitted or required. After the fasteners have been
finally tightened, inspected, and approved (see 4.12.7.6), the exposed parts of the joints
shall be given the full specified protection.

GKW - Alliance 79
SPECIFICATIONS
CIVIL WORKS

1.11.8 Setting-Out

The Contractor shall be responsible for all setting-out of the Works. Before the Contractor
commences erection of steelwork on site, he shall check that the setting-out and levels of
holding down bolts and the levels of concrete foundations, beam faces, columns, etc., and
he shall report any discrepancies immediately to the Engineer.

1.11.9 Erection

1.11.9.1 Procedure

Before commencing erection of steelwork on site, the Contractor shall submit to the
Engineer, for his general scrutiny and information, full details of the erection procedure and
methods of erection.

1.11.9.2 Storage and Handling

All structural steel at the Site shall be so stored and handled that:

 it is not subjected to damage or excessive stress and is kept clean,


 it does not pose any danger to the Works, people and property.

1.11.9.3 Safety during Erection

Although it is an integral part of the design process, the maintenance of safety standards
during erection is the responsibility of the Contractor who shall observe the
recommendations given in the applicable standard.

Adequate temporary bracing or stiffening shall be provided by the Contractor to protect the
structure during erection from:

 the possibility of loss of stability or overstressing of the structure in its partly


completed state, and
 the imposition of loadings (in particular those due to erection equipment or
procedures) that are more severe than those which the completed structure is
intended to sustain.

All temporary work provided for this purpose shall be left in position until such time as
erection is sufficiently advanced for it to be no longer required.

The Contractor shall ensure that connections for temporary bracing, members, or cleats
and additional holes used to facilitate handling or erection do not weaken the permanent
structure or impair its serviceability. If he has any doubts, he shall ask the Engineer for
instructions.

1.11.9.4 Alignment

All pockets that are to receive holding-down bolts, fittings, or steelwork shall be cleaned out
immediately before erection is commenced. Each part of a structure shall be aligned as
soon as possible after it has been erected. Members shall not be permanently connected
until enough of the structure has been aligned, levelled, plumbed, and temporarily

GKW - Alliance 80
SPECIFICATIONS
CIVIL WORKS

connected to ensure that they will not be displaced during the erection or alignment of the
remainder of the structure.

1.11.9.5 Corrections

Drift pins, jacking equipment, and the like, shall not be used to bring improperly fabricated
members into place. A moderate degree of reaming and cutting, however, may be
employed to correct minor misfits only if, in the opinion of the Engineer, this will not be
detrimental to the strength or appearance of the steelwork. Except as allowed in terms of
4.12.6.4 no burning of holes in steelwork will be permitted without the written approval of
the Engineer.

1.11.10 Grouting of Support

1.11.10.1 Responsibility

Unless otherwise required, grouting or bedding will be carried out by the Contractor. The
Contractor shall ensure that all grouting has been completed before cladding and other
loading is applied.

1.11.10.2 Preparation

The Contractor shall ensure that no bedding or grouting is carried out until enough of the
structure has, or, for multi-storey buildings, a sufficient number of bottom lengths of
stanchions have been aligned, levelled, and plumbed and adequately braced by the
Contractor by means of other structural components that have been levelled and are
securely held by their permanent connections.

Steel wedges or packing or other levelling devices of adequate strength and rigidity shall
be used to support the steelwork. Immediately before grouting, the space and all pockets
under the steel shall be cleared of all debris and free water.

1.11.10.3 Bedding of Stanchions in Foundation Pockets

Before steel sections are embedded in concrete, the complete paint system if any, shall be
applied to each member down to at least 100 mm below the level of the concrete and an
additional final coat of the specified protection shall be applied to the surfaces of each
member extending to at least 100 mm above and below the level of the concrete. Where
no paint system is specified a metallic zinc-rich primer followed by one coat of chlorinated
rubber paint shall be applied. Where grouting is to be carried out by the Contractor,
stanchions in pocket bases shall be grouted with dense concrete having a characteristic
cube strength at 28 days of not less than that of the surrounding concrete base or 25 MPa,
whichever is the greater, and with a maximum aggregate size of 10 mm. Rapid-hardening
or high alumina cement may be used only when specifically authorised by the Engineer. At
least two-thirds of the depth of the pocket shall be filled initially and the stanchions shall
then remain undisturbed for at least 48 hours (or an equivalent period where rapid-
hardening or high alumina cement is used) after which the pocket shall be filled.

GKW - Alliance 81
SPECIFICATIONS
CIVIL WORKS

1.11.10.4 Encasing of Steelwork in Foundations

All structural steelwork in foundations shall be solidly encased in dense concrete with a
minimum cover of 100 mm, unless otherwise authorised by the Engineer.

1.11.11 Subcontracting

Should the Contractor wish to employ the services of a steelwork subcontractor, then the
Contractor must satisfy himself that such subcontractor has the requisite facilities and
resources to comply with the requirements of this specification. Furthermore, the
Contractor must obtain prior approval from the Engineer before appointing a subcontractor.
Notwithstanding the foregoing, the Contractor shall continue to assume all contractual
responsibilities and obligations. Therefore the Contractor must identify his subcontractor
during the tender period and include the latter’s name in his tender submission, where after
no changes will be permitted unless specifically so instructed by the Client.

1.11.12 Tolerances

1.11.12.1 Verification of Dimensions

Verification of dimensions shall be carried out:

 on steel that is at normal temperature measurements being made with a tape that is
at normal temperature and tensioned to 70 N;
 for erection, within 3 hours after the time of sunrise or within 3 hours before the time
of sunset, or at such time when, in the opinion of the Engineer, the effect of the sun
is minimal.

Distortion caused by the sun’s rays striking one side of a member or structure shall be taken
into account, and measurements shall be made only at times when this effect is non-
existent or of no consequence, as determined by the Engineer.

1.11.12.2 Fabrication and Assembly Tolerance

The permissible deviation on the dimensions of components (such as gussets, cross-


bracing, etc.), and on the location of bolt holes in components and elements of a structure
shall be ±2 mm (see also 4.12.6.4). Holes for connections shall be aligned as specified in
4.12.7.2.

1.11.12.3 Rounding up of PDs

All calculated permissible deviations shall be rounded up to the next whole millimetre.

1.11.13 Tolerances on Dimensions, Accuracy of Erection, etc.

1.11.13.1 Other Tolerance

The tolerances on all dimensions (other than of rolled sections, accuracy of erection,
location of holding-down bolts, location of column bases, levels, etc.) shall be as given
below:

GKW - Alliance 82
SPECIFICATIONS
CIVIL WORKS

ITEM PERMISSIBLE DEVIATION


(mm)

A. Cross-section
1. Width of flange (b)
b < 400 mm ±4
b > 400 mm ±6
2. Depth (h)
h < 1,000 mm ±3
h > 1,000 mm ±5
3. Flatness of web
tw <hw / 150> <hw / 120>
tw <hw / 150> <hw / 120>

4. Off-centre of web (e) 6

5. Tilt of flange (t) B/200

6. Warpage flange (w) b/200

B. Length
1. The PD of the length of a member from +1
designated length -2

2. For such members as trusses and lattice


girders these tolerances apply to the member
as a whole. The length of component parts
shall be such that the member can be properly
+ 1 assembled with a PD of +1
-2

C. Accuracy of Erection
1. Out of plumb over any vertical height (H) Greater of 12 or H/300

D. Straightness or specified share after erection


1. For compression members and beams (other
than purlins and sheeting rails) of length L,
between points that are to be laterally restrained Greater of 3 of L/1000

2. for other members of length L Lesser of 25 or L/500

E. Location of Holding-Down Bolts ±3


1. The centre line of a holding-down bolt from
its designated location in plan -3

2. The top of the bolt from its designated elevation ±3

F. Column Bases
Designated level and plan position of column
bases

GKW - Alliance 83
SPECIFICATIONS
CIVIL WORKS

ITEM PERMISSIBLE DEVIATION


(mm)

G. Level
Each storey ± 2/storey up to ± 30

H. Gantry Crane Rails


1. Deviation of gauge for span S
(i) less than or equal to 15 m ±6
(ii) greater than 15 m ± (6 + (S-15)) / 4
(iii) with maximum of ± 10
Note: For roller-guided cranes the PD's for (i)
and (ii) can be increased two fold.

2. Maximum differences in level between rails,


measures at right angles to the gantry 10

3. Maximum difference in level over any 2 m


length of rail 2

4. Maximum deviation in plan form a straight line ±5

5. Maximum horizontal offset at any point along


the rail from:
(i) a 2 m chord 1
(ii) a 15 m chord 5

1.11.14 Testing

1.11.14.1 Test Certificates

If required by the Engineer, test certificates, or cast analysis certificates or both, pertaining
to the steel to be used, shall be supplied by the Contractor.

1.11.14.2 Inspection

The Contractor must ensure that the Engineer has access at all times to all places where
the work is being carried out and is provided with all the necessary facilities for inspection
during all stages of fabrication and construction.

1.11.14.3 Testing of Welds

The Contractor shall examine welds as follows:

a) Visual examination of all welds to check that


 there are no uneven leg lengths and there is no cracking or unacceptable
undercutting or porosity, and
 full fusion is being achieved while welding is in progress;
b) Dimensional checks.

GKW - Alliance 84
SPECIFICATIONS
CIVIL WORKS

Only if required by the Engineer, destructive or non-destructive tests shall be carried out.

Welds done in the shop(s) shall be tested and, if necessary, rectified before dispatch.

GKW - Alliance 85
SPECIFICATIONS
CIVIL WORKS

1.11.15 Schedules Items

1.11.15.1 Supply, Fabrication and Erection of Steelwork (Unit: Tonne)

The rate shall cover all costs for the preparation of shop detail drawings; supply and
fabrication of the steelwork complete with all the necessary cleats, brackets, gussets, shop
fasteners, packs, base plates, and the like, surface preparation and shop priming (or
galvanising or other surface treatment if so required); trial assembly; testing; loading ready
for dispatch, transport to site and off-loading upon arrival at Site (and stacking in a
designated area if necessary); and complete erection of steelwork on Site including
assembly, site welding if any, provision of erection equipment, aligning, temporary supports,
safety measures, and touch-up on shop paint or primer; all to the satisfaction of the
Engineer.

1.11.15.2 Holding - Down Bolts (Unit: Tonne or No.)

Separate items will be scheduled for each diameter, size and shade of bolt.

The rate shall cover the cost of supplying and delivering holding down bolts complete with
washers and nuts, and all threading, shaping, anchor plates and frames and stacking them
on site ready for installation.

1.11.15.3 Protective Coatings (Unit: m²)

Separate items will be scheduled for different types of protective coatings.

The rate shall cover the cost of supplying all material, preparation of the surface, the
application, and (where applicable) the curing of coats of paint, as specified, and shall
include provision and removal of scaffolding where necessary.

1.12 Metalwork

1.12.1 Scope

This part covers the supply and installation of engineering metalwork.

1.12.2 Submissions by Contractor

The following submissions are required by this Section of the Specification:

 Drawings
 General arrangement
 Detailed manufacturing Certificates
 Material tests
 Data
 Manufacturers’ catalogues (where alternatives are offered for approval)
 Manufacturer’s catalogues and test data for proprietary fixing bolts.

GKW - Alliance 86
SPECIFICATIONS
CIVIL WORKS

1.12.3 Materials

1.12.3.1 General

The Contractor shall supply and install the items of metalwork specified herein, together
with all fixings, mounting brackets, locking screws, lifting keys and other accessories
normally required for erection and operation.

No orders for engineering metalwork shall be placed by the Contractor until he has
submitted his detailed drawings, and where applicable supporting design calculations, to
the Engineer and received the Engineer's approval.

Where the Contractor proposes to use dissimilar metals either in contact or close enough
for the gap between them to be bridged by an electrolyte, he shall satisfy the Engineer that
adequate anti-corrosion provision is included in the design.

1.12.3.2 Steel Items - General

Steel items for which there is no relevant standard shall be fabricated from steel which is in
accordance with the applicable standard, by welding using procedures in accordance with
the applicable standard.

Unless otherwise specified, all steel items shall be galvanised in accordance with the
applicable standard. Galvanised items shall not be painted except where so specified. No
galvanised metal shall be painted until the Engineer has inspected the coating.

1.12.3.3 Aluminium Items - General

Items of aluminium and aluminium alloy shall comply with the relevant provisions of the
applicable standard.

1.12.3.4 Steel Ladders

Unless otherwise specified, steel ladders shall be generally in accordance with the
applicable standard for ladders with solid steel stringers (stiles) but shall have the following
dimensions:

 minimum thickness of stringer 12 mm


 diameter of rungs 20 mm
 rung spacing 250 mm
 rung length between stringers 400 mm
 minimum clearance to wall or other obstruction 220 mm
 maximum distance between stringer supports 2.0 m

Wherever possible, stringers shall extend 1.0 m above the level of the floor or platform at
the top of the ladder and the clear width between stringers shall be increased to 600 mm
for this length.

Where such an extension to the ladder is not possible, handholds shall be provided in the
upper surface of the floor or platform subject to the approval of the Engineer.

GKW - Alliance 87
SPECIFICATIONS
CIVIL WORKS

The stringers shall be sized to suit the height of ladder and the intervals of the stringer
supports. Stringers shall be drilled to receive the rungs which shall be welded to the
stringers on each side of each stringer. Unless otherwise specified, the bottom ends of the
stringers shall not be designed for floor fixing, but shall terminate at wall fixing supports at
least 150 mm above the floor. All edges of stringers, brackets, splice plates and other
components shall be ground smooth to remove burrs and sharp edges.

Ladders exceeding 3 m high shall be provided with safety hoops at intervals not exceeding
900 mm, with the lowest hoop 2.5 m above the ladder foot unless otherwise specified.
Unless provided otherwise, landings of open mesh flooring and handrails as specified shall
be provided at intervals not greater than 9 m. Anchorage points shall be provided for
attaching safety harnesses instead of the above safety hoops.

1.12.3.5 Steel Stairways

Stairways shall be designed for a loading of 5.0 kN/m 2 of plan area of the stairway. Steel
stairways shall be provided with tubular hand-railing and stringers of cross section suitable
for the span and loading. Treads shall be of open bar gratings, expanded metal grating
panels of cold formed planks in accordance with the applicable standard. Treads of pressed
bar construction shall not be used.

The angle of rise of stairways shall be between 30º and 42º. The rise between treads shall
be uniform and between 155 mm and 190 mm. Stairways in the same area of the works
and in similar locations shall have the same angle of rise and the same rise between treads.

The width of the treads shall be between 250 mm and 300 mm. The width of the stairways
shall be as specified.

The stringers shall be mounted by means of angle brackets with slotted holes for
adjustment of line and level.

1.12.3.6 Manhole Steps

Except where otherwise specified, manhole steps shall be of malleable cast iron. The shape
and dimensions shall be as shown in the following table:

POSITION FIGURE

In brickwork or in-situ concrete 1

In precast concrete manholes 2

Where the thickness of the structure permits, the larger tail dimensions in Figures 1 and 2
shall be used.

Manufacturers’ certificates shall be provided for all manhole steps. Witness of


manufacturers’ inspection tests is not required.

1.12.3.7 Access Covers, Road Gully Gratings and Frames

Except where otherwise specified, access covers, road gully gratings and frames shall be
of ductile iron. Lockable units shall be provided for the locations specified.

GKW - Alliance 88
SPECIFICATIONS
CIVIL WORKS

Covers and frames detailed as sealed shall incorporate suitable neoprene or other
approved synthetic rubber sealing rings, or shall seal by another approved sealing method.

1.12.3.8 Surface Boxes

Surface boxes for key operation of valves and sluice gates shall be of grey or ductile iron.
Except where otherwise specified, they shall be Grade A and coated.

1.12.3.9 Metal Flooring and Walkways

Metal flooring and walkways shall comply with the applicable standard as appropriate.
Subject to anything specified under Particular Requirements, metal flooring and walkways:

 may be of steel or aluminium;


 shall be Heavy Duty, and
 may be of open bar gratings, expanded metal grating panels or cold formed planks
but pressed bar construction shall not be used in places exposed to the weather or
in situations where condensation is likely.

Except where otherwise specified, flooring panels shall be removable and the maximum
weight of each panel shall not exceed 25 kg. Removable sections of flooring shall be
provided with holes for lifting keys, and keys to suit.

Flooring shall be detailed and fabricated so that no cutting is required on site. Supporting
steelwork shall comply with the requirements of Part 5.12 of the Specification (Structural
steelwork). Bolt holes in brackets and mountings shall be slotted to allow for adjustment of
line and level. Cut-outs shall be trimmed with straight or curved bars as appropriate. Angle
kerbing for seating the flooring in concrete shall be provided. Kerbing and other supporting
structures for building into concrete shall have lugs welded on at maximum spacing of 600
mm.

Except where otherwise specified, the width of any access walkway shall be not less than
750 mm.

All members of assemblies shall be marked at the factory with distinguishing numbers,
letters or marks corresponding to those shown on approved drawings or parts lists.

1.12.3.10 Chequer Plate

Except where otherwise specified, chequer plate flooring shall have a raised pattern without
enclosed recesses and shall have a minimum base thickness of 4.5 mm in the case of steel
plats or 8 mm in the case of aluminium. Panels shall be secured to supports with
countersunk screws at maximum spacings of 1.0 m along supports.

1.12.3.11 Handrailing

Metal handrailing shall comply with the relevant provisions of the applicable standard.
Except where otherwise specified, metal handrailing shall consist of standards at regular
intervals not exceeding 1.5 m, and two rails. The upper rail shall be 1.1 m above the
adjacent finished floor level, and 0.9 m above the nosing line on stairways. The lower rail
shall be midway between floor or nosing line and the upper rail. Rails shall be fabricated
from 32 mm bore mild steel tube and standards from 38 mm dia solid mild steel bar.

GKW - Alliance 89
SPECIFICATIONS
CIVIL WORKS

Handrailing shall be ball-jointed. Handrailing terminating against a wall shall either have a
suitable wall fixing flange or shall terminate at a standard or a loop with a gap between the
standard or loop and the wall not exceeding 75 mm. Where the shape of the floor or
platform structure does not incorporate an up-stand at the edge of walkways, toe plates not
less than 4 mm thick and not less than 100 mm high shall be fixed to the handrail standards.
The bottom edge of such toe plates shall be about 15 mm above the surface of the walkway.

The handrail standards for stairways and for landings and walkways of width less than 1.2
m shall have palm fittings for bolting to the sides of the structures. Elsewhere the standards
shall be designed for fixing 100 mm (minimum) inside the edge of concrete structures, or
at the supporting edge girder of steel flooring, or have palm fittings. Standards either side
of openings shall be equipped with eyes for attaching safety chains at top and middle rail
level.

Safety chains shall be of mild steel of 10 mm nominal size, short link, smooth welded chain.
Each length of chain shall be fitted with a shackle at one end and a snap fastening at the
other.

1.12.3.12 Servicing Hooks

Servicing hooks shall comply with those provisions of the applicable standard, which relate
to the appropriate type. Each hook, together with any beams and other supporting
members, shall be designed (with an appropriate allowance for dynamic loading) to carry
safely the heaviest item of plant required to be lifted.

The safe working load shall be clearly and permanently displayed alongside each hook so
as to be legible from the normal working level.

1.12.3.13 Fixings for Metalwork

Bolts for fixing metalwork to concrete, brickwork or blockwork shall be of the following types:

(a) For fixing in drilled holes in horizontal, vertical or inclined surfaces, approved
proprietary epoxy resin fixed bolts shall be used. The epoxy resin shall be a quick
formulation, supplied in suitable pre-measured sachets to separate the components
until punctured in the hole and mixed by rotation of the fixing bolt. The resin and bolts
shall be used in accordance with the manufacturer’s instructions. When fixed, the
resin shall completely fill the space between the bolt and the hole to the surface of
the concrete, brickwork or blockwork.

(b) As an alternative to (a) approved mechanical expansion type bolts may be used for
fixing to concrete surfaces inside buildings above ground level where the application
proposed by the Contractor is approved by the Engineer. Expansion bolts shall not
be used inside liquid retaining structures, in chambers, basements and similar
locations below ground level, in exterior locations, nor in any brickwork or blockwork.

(c) For fixing to horizontal top surfaces of concrete by grouting with cement based grout
or mortar, foundation bolts may be used in preformed, drilled or cut pockets.

(d) Where approved by the Engineer, screws and approved fixing plugs.

The Contractor shall submit details of his proposed fixings for the approval of the Engineer.
Where required by the Engineer, the Contractor shall demonstrate the effectiveness of the
fixing by suitable tests.

GKW - Alliance 90
SPECIFICATIONS
CIVIL WORKS

Other bolts and nuts used in fabrication or erection shall be in accordance with the
applicable standard.

Bolts, nuts, screws, washers and other fixings shall be stainless, galvanised, sherardised
or electro-plated steel in accordance with the provisions of Section 4.18 of the Specification
(Paints and protective coatings).

1.12.3.14 Opening Tools

Lifting keys and devices for unfastening locking screws shall be of galvanised mild steel.
They shall be supplied at the rate of one set for each five similar covers, with a minimum of
two sets of each particular type.

1.12.4 Workmanship

1.12.4.1 Tolerances

Metalwork shall be constructed and installed within the following tolerances:

 Metalwork at floor level (e.g. joints between flooring sections and between steel
flooring and adjacent concrete):

- difference in level at joints 3 mm


- joint gap 3 mm
- Dimensions shown on Drawings ± 5 mm
- Levels shown on Drawings ± 5 mm

1.12.4.2 Installation

Where metalwork is to be founded on and/or fastened to concrete the Contractor shall use
one of the following methods:

METHOD DESCRIPTION

1 Bolting or screwing the metalwork to plates or angle section having


anchors cast into the concrete structure or set into pockets left in the
concrete structure.

2 Setting the metalwork into pockets left in the concrete structure.

3 Bolting the metalwork to anchor bolts (studs) cast into the concrete
structure or set into pockets left in the concrete structure.

4 Bolting the metalwork to anchor bolts (studs) as specified, in holes


drilled into concrete structure.

5 Bedding the metalwork on cement mortar placed on the concrete


surface.

Cement mortar of 3 parts of sand to 1 part of cement shall be used for bedding access
covers and the like and for filling around metalwork or bolts set into pockets smaller than

GKW - Alliance 91
SPECIFICATIONS
CIVIL WORKS

100 mm square or equivalent. For larger holes, concrete of the same grade as the structure
shall be used instead of mortar. The installation methods permitted for various types of
metalwork are specified in the following table.

METAL WORK ITEMS PERMISSIBLE METHODS OF


INSTALLATION

Stairs, ladders, flooring 1, 3 and 4

Step irons, sockets for removable items 2

Handrailing 2, 3 and 4

Access covers, surface boxes and gully gratings 2 and 5

During installation each item of metalwork shall be temporarily braced as necessary to


resist all forces which are likely to be applied to it during installation fixing and building in.
Any bolted connections required as part of the installation operation shall be fitted and
tightened before fixing bolts are tightened or pockets are grouted. The nuts of grouted or
resin fixed bolts shall not be tightened until the grout or resin has fully cured.

Where approved by the Engineer, small or lightly loaded items may be fixed using screws
and plugs set in drilled holes.

1.12.5 Aluminium Ladders in Chambers

Aluminium ladders in chambers shall be designed to provide the same carrying capacity as
steel ladders. Aluminium ladders shall provide the same clearances and spacings as those
specified for steel ladders. Aluminium ladders shall have a retractable top section which
can be lifted up from the chamber to 750 mm above roof level to ease transfer to and from
the ladder.

1.13 Pipelines for Water Supply

1.13.1 Scope

1.13.1.1 Coverage

This Section contains requirements which, where relevant to this Contract, shall apply to
the supply, handling, installation and testing of pipelines for the conveyance of raw and
treated water including pipes, fittings and appurtenances where required to be laid in, on or
above ground or to be fixed on or built into other parts of the Works. It also applies to uPVC
cable ducts but does not apply to pipework for sewers, drains or building services.

Except as specified otherwise (including in Sections for Valves and Flowmeters), this
Section, including requirements for protection, installation, subsequent pressure testing and
measurement shall apply to valves, flowmeters and the like.

Excavation and backfilling of pipe trenches shall be carried out as specified for Earthworks.

1.13.1.2 Definitions

GKW - Alliance 92
SPECIFICATIONS
CIVIL WORKS

The following terms shall have the meanings hereby assigned to them:

“Pipes” straight pipes, whether whole or cut, and their joints.


“Fittings” all tees, bends, tapers, collars, couplings and similar items.
“Pipeline appurtenances” all items additional to pipes and fittings, required to complete
a pipeline including but not limited to internal and
external protection systems, supports and anchorages,
chambers, washouts, marker posts and any apparatus and
construction required for testing, cleaning, disinfecting or
operating the pipeline.
“Pipeline” the whole pipeline inclusive of pipes, fittings, pipeline
appurtenances, and except where the context requires
otherwise, valves, flow-meters and the like.

1.13.1.3 Glass Reinforced Plastic (GRP) Pipelines

GRP pipelines shall be made to the applicable standards.

1.13.1.4 Pre-stressed Concrete Pressure Pipelines

Pre-stressed concrete pressure pipelines shall be made to the applicable standards.

1.13.2 Submissions by Contractor

Submissions which the Contractor is required to make in relation to pipelines include, where
relevant, the following:

 Drawings

- Typical drawings of standard items.


- Detail drawings of special items.

1.13.2.1 Data

 Pipe, fittings and joint details including manufacturer, pressure/temperature ratings,


material properties and thickness and lubricants.
 Design details of flanges outside the range of Reference Standards.
 External and internal protection and lining system details.
 Method of boxing out and building pipes into structure walls.
 Method for control of line and level of pipeline during installation.
 Welding procedure details including plant, method, weld materials, air testing of joints
and names of welders.
 Thermal fusion jointing details including method, tools and equipment, procedure,
testing programme and jointers names, training and experience.
 Manufacturers’ calculations, catalogues and data sheets.

GKW - Alliance 93
SPECIFICATIONS
CIVIL WORKS

1.13.2.2 Records to be Kept

The Contractor shall keep detailed and up-to-date records in a form to be approved by the
Engineer of all pipes, fittings and pipeline appurtenances, the quantities of each type, size
and class which have been:

 ordered during the course of the Works;


 delivered during the course of the Works;
 declared on delivery to be faulty damaged or deficient;
 broken damaged or lost during the course of the Works.

Each week the Contractor shall provide the Engineer with an up-to-date copy of the above
records.

1.13.2.3 Certificates of Tests

The Contractor shall forward to the Engineer the following certificates:

 works tests on pipes and fittings;


 material tests;
 inspection;
 welder qualification tests;
 non-destructive tests on completed welds.

1.13.2.4 Method and Programme of Pipeline Testing and Cleaning

The Contractor shall submit for the approval of the Engineer details of his proposed
methods and programme for pipeline testing and cleaning (including details of test and
cleaning equipment).

1.13.3 Materials

1.13.3.1 General

Materials for pipelines shall be manufactured to the requirements specified hereunder, and
shall be provided by the Contractor, except as specified otherwise. All items shall be of the
specified diameter and class and be suitable for the required test pressure and working
pressure.

No substance or product which could impart toxicity, taste, odour or colour to water, or be
otherwise objectionable on health grounds, shall be used in the Works where it may be
applied to or introduced into water which is to be supplied for drinking, washing or cooking.
Only those substances and products which meet the requirements of subparagraph (a), (b),
(c) or (d) of paragraph (1) of Regulation 25 of the Water Supply (Water Quality) Regulations
1989 (Statutory Instrument No. 1147, HMSO, London ISBN: 0 11 097147 7) shall be used
in such situations.

Please note, that "according to the rules for the German Financial Corporation it is not
allowed to use asbestos-cement materials. This applies for pipes, fittings and any other
building elements (e.g. roof tiles)".

GKW - Alliance 94
SPECIFICATIONS
CIVIL WORKS

1.13.3.2 Connections between different Pipe Materials

Where different types or classes of pipe material are jointed together, the Contractor shall
supply special fittings or stepped couplings designed and manufactured to suit the ends of
pipes to be jointed. Stepped couplings shall comply with the requirements for detachable
flexible couplings and flange adapters where applicable.

1.13.3.3 Gaskets for Joints

Gaskets for joints shall be obtained from the manufacturer of the pipe or joint.

Joint gaskets shall comply with the relevant requirements of the applicable standard, shall
be of a material suitable for making a long term flexible seal between the pipes, and shall
be resistant to mechanical, chemical or bacteriological attack leading to deterioration of the
flexible seal.

Rubber for gaskets shall be ethylene propylene rubber (EPDM or EPM) or styrene
butadiene rubber (SBR) which complies with the above requirements.

Lubricants used during jointing shall have no deleterious effects on either the gasket, pipes
or pipe coating, and be unaffected by the liquid to be conveyed.

1.13.3.4 Flanged Joints

Except where otherwise specified, flanges and bolting shall be to the applicable standard
where applicable. Flanges to other standards shall be used only if approved by the Engineer
and provided that any differences do not effect mating dimensions. Back faces of flanges
shall be machined. Gaskets shall be inside bolt circle type.

Gaskets shall be of such physical properties as to be capable of forming permanent


watertight joints against pressures up to the maximum test pressure. The use or jointing
paste or grease will not be permitted. Bolts and nuts and washers shall be to the applicable
standard. There shall be two washers per bolt. Each bolt shall be of sufficient length to
show two threads past the nut when installed.

The Contractor shall be responsible for checking and ensuring that mating flanges are
compatible in all cases, including where connections are to be made to existing pipe
flanges.

1.13.3.5 Detachable Flexible Couplings and Flange Adapters

Where detachable flexible couplings or flange adapters are used, these shall be of the
Viking-Johnson type, except where otherwise specified or approved by the Engineer.

Detachable flexible couplings shall be suitable for the angular deflections specified below
without leakage. Flange adapters shall be suitable for half the angular deflection stated.

GKW - Alliance 95
SPECIFICATIONS
CIVIL WORKS

NOMINAL PIPE DIAMETER ANGULAR DEFLECTION


(mm) (degrees)
Up to 600 5

601 to 750 4½

751 to 900 4

901 to 1200 3

1201 to 1800 2

1801 upwards 1

Flexible couplings for each size of pipe shall also be capable of withstanding the shear force
applied by the weight of a 4 m length of pipe of that diameter full of water suspended
between two couplings.

Detachable flexible couplings shall be provided with central registers or location plugs only
where specified.

Flange adapters shall have flanges as specified for flanged joints.

The metal components of detachable flexible couplings and flange adapters shall be
protected by a bonded nylon coating applied at the time of manufacture. All bolts, nuts and
washers shall be stainless steel where detachable flexible couplings and flange adapters
are buried.

All buried detectable flexible couplings and flags adapters shall be protected with wrapping
material as specified in Clause 4.15.4.7.

1.13.3.6 Fusion Bonded Epoxy Coating

Fusion bonded epoxy coatings described in this clause are intended for applications
containing ductile iron, cast iron, steel, and aluminium based substrates used in the
manufacture of pipes, fittings and their components, that will be in contact with potable
water, domestic effluent, any soil conditions and above ground applications. The coating
shall consist of a polymeric anti-corrosion barrier applied at a factory approved by the
Engineer.

The coating system requirements, performance testing and factory applied coating
requirements and practice shall be in accordance with the Interim Water Industry
Specification (WIS) for Polymeric Anti-Corrosion (Barrier) Coatings, ref. No. FR 0028, dated
September 1989 with amendment, Issue l, dated 31 July 1990 published by the Foundation
for Water Research (FWR) Henley road, Medmenham, PO Box 16, Marlow, Bucks, SL7
2HD U.K. Where applicable, all materials shall comply with the second paragraph of Clause
4.16.4.1.

The method of surface preparation and cleaning shall be in accordance with the
Contractor’s specification which shall be no less than the minimum requirements specified
by the coating material manufacturer and the following requirements:

 The pre-coating surface shall be blast-cleaned.

GKW - Alliance 96
SPECIFICATIONS
CIVIL WORKS

 The surface shall be tested for soluble salts and re-blasted if soluble salts are found
to be present;
 All oil, grease and other contaminants shall be removed;
 All slivers and scabs etc. made visible by blast cleaning and detrimental to the coating
process shall be removed;
 Welds shall be fettled smooth;
 Edges and corners shall be smoothed to a 1.5 mm minimum radius;
 Zinc chromate pre-treatment shall not be permitted.

The minimum coating thickness for pipes and fittings shall be 300 microns. The maximum
coating thickness on a pipe wall shall be 1.6 mm. The maximum coating thickness on a
flange shall be 2.0 mm; the minimum and maximum coating thicknesses shall apply to
coating inside bolt holes. Any thickness-critical surfaces shall be coated to the thickness
specified and within the tolerances identified.

Unless otherwise specified, all coatings shall be examined to a Class A coating


classification and each item shall be checked for holidays over all of the coated surfaces.
A fitting with 2 or more holes per 3 m2 of surface area or a pipe with 30 or more holes per
pipe length shall be rejected for subsequent stripping and re-coating. All holes detected
shall be repaired and on completion the item shall be re-examined for holes.

1.13.3.7 Wrapping Material

Wrapping material for external protection of buried pipelines and for site wrapping of
completed joints or fittings shall be heavy duty, self-adhesive, rubber-bitumen compound
with PVC carrier strip together with primer and moulding putty except where otherwise
specified.

All materials shall be supplied by the same manufacturer.

The primer shall be a fast drying bitumen solution type compatible with the wrapping
material and the pipeline materials including coatings to which it is to be applied.

The moulding putty shall be compatible with the wrapping materials and the primer and
shall be capable of being moulded cold by hand. The wrapping material shall possess the
following minimum physical characteristics:

 Thickness:
- Compound 0.85 mm
- PVC 0.75 mm
- Total 1.60 mm
 Tensile strength 12 N/mm
 Elongation 230 %
 Tear resistance 45 N
 Impact Resistance 7 joules
 Adhesion (180Þ peel) 2 n/mm
 Dielectric Strength 20,000 volts minimum
 Insulation Resistance 1,000,000 mega-ohms

GKW - Alliance 97
SPECIFICATIONS
CIVIL WORKS

The material shall be suitable for application in the environmental conditions at the Site. It
shall be supplied in rolls with an interleaved release paper extending 10 mm beyond each
side of the wrapping material.

1.13.3.8 Polyethylene Sleeving

Polyethylene sleeving for loose pipe wrap and for the protection of fittings, valves and the
like shall be in accordance with the applicable standard. Suitable adhesive PVC tape shall
also be provided to fix the sleeving in position and to make joints between the adjacent
sections. The sleeving shall be black.

1.13.3.9 Marker Tape for Buried Services

The marker tape laid above buried services shall be 50 mm wide and 0.1 mm nominal
thickness, coloured polythene or similar approved system boldly printed with the word
“CAUTION” and words to identify the particular service throughout its entire length, in
accordance with the following coding:

TYPES OF SERVICE COLOUR SERVICE IDENTIFICATION


TAPE WORKING

Potable water Blue Water Main Below

Waste water, effluent and Green Waste Pipe Below


sludge of all types

Fuel oil or gas pipe Orange Fuel Main Below

Electricity Yellow Electric Cable Below


Earthing

Instrumentation cable, Red Control Cable Below


Telephone cable,
Telemetry cable

1.13.3.10 Marker Posts and Indicator Plates

Route marker posts shall be of concrete, overall height 915 mm, 75 mm thick, 230 mm wide
with a recess for an indicator plate.

Indicator plates shall be of cast aluminium alloy with raised black characters and be
generally similar to single class A hydrant indicator plates to the applicable standard, with
apertures for the insertion of character plates indicating the pipe diameter in millimetres and
the distance in metres from the plate to the object identified. They shall be of the following
types:

GKW - Alliance 98
SPECIFICATIONS
CIVIL WORKS

OBJECT IDENTIFIED IDENTIFICATION PLATE COLOUR


CHARACTERS
Air valve AV Blue

Stop, flow or pressure control valve SV Blue

Washout valve WO Blue

Hydrant H Yellow

1.13.3.11 Marking and Packing

Each pipe and fitting shall be indelibly marked with the diameter, class and works test
pressure and shall, in addition, carry a unique reference number to enable items to be
correlated to works fabrication records, works test certificates, delivery notes and the like.
Wherever possible the marks shall be painted on the outside of pipes and fittings close to
one end, which in the case of pipes and fittings with socket and spigot joints shall be the
socket end.

Where there is insufficient smooth surface area to accommodate the above information the
marking shall be put on rustproofed metal tags secured to the item with galvanised wire.

The flanges of pipes and fittings shall be protected by wooden discs attached by means of
service bolts or by other approved means.

Service bolts shall not be incorporated in the works.

All other pipe ends shall be protected against impact damage and entry of foreign matter.

Small items, such as bolts, nuts, gaskets and other joint components shall be crated for
delivery. Each crate shall contain a detailed packing list in a waterproof envelope. The
outside of the crate shall bear a general description of the contents and an identification
mark relating it to the detailed packing list.

1.13.3.12 Water for Testing and Cleaning

The Contractor shall provide all water required for testing and cleaning pipelines. For this
purpose the Employer will, if requested by the Contractor, make available metered supplies
of water from existing mains. All water supplied by the Employer will be charged to the
Contractor.

1.13.3.13 Steel Pipelines

Steel pipes shall be manufactured in accordance with API Specification 5L. The pipes shall
be formed by automatic submerged arc welding with either longitudinal seams or spiral
seams. Except where otherwise specified, steel shall be Grade A25, Grade A or Grade B
to API 5L.

A heat analysis of the steel used for the pipes shall be provided in accordance with clause
3.2 of API 5L. Check analyses on the finished pipe shall be taken in accordance with Clause
3.3 and 3.4 of API 5L. The chemical analysis shall be in accordance with the applicable
Standard.

GKW - Alliance 99
SPECIFICATIONS
CIVIL WORKS

Standard length straight pipes shall be the maximum which the pipe manufacturer can
produce by his normal processes and which can readily be transported to Site. Shorter
lengths of pipe shall be supplied as necessary to enable changes of grade or direction to
be made using joints capable of angular deflection as specified below.

Pipes shall be manufactured to the tolerances given in Section 6 of API 5L. The maximum
height of the weld bead on the external surface of the pipe referred to in API 5L Section
10.5d shall not exceed 3mm.

Pipes shall be subjected to non-destructive testing of welds in accordance with Section 9


of API 5L, and shall be hydraulically tested at the place of manufacture in accordance with
Section 5 of API 5L.

Joints and Pipe Ends

Joints shall be in accordance with the applicable standard and as described below with the
amendments stated.

 Pipes for straight runs of pipeline jointed in trench shall have sleeve welded joints,
but excluding hemispherical joints.
 For changes of pipe grade or direction the joints shall be Type 3 (surfaced sleeve)
being spherical (but not hemispherical) joints to take angular deflections up to 2
degrees from the axial. The minimum penetration at maximum deflection shall be
twice the pipe thickness.
 Butt welded joints may be used as an alternative to sleeve welded joints for pipes to
be jointed outside the trench.
 Detachable flexible couplings shall be used.
 Flange joints shall be used.
 Welding collars shall be used for jointing cut pipes or closing lengths in trench.

Sleeve welded joints shall have external fillet welds on pipes of 710 mm o.d. and under but
shall have both internal and external fillet welds on pipes over 710 mm o.d.

The gap between sleeve and spigot at any weld location shall nowhere exceed 1.5 mm and
the average gap around the circumference of any weld shall not exceed 0.4 mm.

The internal surfaces of sleeves and the external surfaces of spigots shall be ground
smooth along the longitudinal fusion welds for a distance of 150 mm from the end of the
pipe in each case. The external surface of plain ended pipes intended for collar or
mechanical coupling joints shall be prepared similarly. Plain pipe ends for use with
mechanical coupling joints shall conform to the requirements of the manufacturer of the
mechanical joint.

Flanges for flanged joints shall be steel flanges welded to the pipe‚ by the electric arc or
other approved method. They shall be raised face type and shall be truly faced over their
whole width.

Welding collars may be provided as single split collars with temporary tightening bolts and
lugs. Split collar ends shall be prepared for butt welding in the same manner as plain ends
of pipes prepared for butt welding. The gap between the ends of a split collar after tightening
shall not exceed 3 mm. The tolerances of the collar shall be such that nowhere shall the
gap between the inside surface of the pipe at fillet weld locations exceed the tolerances for
sleeve and spigot joints.

GKW - Alliance 100


SPECIFICATIONS
CIVIL WORKS

Pipes, flanged pipe ends, flanged branches and plain ends for use with mechanical
couplings which are to be lined with concrete before installation, shall have a steel retaining
ring of the same thickness as the lining, welded inside and flush with the ends of the pipes.

Lengths of pipe from which closing lengths are to be cut, shall be fully sized over the full
length of the pipe. Any pipes which have been specially made for use as closing lengths
shall be clearly marked.

Welded sleeve and collar joints shall be provided with tapped holes with matching plugs, to
facilitate air pressure testing of joints after field welding.

For pipes of 1 m nominal diameter or larger, cable pass holes sealed with screwed plugs
shall be provided in sufficient pipes so that pass holes are available at intervals of about 60
m along the pipeline.

Fittings

All bends, tees and other fittings shall be prefabricated by the pipe manufacturer. Fittings
shall be manufactured in accordance with the applicable standard and shall, where
possible, be formed from straight pipe which has been tested.

Steel fittings shall be designed and reinforced to withstand the specified test pressure in
accordance with the methods contained in the American Water Works Association
(AWWA). When using the AWWA M11 method, the design pressure shall be taken at least
equal to the test pressure and the working pressure (less surge) as equal to two-thirds of
the design pressure. Welding shall be of a standard equal to that of straight pipe and each
butt weld shall be subjected to a 100% radiographic test. Fillet welds shall be subjected to
air tests where appropriate and to magnetic crack detection tests.

Protection

Where not otherwise specified, pipes and fittings shall be protected internally and externally
against corrosion, the external protection being reinforced bitumen enamel wrapping and
the internal protection being spun concrete lining. Both types of protection shall be applied
under factory conditions but not necessarily at the place of manufacture of the pipe.

Protection at joints shall be completed on Site after acceptance of joint weld tests.

Cleaning and Priming

Where bitumen wrapping is to be applied at the place of pipe manufacture, cleaning and
priming shall immediately follow hydraulic testing. Where bitumen wrapping is to be applied
at another location, then the pipes shall be coated with a suitable corrosion inhibitor before
dispatch from their place of manufacture.

Immediately prior to priming, all pipes shall be thoroughly descaled by blast cleaning, Grade
SA2½, or by acid pickling.

Primer shall be hot applied. If the spun concrete lining is to be applied at the place of pipe
manufacture, internal priming of the pipe barrel may be omitted. Otherwise pipes shall be
primed both internally and externally.

GKW - Alliance 101


SPECIFICATIONS
CIVIL WORKS

The above priming shall stop short of the ends of pipes intended for field welding. The ends
of such pipes shall be coated with an approved weldable pre-construction priming paint
both internally and externally.

External Protection

Pipes and fittings for buried pipelines shall be protected externally, using bitumen enamel
wrapping thereof, except that the bitumen thickness shall be a minimum of 6 mm and the
spacings between the pipe and the inner layer of glass fibre and between the inner and
outer layer of glass fibre shall be not less than 2 mm.

The wrapping shall be stopped short 100 mm from ends prepared for butt welding, 150 mm
from ends of all spigot and socket pipes, and 300 mm from the ends of all plain ended pipes
for use with mechanical couplings or flange adapters. The edge of the wrapping shall be
chamfered at 25 degrees to the axis of the pipe.

Before dispatch from the factory, the wrapping on all pipes and fittings shall be tested with
a holiday detector, and an discontinuities, pinholes or other defects made good. After the
wrapping has been tested, it shall be given one coat of a non-stick light and heat reflecting
paint.

Spun Concrete Lining at Factory

Pipes and fittings shall be lined in accordance with the applicable standard. The quality
deemed to be satisfied when (a) any fins or other excrescences have been ground away
and (b) the distance between the finished surface and a 3000 mm straight-edge held
parallel to the pipe axis does not exceed 2 mm.

The frequency of the tests shall be at least once for every 250 m length of pipe lined or
during each working shift, whichever is the more frequent.

Immediately before lining commences, the pipe bore shall be cleaned of all scale, loose
rust, oil, grease or any other foreign matter likely to contaminate or harm the concrete.
Priming coat bonded to the pipe such that wire brushing does not cause areas to flake off
will be acceptable as a base for applying the lining.

Temporary end restraints shall be fixed to the pipe ends on completion of lining and before
removal of the pipe from the lining machine. The pipe shall not be rotated about its
longitudinal axis after the fixing of the restraints when being handled and transported on
site.

Fittings shall be concrete lined at the factory. During the lining process, all rebound
material, dribbles, etc. shall be removed so that the lining is applied in a homogeneous
mass to a clean surface.

Inspection of the lining may be carried out at any time prior to and after installation of the
pipes. Any pipe with lining that is broken, defective or otherwise not in accordance with the
Specification shall be rejected. Remedial lining operations may be carried out by a method
that has been approved in writing in advance by the Engineer.

Surface crazing of the lining will be acceptable unless cracks are so severe that they can
be penetrated to a depth of 2 mm by a 250 microns feeler gauge at 10 points or more over
a length of 300 mm when measured with the lining in a saturated condition. Such cracks
shall be cut back to full depth and sealed with an approved epoxy resin filler.

GKW - Alliance 102


SPECIFICATIONS
CIVIL WORKS

Concrete lining shall be omitted at the following locations:

Sleeve and spigot ends: lining shall terminate 100 mm back from both sleeve and
spigot pipe-ends. The edge of the lining shall be angled
back at 75 degrees to the pipe axis in order to provide a
positive key for in-situ joint protection.

Pipe-ends for butting: the lining shall terminate 100 mm back from welding of the
pipe-end. The edge of the lining shall be angled back at 75
degrees to the pipe axis in order to provide a positive key
for in-situ joint protection.

Cable pass holes: the lining shall be omitted over an area 25 mm around cable
pass holes and provide a positive key for in-situ protection
after the cable pass hole has been permanently closed.

Curing of Factory Applied Concrete Lining

Lined pipes shall be moist cured at atmospheric pressure in sealed chambers. Curing shall
be continuous and the lining shall not be subjected to rapid changes of temperature either
during or at the end of curing.

Within one hour of completion of lining, the lined pipes shall be sealed into the curing
chambers in which air shall be maintained in a saturated state while the temperature is
raised þ at a rate not exceeding 16C per hour to 43C. The lining shall then be cured for
at least 24 hours during which time the temperature shall be maintained between 43C and
65C. The lining shall then be kept moist by continuous water spraying for a period of at
least 3 days. This procedure may be varied in the light of experience with the approval of
the Engineer.

On completion of water curing, pipes shall be protected from sunlight and the linings shall
be kept moist for a further period of one week.

Zinc Coating

Where exposed in chambers or otherwise specified, pipes and fittings shall be given, after
blast cleaning, an approved system of abrasion-resistant zinc based coating consisting of
three layers built up to a minimum total dry film thickness of 150 microns. This coating shall
conform to the applicable standard.

Other Coatings

The external surfaces of the pipe-ends for use with mechanical couplings and flange
adapters shall be given, after blast cleaning, a low friction vinyl-based protective coating.
The coating shall be applied in accordance with the manufacturer’s instructions. Where
zinc or bituminous coatings adjoin the low friction coating, they shall overlap each other by
25 mm. The length of pipe barrel to be so protected by the low friction coating shall be 300
mm, unless directed otherwise. After curing but before removal from the factory, the coating
shall be wrapped with tape suitable for protecting the coating from damage in transit to and
on the Site. The tape shall be removed immediately prior to installation.

Steel couplings, flange adapters and fittings shall have all parts protected at time of
manufacture by a nylon coating.

GKW - Alliance 103


SPECIFICATIONS
CIVIL WORKS

1.13.3.14 Ductile Iron Pipes

General

The pipes and fittings shall be manufactured according to the specification for centrifugally
cast ductile iron pipes, fittings and appurtenance as specified in ISO 2531 and ISO 7186,
any equivalent approved standard for ductile iron pressure pipelines.

Pipes, fittings and accessories should have no faults likely to be detrimental to their use.

An appropriate heat treatment to give the required mechanical characteristics is acceptable


but subject to approval and marking of so treated units. Units showing small imperfections
inseparable from the method of manufacture may be rejected.

Repairs of imperfections or defects whatsoever are subject to previous agreement with the
Engineer. Welding of defects will not be acceptable.

Jointing

Pipes and fittings are generally of socket and spigot type if not otherwise stated.

Joint rings are moulded components. Their general cross-section shall give a large sealing
surface and a substantial reserve of elasticity. They shall have a smooth and clean surface,
and must be without visible defects, neither permeable nor spongy.

Different joint qualities are subject to prior approval of the Engineer.

Test of joint rings shall be performed but not limited to the tests stated below. Where
applicable, they have to be performed for new, artificially aged and cold stored rings
according to relevant acceptable standards as before indicated.

 Shore - Hardness
 Tensile strength, elongation
 Elasticity
 Swelling
 Artificial aging and cold storing

Marking of joints shall include:

 Manufacturer's sign,
 an indent that the casting is for ductile iron,
 nominal diameter,
 the mould number,
 the year of manufacture,
 identification of rubber quality.

Each consignment has to specify in the shipping documents:

 Specification of rubber quality,


 Reference number of order,
 Dispatch date.

GKW - Alliance 104


SPECIFICATIONS
CIVIL WORKS

Coating

Except where otherwise specified, pipes, fittings and accessories shall be coated inside
and outside in accordance with ISO 4179 and ISO 179, respectively.

The coating must be set quickly and not flake off.

(i) Inside Coating

The inside coating must not contain any constituent soluble in water or any ingredient
liable to impart any taste or smell to the water after suitable washing of the main.

Pipes and fittings must have inside coating in cement mortar lining.

Selection of the raw materials, evaluation of the quality of the finished lining and
determination of the layer thickness has to be made in accordance with ISO 4179-
1985 (E).

The mixing water for the preparation of the mortar shall not contain substances
deleterious to the mortar, nor to the water it is eventually intended to transport in the
pipe.

The mortar for the lining shall be cast centrifugally inside the pipe.

The minimum standards of the hydraulic efficiency for ductile iron pipes have to be
kept.

(ii) Outside Coating

The ductile iron pipes, fittings and specials shall be protected by the application of
zinc layer with bitumen coating in conformity with ISO 8179-1:1995 (E).

However, the Contractor may offer alternative protection as described under sub-
paragraphs (a) and (b).

(a) Special Coating

(SECURITY BITUMEN ENAMEL WRAPPING)

The pipe is primed with a compatible primer. Hot bitumen enamel, a mixture
of blow asphaltic bitumen and slate flour, is applied and spiral wrap of glass
tissue, at controlled tension impregnated by the enamel. A second spiral wrap
of pre-impregnated, longitudinally reinforced glass tissue is applied and
completely bonded to the centre surface.

The minimum overlap for each spiral wrapping is 2 cm. The minimum thickness
of the protection is 3 mm at any one point. Finally a coating of lime-wash is to
be given.

(b) Plastic Coating

In the areas with aggressive soil conditions polyethylene hoses may be


required. Alternatively, plastic coating may be applied. This has to be
executed in a fusion-bonding process. The descaled pipes are suitably heated
and the pulverized polyethylene is spread evenly over the rotating pipe for a
certain period of time. The pulverized polyethylene fuses on the pipe surface

GKW - Alliance 105


SPECIFICATIONS
CIVIL WORKS

to form a homogeneous, firmly adhering plastic coating without porosity.


Minimum thickness of plastic layer should be according to the applicable
standard.

(iii) Materials for Joint Coating

The Contractor shall supply sufficient coating materials so as to enable execution of


the insulation accordingly at all joints inside and outside, and to perform necessary
repairs.

(iv) Tests on Coating

Apart from the standard tests to be executed during manufacture, the Engineer may
call for tests and if it is necessary, subsequent repair prior to taking over at site. Such
tests may include:

 Ultrasonic and electromagnetic inspection for coating thickness;


 High voltage tests on thickness of outside protection;
 Chemical analysis.

(v) Pipe Lengths

The standard manufacturing lengths of spigot and socket pipes should be a minimum
of 6.0 m. Out of this the Contractor may supply up to 10% in lengths shorter than the
standard lengths specified.

Admissible reduction in length: 0.3 - 1.0 - 1.5 - 2.0 m.

1.13.3.15 Unplasticised Polyvinyl Chloride (uPVC) Pipelines

uPVC pipes and fittings shall be in accordance with the applicable standard.

Joints for uPVC pipelines buried in ground shall be push-in flexible mechanical type with
resilient sealing gaskets, except where otherwise specified or shown.

Joints for uPVC pipelines installed above ground shall be solvent welded type to the
applicable standard, except where otherwise specified or shown. The Contractor shall
obtain and submit to the Employer’s Representative test certificates from the manufacturer
showing that the materials supplied can be expected to meet the strength requirements for
the class of pipe supplied at the age of 50 years.

1.13.3.16 Glass Reinforced Plastic (GRP) Pipe

Scope

This specification applies to the materials and workmanship involved in the manufacture,
testing, delivery and installation of large diameter underground glass reinforced plastic
piping, joints, fittings and specials.

Codes and Standards

All pipes, joints and fittings shall be supplied in accordance with this specification for
“Fibreglass” (Glass-Fibre Reinforced Thermosetting - Resin) Pressure pipe.

GKW - Alliance 106


SPECIFICATIONS
CIVIL WORKS

Product Description - Materials

Resin

The manufacturer will use only approved polyester resin systems for which he can provide
documented performance in this particular application. The data shall have been acquired
from a composite material of similar construction and composition as the product proposed
for this project.

Glass Reinforcements

The reinforcing glass fibres to be used to manufacture the components shall be of highest
quality commercial grade of glass filaments suitably treated with binder and sizing
compatible with impregnating resins.

Fillers

Silica sand or other suitable materials may be used as fortifiers in the laminates.

Additives

Resin additives, such as pigments, dyes, and other colouring agents, if used, shall in no
way be detrimental to the performance of the product, nor shall they impair visual inspection
of the finished product.

Elastomeric Sealing Rings

Elastomeric sealing rings must be supplied by recognised, acceptable quality


manufacturers. The elastomeric compound used must be compatible with the use
environment.

Manufacture and Construction

Pipes

Pipes shall be supplied in accordance with the diameters, pressure classes, stiffness
ratings and tolerances necessary to meet all applicable constructional and operational
conditions. They shall be manufactured by a controlled, reproducible process using the
specified materials to result in a corrosion resistant, composite structure to meet the
operating conditions. Stiffening ribs may be used to increase the overall pipe stiffness.

Couplings

Pipes shall be connected together using glass reinforced plastic sleeve couplings that utilise
elastomeric sealing rings as the sole means to maintain joint water-tightness. The joints
must meet the performance requirements of ASTM D 4161.

Fittings

GKW - Alliance 107


SPECIFICATIONS
CIVIL WORKS

Flanges, bends, reducers, tees, junctions and other fittings shall, when installed, be capable
of withstanding all operating conditions. They may be contact moulded, filament wound or
manufactured from mitred sections of pipe joined by glass-fibre reinforced polyester
overlays.

Dimensions

Pipe dimensions including length, diameter and wall thickness shall be consistent with
standard manufacturing configurations and tolerances. Alternative section lengths may be
supplied for special orders, subject to the approval of the Engineer. A maximum of 10% of
the pipe sections may be supplied in random lengths and, where designs require it, short
lenghts “rocker” pipes may be supplied. Minimum single point wall thickness shall not be
less than 87.5% of the stated thickness. Pipe ends shall be square to the pipe axis + 6 mm
or + 0.5% of the nominal diameter, whichever is the greater. Angle tolerances on bends,
junctions and tees shall not exceed + 2.0 deg. and the tolerance on laying length is + 50
mm.

Other Characteristics

GRP pipes shall have a stiffness suitable for the expected operational conditions including
negative pressure. Pipes shall be suitable for operating classes PN10, PN 16 and PN 25
with a 40% increase allowable for transient (surge) pressures.

Qualification Testing

The physical properties and characteristics of the pipes shall be determined by prototype
testing of the manufactured product. All prototype tests results shall be retained by the
Manufacturer and made available to the Engineer.

Quality Control Testing

Quality control testing on pipes shall be conducted in strict accordance with this
specification. These tests will, as a minimum, cover:

A. Raw materials
B. Pipe stiffness
C. Hydrostatic testing (as agreed with the Employer’s Representative)
D. Load capacity
E. Barcol hardness
F. Critical dimensions
G. Visual appearance

Adequate records must be kept by the Manufacturer, Contractor and Engineer. Quality
Control Tests may be witnessed by the Engineer.

Raw Materials

Raw materials for use in pipes covered in this specification shall be sampled and tested by
the manufacturer prior to their use, to ensure that they comply with the specifications in

GKW - Alliance 108


SPECIFICATIONS
CIVIL WORKS

effect at the time of purchase. Any materials failing to meet the requisite standards shall
immediately be rejected.

All materials shall be delivered with appropriate vendor certificates to demonstrate their
compliance with the Manufacturer’s specification.

Pipe Stiffness

Samples of pipe shall be tested for compliance with the specified pipe stiffness. The
frequency of pipe ring sampling shall be once per shift/machine or one per 100 pipes,
whichever is the most frequent. If one sample fails the whole series of pipe should be re-
tested. If it still fails, two (2) additional samples shall be cut from the lot (from the preceding
and following pipes). If they both pass, then the entire batch except the pipe is considered
acceptable. If not as above, the pipes must be proven individually acceptable. Testing will
be carried out in accordance with ASTM D2412, with the stiffness value rated at 5%
deflection.

Hydrostatic Leak Testing

The manufacturer shall, in agreement with the Engineer, hydrostatically test pipes in
accordance with section 2.3.1.1 of AWWA C950. Any pipes failing to pass this test will be
rejected. Rejected pipes may be repaired and re-tested, if they pass, they will be accepted.

Load Capacity (Hoop and Axial)

Tests will be performed in accordance with the requirements of AWWA C950 and ASTM
D3517 to check load capacity (or strength), both in the hoop and axial directions. One test
for each characteristic shall be made per 100 pipes.

Should samples fail to meet or exceed the stated values for each test, two additional
samples shall be cut from the preceding and following pipes. If they both pass and the
average of all three sets also passes, then the entire lot is considered acceptable.

Barcol Hardness Test

Barcol hardness tests will be conducted in accordance with ASTM D2583. Pipes failing to
reach the required level of cure will be rejected. Rejected pipes may be re-tested in
accordance with this specification. If their cure at this time has reached the required
standard, they will be acceptable.

Critical Dimensions

Pipes will be measured for compliance with critical dimensions and their tolerances
including diameter, thickness, end-form and length. Measurements will be made in
accordance with ASTM D3567.

1.13.3.17 Pre-stressed Concrete Pressure Pipes

Manufacture

GKW - Alliance 109


SPECIFICATIONS
CIVIL WORKS

Pre-stressed concrete pressured pipes (cylindrical and non-cylindrical), joints, fittings and
accessories shall be manufactured to comply with the provisions of European Standards
EN 639 and EN 642. These standards cover the requirements and the manufacture of pre-
stressed concrete pressure pipes in sizes from ND/ID 500 to ND/ID 4000 inclusive.

Materials are specified in Clause 5 of EN 639 - Common Requirements.

Joints

The joint consists of the spigot of one pipe, with a groove, and of the socket or “bell” of
another, between which the elastomer gasket is confined. The elastomer gasket is made
of a cord of circular section sealed by vulcanised welding, and it ensures water-tightness
between two pipes. Maximum clearance inside the joint shall be 1 cm.

Coating

Coating shall be either by mortar coating or concrete coating. The coating shall be of the
highest quality to protect the pre-stressed core. For waters which are aggressive to
ordinary cement, and for extremely corrosive soils, the Contractor shall be required to prove
stability and durability of the standard coatings and the non-corrosiveness of the concrete
and steel, or additional protection shall be provided such as the use of polyethylene
wrapping.

Dimensions

Pipe dimensions (internal and external diameter, wall thickness, overall and effective
lengths) shall be appropriate for the works to be provided in terms of hydraulic and structural
designs.

Product

Concrete Strength

At the time of applying the circumferential pre-stressing the concrete shall have a minimum
compressive strength of 27 MPA. At 28 days the concrete shall have a minimum
compressive strength of 35 MPA.

Pressure Classes

Pressure classes shall be PN 10, 16 and 25 bars.

1.13.3.18 Cable Ducts

Cable ducts shall be uPVC pipes. Joints for uPVC ducts shall be spigot and socket welded,
push in rubber ring or other approved. Draw cord shall be polypropylene cord having a
breaking load of not less than 5 kN.

1.13.4 Workmanship

GKW - Alliance 110


SPECIFICATIONS
CIVIL WORKS

1.13.4.1 Handling

The Contractor shall supply handling equipment as necessary for installation of pipelines,
without damaging pipeline materials including exterior and interior coatings. The equipment
shall include lifting beams, reinforced canvas slings, protective padding, struts, cradles,
pipe trailers and the like. Wire rope or chain slings shall not be used for handling pipeline
materials.

Throughout the installation of the pipeline, the Contractor shall not use methods, plant or
equipment which may cause damage to the pipeline materials.

Temporary packing, coverings or crates provided for the protection of pipeline materials in
transit shall not be removed (except for purposes of inspection after which they shall be
replaced) until immediately before installation, and shall then be disposed of by the
Contractor.

The Contractor shall ensure that the above requirements are also observed whenever pipes
are handled, whether during shipment or otherwise, and that all necessary precautions are
taken, including the provision of adequate temporary protection, to ensure that pipes will
not be damaged in any way whilst being handled, transported and stored.

1.13.4.2 Delivery

The Contractor shall take delivery of pipeline materials at times and locations or storage
areas on or about the Site to be arranged with the suppliers. Any such location or storage
area which is not part of the Site shall be arranged for by the Contractor at his own risk and
without extra cost to the Employer.

All items shall be inspected for damage and checked for shortages against packing lists
immediately on delivery. Damage and shortages shall be remedied with the minimum of
delay.

The Contractor shall keep records of all pipes and fittings received on the site. The records
shall include the unique reference number of the piece the reference of fabrication records,
works test certificates, delivery notes and the report on the condition of the piece as found
during inspection upon delivery and before storage. The Contractor shall check for and
resolve any numerical anomalies that are found in reference numbering of pipes and fittings
arriving on the Site. The Contractor shall copy the above record to the Engineer at least
once per week during the currency of delivery of pipes and fittings.

In the event of a fusion bonded epoxy coating being damaged after leaving the factory, the
item shall be returned to the factory for repair or, with the approval of the Engineer, be
repaired at Site. Repairs shall be effected in accordance with the following requirements:

(a) repair materials shall be compatible with the original factory-applied coating materials
and, where applicable, shall comply with the second paragraph of Clause 4.15.4.1;

(b) the edges of the original factory-applied coating shall be ground off to a taper or
feather edge;

(c) exposed metal shall be treated as specified in Clause 4.15.4.6;

(d) the relative humidity of the atmosphere in which the repair is to be effected shall be
maintained (if necessary by the use of hot air blowers and tenting) at less than 85%.

GKW - Alliance 111


SPECIFICATIONS
CIVIL WORKS

(e) the surface temperature of the exposed metal shall be raised to at least 3°C above
dew point and the coating shall then be applied in stages, as recommended by the
manufacturer, so as to achieve a total thickness in accordance with Clause 4.15.4.6.

All repairs shall be checked with a holiday detector and any holes shall be repaired, after
which the repairs shall rechecked.

1.13.4.3 Storage

The Contractor shall take into temporary protective storage all pipeline materials not
required for immediate installation in the Works or, in the case of pipes, be responsible for
stringing them out along the pipeline route.

Pipes and fittings, at all times prior to installation, shall be laid on wedged timber bearers
so as to be at least 75 mm clear of the ground. Subject to the manufacturer’s
recommendations pipes may be stacked up to three pipes high if suitable protective packing
is placed between the layers. All pipes and fittings shall be suitably cushioned at all points
of support so as to prevent damage to the pipe wrapping or coating.

The period between taking delivery of a pipe and the completion of its installation shall be
kept to a minimum. Pipes may be strung out along the pipeline route prior to installation
providing that any necessary temporary fencing has first been erected. Jointing parts and
materials shall be stored under cover. Pipes and fittings liable to be affected by exposure
to ultra-violet radiation shall be kept under cover, except when being handled during
delivery or installation.

1.13.4.4 Installation

Trench excavation and backfill shall be carried out in accordance with the requirements for
Earthworks in this Specification.

Trench excavation and backfill shall be co-ordinated with the construction of the pipeline as
a whole so as to ensure expeditious completion of the whole operation.

Where Trench Excavation is to be carried out in areas where buried pipes or cables are
likely to be encountered, the location of such pipes or cables shall, whenever practicable,
be determined ahead of Trench Excavation. Methods used for detecting the location of
pipes and cables shall include the use of electronic detection equipment.

The lines and levels of the pipeline and the positions of bends, junctions and other fittings
may be adjusted by the Engineer as necessary before construction of a particular section
commences. The pipeline shall be accurately installed to the lines, levels, grade and
positions set out by the Contractor from data supplied to him by the Engineer, so that the
barrel of the pipe shall be continuously supported throughout its length by the bottom of the
trench or by bedding material as specified.

The Contractor shall submit full details of the methods he proposes to use for control of the
accuracy of pipe laying. The invert level of any pipe shall be within  6 mm of the specified
level unless specified otherwise.

Pipes shall be laid to even grades for as long a length as possible, with a minimum. grade
of 0.2%, irrespective of local changes of elevation of the ground surface. Changes in
direction or in grade of the pipeline shall be carried out by making use of any permissible
deflection of joints between straight pipes or by the introduction of bends.

GKW - Alliance 112


SPECIFICATIONS
CIVIL WORKS

Flexibly jointed socket and spigot pipes shall normally be laid with sockets leading. Where
the gradient exceeds 5%, installation shall proceed on an ascending grade with sockets
leading. Except as otherwise specified, pipes shall generally be installed singly and shall
not be jointed until after they have been laid. After laying and jointing, the invert level of
each pipe shall be checked before the next pipe is laid.

Joint holes shall be excavated to provide adequate clearance to enable joints to be made
satisfactorily and any specified wrapping to be completed and to provide a clearance of at
least 50 mm from the trench bottom below the joints.

The Contractor shall keep the interior of pipes clean and free from water, dirt, stones and
other foreign matter as installation proceeds, and at the end of the day’s work or at other
times when installation work is not proceeding the open ends of pipes shall be sealed by a
suitable stopper. The Contractor shall take such precautions as are necessary to prevent
pipes from floating.

Wherever pipes, cables, ducts and similar services are buried in the ground, a marker tape
shall be laid 300 mm above each and every service in the trench.

GKW - Alliance 113


SPECIFICATIONS
CIVIL WORKS

1.13.4.5 Jointing

Before making any joint the Contractor shall ensure that the interior of each pipe or fitting
is clean. The Contractor shall clean the end of each pipe to be jointed and shall prepare
the ends for jointing as necessary. All mechanical joints shall have their coating made good
before assembly in accordance with the coating manufacturer’s recommendations.

The Contractor shall use only the proper jointing parts as specified and obtained from the
suppliers of pipes or fittings. All joints shall be assembled and tightened and shall be made
only on pipes which comply dimensionally and have been prepared in accordance with the
joint manufacturer’s instructions, and shall be capable of passing tests for individual joints
and for the completed pipeline as specified.

Longitudinal movement of pipes joined by mechanical couplings shall be restricted by a


steelwork harness approved by the Engineer. After installation the harness shall be cleaned
and painted with two coats of bituminous paint before wrapping.

Where a change of direction is to be achieved by the deflection of a flexible joint of any


kind, the deflection shall not exceed 50% of the maximum value for the size and type of
joint as specified by the manufacturer, unless otherwise specified.

After completing the joint any protective or other coating shall be made good and any lining
and joint protection completed as specified, without delay.

1.13.4.6 Flanged Joints

When assembling flanged joints, the rubber joint ring may be fastened to the bolts with
cotton thread. The use of jointing paste or grease will not be permitted. The bores of
abutting pipes or fittings and the joint gasket shall be concentric; no joint material is to be
left protruding into the bore. All nuts shall first be tightened by hand and nuts on opposite
sides of the joint circumference shall then be alternately and progressively tightened with a
spanner so as to ensure even pressure all round the joint.

1.13.4.7 Work inside Pipelines

The Contractor shall provide, operate and maintain adequate systems of access, lighting
and ventilation to any part of a pipeline where work is in progress inside the pipes.

1.13.4.8 Sleeving of Pipelines

Where the application of polyethylene sleeving is specified, the following procedure shall
be followed. Immediately before lowering the pipes into the trenches the sleeving as
specified shall be slipped over the pipes and secured in place using adhesive PVC tape.
The sleeving shall be pulled tight against the lower part of the pipe and the excess girth
shall be gathered into a fold situated in the upper part of the pipe as laid. This fold shall be
directed downwards from the crown of the pipe. The sleeving at the ends of the pipes shall
be left loose until after jointing and wrapping has been completed. The loose sleeving shall
then be carefully pulled over the joints so that it is continuous, and joints at the overlaps
shall be secured with PVC tape. Bends, tees and similar fittings shall be protected similarly.
Any sharp edges such as at bolted gland or flanged joints shall be padded with four
thicknesses of sleeving material before the sleeving is placed over them. Care shall be
exercised during handling, installing and backfilling to prevent damage to the sleeving. Any
minor damage to the sleeving shall be repaired by wrapping a sheet of material cut from
the sleeving material right round the pipe, and so that it provides an overlap of at least 200

GKW - Alliance 114


SPECIFICATIONS
CIVIL WORKS

mm past each side of the puncture; all edges being taped to the sleeving. Polyethylene
sleeving shall be discontinued where pipes are fully surrounded with concrete, the sleeving
being lapped a minimum of 150 mm by the concrete.

Where the sleeving is to terminate where a pipe enters a concrete structure, the end of the
sleeving shall not be embedded in the concrete. Before placing the concrete, the end of
the sleeving shall be folded back clear of the concreting operations and a run of adhesive
PVC tape not less than 50 mm wide shall be fixed around the pipe barrel so that the centre
of the tape is aligned with the eventual position of the concrete face. After concreting is
completed, the sleeving shall be reinstated around the pipe up to the concrete face, any
surplus being neatly folded back and secured to the pipe barrel with PVC tape. This shall
be done in a way such that the end of the sleeving overlaps the tape previously placed
around the pipe and such that no part of the pipe remains exposed. The termination of the
sleeving shall be completed by placing a further run of adhesive PVC tape around the pipe,
spanning between the end of the sleeving and the face of the concrete.

1.13.4.9 Cutting Pipes

Pipes which are to be cut to enable fittings to be accurately positioned or to form closing
pieces in any portion of the pipeline, or to terminate in manholes or other parts of the work,
shall not be cut until after adjacent pipes have been laid and jointed and accurate
measurement of the length required can be made. The Contractor shall determine the
length of each cut pipe and the required angle and shape of the cut. The cut shall be neatly
performed by an experienced skilled man using tools or machinery appropriate for the type
and diameter of pipe to be cut. The cut ends of the pipes shall be shaped up and trimmed
so as to ensure an accurate joint or termination as the case may be. Any damage to
wrapping, coating or lining shall be made good.

The unused part of any cut pipe shall be disposed of off the Site unless, with the Engineer's
approval, it can be used elsewhere in the Works or is required to be returned to the
Employer for use in future maintenance works.

1.13.4.10 Closing Lengths, etc.

Pipes for closing lengths, or for inserting into pipelines already laid, shall be cut to allow a
20 mm gap between adjacent pipe ends. The closing joints in pressure pipelines shall be
made with detachable flexible couplings with locating plugs except where otherwise
specified.

Where in the opinion of the Engineer completion of the internal lining would be impracticable
or undesirable, the pipe ends (including the inside and outside of the pipe walls) shall be
protected with an approved site-applied coating, applied in accordance with the
manufacturer’s instructions, and the coupling shall be protected with a factory-applied
thermoplastic nylon coating.

GKW - Alliance 115


SPECIFICATIONS
CIVIL WORKS

1.13.4.11 External Wrapping

Where specified, pipelines shall be wrapped with material as follows:

After the jointing operation is complete, the pipe joint or fitting shall be thoroughly cleaned
and dried and given one coat of primer supplied by the manufacturer of the wrapping
material. The joint or fitting profile shall then be modified by the application of moulding
putty supplied by the manufacturer of the wrapping material to provide a suitable profile for
wrapping. Wrapping shall then be continued over the joint and shall lap with the works
applied external protection on the pipes, each side of the joint or to the extent specified
elsewhere. The wrapping shall be applied under tension to achieve conformability and
intimate adhesion without trapped air pockets. Longitudinal overlap between adjacent
strips shall be 25 mm minimum. End overlaps where a new roll joins a completed one shall
be 150 mm minimum.

1.13.4.12 Concrete Bed and Surround

Where specified, pipes shall be bedded and surrounded in concrete. Concrete shall be
unreinforced of the adequate class. Any formwork required shall be of Class F1.

Each pipe shall be supported on at least two purpose-made precast concrete blocks, which
shall be left in place. Concrete, other than the precast blocks, shall not be placed until the
joints at each end of the pipe have been completed. The full width and depth of bedding
concrete shall be placed and carefully worked and compacted beneath the pipe, followed
at once by the addition of concrete surround. Unformed surfaces shall be of spade finish.
The pipe shall be prevented from floating or otherwise moving during concreting.

The continuity of concrete bed, haunch or surround to pipes with flexible socket and spigot
joints shall be broken at each flexible joint by 25 mm thick fibreboard, placed against the
face of the socket. The concrete bed, haunch or surround shall be discontinued at
detachable flexible couplings, leaving a clearance of 75 mm each side of the coupling.

1.13.4.13 Anchor and Thrust Blocks

Concrete anchor and thrust blocks shall be constructed at all tees, bends, tapers, valves
and hydrants for the anchorage of the pipeline. Concrete shall be of the specified class.

Unless otherwise stipulated, thrust blocks shall be constructed with the bottom and thrust
side surfaces bearing against undisturbed ground.

If blinding concrete is required or allowed to be placed beneath any horizontal thrust block,
shear keys shall be formed on its upper surface as directed by the Engineer.

1.13.4.14 Chambers and Manholes

Valve chambers, air valve chambers, flow-meter chambers, manholes and similar
structures shall be built into the pipeline and shall be constructed in accordance with the
Specification.

Valve chambers in which pipes are anchored shall be treated as specified for anchor and
thrust blocks.

If undisturbed ground has not been maintained next to a thrust bearing surface, the gap
shall be backfilled with mass concrete.

GKW - Alliance 116


SPECIFICATIONS
CIVIL WORKS

All chambers and manholes shall be cleaned of any accumulation of silt, mortar, debris or
any other foreign matter and shall be free of any such accumulation at the time of final
inspection.

1.13.4.15 Pipelines built into Structures

Any pipeline which is built into a chamber, manhole or other structure, including a thrust
block, shall be provided with two flexible joints outside each face of the structure. Unless
otherwise specified, the first joint shall be not more than one pipe diameter or 500 mm,
whichever is the smaller, from the outside face, and the length of pipe between the flexible
joints shall be equal to two pipe diameters or 1000 mm, whichever is the greater.

The flexible joints shall be either flexible spigot and socket joints or detachable flexible
couplings.

Pressure pipes passing through the walls of valve chambers or other structures shall be
ductile iron or steel provided with anchorage flanges designed to transmit the full end thrust
with closed valve under test into the structures wall. Boxouts, if used, shall be designed to
fulfil the above requirements. Drawings showing the method of construction using boxouts
shall be submitted for review by the Engineer.

Where no anchorage flanges are detailed for pipes passing through the walls of structures,
the pipe shall be provided with a puddle flange integral with the pipe wall or bolted on to
resist movement of water along the pipe to concrete interface. Such puddle flanges shall
protrude at least 50 mm from the pipe barrel.

Where the pipeline is above ground level, the short length of pipe providing flexibility shall
be self-supporting.

1.13.4.16 Pipelines in the same Trench

Where two or more pipelines are detailed as being laid in the same trench, the pipes shall
be laid so that there is a minimum distance of 300 mm between the barrels of the pipes,
measured in plan at mid-barrel height, unless a greater distance is required to enable
jointing to be properly completed. The invert levels of the pipelines shall be the same at
any cross section, unless otherwise required.

The larger of the pipelines shall be laid in straight lines between bends. Where it is
necessary to increase the distance between the pipelines from that specified above to allow
the construction of air valve or washout chambers or for any other reason, the deviation of
a pipe from the line of the preceding pipe shall be made by deflecting as many flexible joints
as necessary to limit the amount of deflection at each joint to not more than half that
available.

1.13.4.17 Installation of Pipelines other than Buried Pipelines

The Contractor shall take due care to support adequately the pipework during installation
until permanent supports and anchorages have been completed. The Contractor shall
ensure that no excessive loads or stresses are imposed upon the plant, pipework or
structure during installation.

Pipework systems shall be complete and checked for correct position and alignment with
adjacent plant and structures immediately before and after being embedded in concrete.

GKW - Alliance 117


SPECIFICATIONS
CIVIL WORKS

1.13.4.18 Crossing Existing Pipelines and Buried Cables

Where pipelines cross existing pipelines or buried cables, the crossings shall be
constructed taking particular care to avoid damage to the existing pipelines or cables. The
Contractor shall give one month’s advance notice of the work to the owners of the existing
pipelines or cables, and shall comply with any special requirements of the owners for safety
or security during progress of the work.

1.13.4.19 Connecting to Existing Pipelines

Where a connection of any kind is to be made into an existing pipeline, or whenever directed
by the Engineer to make such a connection, the Contractor shall verify before starting work
on the connection, if necessary by excavating trial pits, that the materials to be furnished
under the Contract will be suitable for making the connection.

Before connecting on an existing pressure pipeline, the Contractor shall locate the valves
governing the flow to the section of pipeline in question. These valves shall be shut and
subsequently re-opened only after obtaining the approval of and at times approved by the
Engineer. The period of interruption of the service in the existing pipeline shall be
minimised.

The new pipeline and where practicable the existing pipeline at the connection shall be
tested for leakage. Any existing pipe, fitting or joint leaking due to damage occurring during
the connection operation shall be removed and replaced by the Contractor at no extra cost
to the Employer. The test shall be repeated until a satisfactory test is obtained. Additional
cleaning and disinfection procedures required in respect of the connection shall be
performed by the Contractor.

1.13.4.20 Plugging of Dead Ends

The dead ends of pipes and fittings shall be plugged and concrete anchors shall be
provided.

1.13.4.21 Cables Sharing Pipeline Trenches

Where cables are to be laid in pipe trenches, the pipes shall be installed and fine backfill
shall be placed to 150 mm above the crown of the pipe. The cable shall then be laid before
the remainder of the trench is backfilled.

Where ducts are detailed as being laid in large radius curves in either the horizontal or
vertical plane, these shall normally be not less than 50 m radius, unless a smaller radius is
specifically detailed. In no case shall a curve of less than 25 m radius be installed. Ducts
shall be laid in regular curves of the required radius by bending the pipe during installation.
Curves shall not be formed with angular deviations at flexible joints.

The Contractor shall provide the cable duct and draw cord as specified and shall lay and
joint the duct, complete with draw cord, in the pipe trench to the lines and levels ordered by
the Engineer within the nominal dimensions of trench excavations.

Joints in the draw cord shall be kept to a minimum; they shall be at least as strong as the
cord and shall be so made as not to cause any jamming in use.

GKW - Alliance 118


SPECIFICATIONS
CIVIL WORKS

In refilling trench excavation the Contractor shall ensure that the duct is not displaced or
distorted and that, whatever its position in the pipe trench, it is surrounded by at least 150
mm of well compacted soft material (free from stones greater than 20 mm in size). Where
directed by the Engineer the cable duct shall pass through sleeves cast into anchor and
thrust blocks and the walls of junction boxes and the like, but it shall not be buried in
concrete surround to pipes.

1.13.4.22 Marker Posts

In order to leave permanent indication of the route of the pipeline and the location of valves
and hydrants where they are below ground, the Contractor shall provide and set up marker
posts with indicator plates in accordance with the details specified. Route marker posts
shall be installed at every field and property boundary and elsewhere as ordered by the
Engineer. The Contractor shall insert a peg at the proposed location of each marker post.
Marker posts shall be installed only after their location has been approved by the Engineer.

The marker posts shall be set up as soon as practicable after trench excavations have been
refilled, but the Contractor shall provide any temporary marking required and shall be
responsible for correct information being given on the indicator plates. Indicator plates shall
be fixed to their marker posts.

1.13.4.23 Cleaning Pipelines

Before commencing pressure testing, the Contractor shall clean out the part of the pipeline
to be tested to the satisfaction of the Engineer.

After the whole pipeline has been successfully pressure tested (whether as a whole or in
sections) and the Contractor has removed all temporary works and has reconnected any
parts temporarily removed from the pipeline, the Contractor shall finally clean out the whole
pipeline and flush it through with clean water.

Flushing water shall be discharged only on sites or into conduits that are suitable.
Discharges which cause damage, create a nuisance or health hazard, or interfere with the
work of others will not be permitted.

The Contractor shall be liable to the Employer for any damage caused to the pipeline or to
pumps and other equipment of the Employer, as a result of foreign matter of any kind not
having been cleared out of the pipeline before it is handed over to the Employer.

1.13.4.24 Disinfection of Pipelines

Disinfecting pipelines shall be carried out in accordance with AWWA C601, except as
otherwise specified.

Liquid chlorine, calcium hypochlorite or sodium hypochlorite may be used for disinfecting.
If liquid chlorine is to be used, it shall be used only in conjunction with proper equipment
and under the supervision of qualified personnel who are familiar with the physiological,
chemical and physical properties of this element, and who are properly trained and
equipped to handle any emergency that may arise.

Potable water pipelines shall be disinfected by the continuous feed method. Water entering
the pipeline shall be maintained at a minimum of 20 mg/1 available chlorine or such level
as may be necessary to ensure that at the end of 24 hours the treated disinfecting water
shall contain not less than 2 mg/1 of chlorine at all points in the pipeline being disinfected.

GKW - Alliance 119


SPECIFICATIONS
CIVIL WORKS

The chlorine concentration shall be measured at regular intervals in accordance with


AWWA M12 to assure that the required concentration is maintained.

After the required retention period the heavily chlorinated water shall be flushed from the
main, using potable water, until the chlorine concentration in the water leaving the main is
no higher than that generally prevailing in the systems and not exceeding 1.0 mg/l. Chlorine
residual determinations shall be made to ascertain that the heavily chlorinated water has
been removed from the main. Discharges shall be in accordance with Clause 4.15.5.23.

After final flushing and before a potable water pipeline is put into service, a sample, or
samples, shall be collected from the end of the main and tested for bacteriological quality
and shall show the absence of coliform organism. Samples shall be collected in sterile
bottles treated with sodium thio-sulphate. No hose or fire hydrant shall be used in the
collection of the samples. The Contractor shall install in the main, at no extra cost to the
Employer, a sampling cock with a copper tube gooseneck. The sampling cock shall remain
in place upon completion of the test.

If the initial disinfection fails to produce satisfactory samples, disinfection shall be repeated
until satisfactory samples have been obtained.

1.13.4.25 Steel Pipelines

Workmanship shall generally be in accordance with Sub-Sections 4.15.5.1 to 4.15.5.23 of


the Specification, with the following amendments and additional requirements. Installation
shall be in accordance with the recommendations of CP2010: Part 2 except where
otherwise specified.

1.13.4.26 Handling and Storage

Pipes shall be provided with adequate cushioned support during all stages of handling,
transport and storage in order to prevent damage to the pipe its wrapping or lining. Steel
pipes with concrete lining shall not be moved by rolling. If stacked in tiers, each pipe of the
bottom tier shall be supported on at least two purpose made cradles, each giving
continuous 120 support and cushioned with bags of sand, sawdust or other approved
material. Each pipe of the upper tier and of any intermediate tier shall be similarly
cushioned at all points of contact. The pipe manufacturer’s recommendations as to
stacking shall be strictly observed.

The period between completion of the external protection of a pipe and the completion of
its installation shall be kept to a minimum, and this period shall not generally exceed six
months.

1.13.4.27 Installation

Unless specified otherwise or as permitted below, pipes shall be installed singly and shall
not be jointed until after they have been laid.

Jointing of concrete lined steel pipes outside the trench and installation as a string of pipes
will be permitted only in straight trench, where all parts of the string are lowered into the
trench simultaneously. Such pre-jointed lengths shall not exceed 20 m without the
Engineer's written approval. Snaking into the trench of a pre-jointed string of concrete-lined
steel pipes will not be permitted. Changes in direction or in grade of the pipeline shall be
achieved whenever possible by the use of normal or shorter length pipes with the average
deflection per joint not exceeding l.5.

GKW - Alliance 120


SPECIFICATIONS
CIVIL WORKS

The deflection at any steel pipe sleeve and spigot joint shall not exceed 2.

Pipes manufactured with longitudinal or spiral welds shall be lined up before jointing, so
that these welds are at least 15 apart around the joint circumference.

1.13.4.28 Site Welding of Joints

Welding of joints in trench for steel pipes shall be carried out manually by the metal-arc
process.

Before starting the welding of pipe joints on Site, the Contractor shall submit, for the
Engineer's approval, details of the plant, methods and materials he proposes to use,
including make and size of electrodes, number of runs, current strength, and arrangements
for air testing of individual joints.

If required by the Engineer, the Contractor shall carry out tests to establish his proposed
procedure under Site conditions and on pipes of the same diameters and thicknesses as
are to be used in the Works.

Welded joints in trench shall generally be of the parallel short sleeve, spherical spigot and
socket type with a circumferential full strength fillet weld both internally and externally.
Welding gap tolerances shall be as specified. Full strength fillet welds shall have a throat
thickness not less than 0.7 times the thickness of the pipe to be welded.

Where pre-jointing of straight runs of pipe outside the trench is adopted, full penetration
butt welds executed by manual or automatic procedures to the approval of the Engineer
may be used. Butt welds shall have a throat thickness not less than the thickness of the
pipe wall. During welding, the pipe ends shall be securely held by an approved method
ensuring a correct and uniform root gap.

At closing lengths where two plain ended pipes are to be joined by a welded collar joint, the
gap between the two pipe ends shall not exceed 75 mm, and the collar shall be placed
centrally over the two ends to be jointed. The end of each pipe shall be welded to the
sleeve collar using circumferential full-strength fillet welds both internally and externally.
Where a split collar is used, the two halves shall be drawn together by tie bolts until the gap
between them is less than 3 mm. The four circumferential welds shall then be made, after
which the tie bolts shall be removed and the longitudinal seam between the collar pieces
welded. The tie bolt lugs shall then be cut off and the attachment points smoothed before
the welds are tested.

Welding gap tolerances for collar joints shall be as specified.

All parts to be welded shall have scale, slag, loose rust, paint and other foreign matter
removed by means of a mechanical brush and shall be left clean and dry immediately before
welding. All scale and slag shall be removed from each weld run when it is completed and
prior to air testing.

After completion of welding, at each joint magnetic crack detection tests shall be carried
out on all fillet welds made, and 100% radiographic examination carried out on all butt welds
made. All such tests shall be carried out by the Contractor in the presence of the
Employer’s Representative. Where butt joints are being welded mechanically, the
Employer’s Representative may permit the proportion of weld radio-graphically examined
to be reduced to 20% if and when and for as long as he is satisfied with the results being
obtained. Where necessary, welds shall be repaired in accordance with Section 10 of API
5L. Weld repairs shall not be made more than once at any position on the joint.

GKW - Alliance 121


SPECIFICATIONS
CIVIL WORKS

1.13.4.29 Welders and Welder Performance Tests

Welding shall be carried out only by welders approved by the Engineer, and each welder
shall identify his own work by means of a stencilled mark.

The Contractor shall submit for the Engineer's approval, the names of persons whom he
proposes to employ as welders and they shall carry out on Site the qualifying tests. The
Contractor shall maintain an up to date list of welders approved by the Engineer and, if
ordered by the Engineer, he shall remove from the approved list any welder whose
workmanship, as demonstrated by the results of air pressure and/or other tests and visual
inspection of individual welded joints, is in the Engineer's opinion below a reasonable
standard of quality or consistency.

1.13.4.30 Air Testing of Sleeve and Spigot Welded Joints

After each joint has been welded, it shall be subjected to an air test in the presence of the
Engineer.

A tapped hole, not less than 6 mm diameter, shall be provided in the sleeve end of each
pipe, into which a suitable pressure gauge shall be fitted for purposes of the test. An air
pressure of 4 bars shall then be pumped into the annular space between the sleeve and
spigot and the pump disconnected. In the case of split collar joints, a tapped hole shall be
provided at each end of the collar and each side of the joint shall be pressurised.

If no drop in pressure occurs over the ensuing period of 15 minutes, the test shall be
deemed successful. If the test pressure is not maintained for 15 minutes, the position of
the leak shall be determined using soap solution.

All defects in the weld shall be cut back and re-welded, and the test re-applied until
successful.

After testing, the tapped test holes shall be sealed with screwed plugs.

The requirements of this clause shall not limit the Contractor’s obligations in achieving
satisfactory results in the tests on completion as prescribed later.

1.13.4.31 Internal Protection at Joints

Hand placed in-situ mortar shall be used to complete the lining at joints and cable pass
holes in factory lined steel pipe. It shall be completed within 24 hours of backfilling that
length of pipe.

The Contractor shall not commence hand placed lining at joints until the two pipes
concerned have both been jointed and laid to the correct line and level in the trench, and
backfilled to the specified standard to at least 300 mm above the top of the pipe. Hand
placed mortar shall be finished with a steel trowel and shall have a smooth surface of
uniform appearance with even transitions to adjacent machine placed lining.

Hand placed in-situ mortar shall be as specified in Concrete and shall consist of 1 part of
cement to 1.5 parts of sand by volume, or other approved mix, and shall be of suitable water
content and consistency for adhesion and trowelling to a smooth finish. The thickness of
hand applied mortar shall be the same as the adjacent factory applied lining.

GKW - Alliance 122


SPECIFICATIONS
CIVIL WORKS

Areas to which hand applied mortar is to be applied shall be thoroughly cleaned of all loose
material and grease, and shall be moistened with water just prior to the application of the
mortar. Hand mortaring shall not commence until the Contractor has received written
confirmation from the Engineer that the surface preparation is acceptable.

Curing of the lining shall commence immediately after completion of the lining operation at
each joint or area of defect. The sections of the pipe to be cured shall be isolated and a
moist atmosphere shall be maintained at the place to be cured to keep the mortar lining
damp and to prevent evaporation of water from it. Curing shall continue for two weeks.

Curing compounds shall not be used without the approval of the Engineer, and if approved,
shall be used in accordance with the manufacturer’s recommendations or otherwise as
determined by the Engineer.

1.13.4.32 External Protection of Joints

All pipe joints in steel shall be protected from corrosion by external wrapping as specified.

No external protection shall be completed at joints until, where applicable, electrical


continuity has been provided and until the joint has been successfully tested: No backfilling
at joints shall take place until the Engineer has inspected and approved the external
protection of the joints.

1.13.4.33 Access to Interior of Pipelines

Pipes provided with cable pass holes shall be laid so as to provide a pass hole positioned
on the top of the pipeline at intervals of approximately 60 m. When a pass hole is no longer
required, the screw plug shall be replaced and welded to the pipe externally, and the internal
lining and external wrapping of the pipe shall be made good over the plug and holiday
tested.

The Contractor shall record the location of all cable pass holes and ensure the correct
sealing thereof.

1.13.4.34 Ductile Iron Pipelines

Workmanship shall generally be in accordance with relevant Sub-sections of the


Specification with the following additional requirements.

Installation shall be in accordance with the applicable standard except where otherwise
specified. Pipes of 450 mm nominal diameter and larger shall be cut only by means of a
motorised pipe cutting machine equipped with pipe cutting heads.

1.13.4.35 Un-plasticised Polyvinyl Chloride (uPVC) Pipelines

Workmanship shall generally be in accordance with Sub-sections 4.15.5.1 to 4.15.5.23 of


the Specification, with the following additional requirement.

Installation shall be in accordance with the recommendations of CP 312: Parts 1 and 2.

1.13.4.36 Glass Reinforced Plastic (GRP) Pipelines

GKW - Alliance 123


SPECIFICATIONS
CIVIL WORKS

Workmanship shall generally be in accordance with Sub-sections 4.15.5.1 to 4.15.5.23 of


the Specification, with the following additional requirement.

Field service representatives of the Manufacturer may be requested to be present


periodically during the installation of the pipes, and particularly at the outset of installation.

Classification of Soils in Relation to the Installation of GRP Pipes

Native soils are classified into five main groups of which the first two have two subgroups.
The soil groups are a function of both soil types (classification) and soil density, which
together determine the modulus of the soil. Relative quantification of densities may be
determined from blow counts (1) measurement as given in Table 4.15.1.

The blow counts (1) must represent the most severe (weakest) conditions expected to exist
for any significant period of time. (Normally this occurs when the water table is at its higest
elevation.)

 Group 1 VERY STABLE SOILS

1A DENSE (per Table 4.15.1)

Gravels or sands according to ASTM (2) GW, GP, SW and


SP containing less than 5% fines (or ATV type 1).

 Group 2 STABLE SOILS

2A MEDIUM (per Table 4.15.1)

Slightly silty or clayey gravels or sands according to


ASTM (2) GM, GC, SM and SC containing less than 15%
fines (or ATV type 2).

2B STIFF

Cohesive soils per Table 4.15.1.

 Group 3 SOIL MIXTURES

Typicall medium cohesive and/or loose granular (per Table


4.15.1) soils according to ASTM (2) ML or CL with liquid limit
less than 50 and GM, GC, SM and SC (or ATV type 3).

 Group 4 COHESIVE SOILS


Soft (per Table 4.15.1) soils per ASTM (2) MH, CH, OL and
OH (or ATV type 4).

 Group 5 COHESIVE SOILS

Very loose (per Table 4.15.1) soils per ASTM (2) MH, CH, OL
and OH (or ATV type 4).

Table 4.15.1: Native Soil Groups Classification

GKW - Alliance 124


SPECIFICATIONS
CIVIL WORKS

SOIL GROUP 1 2 3 4 5

Cohesive (3) Hard Stiff Medium Soft Very


(Fine Grained) Very Soft
Stiff

Granular (4) Very Dense Medium Loose Very


(Coarse Grained) Dense Loose

Blow Count (1) > 30 16-30 6-15 3-5 >3

(1) Blows measured according to standard method for Penetration and Split-Barrel
Sampling of Soils (SPT). ASTM Designation D1586.

(2) ASTM D2487, “Standard Test Method for Classification of Soils for Engineering
Purposes”.

(3) Soils containing a large portion of fine particles (clay and colloid size). Shear
strength is largely or entirely derived from cohesion (natural attraction of particles).
Includes clays, silty clays and clays mixed with sand or gravel.

(4) Soils not exhibiting a natural particle attraction. Shear strength is mostly related to
compactness (density) of the confined grains. Includes sand, gravel, cobbles,
stones, etc.

Bedding Note

Where rock, hard pan, soft, loose, unstable or highly expansive soils are encountered in
the trench bottom, it may be necessary to increase the depth of the bedding layer to achieve
adequate longitudinal support.

DN
Depth =  150 mm (max.)
4

1.13.4.37 Pre-stressed Concrete Pipes

Workmanship shall generally be in accordance with Sub-sections 4.15.5.1 to 4.15.5.23 of


the Specification.

1.13.4.38 uPVC Ducts

uPVC pipes used as ducts for cables or small bore pipework shall as far as possible be laid
in straight lines between drawpits or other terminations, except where bends or large radius
curves are deemed necessary.

1.13.5 Inspection and Testing

1.13.5.1 Specialist Inspection and Testing

The Contractor shall give the Engineer such assistance as he may require in any matter
connected with pipelines, including the inspection of materials and workmanship and the

GKW - Alliance 125


SPECIFICATIONS
CIVIL WORKS

witnessing of tests at any stage (including manufacture) during the execution and
maintenance of the Works.

The Engineer may supervise welding procedure tests and welder performance tests, and
to carry out various independent tests such as holiday tests, Pearson tests, magnetic crack
detection and radiographic examination of welded joints. Such independent tests may be
carried out at any stage during the execution and maintenance of the Works, but they shall
not relieve the Contractor of any of his own obligations under the Contract.

To the extent ordered by the Engineer, the Contractor shall provide labour plant and
materials for direct assistance to the specialist firm in their inspection and independent
testing and for any further work of investigation and repair which the Engineer considers
necessary as a result of such inspection or testing. Except where such provision is
otherwise covered by the Contract, the cost of providing such labour, plant and materials
shall be paid for by the Employer except in cases where, in the Engineer's opinion, the
inspection, test or further investigation shows that materials and workmanship provided by
the Contractor do not comply with the specified requirements, in which case the cost shall
be borne by the Contractor.

1.13.5.2 Inspection at Time of Installation

In addition to any inspection and tests made when delivery is taken, pipeline materials,
including any coating, lining or other protection, shall be inspected by the Contractor
immediately before and after installation, and any damage shall be repaired by the
Contractor as directed by the Engineer before the pipe or fitting is installed or jointed as the
case may be. Any special material required for the repair of pipe lining, coating or protection
shall be obtained from the pipe supplier and shall be used in accordance with his
recommendations.

The Engineer may himself, and without thereby relieving the Contractor of any of his
obligations, inspect and test the pipeline materials by any means he considers appropriate
and any damage discovered by such inspection shall be repaired by the Contractor.

The Contractor shall remove from the Site and shall provide a replacement for any pipe or
fitting which in the opinion of the Employer’s Representative is so badly damaged as to be
unfit for repair on the Site.

1.13.5.3 Testing Pipelines - General

The Contractor shall subject all parts of the completed pipeline system to a final test. For
the purposes of this final test, the pipeline system shall be divided into suitable sections as
agreed with the Engineer. Each section shall be tested as soon as is reasonably
practicable. All testing shall be witnessed and approved by the Engineer.

Where directed by the Engineer, a section of pipeline in a particularly difficult location, shall
be subjected to a hydrostatic test immediately the section has been completed using the
final test pressure.

Notwithstanding the foregoing, the Contractor may at any stage of construction carry out
such preliminary tests as he considers desirable to check materials and workmanship on
the pipeline, but this shall not relieve the Contractor of his obligations to achieve approved
test results on completion.

The Contractor shall, during testing, demonstrate satisfactory operation under working
pressure of each valve and hydrant installed under the Contract.

GKW - Alliance 126


SPECIFICATIONS
CIVIL WORKS

The Contractor shall supply all pressure gauges, meters, hoses, pumps, stop ends and
other temporary supports and equipment necessary for carrying out tests.

The Contractor shall remain responsible for the care of the Works during testing and
cleaning of the pipeline.

1.13.5.4 Procedure for Pressure Testing

Before filling for pressure testing is started, the Contractor shall re-check pipes and valves
for cleanliness and shall re-check the operation of all valves. The ‘open’ ends of the pipeline
(or sections thereof) shall normally be stopped off by blank flanges or cap ends additionally
secured where necessary by temporary struts, wedges or thrust blocks. All thrust blocks
and valve chambers shall have been completed with backfill placed around them, and the
concrete shall have attained its specified 28-day strength, all pipe straps and other devices
intended to prevent the movement of pipes shall have been securely fastened and
backfilling of the trench between pipe joints shall have been placed to the extent necessary
to prevent movement of the pipeline.

The section of pipeline to be tested shall be filled with water, and all air shall be removed.
Before the test proceeds further, the pipeline shall stand full of water for at least 24 hours
at the working pressure. The pressure shall then be raised by pumping in water until the
specified test pressure is reached and shall be maintained at this pressure by further
pumping for a period of not less than 1 hour, during which time the pipeline shall be
inspected for points of concentrated leakage. In the case of pipelines of absorbent
materials, this period shall be extended as necessary until the absorption has ceased.
Pumping shall then cease and the time (T) for the observed pressure head to fall by 10 m
shall be recorded. Pumping shall then be resumed and the quantity of water (Q) pumped
into the pipeline from calibrated container(s) in order to restore the test pressure shall be
recorded. Provided that if the observed pressure head has not fallen by 10 m before an
expired period of three hours, then pumping shall be resumed at once and the time (T) shall
be recorded as being three hours. The rate of loss shall be calculated as being the quantity
(Q) into the pipeline from calibrated container(s) divided by the time (T).

GKW - Alliance 127


SPECIFICATIONS
CIVIL WORKS

1.13.5.5 Test Standard for Pressure Pipelines

If the rate of loss as calculated above does not exceed the figure given below, the pipeline
(or section thereof) shall be deemed to have passed the pressure test, provided that there
is no evidence off concentrated leakage.

TYPE OF PIPELINE ALLOWABLE RATE OF LOSS


(Litres per 24 Hours per 10 mm of
nominal internal Pipe Dia. per km of
Pipe for each 30 m Head of Pressure
applied)

Asbestos-cement pipelines As per applicable standard

Steel pipelines with butt welded or


internally and externally welded sleeve 0.25
and spigot joints, and less than 10 %
flexible joints

All other pipelines 1.0

1.13.5.6 Action Following Test Failures

If the pipeline (or a section thereof) fails to pass the pressure test, the Contractor shall
locate the faults and shall uncover, repair, retest and reinstate the pipeline as may be
necessary until all parts of the pipeline shall have passed the pressure test.

1.13.5.7 Testing of Cable Ducts

The Contractor shall test the completed duct by pulling through a suitable dolly.

Pressure testing of ducts after installation is not required.

1.13.6 Particular Requirements

1.13.6.1 Working Pressure and Test Pressure

For the purposes of testing the pipeline and chambers, the working pressure and test
pressure, and the lengths of section to be tested shall be calculated and arranged according
to the following criteria, in which the pressure in metres shall be such that a water column
connected to the pipeline at the location stated would rise to the number of metres stated
above ground level at the location.

Over any section of pipe to be tested:

 The working pressure at the highest point in the section shall be (the nominal working
pressure in bar of the pipe at the location  10) metres.
 The test pressure at the lowest point in the section shall be (the nominal working
pressure in bar of the pipe at the location  15) metres.
 The test pressure at the highest point in the system when the test pressure is applied
at the lowest part in the system shall be not less than (the normal working pressure
in bar of the pipe at the location  11.5) metres.

GKW - Alliance 128


SPECIFICATIONS
CIVIL WORKS

Each section shall for testing also be arranged so that it contains pipeline of only one
pressure class and only one diameter.

1.13.6.2 Pipe Installation

Since steel and, to a large extent, ductile iron are flexible conduits which in the buried
condition rely on the pipe/soil structure interaction for their load bearing capacity, it is
essential that the pipes are bedded and surrounded in material which is capable of
transmitting the lateral thrusts from the pipe to the undisturbed ground forming the trench
wall and that the undisturbed ground does not become over-stressed.

Due to the difficulty of obtaining good compaction of the surround, particularly beneath the
pipe just above the bedding, the care with which this material is placed and compacted
shall receive special attention.

In all cases care shall be taken that the backfill bedding and surround are compacted
uniformly and to at least the required compaction standard.

The standard of refilling set out in this Specification gives minimum requirements, and the
Contractor shall take any additional precautions necessary in order to meet the specified
limits of deflection and other parameters. In order to optimise the pipe design, the
Contractor may adopt a standard of compaction higher than the minimum specified.

The suitability of any part of the pipeline for use under working and test pressures may
depend upon factors which include:

 the depth of cover over the pipe,


 the quality and stiffness of the bedding and pipe surround,
 the strength and stiffness of in situ soil and
 any superimposed load applied e.g. by surcharge or by traffic.

Pipes shall be deemed installed only where all the specified requirements are complied
with.

The bedding and pipe surround material shall be selected to meet the specified
requirements, including the particular trench conditions. The material shall be capable of
being compacted and shall be free from lumps and clods. The plot of dry density against
moisture content shall show a single maximum and no minimum, and the material shall not
be subject to bulking at intermediate moisture contents. The material shall be inert and the
structure of the fill shall be stable and shall not degrade under the action of water or load
or otherwise in service. The material shall not include the following:

(i) peat, logs, stumps or other vegetable matter;


(ii) perishable material or material liable to spontaneous combustion;
(iii) rubbish or organic material;
(iv) clay of liquid limit exceeding 80 or plasticity index exceeding 55 or both;
(v) materials having an in situ moisture content greater than the maximum permitted for
such materials in the Contract unless otherwise permitted by the Engineer.

Where saturated conditions may occur, the material selected shall be such that fines will
not migrate into the adjacent soil of the trench bottom or walls, and material from the trench
bottom or walls will not migrate into the bedding or pipe surround. Any migration or
movement of soil particles from one area to another will result in the loss of the necessary

GKW - Alliance 129


SPECIFICATIONS
CIVIL WORKS

support for the pipe. The grading shall be chosen to prevent migration (using filter rules)
or where this is not practicable then the trench shall be lined with an appropriate geotextile
filter.

Bedding and surround shall be compacted to at least 90 per cent maximum dry density, (or,
for free draining materials to at least 70 per cent relative density) determined as specified
and to the correct levels.

The top 50 mm of bedding may be left loose to form a uniform support for the bottom arc of
the pipe as described in AWWA M11 and the depth below the top 50 mm shall be
compacted as specified. Alternatively, all of the bedding shall be compacted and the upper
surface shall be accurately shaped by template to match the pipe bottom. In either case
the bedding shall be such that pipes are given full support at the correct level line and
gradient along the entire barrel length and over the widths, as required by the Contractors
design. Recesses shall be formed in the bedding to accommodate joints.

Bedding type A shall apply where the trench bottom is in Rock: the trench shall be
excavated to a depth of at least 150 mm below the pipe bottom, and this excavation shall
be refilled with bedding material as specified. Bedding type A shall also apply where the
trench bottom is in other hard or unyielding material which is likely to damage the pipe or
its coating.

Bedding type B shall apply to thin walled steel pipes in all other materials: the trench shall
be excavated to a depth of at least 50 mm below the pipe bottom and this excavation shall
be refilled with bedding material as specified.

For ductile iron pipe bedding type B may also be included if it forms part of the Contractor’s
design. Unless bedding type A applies, the trench bottom shall otherwise be trimmed as
specified in the specification.

Where the trench is in soft or unstable ground the trench shall be excavated below the pipe
bottom, and a foundation shall be prepared. The foundation may comprise bedding
material below the pipe or may comprise other measures appropriate to the situation, and
shall be according to the Contractors design and subject to Engineer's approval. Cement
soil slurry will not normally be acceptable.

Bedding and backfill at road crossings shall be compacted to 98 per cent maximum dry
density where the pipe is not surrounded in concrete. Where the cover is shallower than
one metre, the backfill shall be compacted to a density such that the specified criteria are
not exceeded. Where the cover is less than l m where deflections and other criteria cannot
be controlled by soil compaction, the pipe shall be protected by reinforced concrete cover
slabs.

If during any stage of installation of pipes it becomes apparent that the undisturbed original
ground is of insufficient strength to allow the backfill to be compacted as specified right up
to the edge of the trench, or if the undisturbed ground is otherwise unstable or prone to
collapse, the Engineer shall immediately be informed and the Contractor shall submit
proposals for the trench and backfill design for approval by the Engineer. Such proposals
may include increasing the compaction or increasing the trench width or both as described
in ASTM D3839 section 6.2.

Pipes shall not be supported on timber wedges, pre-cast concrete blocks, or similar
materials.

The pipe surround material shall be placed in the trench uniformly on each side of the pipe
in layers of between l00 mm and 300 mm thickness, depending on the type of material and
the compaction method used. It shall be compacted at near optimum moisture content by

GKW - Alliance 130


SPECIFICATIONS
CIVIL WORKS

approved hand, mechanical or pneumatic tampers to the specified density. Care shall be
taken to ensure that the material under the haunches of the pipe is thoroughly compacted.
Backfill with pipe surround material shall be continued to at least 300 mm above the crown
of the pipe.

The pipe surround shall normally be placed within 2 days after laying and, with jointing,
shall be arranged so as to minimise temperature effects.

Stones that are likely to damage the pipe or its coating shall be excluded from the bedding
and surround material, and heavy mechanical compactors shall not be used within 300 mm
of the pipe crown. As the maximum article size will depend on the particle shape, grading
and material as well as the pipe and coating, the Contractor shall demonstrate by trial before
backfill is approved by the Engineer. In no case shall the occasional stone size in well
graded fill exceed 20 mm for steel or 25 mm for ductile iron pipes, and in no case shall the
particle size exceed 10 mm for single sized stone for steel pipes.

In the process of backfilling the trench, pipes shall be protected from falling rocks and direct
impact from compaction equipment.

The backfill above the pipe surround material shall be as specified above for pipe surround,
except that the limits on grading shall not apply provided that the particle size does not
exceed 50 mm within 300 mm of the original ground surface and does not exceed 150 mm
elsewhere, and that each layer is compacted as specified. Where rock particles are used
they shall be well graded and blinded with granular material, so that interstices are filled
and a well graded fill results before the next layer is placed.

Unless otherwise specified, any bedding, haunch or surround shall extend across the full
width of the trench.

Where trench walls require temporary support, such as shoring or sheeting, for stability or
safety, the temporary support shall be withdrawn in stages as the backfilling progresses,
care being taken to ensure that the backfill is thoroughly compacted adjacent to the trench
wall. Particular attention shall be taken to ensure that bedding and pipe surround materials
are thoroughly compacted.

Temporary internal bracing may be used with steel pipes to avoid excessive ovality
occurring during transportation storage, handling or to facilitate jointing, but it shall be
removed before any pipe surround is placed except to the extent that some pre-deflection
(not exceeding the limits for ovality) is permitted.

Construction traffic shall cross backfilled pipe trenches only by means of steel plate bridges
except where, with the approval of the Engineer, such traffic falls within the loadings for
which the particular part of the pipeline is designed or where the Contractor has, with the
approval of the Engineer and at no extra cost to the Employer, strengthened the pipeline
so that it is suitable for such use.

1.13.6.3 Tests on Bedding, Pipe Surround and Trench Backfill

The Contractor shall be responsible for carrying out all field and laboratory tests to ensure
that all fill material placed complies with the grading limits specified and plasticity index
(where specified), that the material is compacted to within the specified limits of dry density
and at moisture contents within the limits specified.

Particle size distribution (grading) shall be determined by the appropriate test.

GKW - Alliance 131


SPECIFICATIONS
CIVIL WORKS

Bedding and fill density shall be determined by the sand replacement method generally in
accordance with the test described in the applicable standard.

Samples for laboratory testing of maximum dry densities and optimum moisture contents
shall be on samples taken adjacent to, and including in-situ density test locations.

Maximum dry densities and optimum moisture contents for compaction control by relative
compaction shall be derived using the test described in the applicable standard, and
maximum and minimum dry densities for compaction control by relative density shall be
derived using the test described in Appendix E12 United States Bureau of Reclamation
(USBR) Earth Manual, 2nd edition.

Tests for determining soil and backfill stiffness shall include oedometer tests and triaxial
tests on laboratory compacted samples and samples of in situ soil, as specified.

The location of each field test or sampling point shall be to the approval of the Engineer.

Test results and copies of calculations shall be submitted promptly upon completion.

1.13.6.4 Frequency of Testing

The Contractor shall carry out tests on bedding, surround materials and each l m depth of
trench backfill as follows:

 Before starting pipelaying:


- particle size distribution tests
- laboratory compaction control tests
- field density tests

During subsequent pipelaying at least one set of the above tests shall be carried out at not
more than 50 m intervals along each pipeline.

The carrying out of any tests by or on behalf of the Engineer shall not relieve the Contractor
of any of his responsibilities for testing in accordance with the Specification

1.13.6.5 Deflection of Pipes

Placing and compaction of pipe surround at the sides of the pipe causes a reduction of its
horizontal diameter and an increase in its vertical diameter (negative deflection). Then, as
backfilling above the pipe proceeds, the imposed loading first tends to re-round the pipe
before inducing positive deflection. During this procedure the pipes shall be maintained as
truly circular as possible without use of props, bracing or other unspecified supports.

Parts of the pipeline may be empty for long periods (i.e. between construction and fully
commissioning) and may not have the design loading at the time of measurement.
Deflection may be expected to continue with time after installation. At no time in the pipes
life shall the deflection exceed 3 per cent of diameter for concrete lined steel or ductile iron
pipes, or such lower value as may be imposed by limits of stress or strain. Within 2 days
after completion of backfilling any departures from true circular diameter shall not exceed
2 per cent for steel or ductile iron pipes, or such lesser figure as may be calculated taking
into account the installation situation, the depth of cover and loading at the time of
measurement.

GKW - Alliance 132


SPECIFICATIONS
CIVIL WORKS

For all pipes ND 600 or larger, the vertical and horizontal diameter, together with
measurement of radius of curvature around the circumference and such other check
measurements as may be relevant, as determined during trials, shall be recorded at the
mid-length of every pipe and if necessary, at the ends and quarter points and elsewhere
along the length of the pipe. The pipe diameters shall be measured by use of calibrated
gauging rods and radius of curvature shall be measured by templates, both of which shall
be kept available for use by the Contractor or by the Engineer at every point where pipes
are being installed. In case of doubt, the true circular diameter shall be determined by
measurement of the internal circumference of the pipe and division of the result by π.
Measurements of deflection shall be within 0.1 per cent of diameter.

Should any pipe be found to be out of round by more than the specified tolerance, or the
predicted value of deflection or stress or strain be found to be more than the permitted
value, the Engineer shall be informed and the backfill and pipe surround material shall be
removed and replaced. During removal, the backfill shall be tested to determine the cause
of the excess deflection.

If such measures do not reveal the full cause of the excessive deflection in the opinion of
the Engineer, then the pipe and bedding shall be removed. The pipe may be re-used if not
defective.

1.13.6.6 Bedding and Surround

Material for pipe bedding and surround shall, wherever practicable, be obtained from
adjacent excavations and failing that from other excavations or borrow pits.

The contractor will be deemed to have made his own estimation of the available material,
and to have allowed for any transportation of suitable material and other costs involved in
provision of specified backfill including any sieving or other processing which may be
necessary.

1.13.7 Design

1.13.7.1 General

Subject to minimum requirements set out in the Contract, the Contractor shall be
responsible for design of the pipe wall thickness and pipe wall structure, and for selection
of material for and design of compaction of the pipe bedding, backfill and, if required, any
pipe foundation.

The Contractor shall also be responsible for hydraulic design and for design of thrust blocks,
chambers and other works.

The Contractor’s design calculations shall be submitted to the Engineer for approval.

The Engineer will review the Contractor’s pipe design and the Contractor’s bedding,
foundation and backfill design. The approval process is specified below. The Engineer
may give provisional approval allowing the Contractor to proceed subject to field tests and
trials. Approval of the Engineer shall not relieve the Contractor of his liabilities.

1.13.7.2 Loads

Pipelines shall be designed for internal pressures as follows:

GKW - Alliance 133


SPECIFICATIONS
CIVIL WORKS

(a) the pressure class;


(b) the greater of (i) a surge pressure of the pressure class plus 10% (ii) the surge
pressure set out in Reference Standards for the pipe material;
(c) subatmospheric pressure of 3 m water (0.3 bar) and to external loads as follows:
(d) soil load, assuming the ‘wide trench’ condition (unless the Contractor can
demonstrate that other conditions will prevail);
(e) traffic load from 2 number 70kN wheel loads 900 mm apart with an impact factor of
1.5 (representing two vehicles passing, parallel to the pipeline);
(f) ground water at ground at surface.

The subatmospheric pressure is a preselected figure. It links to the specification for the air
valves which are required to admit air rapidly in the event of a burst.

Load combinations shall be as follows:

 pipe empty: (d) plus (e);


 pipe full: (a) plus (d) plus (e);
 pipe full: (a) plus (b) plus (d) plus (e).

Soil load shall be considered as dead load: surge and traffic shall be considered as
transients.

Re-rounding due to internal pressure shall not be taken into account except for the
combination of pipe full, internal pressure plus surge. The effects of pipe weight and
contents weight shall be taken into account.

The load combination for buckling shall be (d) plus (e) plus (f) plus (c).

1.13.7.3 Standards and Criteria

The Works shall be designed for a design life of at least 50 years.

Design shall be based on the following standards:

 steel : AWWA M11;


 ductile iron : AWWA/ANSI C150/A21.50-91

In the absence of soil modulus data obtained from the Site, preliminary designs may be
made based on published values of soil modulus.

If in design of ductile iron pipe the backfill soil moduli are used as given in AWWA C950-
88, then a deflection lag factor shall be applied as given in AWWA C950-88.

Values more refined than those given in the above standards may be taken from
internationally accepted references approved by the Engineer, subject to consistency with
the method of analysis and calculation.

In determining calculated deflections, the soil modulus used shall be such that there will be
a probability of at least 95 per cent that the actual average deflection will be less than the
calculated value. Procedures relating to probability value are described in AWWA C950-
88 section A 3.4.2.6.

GKW - Alliance 134


SPECIFICATIONS
CIVIL WORKS

The Contractor shall carry out tests to determine soils modulus and other data for the
materials he proposes to use.

The value of soil modulus E’ shall be determined by the method of all Allgood referred to in
section 4.3.3 of CIRIA report 78 with corrections as follows:

 E' = 0.75.D.KS.H for dry granular backfill;


 E' = 1.5.D.KS.H for saturated granular material;
 E' = 0.75.D.KC for clay.

In Allgood’s method, the constrained modulus of the backfill is measured in an oedometer.


The oedometer shall be a hydraulic cell type as designed by Rowe. Poisson’s ratio is
measured in drained triaxial tests on the same compacted soil as described by Bishop and
Henkel. The soil modulus E’ is derived from the constrained modulus using a formula
containing Poisson’s ratio.

The laboratory test result shall be correlated with values (back calculated and laboratory)
obtained from field trials and from monitoring pipe deflections and with published values,
and shall be submitted to the Engineer together with recommendations for values for
design.

Before results are accepted, at least three sets of laboratory tests shall have been
performed, which shall have given substantially equal results in terms of E'. The same
backfill design shall also have been shown to give uniform results in at least three field tests
on each of three trial backfills.

The Contractor may propose an alternative design procedure but he shall satisfy the
Engineer as to the suitability of the method.

Notwithstanding calculated values, the measured values for deflection and for stress and
strain shall not exceed the limits set out in the Contract.

1.14 Pipelines for wastewater

1.14.1 Scope

1.14.1.1 General

This Section contains requirements which, where relevant to this Contract, shall apply to
the supply, handling, installation, jointing, testing and cleaning of pressure pipelines, sewers
and other gravity pipelines. It also applies to uPVC cable ducts but does not apply to
drainage for roads, or to pipelines for water supply or building services.

Valves, sluice gates and fittings of all kinds (except as may be noted hereunder), whether
required to be laid in, on or above ground, or to be fixed on or built into other parts of the
Works, form part of the mechanical specifications.

Excavation and refilling of pipe trenches shall be carried out as specified for Earthworks.

1.14.1.2 Definitions

The following terms shall have the meanings hereby assigned to them, except where the
context clearly renders these meanings inapplicable:

GKW - Alliance 135


SPECIFICATIONS
CIVIL WORKS

"Pipes" pipes, bends, junctions and other specials and includes jointing parts
(except material required for the completion of run-lead, leadwool,
yarn and mortar, and welded joints).

"Valves" valves, sluice gates (generally described as penstocks in the UK), air
valves, hydrants, metering devices and the like and includes jointing
parts, operating gear, and associated fittings.

"Manholes" manholes and inspection chambers on gravity pipelines; chambers


for air valves and washouts on pressure pipelines; including
precast concrete, manhole sections, access covers, ladders and
other fittings.

"Installation" handling placing and fixing in position ready for jointing pipes and
valves, whether in trench or elsewhere in the Works.

"Pipeline all items additional to pipes, valves and manholes required to com-
appurtenances" plete pipeline including, where relevant, but not limited to internal and
external protection systems, supports and anchorages, washouts,
vent columns and marker posts.

"Pressure pipelines for the conveyance under pressure (normally by pumping)


pipelines" of raw or treated water, stormwater, sewage, industrial waste,
effluent, washwater or sludge, inclusive of pipes, valves, manholes
and pipeline appurtenances.

"Gravity pipelines which do not normally run full, used for drainage and for the
pipelines" conveyance of liquids, including but not limited to stormwater,
sewage, industrial wastes, partially treated wastes, effluents and
washwater inclusive of pipes, manholes and pipeline appurtenances.

1.14.2 Submissions by the Contractor

Submissions which the Contractor is required to make in relation to pipelines for waste
water include, where relevant, the following:

1.14.2.1 Drawings

 Typical drawings of standard items.


 Detail drawings of special items.

1.14.2.2 Data

 Manufacturer’s calculations, catalogues and data sheets including pressure/


temperature ratings for pipes, fittings and joints.
 Method of boxing out for and building pipes into structure walls.
 Methods of control of line and level of pipeline during installation.

1.14.2.3 Records to be Kept

GKW - Alliance 136


SPECIFICATIONS
CIVIL WORKS

The Contractor shall keep detailed and up-to-date records in a form to be approved by the
Engineer of all pipes and valves, showing the quantities of each type, size and class which
have been

(a) ordered during the course of the Works;


(b) delivered during the course of the Works;
(c) declared on delivery to be faulty damaged or deficient;
(d) broken damaged or lost during the course of the works.

Each week the Contractor shall provide the Engineer with an up-to-date copy of the above
records.

1.14.2.4 Certificates of Tests

The Contractor shall forward to the Engineer before dispatch certificates from the
manufacturers to show that pipes and valves have been tested and comply with the
appropriate Standard.

1.14.2.5 Method and Programme of Pipeline Testing and Cleaning

The Contractor shall submit for the approval of the Engineer details of his proposed
methods and programme for pipeline testing and cleaning (including details of test and
cleaning equipment).

1.14.3 Materials and Equipment

1.14.3.1 General

Materials for pipelines shall be manufactured to the specification given hereunder, and shall
be provided by the Contractor, except as specified otherwise. The particular type, size and
class of pipes and valves for each part of the Works shall be as required.

1.14.3.2 Vitrified Clay Pipes

Clay ware pipes shall be in accordance with the applicable standard but shall not be class
L (‘Lower strength’). Alternatively, clay ware pipes may be ‘Extra strength’ pipes, provided
that the application is consistent with Clause 1 (Scope) of that specification.

The Contractor will be at liberty to use pipe lengths up to the maximum normally
manufactured. Some shorter pipes with flexible joints may be required to permit the
required levels, positions and lengths to be accurately obtained.

1.14.3.3 Clay ware Field Drain Pipes

The Contractor will be permitted to use second quality stoneware open jointed spigot and
socket pipes in their place at no additional cost to the Employer.

GKW - Alliance 137


SPECIFICATIONS
CIVIL WORKS

1.14.3.4 Concrete Pipes

All concrete pipes and fittings for gravity pipelines shall be spigot and socket pipes with
Stanton Cornelius flexible joints or similar approved.

The pipes shall be made with an approved aggregate and sulphate resisting Portland
cement, shall be centrifugally spun, and shall be obtained from an approved manufacturer.
The pipes shall generally be in the manufacturer’s full lengths.

The Contractor will be at liberty to introduce half-length and quarter length concrete sewer
pipes at no extra cost to the Employer, if he finds it expedient to do so.

1.14.3.5 Ductile Iron Pipes

All ductile iron pipes and fittings shall be obtained from an approved manufacturer.

Except where indicated otherwise, all socket and spigot pipes and fittings and flanged pipes
and fittings shall be to the standard class designation.

Socket and spigot pipes and fittings shall be suitable for Tyton or Stantyte type joints or,
where required, for Viking-Johnson type couplings. Flanges shall be PNl6.

1.14.3.6 Cast Iron Drainage Pipes and Fittings

Cast iron drainage pipes and fittings shall conform to the applicable standard.

Joints shall be caulked with tarred hemp and sealed with mastic.

1.14.3.7 Un-plasticised Polyvinyl Chloride (uPVC) Pipes

All uPVC pipes for sewerage purposes shall comply with the applicable standard, and shall
have a minimum sustained pressure rating of 12 bar.

1.14.3.8 High Density Polyethylene (DHPE) Pipes

All high density polyethylene pipes for sewerage purposes shall comply with the applicable
standard, and shall have a minimum sustained pressure rating of 12 bar.

1.14.3.9 Connections between different Pipe Materials

Where different types or classes of pipe material are jointed together, the Contractor shall
supply special fittings or stepped couplings, designed and manufactured to suit the end of
pipes to be jointed. Stepped couplings shall comply where applicable with the requirements
for flexible couplings and flange adapters as specified hereafter.

1.14.3.10 Gaskets for Flexible Joints

Gaskets for joints shall be obtained from the manufacturer of the pipe or joint.

GKW - Alliance 138


SPECIFICATIONS
CIVIL WORKS

Joint gaskets shall be of a material for making a long term flexible seal between the pipes,
and shall be resistant to mechanical, chemical or bacteriological attack leading to
deterioration of the flexible seal.

Lubricants used during jointing shall have no deleterious effects on the joint rings, pipes or
pipe coating.

1.14.3.11 Flanged Joints

Flanges and bolting shall be to the applicable standard. Gaskets shall be inside bolt circle
type to the applicable standard. Gasket material shall be single ply fabric reinforced rubber,
3.2 mm thick. Gaskets shall be of such physical properties as to be capable of forming
permanent watertight joints against pressures up to the maximum test pressure. Bolts and
nuts and washers shall be to the applicable standard. There shall be two washers per bolt.
Each bolt shall be of sufficient length to show to threads past the nut when installed.

The Contractor shall be responsible for checking and ensuring that mating flanges are
compatible in all cases, including where connections are to be made to-existing pipe
flanges.

1.14.3.12 Flexible Couplings and Flange Adapters

Where detachable flexible couplings or flange adapters are for use with pipes, these shall
be of the Viking-Johnson type.

Flexible couplings for each size of pipe shall be capable of withstanding the shear force
applied by the weight of a 4 m length of pipe of that diameter full of water suspended
between two couplings. Where specified, flexible couplings shall be provided with central
register ribs or location plugs.

Flange adapters shall have flanges as specified for flanged joints. The metal components
of detachable flexible couplings and flange adapters shall be protected as specified.

1.14.3.13 Fusion Bonded Epoxy Coating

Fusion bonded epoxy coatings described in this clause are intended for applications
containing ductile iron, cast iron, steel and aluminium based substrates used in the
manufacture of pipes, fittings and their components, that will be in contact with potable
water, domestic effluent, any soil conditions and above ground applications. The coating
shall consist of a polymeric anti-corrosion barrier applied at a factory approved by the
Engineer.

The coating system requirements, performance testing and factory applied coating
requirements and practice shall be in accordance with the Interim Water Industry
Specification (WIS) for Polymeric Anti-Corrosion (Barrier) Coatings, ref. No. FR 0028, dated
September 1989 with amendment, Issue 1, dated 31 July 1990 published by the Foundation
for Water Research (FWR) Heniey road, Medmenham, P.O. Box 16, Marlow, Bucks, SL7
2HD.

The method of surface preparation and cleaning shall be in accordance with the
Contractor’s specification which shall be no less than the minimum requirements specified
by the coating material manufacturer and the following requirements:

GKW - Alliance 139


SPECIFICATIONS
CIVIL WORKS

(a) The pre-coating surface shall be blast-cleaned.


(b) The surface shall be tested for soluble salts and re-blasted if soluble salts are found
to be present;
(c) All oil, grease and other contaminants shall be removed;
(d) All slivers and scabs etc. made visible by blast cleaning and detrimental to the coating
process shall be removed;
(e) Welds shall be fettled smooth;
(f) Edges and corners shall be smoothed to a 1.5 mm minimum radius;
(g) Zinc chromate pre-treatment shall not be permitted.

The minimum coating thickness for pipes and fittings shall be 300 microns. The maximum
coating thickness on a pipe wall shall be 1.6 mm. The maximum coating thickness on a
flange shall be 2.0 mm; the minimum and maximum coating thicknesses shall apply to
coating inside bolt holes. Any thickness-critical surfaces shall be coated to the thickness
specified and within the tolerances identified.

Unless otherwise specified, all coatings shall be examined to a Class A coating


classification and each item shall be checked for holes over all of the coating surfaces. A
fitting with 2 or more holidays per 3 m2 of surface area or a pipe with 30 or more holes per
pipe length shall be rejected for subsequent stripping and re-coating. All holes detected
shall be repaired and on completion the item shall be re-examined for holes.

1.14.3.14 Wrapping Material

Wrapping material for external protection of buried pipelines and for site wrapping of
completed joints shall be heavy duty, self-adhesive, rubber-bitumen compound with PVC
carrier strip together with primer and moulding putty.

All materials shall be supplied by the same manufacturer.

The primer shall be a fast drying bitumen solution type compatible with the wrapping
material and also with coal tar, bitumen enamel and epoxy coatings and with plastics pipes.

The moulding putty shall be compatible with the wrapping materials and the primer and
shall be capable of being moulded cold by hand.

The wrapping material shall possess the following minimum physical characteristics:

 Thickness (overall) 1.5 mm


 Tensile strength 10 N/mm
 Elongation 40%
 Tear resistance 20 N force
 Impact resistance 7 Jules
 Adhesion (180 peel) 2 N/mm
 Dielectric strength
(55% overlap) 15.000 V minimum
 Insulation resistance 1.000.000 megohms

The materials shall be suitable for application in the environmental conditions at the site.

GKW - Alliance 140


SPECIFICATIONS
CIVIL WORKS

1.14.3.15 Polyethylene Sleeving

Polyethylene sleeving for loose pipe wrap shall conform to the applicable standard.
Suitable adhesive PVC tape shall also be provided to fix the sleeving in position and to
make joints between the adjacent sections.

1.14.3.16 Marker Tape for Buried Services

The marker tape laid above buried services shall be 500 mm wide and 0.1 mm nominal
thickness coloured polythene, boldly printed throughout its entire length with the word
“CAUTION” and words to identify the particular service, in accordance with Table 16 B.

Table 16 B

TYPES OF SERVICES COLOUR OF TAPE SERVICE


IDENTIFICATION
WORKING

Potable water Blue Water Main Below

Wastewater, effluent and Green Waste Pipe Below


sludge of all types

Fuel oil or gas pipe Orange Fuel Main Below

Electricity, earthing Yellow Electric Cable Below

Instrumentation cable
Telephone cable Red Control Cable Below
Telemtry cable

1.14.3.17 Precast Concrete Manholes

Precast concrete circular manhole sections and cover slabs shall be obtained from
approved manufacturer. They shall be made with an approved limestone aggregate and
the chamber and shaft rings shall be spun. The chambers shall be 1200 mm internal
diameter, and the shafts 675 mm internal diameter, the tapers connecting them being of
the straight back type. All precast cover slabs shall be heavy duty and shall be provided
with 600 mm (minimum) tapered opening over which the cast iron manhole cover will be
set. The slabs shall be provided with built-in lifting rings.

1.14.3.18 Manhole Covers and Fittings

The covers and frames for manholes shall be to the applicable standard with a clear
opening of 600 mm diameter. They shall be carefully set to the slope of the ground or road
surface.

Manhole covers on all foul sewers shall be embossed with the word ‘Foul’.

1.14.3.19 Handrailing

GKW - Alliance 141


SPECIFICATIONS
CIVIL WORKS

Handrailing shall consist of tubular standards with 35 mm outside diameter handrailing and
shall be heavily galvanised.

1.14.3.20 Safety Chains

Safety chains shall be made from 38 mm links and permanently attached at one end and
hooked at the other. The safety chains, including the hooks and rings, shall be heavily
galvanised. Alternatively, the safety chains may be of black nylon of an approved type.

1.14.3.21 Manhole Steps

Manhole steps shall be galvanised malleable iron step irons of approved pattern.

Alternatively, round iron step irons 300 mm wide, and projecting 150 mm from the finished
face of the work, shall be provided and shall be heavily galvanised.

Manhole steps irons shall not be painted.

1.14.3.22 Ladders

Fixed ladders outside water retaining structures shall be mild steel hot dip galvanised.
Inside tanks and reservoirs the ladders shall be of stainless steel.

1.14.3.23 Nuts and Bolts

Two washers shall be supplied and fitted with each bolt. All bolts and nuts shall be zinc or
cadmium electroplated.

1.14.3.24 Bricks

Where engineering brickwork is specified the bricks shall be Class B engineering bricks.

All bricks shall be well shaped, hard, sound, uniform in size and free from cracks and flaking.

1.14.4 Workmanship

1.14.4.1 Handling

Throughout the construction of the pipeline including the operations of off-loading, delivery,
handling, storing and transporting pipes, valves and precast manhole sections on or about
the Site, the Contractor shall use such methods, plant and equipment as will prevent
damage to the pipes, valves, precast manhole sections and to any sheathing, lining or
paintwork, and such methods shall include the use in appropriate cases of pipehooks, lifting
beams, reinforced canvas slings, protective padding, struts, cradles and pipe trailers.

Temporary packing, coverings or crates provided by the suppliers for the protection of pipes
and valves in transit shall not be removed (except for purposes of inspection after which
they shall be replaced) until immediately before the pipe or valve is installed, and shall then
be disposed of by the Contracts.

GKW - Alliance 142


SPECIFICATIONS
CIVIL WORKS

No pipe shall be moved by rolling, save over suitable timber planking so arranged as not to
damage the pipe or its sheathing.

1.14.4.2 Delivery

The Contractor shall take delivery of and off-load pipes, valves, and precast manhole
sections which he is required to provide at times and at locations or storage-areas on or
about the Site to be arranged by him with his suppliers. Any such location or storage area
which does not form part of the Site shall be arranged for by the Contractor at his own risk
and expense.

After pipes, valves and precast manhole sections have been delivered to and off-loaded at
delivery locations as aforesaid, the Contracts shall make all arrangements for subsequent
transport and handling on or about the Site to the point of installation, including where
necessary any movement into and out of temporary storage.

The Contractor shall inspect all pipes, valves and precast manhole sections upon delivery
from the manufacturer and shall note all damaged, broken or otherwise unsatisfactory items
and shall take immediate steps to rectify or replace such broken or damaged or
unsatisfactory items. Items with damaged fusion bonded epoxy coatings shall be treated
in accordance with the specification.

1.14.4.3 Storage

The Contractor shall take into temporary protective storage all pipes, valves and precast
manhole sections not required for immediate installation in the Works or, in the case of
pipes and precast manhole sections, for stringing out along the pipeline route.

Valves shall be stored under cover until they are required for installation, and particular care
shall be taken for the protection of any associated electrical or mechanical equipment.

Pipes in storage shall be laid on wedged timber bearers so as to be at least 75 mm clear of


the ground; pipes may be stacked up to three pipes high if suitable protective packing is
placed between the layers. To prevent damage to the sheathing of pipes which are
sheathed with bitumen the bearers shall be positioned at the unsheathed ends of the pipes.

The period between taking delivery of a pipe and the completion of its installation shall be
kept to a minimum, and in the case of steel pipes this period shall not exceed six months.
Any period during which the pipes are strung out along the pipeline route or placed
alongside the Works awaiting installation shall also be kept to a minimum, and if this period
exceeds one month pipes shall be raised at least 75 mm from the ground on timber bearers.
Jointing parts and materials shall in any case be stored under cover as for valves.

Subject to the foregoing and to any restrictions of the duration of temporary occupation of
parts of the Site, pipes may be strung out along the pipeline route prior to installation,
providing that any necessary temporary fencing has first been erected.

1.14.4.4 Installation of Pipelines - General

Trench excavation and backfilling shall be co-ordinated with the construction of the pipeline
as a whole so as to ensure expeditious completion of the whole operation.

Trench excavation and backfill shall be carried out in accordance with the requirements for
Earthworks in this Specification. The minimum depth of cover above pipelines shall

GKW - Alliance 143


SPECIFICATIONS
CIVIL WORKS

normally be 1200 mm in roads or fields, and 900 mm in gardens, the depth of cover being
measured from original ground level to the top of the barrel of the pipe. Any pipeline with
less than normal cover shall be surrounded with at least 150 mm of concrete.

The Contractor shall submit full details of the methods he proposes to use for control of the
accuracy of pipelaying. Where sight rails are used, they shall be fixed and maintained at
each change of gradient, and at as many intermediate points as may be necessary, but not
more than 35 m apart. Sight-rails shall be clearly painted in contrasting colours and be not
less than 1 metre long and 150 mm deep, straight and level, rigidly supported by stout
wooden posts at each end. Any pipes placed on end for affixing the base of the posts shall
be not less than 225 mm in diameter and shall be filled and rammed solid with earth or
sand. Posts shall otherwise have their bases concreted in, with the approval of the
Engineer. Boning rods or travellers for use with sight rails shall be of robust construction,
clearly painted and accurately made to the various lengths required, the lower ends being
provided with shoes with sufficient projection to rest on the pipe inverts.

Unless specified otherwise, pipes shall be installed singly and shall not be jointed until after
they have been laid. The Contractor shall keep the interior of pipes clean and free from
water, dirt, stones and other foreign matter as installation proceeds, and at the end of the
day’s work or other times when installation work is not proceeding the open ends of the
pipes shall be sealed off by a suitable stopper. The Contractor shall take such precautions
as are necessary to prevent pipes from floating.

Whenever pipes, cables, ducts and similar services are buried in the ground a marker tape
shall be laid 300 mm above each and every service in the trench.

1.14.4.5 Installation of Pressure Pipelines

The specified lines and levels of the pipeline and the positions of the bends, junctions and
other fittings may be adjusted by the Engineer as necessary before construction of a
particular section commences. The pipeline shall be accurately installed to the lines, levels,
grades and positions required.

Pipes shall be laid to even grades for as long a length as possible with a minimum grade of
0.2%, irrespective of local changes of elevation of the ground surface. Changes in direction
or in grade of the pipeline shall be carried out by making use of any permissible deflection
of joints between straight pipes or by the introduction of bends.

Socket and spigot pipes shall normally be laid with sockets leading. Where the gradient
exceeds 5%, installation shall proceed on an ascending grade with sockets leading. After
laying and jointing, the invert level of each pipe shall be checked before the next pipe is
installed.

Joint holes shall be excavated to provide adequate clearance to enable joints to be made
satisfactorily and any specified wrapping to be completed and to provide a clearance of at
least 50 mm from the trench bottom below the joints.

1.14.4.6 Installation of Gravity Pipelines

Each length of pipe shall be laid in a straight line, both in the horizontal and vertical planes,
the specified levels and gradients being rigidly adhered to unless otherwise ordered in
writing by the Engineer.

Site rails shall be used to control the accuracy of pipelaying, unless the Engineer directs
otherwise. Strong site rails shall be placed at each end of the length of pipeline to be laid

GKW - Alliance 144


SPECIFICATIONS
CIVIL WORKS

and not more than 35 metres apart. A third sight-rail shall be used wherever possible for
ease of checking against accidental displacement.

Where pipelines are to be bedded on concrete, precast concrete bedding blocks shall be
set to a level allowing for the thickness of the pipe barrel, and side string lines shall be used
for checking alignment.

1.14.4.7 Installation of Valves

Installation of valves shall include installation and fixing of any operating gear and
associated fittings. Before installing valves the Contractor shall tighten all loose nuts and
bolts on the valves and associated equipment, and shall ensure that they are watertight
and in proper working order.

Valves shall be fixed in manholes before the benching is constructed. They shall be coated
with grease and the Contractor shall take precautions against damaging and fouling them
during concreting operations.

Where a valve is built into the benching it shall be surrounded by 75 mm casing of lime
mortar to facilitate subsequent removal. The lime mortar shall be rendered with cement
mortar 20 mm thick.

After installation valves shall be cleaned inside and out, and shall be left in the closed
position.

The spindles of all valves without actuators shall extend to allow for ease of operation and
bracketed 150 mm below tops of walls and at intervals not exceeding 2400 mm.

The provision for fixing sluice gates to walls shall be subject to the approval of the Engineer,
and all sluice gates shall be watertight on completion. Sluice gates shall be bedded on and
pointed up with cement mortar. Sluice gates shall be maintained in the closed position
during installation.

All bolts, nuts and washers on the sluice gates and the foundation bolts, nuts and washers
shall be of bronze.

Working drawings for all sluice gates shall be submitted to the Engineer for approval, prior
to manufacture.

1.14.4.8 Bedding to Pipes

Clayware, asbestos cement and concrete pipes for gravity pipelines and clayware lateral
pipes shall be laid on concrete bedding. For pressure pipelines of asbestos cement pipes,
and pressure and gravity pipelines of steel, grey iron and ductile iron pipes, the bottom of
the trench shall be finished smooth and free from irregularities, so that the pipes bear
uniformly and are supported thorough out their entire length. The holes required at each
joint shall be made as small as possible.

Where ordered by the Engineer pressure pipelines of asbestos cement-pipes, and pressure
and gravity pipelines of steel, grey iron and ductile iron pipes, shall be bedded on soft
material from nearby trench excavations. The bedding material shall be placed and
compacted using a vibrating plate or similar type of compacting machine, and shaped to
provide continuous support to the bottom of each pipe along its full length.

GKW - Alliance 145


SPECIFICATIONS
CIVIL WORKS

Where the base of the trench excavation is in rock, a further 150 mm of rock shall be
excavated below the intended bedding line for the pipe barrel and this excavation shall be
refilled with soft material, or with sand free from stones greater than 19 mm size, or with
concrete.

1.14.4.9 Concrete Bedding and Surround

Where specified or ordered by the Engineer, pipes shall be bedded haunched or


surrounded in concrete. Concrete shall be unreinforced of the grade required. Any
formwork required shall be of Class F1.

All gravity pipelines and laterals, except those which are surrounded with concrete or are
of steel, grey iron or ductile iron, shall be laid on a concrete bed with a specified minimum
thickness under the pipe. Such concrete shall not be placed until the joints at each end of
the pipe have been completed. The full width and depth of bedding concrete shall be placed
and carefully punned beneath the pipe, followed at once by the addition of any surround
concrete. Unformed surfaces shall be of spade finish.

The pipe shall be prevented from floating or other movement during concreting.

Wherever pipes are provided with concrete protection they shall be supported temporarily
on precast concrete blocks cast to the shape of the bedding, and where they have a
concrete surround the depth of the precast concrete block, shall be increased to suit. Where
pipes other than asbestos cement are used, the precast concrete blocks shall be positioned
behind each socket. In the case of asbestos cement pipes a precast concrete block shall
be positioned at each end of each pipe clear of the sleeve joints. The width of the precast
concrete blocks shall be half the diameter of the supported pipe subject to a minimum and
maximum of 115 mm and 300 mm respectively. The blocks shall be left in and paid for as
in-situ concrete.

To ensure flexibility of the pipeline, a 12 mm thick board of softwood, ‘Flexcell’ or other


approved material cut to shape, shall be placed at each pipe joint to break the continuity of
the concrete protection completely. In the case of clayware pipes the board shall be placed
against the face of the socket and in the case of asbestos cement pipes at one end of the
sleeve joint.

Where two or more pipelines are laid in the same trench the joints shall coincide at the
points where the continuity of the concrete surround is broken, i.e. at the joints in the
pipeline with the longest pipes. Any intermediate joints in the other pipelines with shorter
pipes shall be surrounded in concrete.

1.14.4.10 Granular Bedding and Surround

Where deemed necessary or ordered by the Engineer, pipes shall be bedded with granular
material up to the half pipe diameter and for the full width of the trench. uPVC and other
flexible pipes shall be surrounded with granular material across the full width of the trench
and to a level at least 100 mm above the top of the pipe.

Granular bedding shall be well compacted to the correct levels so that pipes are given full
support along the entire barrel length. Recesses shall be formed in the granular bedding
to accommodate sockets, collars or other pipe joints. Pipes shall not be supported on
timber wedges, pre-cast concrete blocks or other point supports.

After pipes have been correctly laid and tested, further granular material for surround shall
be placed and carefully compacted so no disturbance of the pipe occurs.

GKW - Alliance 146


SPECIFICATIONS
CIVIL WORKS

Material for granular bedding and surround shall be coarse sand.

The material shall be tested, using specimens in the soaked condition, and shall have a
10% fines value greater than 50 kN.

Whenever the Engineer directs, a test for compaction shall be carried out on the material
for granular bedding.

1.14.4.11 Jointing - General

This clause shall be read in conjunction with the particular requirements specified for each
type of joint.

Before making any joint the Contractor shall ensure that the interior of each pipe or fitting
is clean, and that it remains clean. Immediately before starting a joint the Contractor shall
clean the end of each pipe to be jointed and shall prepare the ends for jointing as necessary.
All mechanical joints shall be cleaned and have their coating made good before assembly.

The Contractor shall use only the proper jointing parts as specified and obtained from the
suppliers of pipes or fittings. All joints shall be assembled and tightened in accordance with
the manufacturer’s instructions, and shall be capable of passing the test for individual joints
and for the completed pipeline as specified.

Where specified, detachable flexible couplings shall be installed. The joints shall be
assembled and tightened in accordance with the manufacturer’s instruction.

Where the Engineer requires, a change of direction to be achieved by the deflection of a


flexible joint of any kind, the deflection shall not exceed 50% of the design value for the size
and type of joint as recommended by the manufacturer.

After each joint has been completed, any protective or other coating shall be made good
and any lining shall be completed as specified without delay. Any metal joint which is not
already coated shall be cleaned and painted with two coats of bituminous paint.

1.14.4.12 Joints for Clay-ware Pipes

Clay ware pipes shall be jointed with due regard to the manufacturer’s instructions.

1.14.4.13 Joints for Concrete Pipes

In making joints for concrete pipes, the Contractor shall take account of the manufacturer’s
recommendations as to the methods and equipment to be used in assembling the joints.
In particular, the Contractor shall ensure that rubber rings are correctly positioned and free
from twists. The rubber rings and any recommended lubricants shall be obtained only
through the pipe supplier.

1.14.4.14 Joints for Iron Pipes

In jointing iron spigot and socket pipes and specials, the Contractor shall take account of
the manufacturer’s recommendations as to the methods and equipment to be used in
assembling the joints. In particular the Contractor shall ensure that the spigot end of the
pipe to be jointed is smooth and has been properly chamfered, that the rubber ring is
correctly positioned in the socket and that the two pipes are accurately in line, before the
joint is made. After the joint has been made the Contractor shall ensure by the use of a

GKW - Alliance 147


SPECIFICATIONS
CIVIL WORKS

suitable feeler gauge that the rubber ring is evenly seated in its correct final position. The
rubber rings and any recommended lubricant shall be obtained only through the pipe
supplier.

1.14.4.15 Viking Johnson Type Couplings for Iron or Steel Pipes

In jointing iron plain ended pipes with Viking Johnson or similar couplings, the Contractor
shall take account of the manufacturer’s recommendations as to the methods and
equipment to be used in assembling the joint. In particular the Contractor shall render the
end of each pipe perfectly smooth so as to allow the joint sleeve to slide freely, and where
necessary shall re-coat the pipe ends with two coats of quick drying bituminous solution.

1.14.4.16 Flanged Joints for Iron or Steel Pipelines

When assembling flanged joints the rubber joint ring may be fastened to the bolts with
cotton thread. The use of jointing paste or grease will not be permitted. The bores of
abutting pipes or fittings shall be concentric with the joint gasket positioned centrally; no
joint material is to be left protruding into the bore. All nuts shall first be tightened by hand
and nuts on opposite sides of the joint circumference shall then be alternately and
progressively tightened with a spanner so as to ensure even pressure all-round the joint.

1.14.4.17 Joints for Plastic Pipes

The joints for uPVC, polythene and HDPE pipes shall be of the mechanical type, and
solvent welding or thermofusion techniques shall not be used without the approval of the
Engineer. The pipes shall be laid and jointed strictly in accordance with the manufacturer’s
instructions and shall conform to CP 312.

1.14.4.18 Closing Lengths

Pipes which are required to be cut to form closing pieces in any portion of the pipeline, or
to terminate in manholes or other parts of the Works, shall not be cut until after all adjacent
pipes have been installed and jointed. Pipes for closing lengths shall be cut to allow a 20
mm gap between adjacent pipe ends.

The Contractor shall determine the length of each closing piece and the end of the pipe
shaped up and trimmed so as to ensure an accurate joint or termination as the ease may
be. Any damage to sheathing coating or lining shall be made good.

Pipes terminating in manholes and the like shall, except where otherwise specified, be cut
so that the end of the pipe is flush with the face of the structure into which it is built. The
closing joints in pressure pipelines shall be made with detachable flexible couplings with
locating plugs.

The Contractor may arrange at his own risk for cuts to be performed by the pipe supplier.

1.14.4.19 Work inside Pipelines

The Contractor shall provide, operate and maintain adequate systems of access, lighting
and ventilation to any part of a pipeline where work is in progress inside the pipes.

GKW - Alliance 148


SPECIFICATIONS
CIVIL WORKS

1.14.4.20 Protection of Iron Pipes and Valves

Except where decorative painting is specifically detailed (for example within pump stations),
pipes and valves installed above ground or in chambers and tanks shall be provided with a
bituminous coating at the manufacturer’s works. After installation, the items shall be
thoroughly cleaned and given two further coats of bituminous paint.

All buried iron pipes and valves, including Viking Johnson couplings shall be protected from
corrosion with wrapping material as specified below.

1.14.4.21 External Wrapping

Pipes, fittings and valves which are to be buried in the ground shall be protected with
wrapping material. All items not wrapped before installation shall be clean and dry and
shall be given one coat of primer supplied by the manufacturer of the wrapping material.
Joint and fitting profiles shall then be modified by the application of moulding putty supplied
by the manufacturer of the wrapping material to provide a suitable profile for wrapping.
Wrapping shall then be carried out and shall lap with the works-applied protection on the
pipes on each side of the joint.

The wrapping shall be applied under tension to achieve conformability and intimate
adhesion without trapped air pockets. Wrapping shall be carried out with a 55% overlap of
adjacent strips. End overlaps where a new roll joins a completed one shall be 150 mm
minimum.

1.14.4.22 Pipelines in the Same Trench

Where two or more pipelines are detailed as being laid in the same trench the pipes shall
be laid so that there is a minimum distance of 150 mm between the barrels of the pipes,
measured in plan at mid-barrel height, unless a greater distance is required to enable
jointing to be properly completed. The invert levels of the pipelines shall be the same at
any cross section, unless otherwise required.

The larger of the pipelines shall be laid in a straight line. Where it is necessary to increase
the distance between the pipelines from that specified above to allow the construction of air
valve or washout chambers or for any other reason, the deviation of a pipe from the line of
the preceding pipe shall be made by deflecting the flexible joints.

1.14.4.23 Anchor and Thrust Blocks

Concrete thrust and anchor blocks shall be constructed at all tees, bends, tapers and valves
for the anchorage of the pipeline.

Unless otherwise specified, thrust blocks shall be constructed with the bottom and thrust
side surfaces bearing against undisturbed ground.

Shear keys shall be formed on the upper surface of concrete blinding for horizontal thrust
blocks.

1.14.4.24 Pipelines Built into Structures

Any pipeline which is built into a chamber, manhole or other structure, including a thrust
block, shall be provided with two flexible joints outside the face of the structure. Unless

GKW - Alliance 149


SPECIFICATIONS
CIVIL WORKS

otherwise specified, the first joint shall be not more than one pipe diameter or 500 mm,
whichever is the greater from the outside face, and the length of the short pipe between the
flexible joints shall be equal to two pipe diameters or 1000 mm, whichever is the greater.

The flexible joints shall be either flexible spigot and socket joints or detachable flexible
couplings.

Pressure pipes passing through the walls of the valve chambers or other structures shall
be ductile iron or steel provided with anchorage flanges designed to transmit full end thrust
with closed valve under test into the structures wall. Boxouts, if used, shall be designed to
fulfil the above requirements. Drawings showing the method of construction using boxouts
shall be submitted for approval by the Engineer.

Where no anchorage flanges are detailed for pipes passing through the walls of structures
the pipe shall be provided with a puddle flange integral with the pipe wall or bolted on to
resist movement of water along the pipe to concrete interface. Such puddle flanges shall
protrude at least 50 mm from the pipe barrel.

In the case of clayware gravity pipelines the short length of pipe built into the wall shall be
of the same material and shall be surrounded in concrete. Where uPVC pipes are being
built into walls or surrounded with concrete they shall be protected with wrapping material,
with a 55% lap, to a point 50 mm outside the face of the wall or concrete surround.

Where the pipeline is above ground level the short length of pipe providing flexibility shall
be self-supporting.

1.14.4.25 Installation of Pipelines other than Buried Pipelines

The Contractor shall take due care to support adequately the pipework during installation
until permanent supports and anchorages, as approved by the Engineer, have been
completed. The Contractor shall ensure that no excessive loads or stresses are imposed
upon the plant, pipework or structure during installation.

Pipework systems shall be complete and checked for correct position and alignment with
adjacent plant and structures immediately before and after being embedded in concrete.
Brackets and fixings shall be painted with two coats of bituminous paint.

1.14.4.26 Plugging of Dead Ends

The dead ends of pipes and fittings shall be plugged as directed by the Engineer. Concrete
anchors shall be provided.

1.14.4.27 Cables Sharing Pipelines Trenches

Where cables are specified to be laid in pipeline trenches, the pipes shall be installed and
fine backfill shall be placed to 150 mm above the crown of the pipe. The cable shall then
be laid as required before the remainder of the trench is backfilled.

1.14.4.28 uPVC Ducts

uPVC pipes used as ducts (for cables or small bore pipework) shall be surrounded with
granular material as specified. They shall, as far as possible, be laid in straight lines

GKW - Alliance 150


SPECIFICATIONS
CIVIL WORKS

between drawpits or other terminations, except where bends or large radius curves are
prescribed.

Where ducts are detailed as being laid in large radius curves in either the horizontal or
vertical planes, these shall by not less than 100 m radius, unless a smaller radius is
sanctioned by the Engineer. Ducts shall be laid in regular curves of the required radius by
bending the pipe during installation. Curves shall not be formed with angular deviations at
flexible joints.

Joints shall be spigot and socket solvent cement welded or rubber ring type or other
approved. In jointing or bending the pipe, the Contractor shall take account of any
recommendations made by the pipe manufacturer. Joints may be made before the pipe is
laid.

Pressure testing of ducts after installation is not required.

Draw cords shall be provided where the ducts are for cables. The draw cord shall be a
polypropylene cord having a breaking load of not less than 5 kN. Joints in the draw cord
shall be kept to a minimum; they shall be at least as strong as the cord and shall be so
made as not to cause any jamming in use.

1.14.4.29 Route Marker Posts

In order to leave permanent indication of the routes and depths of pressure pipelines and
cables where they are below ground, the Contractor shall provide and set up marker posts
with aluminium indicator plates.

The marker posts shall be set up as soon as practicable after trench excavations have been
refilled, but the Contractor shall provide any temporary marking required and shall be
responsible for correct information being given on the indicator plates.

Marker posts shall be provided at changes in direction of the main or cable and at field
boundaries, and elsewhere as may be ordered by the Engineer indicating the diameter and
depth of the main cable below giving ground level.

1.14.4.30 Chambers and Manholes

Valve chambers, air valve chambers, flowmeter chambers, manholes and similar structures
shall be built into the pipeline where required.

The requirements for anchors and thrust blocks in respect of excavation, backfilling and
forming shear keys in the concrete blinding for horizontal thrust blocks shall also apply to
valve chambers in which pipes are anchored.

If undisturbed ground has not been maintained next to a thrust bearing surface the gap
shall be backfilled with mass concrete.

All chambers and manholes shall be cleaned of any accumulation of silt, mortar, debris or
any other foreign matter and shall be free of any accumulation at the time of final inspection.

GKW - Alliance 151


SPECIFICATIONS
CIVIL WORKS

1.14.4.31 Manholes on Gravity Pipelines - General

At each alteration of gradient or direction, at each intersection with other sewers and at
such other points, not exceeding 80 metres apart, as are directed by the Engineer, a
manhole shall be constructed.

The excavation for the manholes shall be carried to such depths as may be determined
from the sewer sections or as are directed by the Engineer.

Backfilling around manholes shall be carried out as construction proceeds. On no account


shall the concrete work be built up so far ahead of backfilling as to impede proper
consolidation of the backfill material.

When constructing manholes provision shall be made for future connections thereto from
future sewers by laying one length of pipe sealed by a cap as ordered.

All manholes shall be watertight on completion.

1.14.4.32 Precast Concrete Circular Manholes

Except for the base, precast manholes shall be formed using precast concrete circular
manhole sections and cover slabs.

All joints in precast manhole sections shall be made with cement mortar except in the case
of manholes protected in accordance with the clause ‘Protection of manholes’ hereafter.

The bases shall be cast in situ in concrete 150 mm thick and shall be poured upon a blinding
layer of concrete not less than 80 mm in thickness.

The clayware channel inverts including all necessary bends, tapers, junctions and double
junctions shall be accurately laid to fall, the bends being as ‘slow’ as possible by siting
manholes ‘off centre’ at changes in direction. The sewer pipe shall be built into the vertical
upstands which shall vary in height above the crown level of the sewer pipe to obtain the
required manhole depth with standard precast rings.

The manholes shall be surrounded with grade 20 concrete 150 mm thick and the concrete
shall be shuttered with Class F1 formwork.

Manhole floors shall be constructed of grade 20 concrete benching and grade 25 precast
concrete bullnosed sections, formed to the required shapes. The top of the in-situ benching
shall be sloped back at 1 in 12 and rendered with cement mortar 20 mm thick.

Galvanised malleable iron step irons at vertical intervals of 300 mm and 300 mm centres
horizontally shall be fixed in the precast circular manholes.

1.14.4.33 Cast-in-situ Manholes

Cast-in-situ manholes shall be rectangular and the walls, bases and cover slabs shall be
cast-in-situ reinforced concrete grade 25.

The channel shall be formed using asbestos cement channel on straight-through manholes,
or 20 mm layer of sulphate resisting cement mortar on internal-bend manholes. The
asbestos cement channel inverts, formed by cutting asbestos cement pipes in half, and the
in-situ concrete channel inverts shall be laid or formed accurately to fall. The manhole

GKW - Alliance 152


SPECIFICATIONS
CIVIL WORKS

floors shall be constructed of grade 20 concrete benching formed to the required shape and
the top of the in-situ benching shall be sloped back at 1 in 12.

Junction manholes shall be arranged so that the branch sewer enters the manhole on the
opposite side to the access platform, unless directed otherwise by the Engineer.

All bends on sewers up to and including 600 mm dia. shall be sited inside the manholes.
All bends on sewers over 600 mm dia shall be sited outside and immediately downstream
of the manholes.

Galvanised mild steel ladders, handrailing standards and safety chains shall be fixed in the
rectangular manholes. The safety chains at access openings shall be permanently fixed at
one end and hooked at the other, and the safety chains across sewer openings shall be
fixed at both ends.

1.14.4.34 Flushing Manholes

Flushing manholes shall be placed at the head of each sewer.

1.14.4.35 Fixing and Positioning Manhole Covers

Cast iron covers shall be built with their frames bedded on the concrete cover slabs, except
where the Engineer directs that a course of engineering brickwork shall be introduced. On
no account will more than one course be allowed.

The covers shall be carefully set to the slope of the ground or road surface. After setting in
position the lifting and prising holes provided in the cover shall be cleaned out and refilled
with tarred hemp.

1.14.4.36 Cover Keys

Two pairs of keys for use with each type of cover shall be handed over by the Contractor
at the completion of the Contract.

1.14.4.37 Protection of Manholes

The internal surfaces of manholes located on sewers at and within 2000 metres
downstream of a pumping main discharge connection shall be provided with an anti-
corrosive coating.

Sand epoxy mortar for the joints between clayware channel inverts and the concrete
benching, shall consist of CXL 401(see on) and sand in the proportions recommended by
the manufacturer.

On completion of the construction of the manholes and the testing for water-tightness, all
internal faces including precast concrete sections and cover slabs, benching, precast
concrete bullnosed sections and concrete in manhole bases shall be painted with 1 coat of
CXL 121 followed by 2 coats of CXL 141 (light grey) supplied by Colebrand Ltd., 20
Warwick Street, Regent Street, London, W1R 6BE or with a similar system. The materials
shall be used strictly in accordance with the manufacturer’s instructions, with particular
attention to the provision of fresh air (by means of a power fan) when painting.

GKW - Alliance 153


SPECIFICATIONS
CIVIL WORKS

1.14.4.38 Brickwork

All brickwork shall be uniformly bedded, bricks always being laid frog upwards, and each
brick ‘floated’, ‘rubbed in’ or ‘hammered down’ upon such a sufficient quantity of mortar that
the mortar may be squeezed up into the joints and each joint not already full shall be
‘flushed up’ with the mortar of the next succeeding bed. The whole of the beds and joints
shall be completely filled and compressed so as to ensure the greatest possible density.
Horizontal weathered jointing shall be provided to all external faces. Bricks with a very high
suction may be wetted but not saturated, immediately before laying.

All engineering brickwork shall be built in cement mortar as specified.

1.14.4.39 Cement Mortar

All cement mortar shall be composed of fine aggregate and cement in such proportions as
may be specified or as directed by the Engineer.

The ingredients shall be thoroughly mixed while dry by machine or hand until the cement
colour can no longer be distinguished from the fine aggregate in any part of the mass, and
then shall be uniformly wetted by means of a rose while undergoing further thorough mixing.

The mortar shall be prepared and used at such places and times and in such quantities that
a longer time than thirty minutes shall not elapse between the first wetting and its completed
use upon the Works. If mixed by hand no single mixing shall exceed a quarter of a cubic
metre.

1.14.4.40 Cleaning Pipelines

The pipelines shall be kept thoroughly cleaned and ready for inspection by the Engineer at
any time, and an adequate supply of expanding rubber plugs shall be available at all times
to ensure that all pipe-ends are stopped off. Except when cleaning or water testing, water
shall not be allowed to flow through the pipes.

Gravity pipelines and ducts shall be proved by passing through them a train consisting of
an approved badger and a circular rubber squeegee followed by a wooden ball. The
wooden ball shall not be smaller than 25 mm less in diameter than the pipes under
inspection. The Contractor shall remove any obstruction found during these operations.

Before commencing pressure testing, the Contractor shall clean out the part of the pipeline
to be tested to the satisfaction of the Engineer. The method of cleaning shall be decided by
the Contractor and may include flushing through with water.

After the whole pipeline has been successfully pressure tested (whether as a whole or in
sections) and the Contractor has removed all temporary works and has reconnected any
parts temporarily removed from the pipeline, the Contractor shall finally clean out the whole
pipeline and flush it through with clean water.

1.14.4.41 Repair of Fusion Bonded Epoxy Coatings

In the event of a fusion bonded epoxy coating being damaged after leaving the factory, the
item shall be returned to the factory for repair or, with the approval of the Engineer, be
repaired at Site. Repairs shall be effected in accordance with the following requirements:

GKW - Alliance 154


SPECIFICATIONS
CIVIL WORKS

(a) repair materials shall be compatible with the original factory-applied coating
materials;
(b) the edges of the original factory-applied coating shall be ground off to a taper or
feather edge;
(c) exposed metal shall be treated as specified;
(d) the relative humidity of the atmosphere in which the repair is to be effected shall be
maintained (if necessary, by the use of hot air blowers and tenting) at less than 85%;
(e) the surface temperature of the exposed metal shall be raised to at least 3ºC above
dew point and the coating shall then be applied in stages, as recommended by the
manufacturer, so as to achieve a total thickness in accordance with the specification.

All repairs shall be checked with a holiday detector and any holes shall be repaired, after
which the repairs shall be re-checked.

1.14.5 Inspection and Testing

1.14.5.1 Inspection at Time of Installation

In addition to any inspection and tests made when delivery is taken, pipeline materials,
including any sheathing, lining or protective paintwork, shall be inspected by the Contractor
immediately before and after installation and any damage shall be repaired by the
Contractor as directed by the Engineer before the pipe or fitting is installed or jointed as the
case may be. Any special material required for the repair of pipe sheathing or lining shall
be obtained from the pipe supplier and shall be used in accordance with his
recommendations.

The Engineer may himself, and without thereby relieving the Contractor of any of his
obligations, inspect and test the pipeline materials by any means he considers appropriate
and any damage discovered by such inspection shall be repaired by the Contractor.

The Contractor shall remove from the Site and shall provide a replacement for any pipe or
fitting which in the opinion of the Engineer is so badly damaged as to be unfit for repair on
the Site.

1.14.5.2 Testing Pipelines - General

The Contractor shall subject all parts of the completed pipeline system to a final test. For
the purposes of this final test, the pipeline system shall if necessary be divided into suitable
sections as agreed with the Engineer. All testing shall be witnessed and approved by the
Engineer

Where directed by the Engineer, a section of pipeline in a particularly difficult location shall
be subjected to hydrostatic test immediately the section has been completed, using a
pressure not less than that to be applied for the final test.

Notwithstanding the foregoing, the Contractor may at any stage of construction carry out
such preliminary tests as he considers desirable to check materials and workmanship on
the pipeline, but this shall not relieve the Contractor of his obligations to achieve approved
test results on completion.

The Contractor shall during testing demonstrate satisfactory operation under working
pressure of each valve installed under the Contract.

GKW - Alliance 155


SPECIFICATIONS
CIVIL WORKS

The Contractor shall provide for the supply of water, and shall supply all pressure gauges,
meters, hoses, pumps, stop ends and other temporary supports and equipment needed for
carrying out tests.

The Contractor shall remain responsible for the care of the Works during testing and
cleaning of the pipeline.

1.14.5.3 Procedure for Pressure Testing

Before filling for pressure testing is started the Contractor shall re-check pipes and valves
for cleanliness and shall re-check the operation of all valves. The ‘open’ ends of the pipeline
(or sections thereof) shall normally be stopped off by blank flanges or cap ends additionally
secured where necessary by temporary struts and wedges. All thrust blocks and valve
chambers shall have been completed with backfill placed around them and the concrete
shall have attained its specified 28 day strength. All pipe straps and other devices intended
to prevent the movement of pipes shall have been securely fastened and backfilling of
trench between pipe joints shall have been placed to the extent necessary to prevent
movement of the pipeline.

Asbestos cement pressure pipelines shall be tested in accordance with the applicable
standard, the test pressure being maintained for not less than 4 hours. Other pressure
pipelines shall be tested as follows.

The pipeline or section of pipeline to be tested shall be filled with water and all air shall be
removed. Before the test proceeds further, the pipeline shall be allowed to stand full of
water for at least 24 hours. The pressure shall then be raised by pumping in water until the
specified test pressure (P) is reached and shall be maintained at this pressure by further
pumping for a period of at least 24 hours during which time the pipeline shall be inspected
for points of concentrated leakage. In the case of pipelines of absorbent materials, this
period shall be extended as necessary until the absorption has ceased. Pumping shall then
cease and the time (T) for the observed pressure head to fall by 10 m shall be recorded.
Pumping shall then be resumed and the quantity of water (Q) pumped into the pipeline from
calibrated container(s) in order to restore the test pressure (P), shall be recorded. Provided
that if the observed pressure head has not fallen by 10 m before an expired period of three
hours then pumping, shall be resumed at once and the time (T) shall be recorded as being
three hours. The rate of loss shall be calculated as being the quantity (Q) divided by the
time (T).

1.14.5.4 Test Standard for Pressure Pipelines

The test pressure (P) refers to measurements at the same level as the pumping main
adjacent to the pump station. Where test pressures are measured along the pumping main
at levels significantly above or below the level of the pumping main adjacent to the pump
station, the test pressures shall be decreased or increased accordingly.

Unless otherwise directed by the Engineer, the test pressure (P) shall be such that a water
column connected to the pipeline would reach a height of 60 metres.

A pipeline shall be deemed to have passed the pressure test if the rate of loss as calculated
above does not exceed the equivalent of 0.025 litres per 24 hours per millimetre of nominal
internal pipe diameter per 100 m of pipe.

If any pumping main fails to pass the pressure test, the Contractor shall locate the faults
and shall uncover repair retest and reinstate that pumping main as may be necessary until
all pumping mains shall have passed the pressure test.

GKW - Alliance 156


SPECIFICATIONS
CIVIL WORKS

1.14.5.5 Testing Gravity Pipelines

Each length of gravity pipeline shall be carefully air tested before concrete bedding is placed
and before the trench is backfilled. The air pressure shall give 100 mm head of water on a
manometer tube, and the loss shall not exceed 25 mm over a period of five minutes. The
pipeline shall be tested in convenient lengths and all necessary tester junctions expanding
rubber plugs, testing equipment etc. shall be provided by the Contractor. The Contractor
shall immediately remedy any defect which may become apparent and re-test to the
satisfaction of the Engineer.

With the approval of the Engineer the concrete bedding may then be placed and the trench
backfilled in the manner specified, and the pipeline shall again be tested as before unless
the water table is above the level of the pipeline and the Engineer prefers to test for
infiltration. Where an infiltration test is carried out the water entering the pipeline by this
means shall not exceed 0.40 litres per 24 hours per millimetre of nominal internal pipe
diameter per 100 metres of pipe.

If it appears that any pipe has been broken or any joint has been disturbed during backfilling,
then the Contractor shall re-open the trench and repair the defect or defects until the
pipeline has been retested to the satisfaction of the Engineer.

The Contractor shall ensure that a complete set of testing equipment and all necessary
expanding rubber plugs are available at all times at all parts of the Works where pipelaying
is in progress, in order that the Engineer may carry out a test at any time.

Water testing as an alternative to air testing will be allowed at the discretion of the Engineer
in which case the pipeline shall be tested under at least 1 500 millimetres head of water,
and the loss shall not exceed 0.40 litres per 24 hours per millimetre of nominal internal pipe
diameter per 100 metres of pipe.

Unless the Engineer shall direct otherwise, the Contractor shall be at liberty to retain the
water in the pipes after the first test and during the process of backfilling so that the pipe
lengths need only to be water filled once for testing purposes.

1.14.5.6 Testing Building Laterals and Drains

Each building lateral is to be provided with a junction for the insertion of an expanding test
plug. This junction shall be located next to the junction on the pipeline or the connecting
bends, if used. When testing the pipeline, the plug will be placed on the pipeline side of the
junction so that the water-tightness of the lateral as far as the plug will also be proved.
When testing the lateral, the plug will be inserted on the other side of the junction. Upon
the satisfactory completion of the latter test the plug will be removed and the function sealed
by a clayware stopper with a flexible joint.

If any building lateral or drain fails to stand the test, as described for gravity pipelines the
defect or defects shall be discovered and made good by the Contractor and the lateral or
drain retested.

GKW - Alliance 157


SPECIFICATIONS
CIVIL WORKS

1.15 Painting and protective coatings

1.15.1 Submission by the Contractor

Submissions which the Contractor is required to make in relation to painting and protective
coatings shall include, where relevant, those listed below.

1.15.1.1 Schedule of Paint Systems and Protective Coatings

The Contractor shall prepare a detailed schedule for the complete Works which shall
contain the following information:

1. System reference
2. Type of surface
3. Component or section of the Works
4. Environment of item
5. Surface preparation
6. Paint system or protective coating to be applied
7. Name of coating manufacturer
8. Brand name and reference number for each coat to be used
9. Colour of finishing coat stating the Munsell system colour notation
10. Proposals concerning place of application and detailed method of application of each
coat, including information on equipment to be used
11. Wet film minimum and target thickness for each coat
12. Dry film minimum and target thickness for each coat
13. Density of paint for each coat and coverage of paint per unit volume.

The schedule shall be accompanied by manufacturers’ data sheets for each coat, including
technical description of paint.

The work detailed on the schedule shall meet the requirements specified or otherwise
required by the Contract.

Where practicable, the schedule shall be in the format of the specimen schedule of paint
systems and protective coatings included at the end of this Section.

The schedule shall be subject to the approval of the Engineer.

1.15.1.2 Record Sheets for Steelwork

For each section of steelwork, the Contractor shall provide a numbered record sheet and
continuation pages in duplicate on which the progress of each operation will be recorded
from the initial state of the steel before cleaning through to final inspection.

All relevant data shall be recorded including:

 reference to identify the steelwork precisely;


 date;
 weather conditions (or ambient conditions in a workshop);
 preparation, coating or repair being undertaken;
 area coated and quantity and type of materials used;

GKW - Alliance 158


SPECIFICATIONS
CIVIL WORKS

 details of tests and measurements taken;


 delays and causes, faults observed and corrections made.

There shall also be space for comments or confirmation by the Engineer who shall receive
one copy-not more than 24 hours after the work is completed.

1.15.2 Specimen Schedule of Paint Systems and Protective Coatings

System Reference

TYPE OF SURFACE
Component or section of the Works
Environment category

General Type of coating system

Typical time to first maintenance

Surface preparation prior to Type of surface treatment


painting Quality level
Metal coating Type of metal coating
Thickness of coating
Surface preparation prior to Type of surface treatment
metal coating Quality level
Priming coat
Type of paint Stripe coat
Undercoat
Finish
Priming coat
Number of coats and DFT Stripe coat
Undercoat
Finish
Priming coat
Colour Stripe coat
Undercoat
Finish

GKW - Alliance 159


SPECIFICATIONS
CIVIL WORKS

1.15.3 Materials

1.15.3.1 Materials in Contact with Potable Water

No substance or product which could impart toxicity, taste, odour or colour to water or be
otherwise objectionable on health grounds, shall be used in the Works where it may be
applied to or introduced into water which is to be supplied for drinking, washing or cooking.
Only those substances and products which meet the requirements of subparagraph (a), (b),
(c) or (d) of paragraph (1) of Regulation 25 of the Water Supply (Water Quality) Regulations
1989 shall be used in such situations.

1.15.3.2 Paints - General

Paints shall be supplied only by a manufacturer who has received the approval of the
Engineer. Unless otherwise approved by the Engineer, all paints to be applied to a particular
surface as part of a paint system shall be obtained from a single manufacturer.

Where priming of surfaces is executed before delivery to Site, the Contractor shall ensure
(and obtain written confirmation from the appropriate supplier) that the primers used in
these instances are obtained from the same manufacturer as that approved by the Engineer
for the finishing coats.

Where appropriate the Contractor shall certify to the Engineer that paints supplied for use
on the Works are compatible with any timber preservation or fire proofing treatment which
may be specified.

All paint shall be supplied in sealed containers bearing the following information in addition
to any statutory requirements:

(a) Manufacturer’s name, initials or trade mark.


(b) Type of paint.
(c) Whether priming, undercoat or finishing coat.
(d) Whether for interior or exterior use.
(e) The colour and its reference number.
(f) The method of application (i.e. brush, spray or roller)
(g) The batch number and date of manufacture or re-test.
(h) Storage instructions and shelf life.
(i) Appropriate safety instructions.

Containers for protective materials other than paints shall bear as much of the above
information as appropriate.

Paint containers shall not exceed 5 litres capacity with the exception of containers for
emulsion, spraying paints, bituminous paints, stone, cement and road marking paints which
may be of larger capacity.

1.15.3.3 Paint Colours

All paint colours shall comply with the applicable standard. Final coats shall be in
accordance with colour schedules to be issued by the Engineer. Each coat shall differ
noticeably in tint from the previous coat.

GKW - Alliance 160


SPECIFICATIONS
CIVIL WORKS

1.15.3.4 Thinners and Solvents

The type and quality of thinners to be added to paint shall be that recommended by the
manufacturer for the particular type of paint.

Separate supplies of solvents shall be kept on site for brush or other cleaning purposes.
Solvents for these purposes shall be tinted a different colour to thinners used for thinning
paint.

1.15.3.5 Knotting and Stopping

Stopping for concrete or sand/cement plastering shall be of similar material to the


background and shall have a similar surface finish. Stopping for woodwork, hardboard and
plywood shall be a proprietary spirit-based wood filler tinted to match the undercoat colour.
Stopping for natural finished woodwork shall be a proprietary spirit based wood filler tinted
to match the woodwork.

1.15.3.6 Bitumen Coatings

Bitumen coatings shall be formed of the appropriate grades of materials for cold application,
or for hot application.

1.15.3.7 Primers and Linseed Oil for Wood

Priming paint for wood shall be aluminium wood primer except where the Engineer
approves low lead priming paint or, if narrow strips of galvanised steel and timber abut,
calcium plumbate priming paint, or a quicker drying equivalent.

Linseed oil shall be refined linseed oil of high quality.

1.15.3.8 Cement Paints and Pavement Marking Paints

Cement paints shall comply with the applicable standard.

Pavement marking paints shall comply with the applicable standard.

1.15.3.9 Welding Primers and Priming Paints for Steel

Welding (prefabrication) primers shall be suitable for continuous spray application dry
rapidly, and harden sufficiently within 10 minutes to permit handling of the steel without
damage to the prefabrication primer.

Prefabrication primers shall be non-toxic and shall not give rise to objectionable fumes
during flame-cutting and welding. The prefabrication primers, when applied to the steelwork
in the thickness of coating necessary to protect the steel effectively during the period before
application of the main protective system, shall not affect the strength or quality of welds
made through the coating.

Prefabrication primers and priming paints for steel shall contain corrosion-inhibiting
pigments, adhere firmly to the substrate and form suitable bases for the succeeding coats
in the protective paint system.

GKW - Alliance 161


SPECIFICATIONS
CIVIL WORKS

Where specified to be included in the steelwork paint systems:

(a) zinc inorganic silicate prefabrication primers and priming paints shall contain a
minimum 90% by weight metallic zinc in the dry film;

(b) zinc phosphate prefabrication primers and priming paints shall contain 40% minimum
by weight of zinc phosphate as a percentage of the dry pigment.

1.15.3.10 Epoxy Paints

Containers of epoxy paint shall be of a pack-size suitable for complete usage by one
operator within the pot life of the material at the highest likely ambient temperature. The
Engineer may give approval to the supply and use of larger packs, but only where the
proportioning of the various parts, their mixing, and issue of paint shall be under the direct
control of a skilled and experienced operator. A mechanically operated mixer shall be used
and shall be of a design which does not entrain air in the paint.

Except where otherwise specified, epoxy resin paint shall be so formulated that the epoxy
resin content, together with its curing agent, shall be not less than 40% by weight of the
solid binder.

The pot-life of epoxy primers and paints when mixed shall be not less than one hour at the
temperature at the place of application at the time of mixing. When approved by the
Engineer will have regard to the ambient temperatures likely to obtain for field application
and may restrict paint application to those times when the temperature is sufficiently low for
the specified pot-life to be ensured.

Thinners shall not be mixed with epoxy materials. Strict control shall be exercised in the
issue of thinners for cleaning brushes and equipment.

1.15.4 Workmanship

1.15.4.1 Painting - General

Paint shall be supplied from the Contractor’s paint store to the painters ready for application.
Any addition of thinners shall be made in the store under supervision and up to the limit
detailed on the appropriate manufacturer’s paint data sheet, for the particular method and
conditions of application concerned. Paint shall be thoroughly stirred before and during
use, and shall be strained, as and when necessary.

Paint shall be applied only when the ambient temperature is above 5C, and when the
relative humidity is below 90%. Surfaces to which the paint is applied shall be dry and shall
remain free from moisture until the coating has dried or cured sufficiently to avoid effects
harmful to the subsequent appearance or satisfactory protective behaviour of the paint.
Application of paint shall be by one of the following methods, the choice being the
Contractor’s, unless one particular method is specified or is recommended in the
manufacturer’s instructions for use of the paint:

 brush
 air pressure spraying
 airless spraying

Paints with suitable flow-out properties may be applied to large flat areas by mohair sleeved
rollers. Rollers shall not be used under other circumstances or for the application of paints

GKW - Alliance 162


SPECIFICATIONS
CIVIL WORKS

containing micaceous iron oxide pigments. Each coat shall be allowed to dry, be rubbed
down and be cleaned as necessary before application of any subsequent coat of paint.
Brushes, tools and equipment shall be kept in a clean condition and surfaces shall be clean
and free from dust during painting. Painting shall not be carried out in the vicinity of other
operations which might cause dust. The final coat shall be uniform in colour and free from
brush marks, runs or other defects.

The Contractor shall not dispose of solid or liquid wastes from painting work down any
permanent sanitary fittings, sinks or drains and a non-inflammable portable container shall
be provided and used for this purpose.

The Contractor shall take every precaution to protect newly painted surfaces from damage
by any cause including wind-blown dust. Precautions shall include warning signs, barriers
and covers.

1.15.4.2 Storage of Paint

Paint shall be stored in sealed containers in a lock-up store maintained at a temperature of


not less than 4C and not more than 27C. Any special storage conditions for the paint
recommended by the manufacturer shall be observed. Containers of any one paint shall
be used in strict order of delivery from the manufacturer.

No paint shall be used more than 12 months after the date of its manufacture nor shall any
paint be used after the expiry of the shelf life specified on the paint containers.

At the end of each working period during which paint application has been carried out, all
two-pack primers and similar chemically-cured paints with a limited pot life which have been
mixed but not used, shall be discarded. Other types of paint from painters’ kettles shall be
returned to the store and kept in sealed containers.

A separate store shall be provided for cleaning solvents used for brush or other cleaning
purposes. Cleaning solvents shall not be stored where paint or paint thinners are stored or
where paint is prepared for application.

1.15.4.3 Protection of Surfaces

All necessary precautions shall be taken by the Contractor before the commencement of
any painting activities to ensure that no damage or disfigurement of any kind is caused
thereby to any part of the Works. If in the opinion of the Engineer the precautions taken
are inadequate, the Contractor shall make all such improvements as the Engineer directs.

The Contractor shall exercise particular care not to apply paint to any surfaces not intended
to be painted and shall promptly and thoroughly remove any paint applied to such surfaces.
All floors and surfaces liable to damage or spillage shall be protected with dust sheets.

The Contractor shall remove all ironmongery and door furniture before painting work
commences and re-fix all items on completion of the painting.

1.15.4.4 Safety Precautions for Painting

The implementation of manufacturers’ recommendations concerning health and safety


aspects of all paints used on the Works shall be mandatory under this Contract.

GKW - Alliance 163


SPECIFICATIONS
CIVIL WORKS

1.15.4.5 Preparation of Surfaces for Painting

The Contractor shall regard the preparation of surfaces to be painted as work of


fundamental importance, the object being to ensure the production of sound, clean, smooth
and dry surfaces. The preparation shall have no detrimental effect on the substrate to be
painted nor shall it be prejudicial to subsequent painting operations.

1.15.4.6 Preparation of Wood Surfaces

The preparation of wood surfaces shall include stopping, filling, rubbing down and bringing
to a smooth surface free of dust.

Surfaces which are to be painted shall be rubbed down to remove all contaminating
substances and imperfections which would be visible in the finished paint film. The surfaces
of knots and resinous streaks shall then be painted with two coats of shellac knotting, the
first being allowed to dry before the second is applied.

The surfaces of timber treated with a water-borne preservative by an impregnation process


shall be rubbed down and dry-brushed to remove all traces of efflorescence before the
primer is applied.

Where surfaces are suspected of being infected with mould, they shall be thoroughly
treated with a fungicide.

Wood surfaces shall not be painted when the moisture content of the timber measured with
an electric conductivity moisture meter exceeds 12 percent for interior surfaces or 17
percent for exterior surfaces.

The backs of timber members in contact with walling shall be painted with two coats of
aluminium wood priming paint prior to fixing.

1.15.4.7 Preparation of Plaster, Brickwork and Concrete Surfaces for Painting

Efflorescence present on the surfaces of plaster, brickwork and concrete shall be removed
by scraping brushing and wiping with a dry, coarse cloth followed by a damp cloth. When
efflorescence has been removed, surfaces shall be left for at least three days and shall be
approved by the Engineer before painting. Painting shall be deferred where further salt
deposits form on the surface during this period.

Plaster surfaces to be painted shall be cleaned down, filled and smoothed as necessary.

Brickwork, blockwork and concrete surfaces shall be cleaned of all contaminating matter
before being painted. Subject to the approval of the Engineer large holes which would
cause a break in the paint film shall be filled with mortar the surface being rubbed down to
match the surrounding areas.

1.15.4.8 Preparation of Concrete and Rendered Surfaces for Epoxy Coatings

Concrete and rendered surfaces shall be thoroughly cured before the application of an
epoxy filler primer or paint is begun.

All surfaces to be protected with an epoxy paint system shall be prepared as described
below, maintaining the sequence of operations indicated.

GKW - Alliance 164


SPECIFICATIONS
CIVIL WORKS

Areas of concrete contaminated with machine oil or grease shall be cut out as necessary
to remove all traces of such substances and shall be made good with an approved epoxy
mortar. Areas contaminated with release agent shall be scrubbed with suitable emulsion
cleaners and any mould growth shall be treated with water-soluble fungicide. All surfaces
so treated and any other water-soluble on the surfaces (e.g. salt) shall be rinsed off with
sweet water until they are clean.

All concrete and rendered surfaces to be coated shall be lightly blast cleaned to remove
the cement-rich surface layer, taking care not to roughen the surface unduly. Grit and
detritus shall be removed by vacuum cleaning immediately prior to priming.

Blow-holes and honeycombed areas in the concrete which in the opinion of the Engineer
are not capable of being satisfactorily levelled at the primer stage shall be filled with an
epoxy mortar supplied by the coating manufacturer for the purpose. Such mortar shall be
knifed into the surface to level the area and to leave no excess.

1.15.4.9 Preparation of Metalwork and Associated Fixtures and Fittings for Building Works

The main priming paint coat shall be applied to steelwork as soon as practicable after
fabrication and, where possible, shall be of the same general formulation as that used for
the prefabrication primer, if one has been used.

The preparation of ferrous metal surfaces primed at works shall include the removal of any
rust and touching up with primer within seven days of delivery to Site.

The preparation of ferrous metal surfaces delivered to Site un-primed shall include
removing all mill scale and thoroughly wire brushing before painting.

Steel which is to be totally embedded in concrete shall not be primed.

1.15.4.10 Blast Cleaning Steel

Where steelwork is to be blast cleaned, the period and conditions under which steel stocks
are held and the speed, conditions and methods of fabrication shall be such that
immediately before blast cleaning no significant part shall have rusted more extensively
than is shown for rust grade B.

Surfaces to be blast cleaned shall be prepared by thoroughly removing all dirt, oil, grease
and other contaminants by one of the methods recommended by CP 3012, using an
approved emulsion cleaner which shall be changed regularly.

Blast cleaning shall be carried out only when the ambient temperature is above 5C and
the relative humidity is below 85%. Blast cleaning shall be carried out in conditions under
which no protective coatings can fall onto or condense on the surfaces during or
immediately after cleaning. Special attention shall be paid to the cleaning of any ends, re-
entrant corners and edges which will not be cut off or welded after blasting.

After blast cleaning, dust and blasting grit particles shall be removed from the surfaces,
where possible by vacuum cleaning. Any lamination or other defects in the surfaces
exposed by blast cleaning, which could form a corrosion centre under subsequent
protective treatment cover (but which is not otherwise a cause for rejection of the item),
shall be marked clearly for later remedial work.

Blast cleaning shall be followed within four hours by the application of a blast-primer or the
priming coat of the protective coating system.

GKW - Alliance 165


SPECIFICATIONS
CIVIL WORKS

The Contractor shall supply and operate such dehumidification equipment as may be
necessary to preserve blast-cleaned surfaces in a pristine condition until they can be coated
and/or to provide the curing conditions necessary for such coats.

Steelwork fabricated under factory conditions shall not be blast cleaned until all machining
and fabrication has been completed, with such fabrication comprising continuous welded
runs with all exposed surfaces accessible for subsequent treatment. All slag and spatter
shall be removed from the area of welds by chipping hammer prior to blast cleaning.

Surfaces shall be blast cleaned to, Grade Sa1, Sa2, Sa21/2 or Sa3, as specified, or
otherwise as required or recommended by the Reference Standards and as proposed by
the Contractor and approved by the Engineer. Where not otherwise required (e.g. to give a
rougher surface to receive sprayed metal coatings), the abrasive used shall be chilled iron
grit, (or a steel grit of similar hardness), preferably all passing a No. 30 (0.5 mm aperture)
mesh and all retained on a No. 36 (0.42 mm aperture) mesh but a finer grit, Grade G07
would be an acceptable alternative. The abrasive shall not be re-used without satisfactory
cleaning.

Where surface defects revealed or present during blast cleaning are subsequently ground
out or otherwise made good, the resulting dressed surfaces shall be blast cleaned so that
the preparation grade characteristics of the entire surface are uniform.

1.15.4.11 Galvanising and Other Metal Coatings

Where steel or wrought iron is to be galvanised, the galvanising shall be executed after all
fabrication has been completed. Surfaces shall be prepared by removing all weld slag and
spatter, paint, oil and grease. The articles shall then be pickled by either Method F.l or
Method F.2 of CP 3012 and thoroughly washed and dried.

Galvanising shall be carried out so that the whole of the metal is evenly covered, with clean
edges and bright surfaces being presented. The minimum average coating weight shall be
not less than 610 grams per square metre of galvanised surface except for tubes and sheet,
plate or strip, which shall be galvanised as specified in those standards. On steel of under
5 mm thickness, lower coating weights will be accepted only where they and any over-
coating to be applied will provide the required life to first maintenance.

Zinc or cadmium coatings applied by electroplating or Sherardising shall be used only on


small components where galvanising would be impracticable.

Sprayed metal coatings shall comply with the applicable standard.

1.15.4.12 Cleaning Galvanised Surfaces

Dirt and other adherent contaminating matter shall be removed from galvanised surfaces
by brushing with wire or stiff bristle brushes, or by other methods approved by the Engineer.
Cleaning shall be such as not to damage the galvanising. Oil or grease shall be removed
from galvanised surfaces by the application of an emulsion cleaner. Any zinc corrosion
products remaining shall be removed by washing with sweet water and scrubbing with hard
bristle brushes.

After being cleaned and degreased all galvanised surfaces shall be etched with T-wash. If
any surface fails to turn black, the cleaning, decreasing and etching processes shall be
repeated.

GKW - Alliance 166


SPECIFICATIONS
CIVIL WORKS

1.15.4.13 Application of Paint Generally

All paints shall be prepared and applied in accordance with the manufacturer’s instructions.
Copies of appropriate data sheets and of the relevant parts of this Specification shall be
issued to all the supervisors and foremen concerned with surface preparation and coating.
Where a manufacturer’s instructions conflict with this Specification, a ruling shall be sought
from the Engineer.

No thinners or cleaners shall be employed other than those recommended by the paint
manufacturer.

Except where otherwise specified or approved by the Engineer, all priming paints shall be
applied by brush.

Exposure of intermediate coats of paint for periods in excess of a few days shall not be
permitted except in the case of work delivered to Site in a primed condition.

The dried films of the specified paints shall be free from bloom, shrinkage, sheeriness,
wrinkling, sagging, curtaining, discolouration and extraneous matter.

No exterior or exposed paintwork shall be carried out under adverse weather conditions.

Painting shall insofar as is practicable be shaded from direct sunlight to prevent wrinkling
and blistering. Whenever possible, exterior painting during the day shall be so programmed
as to be carried out in shadow.

Painting of surfaces shall not be carried out when the relative humidity of the atmosphere
is such that condensation is present on such surfaces or the application and/or drying of
the paints is likely in the opinion or the Employer’s Representative to be affected.

1.15.4.14 Painting Building Surfaces

Painting work shall comply with the applicable standard and the instructions of the paint
manufacturer, except where otherwise approved by the Engineer.

Except where otherwise specified or approved, at least 24 hours shall be allowed between
the application of successive coats of paint. Each coat shall be dry before the next coat of
paint is applied and each coat of paint shall be rubbed down with fine glass paper before
the next coat is applied.

All wall and ceiling surfaces scheduled to be painted with emulsion paint, shall receive at
least three coats. On absorbent surfaces the first coat of emulsion may be thinned with the
prior approval of the Engineer. At least 4 hours shall be allowed between the applications
of successive coats of emulsion.

The Contractor shall satisfy the Engineer as to the covering capacity of paints and emulsion
according to the absorption of varying surfaces. The method and application of paints and
emulsions shall be sufficient to give solid cover in the number of coats specified.

The Contractor shall prepare sample panels of painting on internal walls and ceilings and
sample areas of painting to metal surfaces and timber surfaces for the Engineer's approval.

The Contractor shall clean off all paint stains from joinery, metalwork and floors on
completion of the painting work.

GKW - Alliance 167


SPECIFICATIONS
CIVIL WORKS

1.15.4.15 Priming Steel and Iron

The main priming paint coat shall be applied to the steel as soon as practicable after
fabrication and, where possible, shall be of the same general formulation as that used for
the prefabrication primer, if one has been used.

After prefabrication priming of any steel plate or section, edges, corners, crevices or holes
still present after fabrication and not part of a welded joint or interior surface of a
hermetically sealed void, shall be given an additional stripe coat of the appropriate main
primer by brush to ensure continuity of protection of the steel across such edges and the
like.

The inside surfaces of members and similar non-fabricated sections where blast cleaning
is impracticable shall be cleaned otherwise. The priming coat shall be compatible with this
preparation grade.

1.15.4.16 Painting Bolted Connections

Joint areas for bolted connections shall be masked to maintain the surfaces free from any
paint applied prior to making the connection. Masking shall be removed before erection.

After installation and after all bolts have been tightened, the areas of the connection shall
be cleaned to remove all dirt, dust, oil or other contaminant. Particular care shall be taken
to ensure that all traces of oil and grease are removed from bolts, nuts and washers.

Bolts, nuts and washers and any areas exposed at bolted connections shall also be primed
as specified, particular care being taken to ensure that any crevices are fully sealed.

The remaining coats of the paint system shall then be applied.

1.15.4.17 Painting Welds

After the completion and grinding of exposed welds, weld spatter, weld residues and all
alkaline deposits and contaminants shall be removed from the surface of the steel-work,
and welds and any other areas affected or damaged by the welding process shall be blast
cleaned. Primer shall be applied to the blast cleaned areas as specified and the remainder
of the paint system applied as necessary to complete the protection across the welded
seam and damaged are as to the same state as that existing generally on the faces of the
parent metal. Each coat applied shall overlap the corresponding existing paint coat by 50
mm both sides of the weld on each exposed face of the parent metal.

1.15.4.18 Repairing Damaged Coats

Damaged areas of zinc coatings not individually exceeding 40 mm 2 in area shall be made
good by the application of a metallic zinc-rich priming paint. Sufficient material shall be
applied to provide a zinc coating at least equal in thickness to the original coating.

Factory prepared surfaces other than zinc coated surfaces damaged during site fabrication
and/or handling shall be treated as described in the following paragraphs.

All slag and spatter shall be removed from areas of welds by chipping hammer and such
areas together with all other areas of damaged priming or other coat shall be thoroughly
mechanically wire brushed and given one coat. The priming coat shall be applied by brush,

GKW - Alliance 168


SPECIFICATIONS
CIVIL WORKS

taking care to cover uneven surfaces completely, particularly those of welds. Further
approved coats shall be applied where necessary to build up the thickness of the repaired
coating to at least that of the original coating.

Areas of paint on steelwork which have been damaged shall be cleaned to sound material
and the edges of the undamaged paint shall be smoothed with sandpaper to a gentle bevel.
The specified paint system shall then be applied to bring the damaged area up to the same
state of protection as the surrounding paintwork, with each coat of new paint overlapping
the corresponding existing coat of paint by at least 50 mm.

Where the steel is exposed, it shall be cleaned to remove all corrosion, by blast cleaning if
ordered by the Engineer.

Where epoxy coatings are damaged suitable repair material supplied by the manufacturer
of the original coating shall be applied.

1.15.4.19 Epoxy Coating Work - Generally

In addition to the general requirements of this specification the following conditions shall
apply wherever epoxy coating work is being carried out:

(a) The work shall be illuminated to the satisfaction of the Engineer.

(b) Forced drought ventilation to the approval of the Engineer shall be used wherever
required for the needs of personnel or for drying out surfaces.

(c) Operatives shall work in pairs.

The Contractor shall demonstrate all his methods, equipment and materials before any
work commences. Sample areas of substrate shall be prepared and coated as required by
the Engineer and for his approval.

There shall be strict control of surface cleanliness between primer and epoxy coating and
between coats of the same. Vacuum removal of dust and sand shall be employed and
contamination shall be removed as specified in appropriate preparation clauses herein.
Where dirt or dust has become trapped in the epoxy coating surface it shall be removed
with suitable abrasive paper. The surface being coated shall be free of visible moisture
throughout these operations.

Epoxy coating shall be applied only to clean dry primed or previously coated surfaces. Any
thick runs or collections of paint shall be removed before they harden. No fewer than two
coats shall be applied over the primer by airless spray; no fewer than three by brush.

Each coat shall be distinctly different in colour from the primer or previous coat. The colour
of the final coat shall be as required by the Engineer.

Each coat shall be seen to have completely covered the preceding coat without ‘misses’ or
pinholes or any areas visibly low in thickness. A high voltage pinhole detector shall also be
used to determine the integrity of the coats.

The manufacturer of the coating shall stipulate primer and epoxy re-coating intervals for all
curing temperatures likely to be encountered and these shall be adopted with a maximum
tolerance of +4 hours. Where this is exceeded, the surfaces to be re-coated shall first be
suitably abraded or treated with solvent to remove gloss and give key.

GKW - Alliance 169


SPECIFICATIONS
CIVIL WORKS

Wet thickness gauges shall be used continually by the coating operators to check that
sufficient coating is being applied to achieve the desired dry film thickness.

1.15.4.20 Epoxy Coating Concrete and Rendered Surfaces

No priming shall commence until the moisture content of the cementitious surface is less
than 5% measured by “Wet Check” moisture meter or other instrument approved by the
Engineer.

Similarly, moisture measurements over the primer or any epoxy intercoat shall not exceed
1% on the concrete scale of the instrument when the probe tips are held against such
painted surfaces just prior to re-coating.

The primer shall be a low viscosity two or three pack epoxy supplied by the manufacturer
of the approved epoxy coating material. It shall have complete compatibility and inter-coat
adhesion with the first coat of high build epoxy paint.

The primer shall be applied by suitable nylon bristle brush or spray over the whole area to
be coated at such thickness that it may then be squeezed into the pores of the concrete.
Any excess shall be effectively removed before application of the high build epoxy. The
Engineer may approve an alternative application method where the Contractor can
demonstrate a suitable technique.

The protective coats shall be of an approved high build epoxy, 2 or 3 pack, completely
resistant to the corrosion conditions to be encountered. Certain types of coal-tar epoxy
may be approved for this purpose where the Contractor has stated at the time of tendering
the type of curing agent and coal-tar, with the percentage content of the latter. The total
dry film thickness of the paint layer shall have a minimum value of 0.75 millimetres.

Wherever the paint inspection gauge has been used, and wherever the coating has been
otherwise damaged, the surface shall be abraded for 50 millimetres around such damage
and the area shall be touched in with not less than two thick applications to restore the
coating integrity and thickness.

Adhesion tests shall be carried out on the cured coating surface using the test equipment
supplied under the Contract. The resulting test specimens shall show no indication of poor
adhesion to the substrate, residual laitance or intercoat adhesion weakness.

1.15.5 Inspection

The following tests shall be carried out:

(a) Checking wet film thickness

Wet film thickness gauges of an approved type shall be provided for each painter to
check the rate of paint application.

(b) Checking dry film thickness

The thickness of the built-up dry film after each paint coat applied to steel or other
magnetic surfaces shall be measured systematically, with a dry film thickness gauge.

(c) Hole detection on steel and iron surfaces

GKW - Alliance 170


SPECIFICATIONS
CIVIL WORKS

The Contractor shall use a suitable method of detecting pinholes in the coating
system after trials on test plates. The sweep voltage on high voltage dc equipment
shall not exceed half the voltage required to spark through the complete paint system
specified.

1.16 Building Works

1.16.1 Scope

This Part contains requirements which, where relevant to this Contract, shall apply to
supply, installation and testing of materials and the construction of all building works at the
Katosi Water Treatment Plant project sites.

1.16.1.1 Building Specification

1) Brickwork shall comply with the relevant provisions of the applicable standard.

2) The moisture content of the bricks shall be adjusted so that excessive suction is not
exerted on the mortar.

3) Bricks in each course shall break joint correctly with the bricks underneath. The
courses shall be laid parallel with joints of uniform thickness and shall be kept straight
or regular curved as required. Brickwork shall be gauged to rise 300 mm in four
courses. Vertical joints shall be in alignment as required by the bond and shall have
an average thickness of 10 mm. Bricks forming reveals and internal and external
angles shall be selected for squareness and built plumb. Bricks with single frogs shall
be laid frog upwards.

4) Brickwork shall rise uniformly; corners and other advanced work shall be racked back
and not raised above the general level more than 1 m. No brickwork shall be carried
up higher than 1.5 m in one day. No bats or broken bricks shall be incorporated in
the works unless essential for bond.

5) Completed brickwork shall be protected at all times from scaffold splash, mortar
droppings, grout leakage from suspended slabs and the harmful effects of weather.
Brickwork shall be allowed to set thoroughly hard before cutting or chasing is carried
out.

6) Reinforcement for brickwork shall be in accordance with the applicable standard.


Reinforcement for brickwork shall be Type I G or Type III U standard. Reinforcement
shall be detailed, stored and tested as specified under “Reinforcement for concrete”.

1.16.2 Brickwork, Jointing and Pointing

Solid brick shall be laid in common bond with all joints filled solidly with mortar and backs fully
purged to form solid masonry structures. Joints of walls to receive plaster shall be lightly raked
to provide a bond for plaster. Solid brick shall be plastered only when so indicated on the
approved drawings or required in the particular specifications.

Otherwise brickwork masonry shall conform to the previous paragraph “Exposed concrete
block”. Control joints in plastered brick walls shall be carried through the plaster. The joint
shall not be plastered.

GKW - Alliance 171


SPECIFICATIONS
CIVIL WORKS

All masonry shall be laid plumb and true to lines and built to the thickness and bond required
with courses level and joints and bond uniform. Masonry shall be carried up in a uniform
manner. No one portion shall be raised more than a meter above adjacent portions, except
with the approval of the Engineer.

Sample panels 1 m2 shall be prepared for each type of facing brickwork/blockwork, including
jointing or pointing, and the Contractor shall obtain approval before proceeding with the work.

 Hot weather:

Bricks and blocks shall be stacked on a level hardstanding so as to prevent the


absorption or ingress of water. Suitable shading shall be provided to prevent high
temperatures existing within the brick and block stacks.

 Dry weather:

Clay brickwork and blockwork shall be kept wet to the minimum extent necessary to
prevent mortar drying out prematurely.

 Wet weather:

Freshly laid brickwork/blockwork shall be protected during interruption through rain


and at the completion of each day’s work.

Facework shall be kept clean during construction and until practical completion. Scaffold
boards shall be kept clear of the building at night and during heavy rain. Rubbing to
remove stains will not be permitted.

All bricks shall be wetted before being laid.

Clay bricks shall not be used until completely cold from the kiln.

Facing bricks of varying colour shall be distributed evenly throughout the work so that
no patches appear. Different deliveries which vary in colour shall be mixed to avoid
horizontal stripes.

Brickwork shall be carried up, including both skins of cavity work where applicable, with
no portion more than 1.5 m above another at any time, racking back between levels.

Brickwork shall be gauged for four courses to 300 mm including joints.

Bricks shall be laid on a full bed of mortar and all joints filled. Bed and vertical joints
shall be of equal and consistent thickness.

Solid bricks shall be laid on a full bed of mortar with joints filled solid to a consistent
thickness not more than 12 mm.

Should single frogged bricks be permitted, they shall be laid with the frog upwards and
these shall be filled with mortar. Double frogged bricks shall not be used.

Courses shall be kept level and perpends vertical and in line. Quoins and other angles
shall be plumbed as the work proceeds.

Templates shall be used for forming openings in face work where doors and windows
are not built in at the time.

GKW - Alliance 172


SPECIFICATIONS
CIVIL WORKS

Brickwork and blockwork abutting concrete columns, walls and beams shall be tied with
stainless steel ties in accordance with the relevant references and as directed by the
design. Additional ties shall be supplied at openings. Walls which are to be fair face
shall have selected bricks and blocks with perfect appearance and flat surfaces and with
faces in line.

GKW - Alliance 173


SPECIFICATIONS
CIVIL WORKS

1.16.2.1 Sand, Cement, Water

Sand shall be clean and sharp coarse grit, fresh water river or pit sand conforming in all
respects to the applicable standard and shall be re-washed on site if the silt loam or clay
content exceeds the requirements. The sand shall be obtained from a source approved by the
Engineer.

Cement shall be sulphate resisting Portland cement.

Water shall be clean and free from impurities and shall at regular intervals be tested to ensure
compliance with the applicable standard.

1.16.2.2 Mortar Mix

Masonry mortar for setting blocks and bricks shall be of the quality of Group III. The proportion
shall be 1 part cement to 4 parts sand or as otherwise approved by the Engineer.

Mortar shall be mixed with water in an amount compatible with workability. Mortar constituents
shall be measured by volume, using clean gauge boxes made to size to suit volumes required.
Gauge boxes shall be overfilled and excess material struck off with a straight edge.

Mortar shall be mixed in a mechanically operated mortar mixer for at least three minutes after
all ingredients are in the drum, and at least long enough to make a thorough, complete,
intimate mix of the materials.

The mixing of mortar by hand will be permitted only when the quality of hand mixing is
comparable to mechanical mixing. The Engineer reserves the right to reject hand mixing and
require all mixing to be by mechanical means.

Mortar shall be used within two hours of discharge from the mixer at normal temperature and
on no account shall mortar be used after the initial set has taken place. Reconstitution of
mortar will not be permitted.

Mortar boxes shall be cleaned out at the end of each day and all tools shall be kept clean.

Coloured mortar shall be mixed as specified using cement and sand in the above proportions
with the addition of a coloured pigment in accordance with appropriate standards.

1.16.3 Cavity Walls

Cavity walls shall have 50 mm minimum width cavities and shall be built with wall ties
uniformly spaced 450 mm apart vertically and 900 mm apart horizontally, staggered, and
laid to fall outwards. Additional ties shall be used near the sides of all openings, one for
each third course of bricks. Care shall be taken to keep the ties within the cavity free from
mortar or mortar droppings and any mortar or debris collecting at the bottom of the cavity
shall be cleaned out through temporary openings left for this purpose in the bottom courses.

1.16.4 Lintels, Ties, Miscellaneous

The Contractor shall build in or provide all miscellaneous items to be set in masonry including
frames, lintels, reinforcing steel, electrical boxes and fixtures, sleeves, grilles, anchors and
other miscellaneous items. All anchorage, attachments and bonding devices shall be set so
as to prevent stoppage and shall be completely covered with mortar.

GKW - Alliance 174


SPECIFICATIONS
CIVIL WORKS

Wired butterfly and double triangle type wall ties will not be permitted in any wall. Wall ties
shall be stainless steel strip, but of a twist type for the leaves of any cavity walls.

Padstones shall be bedded in mortar of the same strength as in the adjacent wall, to give a
level top surface.

1.16.5 Grouting

Grout and cement mortar for setting structural steel columns, railings, frames in walls and
where otherwise required shall be done with mortar as hereinbefore specified. Before placing
grout thoroughly clean all surfaces.

Grout shall be tamped into place with a blunt tool to fill the entire void. In the event space does
not permit tamping, the Contractor shall build the necessary forms and place grout by pouring
from one side only. When grout is placed by pouring a head of grout shall be maintained in
the form. Grout shall be kept wet for three days and after the temporary supports or adjusting
wedges are removed the empty space shall be grouted and the surrounding grout pointed.

1.16.6 Cleaning

Masonry work, to be exposed, shall be thoroughly cleaned. Mortar smears and droppings on
concrete block walls shall be dry before removal with a trowel. Masonry work may be cleaned
using a mild muriatic acid solution.

1.16.7 Damp Proof Course

Bituminous sheet damp-proof courses shall be laid on a level bed of cement mortar with a
minimum lap of 75 mm at angles and joints and neatly pointed in matching mortar on exposed
edges. Horizontal and sloping damp-proof coursing over door openings shall be in single
pieces of material of a length to extend 225 mm at both sides beyond the width of the frame.

1.16.8 Waterproof Building Paper

Waterproof building paper shall be laid beneath structural concrete. The paper shall be laid
with 150 mm lapped joints which shall be treated and sealed with an approved bituminous
solution. The weight of the paper shall not be less than 0.3 kg/m2.

1.16.9 Corbelling

Oversail corbelling shall not exceed 30 mm on each course.

1.16.10 Bonding to Concrete

Where brickwork is to be bonded to concrete, this shall be achieved by means of metal ties
evenly placed at three per square meter and brickwork shall be brought up subsequent to
the concrete.

1.16.11 Underpinning

GKW - Alliance 175


SPECIFICATIONS
CIVIL WORKS

Underpinning in brickwork shall be carried up to within one course of the underside of the
existing structure and allowed to set. The remaining course shall be bedded in mortar and
wedged with slate pieces tightly against the existing structure.

1.16.12 Centring and Lagging

Centring and lagging used for the construction of brickwork shall remain in place for such
time as is necessary for the brickwork to develop sufficient strength to prevent sagging or
cracking of joints.

1.16.13 Exposed Concrete Block

Concrete block shall be laid in “stack” bond, unless otherwise indicated, with joints not
exceeding 1.0 cm and uniform throughout and finished slightly concave and smooth, tool
dense and neat (no finger pointing allowed). All blocks shall be laid in a full bed of mortar
applied to shells only. Mortar shall be applied to the vertical joint of blocks already set in the
wall and all contact faces of the unit to be set. Each unit shall be placed and shoved against
the block previously laid so as to produce a well-compacted vertical mortar joint for the full
shell thickness. Moisture contents of blocks shall not exceed 35 % when laid. Intersection
bearing walls shall be tied together with metal ties at one meter vertical spacing. Bends of tie
bars and reinforcing shall be embedded in cells filled with mortar. Where indicated, concrete
blocks shall be reinforced and concrete block lintel types shall be built in.

All necessary block cutting shall be neatly done by saws.

Control joints shall be installed at the intersection of block walls with structural concrete and
elsewhere where such joints are useful. Joints not detailed otherwise shall be raked out to a
depth of 2 cm for the full height of the wall and caulked. Maximum length between joints shall
be 10 m.

Joints are to be examined to locate cracks, holes or other defects and all such defects shall
be filled with mortar and pointed.

1.16.14 Concrete Blocks to be plastered

Concrete block walls to be plastered may be laid with bonds described above. Joints are to
be left rough to assist in bounding of plaster. Otherwise, concrete block masonry shall conform
to previous paragraph “Exposed concrete block”. Control joints in plastered block walls shall
be carried through the plaster. The joint shall not be plastered.

1.16.15 Fixing of Plasterboard

Plasterboard for ceilings shall be nailed to support at 150 mm centres with 40 mm


sheradised plasterboard nails and fastened so that the joints are staggered. Noggins or
other fixing surface shall be provided as necessary to ensure that edges of plasterboard
are secured adequately. Ends of sheets shall be butted tightly and edges left with a gap
not exceeding 5 mm.

Where sheeting has been cut, nails shall not be less than 18 mm from cut edges. Nails
shall be driven well home with heads slightly below the surface, but shall not break the
paper.

GKW - Alliance 176


SPECIFICATIONS
CIVIL WORKS

1.16.16 Plastering

1.16.16.1 General

The work required under this Specification shall include all labour, materials, equipment,
scaffolding etc., required to complete all internal and external plastering specified herein.

On completion, all surfaces shall be left in a neat and clean condition before handing over.

Materials, workmanship and construction shall be in accordance with the requirements of the
applicable standard.

Work shall not be started or continued when the air temperature exceeds 40°C.

1.16.16.2 Materials

Sand shall be clean and sharp course grit, fresh water river or pit sand conforming and shall
be re-washed on site if the silt loam or clay content exceeds the requirements. The sand shall
be obtained from a source approved by the Engineer.

Cement shall be sulphate resisting Portland cement.

Water shall be clean and free from impurities and shall at regular intervals be tested to ensure
compliance.

1.16.16.3 Mixing

Plaster shall be mixed with proportions according to the applicable standard.

Plaster shall be mixed with water in an amount compatible with workability.

Plaster constituents shall be measured by volume.

Plaster shall be mixed in a mechanically operated plaster mixer at least long enough to make
a thorough, complete, intimate mix of the materials.

The mixing of plaster by hand shall not be permitted.

Bunkers, gauge boxes, gauging boards, etc. shall be thoroughly cleaned after each mix.

Mixer drums shall be thoroughly washed out at least four times a day if the mixer is in
continuous use, and after each batch if not in continuous use. All tools shall be kept clean,
and care taken to ensure that fresh plaster is not contaminated with set plaster.

1.16.16.4 Preparation

Surfaces that are to receive plaster shall be carefully examined by the Contractor and any
unsatisfactory surface shall be repaired as directed by the Engineer.

Where finished surfaces such as tile, lighting or other fixtures have been installed prior to
plastering they shall be protected from damage during plastering. Protection shall consist of
covering with a non-staining building paper or polyethylene sheet. Protection shall be removed
when plaster work is completed.

GKW - Alliance 177


SPECIFICATIONS
CIVIL WORKS

Concrete masonry and brick surfaces shall have sufficient roughness to provide proper bond
and shall be dampened by brushing or spraying with water followed by plastering.

Unless a bonding agent is used concrete ceilings, ceiling beams, columns and stanchions
shall be dubbed out as necessary before plastering is commended and the mix used for
dubbing shall be similar to that used for first undercoating. The surface of in-situ concrete
shall be cleaned of dust, loose particles and other matter. Surfaces shall be wetted
immediately before plastering is commenced.

Angles between walls and ceilings, vertical angles and joints between dissimilar solid
backgrounds shall be reinforced with 90 mm wide scrim set in plaster and trowelled flat. All
joints between plasterboards shall be similarly treated.

Expanded metal angle beads shall be provided at all external corners.

1.16.16.5 Finish

Finishing coats shall be trowelled to a smooth and even finish.

1.16.16.6 Tolerances

All surfaces shall be true to line, level, plumb and all junctions, angles and arises truly square.
On two or three coat work, the plaster surface shall not show any deviation greater than
specified in the applicable standard.

1.16.16.7 Completion of Work

Completion of work shall be as follows:

 Curing:

Cement sand plasters shall be kept moist by sprinkling with water at regular intervals
for a period of at least three days and until no powdery particles are present.

The Contractor shall plan his work such that rendering and plastering work is not
carried out at extreme temperatures.

 Defects:

Work shall be free of all defects, and any work which shows signs of blistering, bond
failure, hollow patches, flaking, peeling, cracking, crazing, grinning, tool marks,
discolouration or any other defects will not be accepted, and shall be removed and
replaced with acceptable work.

Upon completion of the work, all plaster surfaces shall be cleaned and all rubbish, debris and
excess material and equipment shall be removed.

1.16.16.8 Thickness and Workmanship

All plaster shall be applied according to the following thicknesses. Additional thickness will be
required for any unevenness in the masonry surface.

GKW - Alliance 178


SPECIFICATIONS
CIVIL WORKS

THICKNESS OF COAT (mm)

LOCATION FIRST INTERMEDIATE FINISH TOTAL


THICKNESS

Ceiling 15 - 10 25

Interior wall 10 6 4 20

Exterior wall 10 9 6 25

Plaster shall be of two or three coats: first, intermediate and finish coats. If plaster is to be
applied to a smooth cement or other surface which does not offer bonding characteristics for
plaster, a dash coat shall be required as a bonding surface.

Dash coats shall be of mush consistency, composed of 1 part Portland cement and 1.5 parts
of sand.

The dash coat shall be applied with a whisk broom or fibre brush, in a whipping manner. The
dash coat shall be kept moist for 48 hours before first coat is applied to the dash coat.

First coats shall cover the full length of the wall or to the border line formed by columns, doors
and windows. Before the first coat hardens the surface shall be scratched to provide a
mechanical key for the intermediate coat. This coat shall be kept moist for not less than 24
hours and allowed to set for not less than 14 days before application of the intermediate coat.

Before application of the intermediate coat, the surface of the first coat shall be dampened.
The surface of the intermediate coat shall be brought to a true and even surface, then
roughened with a wood float before setting to provide a bond for the finish coat.

The finishing coat shall be applied while the intermediate coat is moist and if the intermediate
coat dries out it shall be wetted evenly. The finishing coat shall be first floated to a true and
even surface, then trowelled in a manner that the sand particles are not exposed on the surface
and with the final troweling, leaving the surface burnished smoothly and free from rough areas,
trowel marks, checks, or other blemishes.

Before applying the plaster to ceilings, the surface of the ceiling shall be dampened and the
cement paste applied with a whisk broom or fibre brush, to the entire ceiling.

The final plaster layer shall be applied to the ceiling slab tamping it with wood float until the
cement paste is squeezed up through the surface of the plaster and finally troweled to an even
surface leaving the surface burnished smoothly and free from trowel marks, checks and other
blemishes.

1.16.16.9 Waterproof

Waterproof plaster shall consist of plaster waterproofing compound, cement and sand mixed
in strict accordance with the manufacturer’s specification.

Waterproofing compound shall be paste, powder or liquid made by a manufacturer engaged


in the mass production of such items and shall be approved by the Employer’s Representative.

1.16.17 Flooring

GKW - Alliance 179


SPECIFICATIONS
CIVIL WORKS

1.16.17.1 General

All materials and structural components merely to be provided by the Contractor and not,
therefore, ultimately incorporated in the structure shall be new and unused unless otherwise
specified.

They shall be suitable for their intended purpose and appropriately matched to each other.

All materials and structural components shall meet the respective quality and dimension
requirements.

All materials and structural components requiring approval by official regulations shall be
officially approved and shall comply with the conditions laid down for such approval.

Any materials and structural components for which there are neither standards nor official
approval requirements may be used subject to the Engineer's consent only.

The floorings shall be such as to provide a cover surface that can well be walked on. They
must not give rise to any unreasonable inconvenience. Deviations in colour as against the
samples may only be slight.

1.16.17.2 Materials

The quality of marble shall be in accordance with the applicable standard. Marble shall be
first quality, matched for colour and pattern. Slabs displaying defects such as stains, chipped
edges or corners shall be rejected and in no case incorporated in the works.

White marble shall be used for floors.

Concrete paving slabs shall be 50 mm thick hydraulically pressed precast concrete slabs.

Terrazzo shall be in accordance with the appropriate standard. The marble chippings shall be
of an approved quality in irregular pieces with no flaky pieces.

PVC flooring material shall comply with the requirements of the applicable standard and shall
have the following properties: temperature resistant within the limits of -30°C and +70°C,
waterproof, abrasion resistant, flameproof, pigment or colour proof to light, evenly coloured
throughout, resistant to chemicals, fats, slight acids and alkalines, odourless, easily laid and
flexible, non-porous and slip-proof.

All adhesives shall have suitable properties to ensure a firm and durable bond. They must not
adversely affect either the flooring or the underlays or the base and shall be odourless once
applied.

All fillers and levelling compounds shall have a firm and durable bond to the base, provide a
good bonding surface for the adhesive and be of suitable property so as to give an adequate
support to the covering. They must have no adverse effect on base, adhesive, underlay, or
covering.

1.16.17.3 Workmanship - Generally

The Contractor shall examine the base to see whether it is in a suitable condition for him to
carry out his work. Any doubts the Contractor may have in this connection shall be
communicated by him to the Engineer immediately in writing.

GKW - Alliance 180


SPECIFICATIONS
CIVIL WORKS

All materials and structural components whose processing is subject to manufacturer’s


instructions shall be processed accordingly.

The covering must not close any expansion joint in the structure.

The Contractor shall clean the flooring and treat it in accordance with the flooring material
manufacturer’s instructions.

The contractor shall furnish the Engineer with the written instructions for the care and
maintenance of the flooring.

1.16.17.4 Preparation of the Surface

The subsurface will be cleaned.

The base for coverings to the placed without underlay shall be smoothed with filler compound.
In the case of major unevenness a suitable levelling compound shall be used.

Any filler or levelling compound shall be applied so that it will bond firmly and durably to the
base, will not crack and will adequately withstand pressure.

Any screeds such as magnesia and anhydride screed to which the filler or levelling compound
will, but insufficiently, bond, shall receive a priming coat.

1.16.17.5 General Requirements for Application

Workmanship generally shall be in accordance with the applicable standard.

Floorings shall be placed without underlays unless otherwise specified.

The courses shall be laid towards the main window wall, in halls and corridors, however, in
longitudinal direction, unless otherwise specified.

Deviations in colour which are not of minor importance and not due to the flooring pattern shall
not be allowed if marring the overall appearance of the flooring.

Courses with pattern repeats shall be laid so as to suit these.

Where courses run towards doors, recesses and the like, they shall be laid so as to cover also
the floor areas of such door openings, recesses etc. Strips or slabs may be used as coverings
of such floor areas.

Plastic flooring shall not be welded unless otherwise specified or expressly required in the
flooring material manufacturer’s processing instructions.

Any adhesive lodged on the flooring shall be removed at once.

Where floorings are raised in grooves on walls they shall be accurately fitted together in the
corners of the grooves, if necessary, by inserting adapter sections.

1.16.17.6 Marble

Marble slabs shall be stacked under cover on paving of clean level surface, protected against
water penetration from the ground.

GKW - Alliance 181


SPECIFICATIONS
CIVIL WORKS

Units shall be stacked vertically on edge with non-staining laths or battens placed between
each unit.

To avoid discolouration, panels shall not be prematurely delivered to site nor come into contact
with rope, straw, hardwood or other materials likely to cause staining, nor shall they be
exposed to direct sunlight.

Laying:

Marble slabs shall be fixed solid on a bed of cement/ sand mortar (1 : 4 nominal mix), 20 mm
thick with tight joints grouted in lime putty. A protective slurry of lime putty at least 3 mm thick
shall be applied to the marble pavings and subsequently cleaned off.

Slabs shall be laid with staggered joints. Treads to stairs shall be fixed solid on a bed 15 mm
thick. Risers to stairs shall be fixed solid on a backing 10 mm thick.

1.16.17.7 Precast Concrete Slabs

All precast concrete slabs shall be laid in bays not exceeding 10 m in length, the bays being
separated by an expansion joint 10 mm wide.

1.16.17.8 Thin Floor Coverings: PVC

Flexible PVC sheeting or tiles to walls or floors shall be laid on a level and smooth background
generally consisting of anhydride screed. The screed surfaces shall be clean, dust-free and
dry. Tiles shall be laid and bedded in strict accordance with manufacturer’s instructions.

Where resilient backing is used, this shall be a rubber underlay, with glass fibre weave surface.

1.16.17.9 Fitting of Cover Strips and Nosings

All skirting boards and cover strips shall be snugly fitted and durably fastened.

When not otherwise specified wooden cover strips shall be provided throughout all office
rooms, laboratories, residential buildings, etc.

Wooden cover strips shall be fixed at distances not exceeding 60 cm.

Stair tread nosings and other edgings of metal shall be screw-fastened at distances not
exceeding 18 cm unless any other means, e.g. anchoring, is specified.

Any plastic or rubber nosings in stairs shall be fixed to the treads of the steps only.

1.16.18 Screeds

1.16.18.1 General

Workmanship and construction generally, shall be in accordance with the applicable standard.

Materials used for mortar shall be measured in proper gauge boxes.

GKW - Alliance 182


SPECIFICATIONS
CIVIL WORKS

All concrete surfaces shall be adequately keyed to receive screeds.

1.16.18.2 Floor Screeds and In-situ Finishing

The works described below shall generally include the following:

 Dense aggregate cement screeds - base and wearing courses.


 Granolithic and terrazzo toppings.

1.16.18.3 Weather Conditions

Floor screeds shall not be laid in areas exposed to high temperatures, strong sunlight, strong
draughts, or winds, unless protected from such conditions.

1.16.18.4 Screed Dimensions

Screeds shall be as follows:

Floor screeds shall be laid to the thickness, levels and falls according to the approved
drawings. When laid “monolithically” a screed shall not be less than 20 mm and not more than
30 mm thick, and when laid “unbonded” on a separating layer, it shall not be less than 50 mm
thick.

Thick floor screeds shall be laid in bays of maximum size 20 m². Bays shall be laid alternately.
Floor screeds for thin floorings shall be laid in strips not larger than 3 m wide.

Separation layer shall be a bituminous sheeting or equivalent.

1.16.18.5 Materials

Materials for screeds shall be as set out below:

 Cement shall be Portland cement.


 Sand shall comply with the applicable standard and shall be rewashed on site if the
silt loam or clay content exceeds the requirements.
 Granite for granolithic screeds shall be in accordance with the appropriate standard.
 Water shall be clean and free from harmful matter in suspension and solution.
Preferably only clean water from mains shall be used. Where doubt exists, it shall
be tested in accordance with the applicable standard.
 Lime shall be to the applicable standard.
 Anhydride shall be to the applicable standard.

1.16.18.6 Base Concrete Preparation

Base concrete to receive floor screeds shall be prepared as follows:

For screeds laid “separate”: within three to twelve hours of the base concrete being
placed, the laitance on the base concrete shall be removed
by light or mist spraying with water and brushing to
removed prior to laying toppings;

GKW - Alliance 183


SPECIFICATIONS
CIVIL WORKS

or, for screeds laid “separate”: after twelve hours of the base concrete being placed, the
laitance on the base concrete shall be completely removed
by hacking to expose clean aggregate particles. All loose
concrete, dust and dirt shall be removed by thorough
washing with water. Any excess water shall be removed
prior to applying the cement slurry.

For screeds laid “unbonded”: no special preparation is necessary, except to remove all
projecting nibs and sweep the concrete surface clean prior
to laying the separating layer.

1.16.18.7 Screed Mix

The mix preparations shall be in accordance to the applicable standard. Materials for a screed
mix shall be thoroughly and efficiently mixed dry by mechanical means until a uniform
distribution is obtained, and then water added. The water content shall be kept as low as is
necessary to allow sufficient workability for laying and compacting. No extra water, or other
material, shall be added to the mix after it has left the mixer. Where only small quantities are
required, mixing may be carried out by hand, on a clean watertight surface. For this the
approval from the Engineer is required.

1.16.18.8 Placing and Compaction

Fixing of forms etc. shall be as follows:

Form setting:

The side forms shall be fixed rigid on a firm foundation and supported throughout their length
so that they will not be disturbed by the spreading and compacting of the floor screeds. Forms
shall be set true to line with ± 3 mm, and to level within ± 3 mm, and shall be checked for level
immediately before work starts.

Placing and compaction:

The screed mix shall be placed between the forms (and/or other bays) worked around the
penetrations, duct covers, manhole covers, gutters, balustrade standards, pipes, etc., and
shall be fully compacted by means of a screed board, or other suitable compacting equipment,
providing laitance is not brought to the surface.

Joints:

All edge joints of floor screeds shall be simple butt joints without filler. Screeds laid over
construction joints in concrete shall be separated by 10 mm impregnated oakum strips or the
like.

Joints in wearing courses shall be 10 mm polysulphide.

GKW - Alliance 184


SPECIFICATIONS
CIVIL WORKS

1.16.18.9 Finishing

Finishes shall be as follows:

Screed base course shall generally be finished with wood float to give an even texture. The
sprinkling of cement onto the surface and trowelling in to absorb water will not be permitted.

Screed wearing course shall be tamped with a wood float and trowelled twice with a steel
trowel to produce a smooth finish. Matured sub-base shall first be well cleaned, wetted and
brushed with a Portland cement grout before topping is laid. Finishing screeds shall be made
good around gullies and any penetrations through the floor surface.

1.16.18.10 Curing and Protection

As soon as a floor screed has hardened sufficiently to prevent damage to the surface, it shall
be cured for a minimum period of seven days after, by means of either wet canvas, straw mats,
rand, polythene or sheeting laid on the surface and kept continuously damp and in position for
the full curing period.

Protection:

As soon as the laying of the floor screed has been completed, it shall be protected against
rapid drying out caused by wind, draughts and strong sunlight.

1.16.18.11 Tolerances

Tolerances shall be as follows:

General:

The finished surface of base course screeds, when laid, shall not depart more than specified
in the applicable standard.

Floor screeds, when laid, shall be free of all defects and any work which shows signs of bond
failure, hollow patches, crazing, cracking or any other defects will not be accepted, and shall
be removed and replaced with acceptable work by the Contractor.

The extent of the work to be removed and the method to be used in the removal and
replacement of this work shall be to the approval of the Engineer.

All surfaces shall be approved by the Engineer before further work.

1.16.18.12 In-situ Toppings

In-situ toppings shall be as follows:

 Granolithic toppings:

These shall be mixed with sufficient water to give a matured concrete sub-base, the
concrete shall first be well cleaned wetted and brushed with a Portland cement grout.

GKW - Alliance 185


SPECIFICATIONS
CIVIL WORKS

To produce a wearing surface, the granolithic mixture shall be tamped in with a wood
float and trowelled twice with a steel trowel to produce a smooth finish.

The paving shall be laid in alternate bays not exceeding 9 m 2 in area and the bays
shall be separated by expansion strips of mastic or other approved material.

 Terrazzo:

This shall be mixed with sufficient water to give a plasticity suitable for laying. The
finished thickness shall not be less than 25 mm for pavings and 10 mm for wall facing
and skirtings.

Terrazzo shall be laid immediately following screed of cement/sand at least 15 mm


thick. The concrete sub-base shall first be well cleaned, wetted and brushed with
a Portland cement grout.

The terrazzo shall be laid in bays not exceeding 9 m2 in area and the bays shall be
separated by expansion strips of brass or other approved material truly level with the
finished surface.

The pavings shall be rolled and trowelled to a dense and even surface.

Terrazzo pavings shall be rubbed down to a grit finished surface free from blemishes
after the initial set, and cured by covering with waterproof paper or wetted hessian
for a period of a least three days.

After curing, the pavings shall be filled in with a cement grout of the same colour and
polished by approved machine using a suitable carborundum abrasive and potable
water until an even and smooth surface is obtained to the satisfaction of the Engineer.

Before opening to traffic, terrazzo shall be scrubbed with an acid and alkali-free soap.

After 24 hours, all surfaces shall be scrubbed vigorously with hot water and rinsed.

No strong detergents or disinfectants shall be used.

1.16.19 Tiling

1.16.19.1 General

Work under this heading shall comprise all required labour, equipment and the supply of
the appurtenant materials and structural components including off-loading and storage at
the site unless otherwise specified.

Tiling and flooring shall be applied in accordance with the finishes, specified in the particular
specifications.

All materials and structural components not standardised shall be used only with the
approval of the Engineer.

All tiles and slabs for which there are several grades shall be of the best standard
commercial grade unless grade is stipulated in the specifications.

Before starting the work, the Contractor shall ascertain the Employer’s selection of patterns
and colours and the Contractor shall furnish the Engineer with duplicate samples of the
patterns and colours of the material selected by the Employer.

GKW - Alliance 186


SPECIFICATIONS
CIVIL WORKS

Tiling shall be free of all defects and any work which shows signs of bond failure, hollow
patches, misalignment, cracking or any other defect will not be accepted and shall be
removed and replaced with acceptable work.

The Contractor, before the commencement of his work, shall inspect and test backgrounds
to ensure that their cleanliness, moisture content, alkalinity, sulphate content, etc., are such
that they will not adversely affect his work.

Joint fillers, sealer and adhesives shall be mixed and used strictly in accordance with the
manufacturer’s instructions.

Additives shall not be used in rendered backings to receive wall tiling.

1.16.19.2 Materials

In general, tiles and flags shall meet the requirements for quality stated in the applicable
standard.

Where tiles and flags are not standardised, the quality features (e.g. parallelism of the
edges, state and colour of the top surface, water absorption) shall satisfy the standard
commercial requirements.

All floor and wall tiles of a particular type and colour shall be from the same batch.

Glazed ceramic tiles for walls shall be either white or coloured, true to shape, flat, free from
flaws, cracks and crazing, uniform in colour, keyed on the back. The tiles shall be of a
suitable type, size, colour and acid resistant.

Ceramic floor tiles shall be oil and acid resistant, true to shape, flat, free from flaws, cracks,
uniform in colour and of an approved type, make and colour. Dimensions and tolerance
shall comply with the applicable standard.

PVC (vinyl asbestos) floor tiles shall be to the applicable standard.

1.16.19.3 Tiles - Adhesives

Cement based adhesives shall comply with the requirements of the applicable standard.
Other adhesives shall be subject to the approval of the Engineer and mixed and used strictly
in accordance with the manufacturer’s printed instruction.

Mortar materials and adhesives shall not alter or damage the top surface of the covering.

Grout for wall tiling shall be to the applicable standard.

1.16.19.4 General Preparation

Surfaces shall be prepared before covering with tiles is started in accordance with the
manufacturer’s instructions.

GKW - Alliance 187


SPECIFICATIONS
CIVIL WORKS

1.16.19.5 Preparation of Tiles

Tiles, which are to be laid in cement mortar, shall be soaked in clean water for 15 - 30
minutes before fixing and allowed to drain for 10 - 15 minutes. Any surplus water shall be
removed from the backs before laying.

Tiles to be fixed with adhesives shall not be soaked or wetted prior to laying.

All cutting to tiles shall be fair cutting using a tile cutter.

1.16.19.6 Placing

In interior finishing works all tiles, flags and mosaic shall only be set and laid before the fixing
of window and door frames and trims, and after stop rails, plumbing installations and the
application of plaster unless otherwise specified.

All tiles, flags and mosaic shall be set or laid plumb, in true alignment and horizontal or at the
slope specified, without any projections, with regard to any specified reference and level lines.
In wall coverings, projections shall be allowed only to the extent dictated by the particular type
of tile or slab specified.

All tiles, flags, mosaic, or the like shall be set or laid in normal mortar bedding unless otherwise
specified below.

Tiles shall be laid so that the key patterns on the back of the tiles lie in the same direction.

1.16.19.7 Bedding

Fixing and bedding of tiles shall be as follows:

(a) Adhesives:

Thin tiles shall generally be adhesive fixed. Backgrounds shall be cleaned and primed
according to the manufacturer’s instructions and the adhesive shall be applied by the
notched trowel technique and trowelled over the area to be tiled at a thickness of 4 mm,
and then combed with a trowel having 4  4 mm notches at 16 mm centres to form ribs.
Tiles shall be pressed in as recommended.

(b) Mortars:

Thick tiles shall generally be bedded in cement/ sand mortar at least 10 mm thick to a
true vertical or horizontal face with continuous horizontal and vertical joints and shall be
pointed in neat white or coloured cement. Any surplus which adheres to the face of the
tile shall be wiped off with a damp cloth before it sets hard.

The external angles and side and top edges of glazed wall tiling shall be formed with
rounded edge (bullnose) tiles.

At intersections, returned rounded edge tiles shall be used.

Joints shall match those of the floor tiling and special approved fittings shall be used at
the intersections between wall tiles and horizontal surfaces.

GKW - Alliance 188


SPECIFICATIONS
CIVIL WORKS

Where tiling abuts against wood or metal frames or other tiling at angles and around
pipes, etc., it shall be carefully cut and fitted to form a close neat joint. Open irregular
joints filled with cement and sand or plaster will not be permitted.

(c) Tile fittings:

Skirtings, coves, channels and other fittings shall be bedded as tiles.

1.16.19.8 Jointing

The widths of joints shall suit the type of tiles and flags used, the purpose and stress of
coverings and the type of jointing chosen. The joints shall be equal in width.

Unless otherwise specified, the coverings shall have the following widths of joints:

 Ceramic wall tiles with lengths of sides up to 15 cm 2.0 mm


 Ceramic floor tiles with lengths of sides up to 15 cm 2.0 mm
 Glass tiles min. 1.5 mm
max. 3.0 mm
 Ceramic tiles with lengths of sides up to 15 cm min. 2.0 mm
max. 8.0 mm

Jointing shall be by the washing-in method unless otherwise specified.

Cement mortar shall be used in jointing unless otherwise specified.

For jointing wall coverings of glass walling panels, permanently elastic sealing compounds
shall be used.

All parting, expansion and connecting joints shall be closed with suitable sealing
compounds unless other means are specified, e.g. elastic joint sections, open joints.

Parting joints in buildings shall extend into the wall and floor coverings at the same point
and in an adequate width. No mortar bridging shall occur.

The expansion joints of the coverings shall penetrate to the bonding surface.

In oil-proof and acid-proof tile and flag coverings, the kind of stress shall be taken into
account.

The movement joints in tiling mentioned above shall be 6 mm to 10 mm wide, shall be


formed around the perimeter of the floors and generally at 3.6 m in both directions of
surfaces for the full thickness of tile and bed. The joints shall be filled to not more than 6
mm from the face of the tile with joint filler, and sealed with polysulphide sealant applied by
gun and neatly smoothed off and pressed home.

The surface of the tiling shall be protected by the use of masking tape which shall be
removed before the sealant has set. Any sealant on the face of the tile shall be cleaned
off.

Brass junction strip shall be fixed at the junction of tile and other floorings. It shall be set in
position before the tiles are laid and shall extend through the full thickness of the tiling and
bed.

GKW - Alliance 189


SPECIFICATIONS
CIVIL WORKS

1.16.19.9 Tolerances

The surface of the finished wall tiling shall meet the accuracy as required in the applicable
standard.

1.16.19.10 Stone, Concrete and Marble Slabs

General:

Materials and workmanship generally shall be in accordance with the requirements of the
applicable standards.

Cutting:

Stone displaying defects such as cracks, chipped edges and corners, shall be rejected, and in
no case incorporated in the works.

Slabs shall be pre-cut to size, and where the lower edge abuts a staircase flight, the panel
shall be scribed to the stair profile.

Rectangular holes for switch-plates and socket outlets shall be cut with a rebated edge to allow
faceplates to finish flush with the panel surface. Joints between individual panels shall be flush
pointed to ensure an even and continuous surface between arises or changes of direction.

Fitting:

Stone lining slabs shall be fitted using cramps and hooks and plaster dabs leaving an air space
of 12 mm behind the slabs to prevent transfer of soluble salts from the backing material.

Finishing:

All marble work shall be cleaned, polished to a uniform glassy surface and finished with an
approved compound. Exposed edges shall be protected with lime putty or the like and
finished faces shall be free from scratches or other defects.

Fixings:

Fixing dowels and restraining hooks shall be of stainless steel and shall generally comprise
two per slab. Allowance shall be made for drilling holes in the top edge of a slab to receive
dowels, and for site drilling dense concrete blockwork, and wedging and grouting following
insertion of dowels.

Marble shall be best quality. For walls grey marble shall be used, cut square and true and
shall be uniform in shape and thickness.

Window sills shall be bedded hollow on plaster dabs and pointed all around with white
cement/sand mortar (1 : 4 mix).

GKW - Alliance 190


SPECIFICATIONS
CIVIL WORKS

Skirtings shall be fixed solid on a backing 10 mm thick. Joints in skirtings shall be arranged
to coincide with joints in adjacent paving.

Rounded arises, nosings and mouldings shall be adequately protected by means of timber
casings or lime putty coatings.

Treads, risers, skirtings and window sills shall be grouted and protected in a manner similar
to pavings.

1.16.20 Suspended Ceilings

1.16.20.1 General

The standard of workmanship for these works shall be of the highest standard and in strict
accordance with manufacturer’s instructions.

The terms “suspended ceiling” or “ceiling” mean all component parts of an integrated ceiling
installation including all junctions to perimeters, cores, columns, etc.

The ceiling panel surface shall be of a consistent appearance and the Contractor shall
ensure that the surface finishes are uniform in colour, texture and appearance throughout.

No fixing screws, cleats, etc., shall be visible on the ceilings.

1.16.20.2 Materials

Materials used in suspended ceilings shall in general comprise one of the following:

 Mineral fibre ceiling tiles;


 Aluminium strip acoustic ceiling;
 Plasterboard ceiling.

Ceiling installation systems shall have the approved fire classification.

Ceilings shall include a concealed, clipped metal suspension and framework system,
installed in accordance with the manufacturer’s written instruction.

Additionally, a framework shall be provided of galvanised mild steel angles supported from
the structure above by means of galvanised mild steel hangers. Ends of hangers shall be
threaded and bolted to the framework in such a way as to permit reasonable degree of
adjustment to achieve the required levels and effect. All metal components shall be
corrosion resistant.

Plasterboard used in metal stud partitions or suspended ceiling systems shall be 12.5 mm
wall board. The inner lining to walls providing one hour fire resistance shall be board
comprising a gypsum core. The suspended ceiling or any of its parts shall not contain any
substance which, as a result of overheating or combustion, will emit abnormally toxic fumes.

1.16.20.3 General Requirements

The suspended ceiling shall be capable of sustaining and transmitting to its point of support
all loadings resulting from its dead weight, and the dead weight of integral lighting fittings,
without deflection, fracture or permanent deterioration of its performance. No irreversible

GKW - Alliance 191


SPECIFICATIONS
CIVIL WORKS

deformation or progressive creep shall occur beyond the tolerances given herein from such
applied force.

Ceiling panels and their method of fixing shall be sufficiently robust to withstand removing
without permanent damage or disfigurement (especially during commissioning or any air
conditioning installation).

Any changes in dimensions and shape of the suspended ceiling system or its parts, due to
changes in temperature or humidity, shall not affect its performance.

The construction method proposed shall include bracing stiffeners, etc., to render the
finished work rigid, free from deflection, distortion, bending, warping, etc.

In addition to the above requirements, all work shall remain securely fixed without free play.

Finished ceilings shall be level and true to line in all directions. Joints between tiles shall
be straight and level and no deflection shall be apparent at butt edges between tiles and
other components. Any variation from true level shall not be more than 3 mm in any 3 m.

1.16.20.4 Coordination

The Contractor shall ensure that an adequate number of permanent access hatches are
incorporated in all suspended ceiling systems.

Particular attention is drawn to the requirement that the component parts of the works shall
be fixed by tradesmen normally responsible for such work, e.g. electrical work and light
fittings fitted by electricians, ceilings by ceiling firms, etc.

The method of construction shall allow for prefabrication and other forms of off-site
manufacture as necessary to suit the nature of the works and the incomplete state or
otherwise of the project at the time of construction.

1.16.20.5 Suspension Systems

Suspension systems shall be adequate and suitable to meet the specified requirements.

The method of construction shall take account of the following restrictions with regard to
fixings:

 Fixings and suspension systems shall not be connected to any services installation.
All ceiling suspension members shall be fixed clear of all services or insulation.
 Fixings to reinforced concrete beams and slabs shall be made using a fixing method
approved by the Engineer.
 Fixing to steelwork shall be by drilling and bolting. Clip-on fixings will not be permitted.

1.16.20.6 Setting out Tiles

Acoustic and other tile ceilings shall be set out each direction from the centre of the room,
on either the centre of a tile or a tile joint as agreed in each case by the Engineer.

1.16.20.7 Fixing Devices

GKW - Alliance 192


SPECIFICATIONS
CIVIL WORKS

Metal fixing devices shall be manufactured entirely of non-ferrous metals or be otherwise


thoroughly protected from corrosion.

Timber fixing devices shall be pressure impregnated with an approved preservative.

Brackets, plugs or bolts shall be of a type, make and pattern approved by the Engineer.
The Engineer approval shall be obtained for all proposed methods of fixing.

1.16.21 Roofing

1.16.21.1 General

The work shall consist of supplying, laying and finishing complete insulation and roof
coverings and shall include provision of all necessary skirtings, copings, flashings etc., as
required.

On completion, all roofs shall be left sound and watertight and in a neat and clean condition.
All roof finishes shall be carefully worked or fitted around pipes or openings.

Roofing systems shall be in general the “inverted roof” or “protected membrane roof”
system where the waterproof membrane is laid directly onto the structural slab. The
insulating layer is then laid on the membrane and protected by a layer of files.

Any special working details that may be prepared by the Contractor shall be submitted to
the Engineer for approval. This work shall be done in good time, prior to commencement
of construction.

Falls for rainwater drainage shall slope away from movement or other joints where
practicable.

1.16.21.2 Waterproofing

The structural slab or surface screed membrane shall be primed with primer before application
of the membrane according to the manufacturer’s instructions.

1.16.21.3 Roof Insulation

Roof insulation board shall have a minimum density of 35 kg/m3.

1.16.21.4 Precast Cement and Sand Roofing Tiles

Precast cement and sand roofing tiles shall be formed with a minimum 10 mm facing of one
part white cement and three parts of sand, set on a backing of sulphate resisting cement
mortar with a minimum cement content of 305 kg/m3.

1.16.21.5 Aluminium Flashing

Flashings shall be formed out of 0.8 mm super purity aluminium with natural mill finish.
Accessories such as hooks, nails, screws and clamps shall be of the same material and
alloy.

GKW - Alliance 193


SPECIFICATIONS
CIVIL WORKS

1.16.21.6 Screeds

Cement, sand and water for screeds shall be as described in the section for concrete.
Lightweight aggregate shall be a proprietary type approved by the Engineer.

1.16.21.7 Rainwater Outlets

Rainwater outlets shall be a proprietary type approved by the Engineer. Outlets shall drain
from the top interface between the waterproof membrane.

1.16.21.8 Workmanship

Workmanship shall be carried out in accordance with the applicable standard. The roof
surfaces shall be uniform, compact and free from all debris.

Waterproof membranes shall be 1.5 mm thick self-adhesive rubber bitumen applied strictly
in accordance with the manufacturer’s instructions. The membrane shall be continuous
and taken up abutments and pipes to above the insulation layer. Exposed membrane shall
be solar protected.

The waterproof membrane shall be carried up walls, beams, etc., over fillets to form a
skirting continuous with the roof covering.

The waterproof membrane shall be dressed and bonded into rainwater outlets and under
flashings.

The insulation boards shall be not less than 50 mm thick closed cell extruded polystyrene
loose laid in a single layer with tight staggered butt joints in accordance with the
manufacturer’s instructions.

The boards shall be trimmed to fit any fillets used under the waterproof membrane.

Flashings shall be sheet aluminium neatly cut to a width and length required. Aluminium
shall be carefully bent using a slightly rounded former so as to avoid surface cracking.

Where surface fixing is required, the sheet shall be pre-drilled and fixed with stainless steel
screws to proprietary fixings or hardwood grounds let into the surface of the base concrete
or brickwork.

Where flashings are built into joints or tucked into grooves, the aluminium shall be set to
full depth. Where set into grooves, aluminium shims or wedges shall be used at 450 mm
intervals to secure the flashing. The exposed edges above the flashing shall be neatly flush
pointed with cement mortar.

Lightweight screeds shall be laid in accordance with the manufacturer’s instructions and to
falls not less than 1 in 40 with a minimum thickness of 100 mm. The screed shall be laid in
two courses, the lower course not less than 50 mm thick and in bays not exceeding 15 m 2
or 1.80 m in width laid alternately and finished with a 10 mm thick topping of 1:4
cement/sand mortar. Screeds shall be trowelled smooth.

Immediately after laying, the screed shall be protected from wind or strong sunlight and
upon hardening shall be protected with waterproof sheeting for a period of not less than 7
days.

GKW - Alliance 194


SPECIFICATIONS
CIVIL WORKS

Screeds shall be laid to a tolerance in accordance with the applicable standard accuracy
class with high spots between drainage outlets, and shall be thoroughly cured before the
roof finish is laid. Care shall be taken to avoid damage to screeds prior to installation of the
roof finish.

1.16.21.9 Galvanised Iron Sheet Covering (pitched roofs)

In the case of a pitched roof with galvanised iron sheets, corrugated galvanised iron
sheeting shall be new sheets of 0.65 mm thickness fixed with forge headed screws and
rubber and leather washers or special mastic into 8 cm  5 cm hardwood purlins. All ridges,
cappings, flashings, etc., are to be of galvanised iron 0.65 mm thick.

1.16.21.10 Timber Roof Structure

Where timber roof structures are foreseen, the timber for trusses and the timber for purlins
and joists shall be selected hardwood. Trusses are generally to be constructed in the
connected double-wood system and bulldog connectors and all necessary ironmongery are
to be allowed for. Unless otherwise indicated, timber trusses shall be spaced 2 m apart,
and shall be wall-plated, secured to beams, or string course by means of rag-bolts, rag-
bolted angle cleats with bolts, cast-in reinforcing bars, or cast-in hoop irons to the approval
of the Engineer. If open soffits are indicated, all visible members of trusses shall be planed
and painted with three coats of oil paint. All timber utilised in the construction of roof
structures shall be well sawn, sound, free from warps and other defects, and shall be treated
in accordance with the general specification for painting and protective coatings.

1.16.22 Carpentry and Joinery

This Specification covers the requirements for, but is not limited to, all carpentry and joinery
works.

1.16.22.1 General

A high standard of workmanship and materials shall be achieved in the works. The
completed installations shall be durable, well finished, complimentary to the works and
designed and constructed to achieve a service life of at least 25 years.

Workmen employed in the manufacture and installation of the timberwork shall be


experienced cabinet makers.

1.16.22.2 Materials

Timber shall be of best quality, sound, in good condition, reasonably free from shakes, and
free from loose dead knots, insect attack, decay, twisting and warping. Timber shall be
properly seasoned to suit the purpose for which it is intended.

Only knots with characteristics similar to those detailed in the applicable standard will
generally be allowed. Where timber is described as “Selected” it shall be free from knots.

GKW - Alliance 195


SPECIFICATIONS
CIVIL WORKS

1.16.22.3 Soft Wood

Soft wood shall be as follows:

 Redwood, specially selected from the best unsorted and joinery quality.
 Douglas fir or selected merchantable quality or better.

1.16.22.4 Hardwood

Hardwoods shall be selected and of the best quality; it shall be particularly checked for
infestation by pinhole borers. Selected Iroko hardwood shall comply with the applicable
standard.

1.16.22.5 Plywood

All plywood shall be approved by the Engineer and shall comply with the requirements of
the applicable standard.

Grade FU I/II or TI I/II where varnished.

Grade FU II/II or TI II/II elsewhere.

Plywood and face veneers shall be free from end joints (including joints in veneers),
overlaps in core veneers, dead knots, patches and plugs, open defects, depressions due
to defect in cure, insect attack, fungal attack, and from discolouration differing from that
normally associated with species.

Face veneers require approval by the Engineer and shall be hard and durable and shall be
capable of being finished to a smooth surface. Face veneers shall closely match the
general joinery timber supplied and shall be applied to one or more sides as required.

1.16.22.6 Fibreboard

Fibreboard shall be in accordance with the applicable standard (insulating board), type
HFD.

1.16.22.7 Hardboard

Hardboard shall be in accordance with the applicable standard (standard hardboard), type
HFH.

1.16.22.8 Chipboard

Chipboard or materials incorporating chipboard elements shall not be used in the works
without the express permission in writing of the Engineer.

Where authorised, it shall be medium density wood particle board, produced in factories by
an approved process.

Veneered chipboard, where used, shall be faced at factory with hardboard veneer
(minimum 1 mm thickness). Where work has only one visible face, the rear (invisible) face
shall have an approved balancing system. Veneers shall be carefully chosen and applied

GKW - Alliance 196


SPECIFICATIONS
CIVIL WORKS

so as to present a good appearance. Choice of veneer shall be at the discretion of the


Engineer. Full sheets shall have edges lipped with matching hardwood fillets. The fillets
shall cover the full thickness of the sheet, and shall have a minimum thickness of 6 mm.

1.16.22.9 Melamine

Laminate shall be high pressure laminated sheets with a white suede or matt finish, with
melamine resin surface, with a resistance to surface spread of flame.

Laminate adhesives shall be selected, stored and applied in accordance with the
recommendations of the laminate manufacturers.

1.16.22.10 Samples

Before commencing work, the Contractor shall submit samples of all types of timber to be
used for the approval of the Engineer.

Timber, or carpentry and joinery units of which the material on delivery to the site does not
conform to the standard of approved samples will be rejected and replaced by the
Contractor at his own expense.

1.16.22.11 Miscellaneous Material

Screws shall comply with the applicable standard.

Timber connectors, where used, shall be two single-sided toothed plate (round or square)
for demountable joints or one double sided toothed plate (round or square) for permanent
joints in accordance with the applicable standard.

Fixings to walls and floors and ceilings shall be carried out by the following means:

 Approved patent fibre or purpose made filling plugs fixed in accordance with
manufacturer’s instruction;
 Approved parallel expanding anchors;
 Hardwood plugs cut on the twist, providing the structure is approved as sufficient to
take the plugs.

Soft wood plugs shall not be used.

1.16.22.12 Ironmongery

The Contractor shall provide all necessary ironmongery including matching screws, bolts,
plugs and other fixings. The use of nails for fixing ironmongery will not be permitted.

Ironmongery shall be of the best quality and to the approval of the Engineer and, unless
otherwise specified, shall be solid brass. The Contractor will be required to submit samples
of all items of ironmongery (including hinges) for approval.

All fittings shall be removed before starting any painting operation and shall be refixed in
place after all painting works are completed and approved by the Engineer.

GKW - Alliance 197


SPECIFICATIONS
CIVIL WORKS

1.16.22.13 Selected Timber

Timber described as “selected” shall be selected and kept clean for polishing, varnishing,
staining or oiling and prices shall include for finishing by hand with fine glass paper and for
carefully matching adjacent pieces of timber to the same colour and character. Staining of
timber will only be permitted as an integral part of the surface finishing process and if carried
out by a fully trained operative.

1.16.22.14 Protection of Soft Wood

All soft wood incorporated in the works or delivered to the site shall be treated by means of
double vacuum impregnation after final machining, but before assembly.

Where cutting or boring after treatment is essential, two coats of the preservative medium
shall be liberally applied to the cut surfaces.

Where the preservative leaves visible evidence of treatment, it shall be suitable to receive
the specified painting or staining. Where the preservative leaves no visible signs of
treatment, a chemical tracer shall be incorporated in the preservative and a spray reagent
applied by the preservative manufacturer as a ready means of identifying treated timber
from untreated timber on site.

The treatment shall be applied only to the fully machined components which in all cases
shall have a moisture content of less than 16 %.

Drying out time shall be as recommended by the supplier of the preservative fluid and the
equipment.

A certificate in quadruplicate stating that the required preservative treatment has been
carried out shall accompany the consignment of joinery on the site and shall be handed
over to the Engineer.

1.16.22.15 Moisture Content of Timber

All timber shall be seasoned. The moisture content of the timber during transit, storage and
on site shall be about 25% and shall be maintained until the works are commissioned.

Prior to transportation all timber shall be polythene wrapped. On arrival to store or site, the
polythene shall be removed and timber close-stacked on level bearers or suitable racks
spaced to allow circulation of air and protected against water, dirt, decay, insect attack, soil
and other deleterious matters.

The Contractor shall take all necessary steps to preserve the timber in best quality condition
and at the required moisture content.

Timber for internal use shall be stored on site under dry and warm conditions similar to
those of the finished building and for external use shall be stored under cover and protected
from sun and rain.

GKW - Alliance 198


SPECIFICATIONS
CIVIL WORKS

1.16.22.16 Wet-check Meter

The Contractor shall use an approved wet-check moisture meter to monitor the timber.

1.16.22.17 Dimensions

All timber is to be sawn, planed, drilled or otherwise machined or worked to the correct
sized and shapes as required. Where the “nominal” dimensions are stated for wrought
timber, an allowance of 3 mm shall be permitted for each wrought surface. Contractor’s full
size drawings shall be held to show the “actual” dimensions.

1.16.22.18 Exposed Faces

All timber that is to be exposed in the finished surfaces of the work shall be wrought on the
appropriate faces, unless otherwise specified.

1.16.22.19 Natural Finish

When natural finish or finish for staining, clear polishing or varnishing is required, the timber
in adjacent pieces shall be matched, uniform, and symmetrical in colour and grain.

1.16.22.20 Shrinkage

The arrangement, jointing and fixing of all joinery works shall be such that shrinkage in any
part and in any direction shall not impair the strength and appearance of the finished work,
and shall not cause damage to contiguous materials or structures.

1.16.22.21 Tolerance

Reasonable tolerance shall be provided at all connections between joinery works and the
building carcass, whether of masonry frame construction, so that any irregularities,
settlements or other movements shall be adequately compensated.

1.16.22.22 Fabrication

The cabinet maker shall perform all necessary mortising, tenoning, grooving, matching,
tonguing, housing, rebating, and all other works necessary for correct jointing. He shall
also provide all metal plates, screws, and other fixings that may be specified or that may be
necessary for the proper execution of the works and shall also carry out all works necessary
for the proper construction of all framings, linings, etc., and for their support and fixing in
the works.

No nails shall be used to assemble or fix hardwood, major supports, or ironmongery.


Screws used in exposed locations and/or for hardwood work shall be brass and complete
with brass surrounds.

GKW - Alliance 199


SPECIFICATIONS
CIVIL WORKS

1.16.22.23 Joints

The joinery shall be constructed exactly as shown on the approved drawings. All joints
shall be the recognised forms of joints for each position. The joints shall be made so as to
comply with the applicable standard.

Loose joints are to be used where provision must be made for shrinkage or other
movements acting other than in the direction of stresses of fixing or loading.

Glued joints shall be used where provision need not be made for shrinkage or other
movements in the connections, and where sealed joints are required. All glued joints shall
be cross-tongued or otherwise reinforced. All nails, sprigs, etc., are to be punched and
puttied. Surfaces in contact shall have a good sawn or planed finish. All cutting edges of
tools are to be sharp to avoid burnishing. The surface of plywood to be glued shall be lightly
dressed with sand or glass paper. The sand or glass paper must not be allowed to clog
and cause burnishing.

Members in construction to be joined by gluing are to be of similar size and shape. All
surface to be glued shall be kept clean, free from dirt, sawdust, oil and any other
contamination. Adequate pressure shall be applied to glued joints to ensure intimate
contact and maintained whilst the glue is setting.

All joints shall be flush, without gaps or imperfections.

Mixing, application and setting conditions should be in accordance with the glue maker’s
instructions.

1.16.22.24 Adhesives

Adhesives for joints in non-loadbearing internal work and for joints in work where the
moisture content is always less than 16 %, organic glues or casein may be used.

For work under damp conditions (moisture content normally 20 % or more or conditions
liable to fungal attack) resin type adhesives are to be used.

1.16.22.25 Mouldings

All moulded work shall be accurately worked to the full-size details required. All mouldings
shall be worked on the solid, except where otherwise specified.

1.16.22.26 Bendwork

Where bending is specified, the work is to be performed by saw-kerfing, keying, backing-a-


veneer, laminating or steaming, and shall be carried out to the satisfaction of the Engineer.

1.16.22.27 Circular Work

When circular work is specified, it shall be built up with an appropriate number of pieces cut
to the required shapes. The pieces shall be put together in two (or three) thicknesses so
that joints are staggered and shall be secured with oak keys and wedges or with oak pins
(whichever is more appropriate).

GKW - Alliance 200


SPECIFICATIONS
CIVIL WORKS

1.16.22.28 Veneering

Veneering shall be carried out in an approved manner, and to the entire satisfaction of the
Engineer.

1.16.22.29 Scribing

All skirtings, architraves, plates and other joinery works shall be accurately scribed to fit the
contour of any irregular surface against which they may be required to form a close butt
connection.

1.16.22.30 Capillarity

The Contractor shall take all reasonable measures to check or prevent capillary penetration
of water in the joints and open connections of external work, and in all other positions where
timber may be exposed to water.

1.16.22.31 Weathering

All weathering surfaces, throatings, grooves and joints etc., and all open connections in
external work shall be properly executed, and shall obtain good degree of weather
resistance.

1.16.22.32 Finishing

All wrought surfaces shall be finished with a glass papered or scraped surface for
decorations as required.

1.16.22.33 Hardwood Work Fixings

Fixings shall be by jointing to other timber (glued) or by means of brass screws with
countersunk heads to proprietary plugs. Where work is face screwed, heads of screws
shall finish not less than 6 mm below the surface and be covered with round hardwood
pellets of appropriate thickness. Pellets shall be chosen and fixed so as to match colour
and pattern of grain so far as is practical. Nailing will not be permitted. Sections shall be
neatly and accurately cut with fine toothed saws.

1.16.22.34 Priming

All joinery which is to be painted shall be delivered to site unpainted and shall be primed
on site immediately after the Engineer's inspection and acceptance and before fixing.

1.16.22.35 Accuracy

The finished tolerances for the work shall be stated on the drawings and approved by the
Engineer.

All joints, appearance, recesses, etc., shall be plumb, true and square. All units and
members shall be installed such that they are truly plumb or horizontal.

GKW - Alliance 201


SPECIFICATIONS
CIVIL WORKS

1.16.22.36 Defective Work

All defective materials, workmanship or timber that is defaced or that splits, shrinks or warps
excessively shall be removed and replaced, including any ancillary works affected.

1.16.22.37 Clearing Up

The Contractor shall clean out all shavings, cut ends and other timber waste from all parts
of the building before coverings or infillings are constructed. All waste and rubbish is to be
destroyed or removed.

1.16.22.38 Framing

Where described as framed, all joinery shall be put together with well-fitting mortise and
tenon joints and glued and wedged up solid. Final wedging up shall not be completed until
fixing of joinery is commenced. All glued joints shall be cross-tongued and all hardwood
joinery shall be secretly fixed. All joinery to be painted shall be knotted and primed with an
approved primer before leaving the shop but not until inspected by the Engineer.

1.16.22.39 Fixing of Frames

Where windows or door frames are built into existing openings, the jambs shall be plugged
at the door head and sill and, in the case of door frames or windows over 900 mm high, at
one intermediate point per side. (This timber may be fixed with nails unless otherwise
described).

1.16.22.40 Flush Doors

Generally flush doors shall have a minimum thickness of 40 mm. They shall be faced both
sides with hardwood veneered faces. Flush doors shall be approved by the Engineer and
shall comply with the requirements of the applicable standard. All edges shall be bevelled
and lipped with hardwood tongued into the edge of the door.

The core of solid core flush doors shall be constructed of longitudinal laminations of
precision planed timber, butt jointed and glued with resin based adhesive under hydraulic
pressure, the whole forming a rigid fire-resistant raft.

All external doors shall be glued with AW100 grade adhesive and faced with AW100
bonded exterior grade plywood.

Fire-resistant flush doors, if required, shall be constructed in accordance with the applicable
standard.

1.16.22.41 Hardwood Doors

Hardwood doors shall be constructed out of teak or similar approved hardwood, with 100 x
38 mm stiles, 125 x 28 mm top rails and 225 x 38 mm middle and bottom rails.

Where required, the doors shall be glazed with 6 mm wire polished plate glass, fixed with
hardwood glazing beads and shall provide a fire-resistance in accordance to the applicable
standard.

GKW - Alliance 202


SPECIFICATIONS
CIVIL WORKS

1.16.22.42 Hardboard in Doors

Internal doors shall not contain hardboard.

1.16.22.43 Folding Shutter Doors

Folding shutter doors shall be proprietary sliding shutter vertically folding doors with panels
constructed from galvanised steel and jointed together by galvanised steel hinge sections.
The doors shall be approved by the Engineer and shall be supplied complete with all
necessary tracks, posts, soffit and jamb closing pieces, etc.

1.16.22.44 Frames

In general frames, architraves and extension pieces shall be manufactured from red and/or
whitewood timber and shall include the use of finger-jointed material.

If exposed in the laboratory the frames shall be in hardwood.

1.16.22.45 Floor Runners

Floor runners shall be constructed from 5  10 cm and 5  7 cm hardwood joists. The joist
hangers shall be of the same type of wood and size.

1.16.22.46 Timber Ceilings

Ceilings under floor and roof structures of other than concrete construction shall be of 10
mm termite proof “Treetex” fixed with galvanised nails to 50  80 mm hardwood battens
provided at 600 mm centres in both directions and secured thereto by 25  5 mm hardwood
cover fillets to form squared pattern of approximately 600  600 mm; prices for ceilings shall
include for battens, cover fillets, any cornices indicated at junctions of ceilings and walls,
and for three coats of oil distemper.

1.16.22.47 Timber Boarded Floors

Flooring shall not be laid until all wall and ceiling coverings have been formed or
constructed. Timber boarded flooring shall be of 30 x 100 mm apart measured in any
direction. Boarded flooring shall be secret nailed to hardwood battens laid at a maximum of
500 mm centres and - if on a concrete or reinforced concrete floor slab - the spaced
between battens shall be filled with screed. Heading joints shall be formed over battens
and shall generally be splayed unless specified to be tongued and grooved. Floor boards
shall be thoroughly cleaned off and polished on completion. Prices shall include for the
provision, fixing, and laying of battens and screed.

1.16.22.48 Timber Soffits

Fascia boards and barge-boards (to gables) shall be constructed of selected 25 mm planed
selected hardwood as indicated to heights shown, and, where closed soffits are indicated,
such soffits shall also be constructed of hardwood 20 mm thick, well planed, tongued and

GKW - Alliance 203


SPECIFICATIONS
CIVIL WORKS

grooved, “V” joined, and fixed to 50 x 50 mm battens. Soffits shall receive three coats of
approved oil paint.

1.16.23 Metal Windows, Louvres and Doors

Metal windows and doors shall be handled with care and until fixed shall be stacked on
edge on clean surfaces.

In brick openings, frames shall be fitted with fixing lugs in adequate number, and bedded
in mortar.

In concrete openings, frames shall be plugged to the walls using zinc-coated screws.

To avoid corrosion of aluminium alloy frames, screws and other metal fixing in contact with
them shall be of aluminium, zinc or cadmium plated. In no circumstances shall copper
fixings be used.

Frames shall not be used as centring for brickwork or to support a lintel.

Frames shall be carefully pointed in 1:3 cement mortar and, after raking out the gap, shall
be pointed with mastic.

1.16.23.1 Kind of Windows and Doors

When not otherwise specified, the Contractor shall use aluminium windows which shall be
robust and of good quality.

Extruded aluminium members shall be fabricated conforming to the applicable standard.

Where members are formed from sheet materials they shall be fabricated conforming to
the applicable standard.

The main elements of the aluminium solid section out frame shall be at minimum tolerance
not less than 2.0 mm thick. The thickness of all other structural elements of the sections
shall be at minimum tolerance not less than 1.2 mm except for weather-stripping retaining
flanges and glazing beads which may be thinner.

All aluminium alloy parts shall be finished satin matt and anodised in accordance with the
applicable standard.

Weather-stripping shall:

 be made from materials known to be compatible with aluminium;


 not shrink or warp or adhere to sliding surfaces or closing surfaces;
 not promote corrosion when in contact with the aluminium alloy used; and,
 be resistant to deterioration by weathering.

Joints in frames shall be made neatly and accurately either by welding or by mechanical
means (e.g. cleating and screwing) and may have flush, stepped or lapped surfaces.
Welded joints shall be cleaned off smooth on the surfaces which are exposed when the
window or door is in the closed position or where they come into contact with glazing.

Hinges and pivots shall be either of suitable corrosion-resistant materials or, if not
compatible with aluminium, shall be separated from the aluminium by materials which are

GKW - Alliance 204


SPECIFICATIONS
CIVIL WORKS

compatible with it. Hardware, including fixings, shall be of suitable corrosion-resistant


materials. Materials or finishes which are not compatible with aluminium shall not be used
unless they are satisfactorily separated from the aluminium by materials which are
compatible with it.

Glazing beds, gaskets, glass adaptors and glazing compound shall be of materials
compatible with aluminium and finishes thereon.

Windows and doors shall be such that glazing and re-glazing on site is possible without the
need to remove the outer frames from the structure of the building.

Mosquito screens shall be fitted to all windows and external doors.

1.16.24 Finish Hardware

1.16.24.1 General

The Contractor shall furnish and install all finish hardware to complete the work as specified.

The Contractor shall submit samples of all hardware to the Engineer for approval.

All hardware shall have the required screws, bolts and fastenings necessary for proper
installation, wrapped in paper and packed in the same package as the hardware. Each
package shall be legibly labelled, indicating that portion of the work for which it is intended.

All hardware shall be of the best grade, entirely free from imperfections in manufacture and
finish.

Quantities, weight and sizes specified herein are the minimum that will be acceptable.

Finish of all hardware shall be dull stainless steel unless otherwise noted.

1.16.24.2 Hardware Description

Locks:

1. Tabular cylinder locks: stainless finish

2. Entry, exit and office doors: keyed on side, button opposite side

Passage doors: knobs both sides, no lock


Storage room: singe knob with key
Toilet room: stainless outside, chrome inside, pin opening outside for
emergency with button inside

All keyed locks to be master keys for same building. All locks to have two keys each.

Door closers: heavy duty type with stainless cover; top installation for either
right or left hand operation
Stops: floor or wall mounted type, stainless
Door pull: 10 x 30 cm stainless plate, with 15 cm shaped pull securely
fastened to plate; mounted with oval head stainless screws

GKW - Alliance 205


SPECIFICATIONS
CIVIL WORKS

Kick plates: 20 cm stainless plate, width of door less 5 cm


Coat holder: stainless steel, standard
Door hinges: 10 x 10 cm stainless steel, three per door
Flush bolts: 15 cm stainless
Gravity hinges: set of upper and lower, chrome finish, adjustable to stay
slightly ajar
Cabinet hinges: 6 x 10 cm stainless, three per door
Friction catch: heavy duty - two parts with rubber grips concealed installation

Cabinet and drawer pulls: stainless steel, 10 cm grip with concealed bolt fastenings.

Window Hardware:

Windows indicated to be pivot type shall be furnished with a pair of window fittings (friction
stays), a window pull and one barrel bolt lock. Window fittings shall be galvanised or
stainless steel. Window pull shall be 2.5 x 10 cm with 4 screws and barrel bolt 10 cm long,
6 mm bolt.

Installation:

Unless otherwise indicated, all hardware installation and hanging shall be done at the site.

Exteriors doors and doors in air conditioned areas shall be weather-stripped.

Provide one (1) painted wood key case in each structure, size 25  50 cm with door and
lock. Supply plywood back inside with hooks for spare keys. All keys shall be clearly
labelled with metal or hardboard tags size approximately 50  20 securely fixed to the keys
and handed over to the Engineer.

Upon completion of the hardware installation, all items shall be inspected for proper
operation. All work shall be protected and any damage or incorrectness shall be repaired.

Hardware shall not be fitted until the latest time in the Contract.

1.16.25 Glass and Glazing

1.16.25.1 General

The Contractor shall supply all the glass required in those items of plant, furnishings and
fitments included in the Contract.

Glass shall be free from all defects. Sheets shall be SQG (selected quality glazing) and of
approved weight.

Labels showing glass manufacturer’s name, type of glass thickness and quality will be
required on each piece of glass. Labels must remain on glass until it has been set and
inspected.

All glazing compounds shall be delivered in labelled containers with the seals unbroken.

GKW - Alliance 206


SPECIFICATIONS
CIVIL WORKS

1.16.25.2 Materials

Obscured glass shall be rough cast to an approved pattern, un-tinted and 6 mm nominal
thickness.

Wired glass shall be transparent with a polished surface, 6 mm thick, selected and cut
parallel to the reinforcement. Where individual panels are adjacent the glass wires shall
line up.

Clear float glass shall be 6 mm thick.

Putty for glazing to timber frames and to metal frames shall be of approved manufacture.

1.16.25.3 Size, Delivery and Storage

The Contractor shall determine the actual sizes required by measuring frames to receive
the glass at the work site or from guaranteed dimensions provided by frame supplier.

Dimensions for glass and frame shall provide minimum clearance equal to glass thickness
for single glass on all four sides.

The sealed space between face of glass and fixed or applied glazing stops shall be not less
than 3 mm minimum.

Deliver glass to site in suitable containers that will protect glass from the weather and from
breakage.

1.16.25.4 Installation

Clear glass shall be used except where indicated otherwise. The glass shall be cut and
installed with any visible lines or waves running horizontally.

Glazing in wood shall have rebates and beads primed and painted. The glass shall be
firmly seated into the previously beaded and back-bedded rebate with glazing compound
and secured in place with wood beads, attached with not less than 2.5 cm length finish
nails, or flat headed screws, countersunk and set approximately at 15 cm centres. Nails or
screws used in beads shall be of the corrosion resistant type.

1.16.25.5 Tests

Glazing shall be flooded from top to bottom using water from a hose without nozzle. Any
leaks revealed by the hose test shall be corrected as directed.

1.16.25.6 Cleaning Up

All glass shall be cleaned at the completion of construction and any broken glass replaced.

The glazing shall be maintained in a clean condition until the date of handing over the works.

GKW - Alliance 207


SPECIFICATIONS
CIVIL WORKS

1.16.26 Sanitary Installation

1.16.26.1 Connections to Equipment and Fixtures

The Contractor shall provide all equipment and necessary material and labour to fixtures
connect to the plumbing system all fixtures and equipment having plumbing connections,
which are specified elsewhere. All connections to the sanitary drainage system shall be
trapped. The supply line to each item of equipment or fixture shall be equipped with a cut-
off valve to enable isolation of the item for repair and maintenance without interfering with
operation of other equipment or fixtures.

1.16.26.2 Cutting and Repairing

The work shall be carefully laid out in advance, and no excessive cutting of construction
will be permitted. Damage to buildings, piping, wiring, equipment or appurtenances as a
result of cutting for installation shall be repaired by persons skilled in the trade involved.

1.16.26.3 Protection to Fixtures and Equipment

Pipe openings shall be closed with fixtures and caps or plugs during installation. Fixtures
and equipment shall be tightly covered and protected against dirt, water and chemical or
mechanical injury. Upon completion of all work, the fixtures, materials and equipment shall
be thoroughly cleaned, adjusted, and operated. Belts, pulleys, chains, gears, couplings,
protecting setscrews, keys and other rotating parts shall be located so that any person in
close proximity thereto shall be fully enclosed or properly guarded.

1.16.26.4 Sanitary, Waste Water and Vent Piping - Generally

Pipe materials shall conform to the following requirements:

 Polyvinyl Chloride (PVC) Pipe:

Fittings on PVC pipes shall be PVC socket type and shall be installed by solvent welt
method.

 Cast Iron Pipe:

“Specifications for cast iron soil pipe and fittings (ISO R-13), spigot and socket”; the
pipe shall be coal tar pitch coated.

 Ductile Iron Pipe:

As specified elsewhere.

1.16.26.5 Sanitary, Waste Water and Vent Piping Installations

Horizontal waste and drain pipes shall have a minimum slope of 10 mm per meter. Vent
pipes in roof spaces shall be run as close as possible to the underside of the roof without
forming traps in pipes, using fittings as required. Vent and branch-vent pipes shall be so
sloped and connected as to drip back to the vertical stack by gravity.

Changes in pipe size on sanitary and waste water drain lines shall be made with reducing
fittings. Use of bushings will not be permitted. Changes in direction shall be made by the

GKW - Alliance 208


SPECIFICATIONS
CIVIL WORKS

appropriate use of 45 Y-branches, long or short-sweep 90, 45, 22½, or 11¼-bends, or
by a combination of these or equivalent fittings. Sanitary tees and 90-bends or elbows
may be used in drainage lines only where the direction of flow is from horizontal to vertical,
except elbows may be used where the change in direction of flow is either from horizontal
to vertical or from vertical to horizontal, and may be used for making necessary offsets in
vertical lines.

Slip joints will be permitted only in trap seals or on the inlet side of the traps.

Installation of pipes and fittings shall be carried out in accordance with the manufacturer’s
recommendations. Mitring of joints for elbows and notching of straight runs of pipe for tees
will not be permitted. Threaded joints shall have ISO/R7 pipe threads with graphite or inert
filler and oil, with an approved graphite compound or with polytetrafluoroethylene tape
applied to the male threads only.

1.16.26.6 Buried Drainage Pipes

Underground drainage pipes between buildings and manholes of drainage systems shall
be 150 mm diameter of the material specified above.

When passing under buildings, paths, roadways, etc., drainage piping shall be laid
accurately to falls on a bed of class B 10 concrete, 15 cm thick and 30 cm wide and after
laying shall be entirely encased in class B 10 concrete. Piping outside building shall be laid
on a bed of class B 10 concrete 15 cm thick and 30 cm wide and shall be haunched up on
both sides with class B 10 concrete. Piping fixed vertically is to be well secured to walls,
etc., with approved metal holder bats at every joint, built into walls as directed. Rodding and
inspection eyes are to be provided at all ends and junctions for cleaning purposes.

The Contractor shall give notice in writing when drainage trenches have been excavated to
their full depths and trenches shall be inspected and approved by the Engineer before
concrete beds are laid. The Contractor shall give further notice in writing when concrete
beds have been laid and these must also be inspected and approved by the Engineer. No
drainage trenches shall be filled or drains covered up until they have been inspected,
properly tested, and finally approved by the Engineer, or until the dimensions of trenches,
etc., have been checked and agreed upon by the Contractor and the Engineer.

1.16.26.7 Flashing

Pipes passing through roofs shall be flashed using lead or copper flashing with an
adjustable integral flange of adequate size to extend not less than 200 mm from the pipe in
all directions and flashed into the roofing to provide a watertight seal.

Sanitary vent stacks through corrugated asbestos roofing shall be installed to be watertight
to the details shown, with a PVC reducing socket, copper flashing and cement mortar.

1.16.26.8 Traps

Each fixture and piece of equipment having an integral trap or seal, requiring connections
to the sanitary drainage system shall be equipped with a trap. Each trap shall be placed
as near the fixture as possible, and no fixture shall be double trapped. Traps installed on
PVC pipe shall be PVC. Traps installed on lavatory wastes shall be brass recess-drainage
pattern, or brass-tube type, chrome plated.

GKW - Alliance 209


SPECIFICATIONS
CIVIL WORKS

1.16.26.9 Floor Drains

Floor drains shall have cast iron bodies with double drainage flange, weep holes and bottom
outlet. Outlet shall be inside caulked or screwed.

Shower and toilet room drains shall have adjustable chrome plated brass strainers with free
strainer area not less than one and one half times the connecting pipe size.

Pump room, equipment room and area drains shall have anti-tilting slotted cast iron grates
of not less than 150 mm diameter.

1.16.26.10 Downspouts and Gutters

Downspouts for roof drainage shall have a diameter not less than 100 mm and shall be
fabricated of light gouge galvanised steel or PVC. All offsets and bends shall be made with
45-bends and no skewed joints or bowed down spouts will be permitted. Downspouts shall
be supported with galvanised steel straps or PVC straps.

Gutters shall have half round or rectangular profiles in asbestos cement, PVC, or
galvanised iron. The width or diameter of gutters shall be 150 mm.

1.16.26.11 Water Pipe, Fittings and Connection - Generally

Water pipe within structures shall be of copper and water piping in the ground shall be either
of PE or PVC.

Fittings for copper tubing shall be flared brass or solder-type bronze or wrought copper.
Fittings for brass pipe shall be brass. Fittings for PVC pipe shall be PVC socket type.

1.16.26.12 Water Pipe, Fittings and Connection

The piping shall be extended to all fixtures, outlets, and equipment. The water piping
system shall be installed so as to be drained. Drainage shall be accomplished using 12 mm
plugged or capped fittings at each low point, except where a drain valve or a hose tap is
reasonable.

Pipe shall be cut accurately to measurements established at the building by the Contractor
and shall be worked into place without springing or forcing. Care shall be taken not to
weaken structural portions of the building. Exposed piping shall be run parallel with the
lines of the building, unless otherwise indicated. Branch pipes from service lines may be
taken from top, bottom, or side of the main, using such crossover fittings as may be required
by structural or installation conditions. Pipes, valves and fittings shall be kept in a sufficient
distance from other work and other pipes to permit not less than 25 mm between pipes and
other work. No water pipe shall be buried in floors or cast in concrete walls, unless
specifically indicated or approved. Changes in pipe sizes shall be made with fittings. Use
of bushings will not be permitted. Change in direction shall be made with fittings.

Allowance shall be made throughout for expansion and contraction of pipe. Sufficient
flexibility shall be provided on all branch run-outs from mains to provide for expansion and
contraction of piping. Flexibility shall be provided by installing one or more turns in the line
so that the piping will spring enough to allow for expansion without straining.

Joints in steel piping may be screwed or flanged. Installation of pipe and fittings shall be
made in accordance with the manufacturer's recommendations. Mitring of joints for elbows

GKW - Alliance 210


SPECIFICATIONS
CIVIL WORKS

and notching of straight runs of pipe for test will not be permitted. Threaded joints shall
have ISO/R7 pipe threads with graphite or inert filler and oil, with an approved graphite
compound, or with polytetrafluoroethylene tape applied to the male threads only. Unions
shall be provided where required for disconnection.

1.16.26.13 Valves

Valves shall be provided for piping to equipment and fixtures. No valve shall be installed
on any line with its stem below the horizontal. All valves shall be gate valves, unless
otherwise specified or indicated.

1.16.26.14 Unions

Unions shall be installed in easily accessible locations. Gaskets for flanged unions shall be
of the best quality fibre, plastic or leather. Unions shall not be concealed in walls, ceilings,
or partitions.

1.16.26.15 Hose Taps

Hose taps shall be brass with 13 mm inlet threads, hexagon shoulder, and 20 mm hose
connection, unless otherwise indicated. Hose taps installed on exterior walls of buildings
shall have an integral wall flange which shall be securely anchored to the wall to prevent
any strain on the supply pipe when attaching or disconnecting hose. Anchors shall use
brass or bronze bolts or screws with expansion shields in the concrete or masonry wall.

1.16.26.16 Pipe Sleeves

Pipe passing through concrete or masonry walls or concrete floors shall be provided with
pipe sleeves fitted into place at the time of construction. Sleeves shall be steel pipe. Each
sleeve shall extend through its respective wall, floor or roof, and shall be cut flush, except
sleeves in toilet room floors shall extend 25 mm above the finished floor. Unless otherwise
indicated, sleeves shall be of such size as to provide a minimum of 6 mm all around
clearance between bare pipe and sleeves. The annular space between pipe and sleeve
shall be packed and caulked watertight.

1.16.26.17 Pipe Hangers Insert and Supports

The location of hangers and supports shall be co-ordinated with the structural work to
assure that the structural members will support the intended load.

1.16.26.18 Fixture Support

Wall-hung fixtures shall be fastened to the wall by 9.5 mm through bolts where appearance
of the bolts is not objectionable. Exposed bolt heads in finished areas shall be hexagonal
and painted. Exposed nuts shall be chromium-plated hexagonal cap nuts. Washers shall
be painted or chromium-plated to match bolt heads or nuts.

For solid masonry and where through bolting is objectionable, fixtures shall be fastened
with 9.5 mm machine bolt expansion shields or 9.5 mm stud-type expansion bolts.

GKW - Alliance 211


SPECIFICATIONS
CIVIL WORKS

For cellular-masonry construction, where through bolting is objectionable, fixtures shall be


fastened with 9.5 mm toggle bolts. Toggle bolts shall extend into the cell of the masonry
unit and shall be of the gravity or spring-wing type. Lavatories mounted on pipe chases
shall be installed with one or two steel backup plates as required. The backup plates shall
be 3.2 mm thick, 100 mm wide and not less than the width of the fixture.

Urinals mounted on pipe chases shall be installed with one or two steel backup plates as
required, as specified for lavatories. Backup plates shall be suspended on the inner side
of the chase by two 3.2 mm thick metal clips placed in the mortar joint. The metal clips and
through bolts shall be tack-welded to each plate. The plates shall be installed horizontally
and fastened to the top and bottom of the lavatory or urinal as required.

1.16.26.19 Type of Fixtures - Generally

Material specified herein shall be the product of manufacturers regularly engaged in the
manufacture of such products.

Generally, all fixtures, except water closets and urinals, shall have the water supply above
the rim. Fixtures with the supply discharge below the rim shall be equipped with backflow
preventers. Angle stops, straight stops, stops integral with the taps, or concealed type of
lock-shield, and loose-key pattern stops for supplies shall be furnished and installed with
fixtures.

Where space conditions will not permit standard fittings in conjunction with the cast iron
floor flange, special short-radius fittings shall be provided. Connections between
earthenware fixtures and sanitary pipe shall be made absolutely gastight and watertight
with a closet-setting compound or with a neoprene gasket and seal. Use of natural-rubber
gaskets or putty will not be permitted for these connections. Bolts shall be not less than
6.4 mm in diameter and shall be equipped with chromium-plated nuts and washers.
Fixtures with outlet flanges shall be set the proper distance from floor or wall to make a first
class joint with the closet-setting compound or gasket and fixture used.

1.16.26.20 Fixtures

The type of fitting to be used in each location shall be in accordance with the following
schedule in which the sizes given for wastes taps outlets, etc., refer to the external diameter
of the fitting:

 Taps generally shall be chrome plated easy clean deck pattern bib taps.
 Taps shall be 15 mm in diameter and shall have capstan heads clearly marked as
appropriate with red and blue spots signifying “hot” and “cold” respectively.
 Shower fittings shall be breech pattern complete with exposed fixed chrome plated
riser pipes matching clips swivel pattern shower rose and taps.
 Wash down W.C. pans shall be white vitreous china with matching traps and black
solid plastic ring seats and covers, complete with chrome plated bar hinges and
rubber buffers. Each flushing cistern shall be white vitreous china or plastic with a
capacity of 9 litres and shall be provided with a side connection reversible plastic
syphon and flush pipe. The cistern shall include a ball valve with rubber cone joint
and a chrome plated flushing lever and shall be supported on white plastic coated
support brackets.
 Eastern type W.C.s shall be white vitreous china suitable for sinking into floors and
provided with raised foot treads and matching traps and vents. Each suite shall be
supplied with a 9 litres white vitreous china or plastic side inlet flushing cistern on

GKW - Alliance 212


SPECIFICATIONS
CIVIL WORKS

white plastic coated support brackets. The cistern shall be complete with the
following items:
- Plastic valve-less syphon;
- Ball valve with rubber cone joint;
- Overflow;
- Chrome plated chain and plastic pull;
- 42 mm diameter stainless steel flush pipe and matching fixing clips.
 Urinals shall be white vitreous china to complete with division wall hangers and
supports. An automatic flushing cistern of 14 litres capacity with syphon drip tap and
wall hangers shall be provided. The flush pipe shall be in stainless steel complete
with matching spreaders and clips together with 35 mm diameter outlet gratings and
35 mm diameter chrome plated traps.
 Counter top lavatory basins shall be self-rinsing white vitreous china supported on
white plastic coated support brackets and complete with the following items:
- Overflow;
- Chrome plated chain and plug;
- 35 mm diameter chrome plated waste outlet;
- Hot and cold taps;
- 35 mm diameter chrome plated bottle trap.
 Wall laboratory basins are to be white vitreous china to with minimum dimensions of
550 x 400 mm. Each basin shall be complete with the following items:
- Skirting;
- Gap overflow;
- White plastic coated support brackets;
- Hot and cold taps;
- 35 mm diameter chrome plated waste outlet;
- chrome plated chain and plug;
- 35 mm diameter chrome plated bottle trap.
 White glazed fire clay sinks with dimensions 500 x 400 x 25 mm. Each sink shall be
complete with the following items:
- Gap overflow;
- White plastic coated support brackets;
- Wall mounted 15 mm diameter hot and cold bib taps;
- 42 mm diameter chrome plated waste outlet;
- chrome plated chain and plug;
- 42 mm chrome plated bottle traps.
 Combined stainless steel sink drainer units shall be to the appropriate standards.
Each unit shall be 1,000  600 mm and be complete with the following items:
- 42 mm diameter combined overflow and waste fitting;
- chrome plated chain and plug;
- 15 mm diameter chrome plated sink mixer taps with capstan heads clearly marked
as appropriate with red and blue spots signifying “hot” and “cold” respectively;
- 42 mm diameter chrome plated bottle traps.
 Shower trays shall be in white glazed fire-clay with minimum dimensions of 800  800
 200 mm and with 42 mm diameter strainer waste complete with plug chrome plated
chain and stay fixed to tiled wall and 42 mm diameter bottle trap.

GKW - Alliance 213


SPECIFICATIONS
CIVIL WORKS

 Shower curtain rails shall be chrome plated 25 mm diameter tube with chrome plated
and brackets plugged and screwed to walls. Shower curtains shall be in plain white
plastic complete with eyelets and hooks.
 Towel rails shall be chrome plated 25 mm diameter tube with chrome plated end
brackets plugged and screwed to walls.
 Toilet roll holders shall be chrome plated with roller holders of an approved pattern
and shall be of the lockable type.
 Mirrors shall be copper backed float glass mirrors 6 mm thick, pre-drilled and fixed
with chrome plated dome headed screws. Distance washers shall be fixed with mirror
fixing points.
 Water coolers shall be of an approved type and manufacture. They shall be free
standing models of the electrically refrigerated type with a minimum cooling capacity
of 30 l/h from 25C inlet water to 10C drinking water in a room temperature of 30C.
The cabinets are to be corrosion proof with the cabinet frame fasteners and bases in
stainless steel.
 The bubbler shall have a lever handle and built in pressure regulator to deliver a
smooth steady flow of water at supply pressures from 1.40 to 8.60 bars.
 Waste outlet shall be 35 mm diameter and supply pipes shall be 15 mm diameter.
The coolers shall be fitted with chrome plated swan necked glass fillers with push
down valves.
 Electric water heaters shall be of an approved pressure vessel type, comprising the
electric heating element, adjustable thermostat, control pumps, complete piping
connection system with combined check/pressure relieve valve in the inlet side,
necessary connection cable and protection switch with fuses. The storage capacity
shall be not less than 120 litres.

1.16.26.21 Testing and Sterilisation of Sanitary System - Generally

Sanitary, waste, vent and water piping shall be tested by the Contractor and approved
before acceptance. Underground sanitary and waste piping shall be tested before
backfilling. Equipment required for test shall be furnished by the Contractor.

1.16.26.22 Drainage and Venting System

Piping shall be tested with water before the fixtures are installed. After the plumbing fixtures
have been set and their traps filled with water, the entire drainage and venting system shall
be submitted to a final test with smoke.

1.16.27 Openings in Walls, Floors and Ceilings

The Contractor shall box out and/or cut openings through walls, floors and ceilings for the
passage of pipes and cables and, where described in the Contract, shall provide and fix in
position approved tube sleeves cut off flush with the finished surface. All openings and
ducts shall be sealed on completion to prevent the passage of toxic or explosive gases.

1.16.28 Tolerances for Building Works

Tolerances for building works, except where otherwise described in the Contract, shall not
exceed the permissible deviations from levels and dimensions given in the relevant
standards, where applicable, for the corresponding types of work.

GKW - Alliance 214


SPECIFICATIONS
CIVIL WORKS

1.17 Roadworks

1.17.1 Road Formations

 The road formation shall be the surface obtained after completion of any earthworks.
 Formations, immediately before being covered with sub-base or road base material,
shall be clean, free from mud and slurry and properly shaped and compacted to an
even and uniform surface.
 The preparation and surface treatment of formations shall be carried out after the
reinstatement of any excavations for services.

1.17.2 Sub-Base Construction

Within 48 hours of completion of a road formation, granular sub-base material shall be


spread and compacted to the required thickness. The sub-base shall be protected from
deterioration due to ingress of water, the adverse effects of weather and the use of
Constructional Plant. Compaction shall be carried out in accordance with the following
table:

Type of Category Number of Passes for Layers


Compaction Plant not greater than:
110 mm 150 mm 225 mm
Smooth-wheeled Mass per metre width of roll:
roller
over 2,700 kg up to 5,400 kg 16 unsuitable unsuitable
over 5,400 kg 8 16 unsuitable
Pneumatic-tyred Mass per wheel:
roller
over 4,000 kg up to 6,000 kg 12 unsuitable unsuitable
over 6,000 kg up to 8,000 kg 12 unsuitable unsuitable
over 8,000 kg up to 12,000 kg 10 16 unsuitable
over 12,000 kg 8 12 unsuitable
Vibrating roller Mass per metre width of vibrating
roll:
over 700 kg up to 1,300 kg 16 unsuitable unsuitable
over 1,300 kg up to 1,800 kg 6 16 unsuitable
over 1,800 kg up to 2,300 kg 4 6 10
over 2,300 kg up to 2,900 kg 3 5 9
over 2,900 kg up to 3,600 kg 3 5 8
over 3,600 kg up to 4,300 kg 2 4 7
over 4,300 kg up to 5,000 kg 2 4 6
over 5,000 kg 2 3 5
Vibrating-plate Mass per unit area of base plate:
compactor
over 1,400 kg/m² up to 1,800 kg/m² 8 unsuitable unsuitable
over 1,800 kg/m² up to 2,100 kg/m² 5 8 unsuitable
over 2,100 kg/m² 3 6 10

GKW - Alliance 215


SPECIFICATIONS
CIVIL WORKS

Type of Category Number of Passes for Layers


Compaction Plant not greater than:
110 mm 150 mm 225 mm
Vibro-tamper Mass:
over 50 kg up to 65 kg 4 8 unsuitable
over 65 kg up to 75 kg 3 6 10
over 75 kg 2 4 8
Power rammer Mass:
100 kg up to 500 kg 5 8 unsuitable
over 500 kg 5 8 12

1.17.3 Wet-mix Macadam Construction

 Wet-mix macadam shall be spread evenly on the sub-base and compacted in layers
of not more than 200 mm thickness at the optimum moisture content + 0.5 %.
 Spreading shall be undertaken concurrently with placing. Compaction shall be
completed as soon as possible after the material has been spread.

1.17.4 Lean Concrete Construction

 Lean concrete construction for roads shall be Grade C7.5 and shall be spread evenly
on the sub-base and laid and compacted in layers of not more than 200 mm
thickness.
 Spreading shall be undertaken concurrently with placing. Compaction shall be
completed as soon as possible after the material has been spread. The maximum
period of time between mixing of the materials and final compacting of any given
material shall be 2 hours.
 Where practicable, joints against hardened material shall be avoided. Where such
joints are unavoidable, the hardened material shall be cut back vertically for the full
depth of the layer before placing any further adjacent material.
 Lean concrete shall be cured for a period of not less than 7 days. No vehicular traffic
shall be allowed to run on the base during this time.

1.17.5 Laying Coated Macadam

Transportation, laying and compaction of all coated macadam shall be carried out in
accordance with the relevant provisions of the applicable standard.

1.17.6 Laying Hot Rolled Asphalt

Transportation, laying and compaction of hot rolled asphalt shall be carried out in
accordance with the relevant provisions of the applicable standard.

GKW - Alliance 216


SPECIFICATIONS
CIVIL WORKS

1.17.7 Waterproof Underlay for Concrete Carriageways

Waterproof underlay shall consist of waterproof paper or impermeable plastic sheeting, laid
to provide a membrane immediately below the concrete. Overlaps shall be not less than
300 mm and precautions shall be taken to prevent ponding on the membrane.

1.17.8 Reinforcement of Concrete Carriageways

 Reinforcement in concrete carriageways shall be so placed that, after compaction of


the concrete, its cover below the finished surface of the slab is 60 mm (+ 10 mm) and
it terminates 125 mm (+ 25 mm) from the edges of the slab and all pre-formed joints
in the concrete.
 At transverse joints between mats of steel fabric reinforcement, the longitudinal bars
shall overlap by at least 35 times the bar diameter, provided that such overlap shall
not in any case be less than 450 mm. Mats shall be placed so as to maintain the
same spacing between edge longitudinal bars as in the body of the mat.
 Reinforcement shall be positioned above dowel bars and tie bars irrespective of the
tolerances on position.

1.17.9 Laying Concrete Carriageways

 Placing, compacting and finishing of concrete in carriageways shall be carried out in


one layer as rapidly as possible and shall be so arranged that, in any transvers
section, the time for completion of mixing the first batch of concrete to completion of
compaction of that section shall not exceed 2 hours.
 Carriageway surfaces shall have a Screeded Finish, which shall be brushed
transversely with a medium textured wire broom to produce a lightly brush-marked
finish, with a 100 mm arrise Steel Trowel Finish to sides and at joints.
 Surface irregularities shall not exceed 3 mm when checked with a 3 m straight edge.

1.17.10 Laying Kerbs and Channels

 Kerbs, edgings, channels and quadrants shall be laid and bedded on a layer of Class
M1 mortar, either on the concrete carriageway or on a Grade C20 concrete
foundation, as described in the Contract. They shall be butt-jointed except where
otherwise described in the Contract, save that where laid on concrete carriageways
they shall be provided with joints coincident with the carriageway movement joints,
of width and with filler identical to that used in the carriageway joints. All kerbs shall
be backed with Grade C20 concrete.
 For radii of 12 m or less, kerbs and channels of the appropriate radius shall be used.
 Alignment of kerbs and channels shall not deviate from that described in the Contract
by more than 10 mm, with no lipping of visible faces.

1.17.11 Foundations for Footways

 Foundations for footways shall consist of Type 1 granular sub-base material spread
evenly and compacted in layers of not more than 100 mm thickness.
 Compaction to the correct levels shall be carried out using a vibratory roller having a
static load of at least 1,000 kg/m width of roll.

GKW - Alliance 217


SPECIFICATIONS
CIVIL WORKS

1.17.12 Laying Concrete Paving Flags

 Precast concrete flags shall be laid to the required falls on sub-base material as
described in the Contract, bonded with joints at right angles to the kerb, and sport
bedded with Class M4 mortar with no lipping of top surfaces.
 Flags shall be cut to fit around surface boxes and other furniture and, on circular work
where the radius is 12 m or less, shall be radially cut on both edges to the required
lines.

1.17.13 Tolerances for Finished Carriageway Surfaces

 Finished surfaces at each stage of road construction shall not vary from the levels
described in the Contract by more than the following permissible deviations:

Surface Permissible Deviation


(mm)

Formation and sub-base + 10, -30

Base ± 15

Wearing surface or slab


surface ±6

 The combination of permitted tolerances in the levels of different pavement courses


shall not result in a reduction in thickness of the pavement, excluding the sub-base,
by more than 15 mm from the specified thickness, nor a reduction in the thickness of
the bituminous wearing course by more than 5 mm from that specified, and the
maximum allowable irregularity of the wearing surface below a 3 m straight edge shall
be 3 mm.

1.17.14 Fixing of Gullies

 Gullies shall be bedded and surrounded with Grade C20 concrete to the thickness
described in the Contract.
 Frames shall be bedded in Class M1 mortar on two courses of Class ‘B’ engineering
brickwork or precast concrete gully cover slabs.

GKW - Alliance 218