Performance of A Test Embankment Constructed On An Organic Clayey Silt Deposit
Performance of A Test Embankment Constructed On An Organic Clayey Silt Deposit
Construction of the embankment was performed in four stages. During the first, second, and
third stages, the thickness of fill in the embankment was increased to 1.3, 2.25, and 3.4 m,
respectively. In the last stage of construction, it was rapidly built to failure over a 3- day period.
To monitor the development of excess pore pressures in the foundation subsoil, a total of ten
pneumatic piezometers were installed, four heave plates, four settlement plates, and three
augers at different depths were installed on the main part of the unreinforced embankment to
monitor the movement of the specific points on the ground surface and the foundation soil.
Another set of three augers at different depths, two settlement plates, and three heave plates
were installed on the berm) side of the embankment. Lateral displacement of the foundation
subsoil was monitored with three vertical inclinometers that were installed close to the toe of the
embankment. Inclinometer casings were installed up to a depth of about 10 m, where a stratum
of stiff clayey silt was encountered. A pneumatic total pressure cell was installed close to the
centerline of the unreinforced section to measure the pressure imposed by the fill on the
foundation subsoil.
Following are some of the key findings of the experiment, which are relevant to the practicing
Engineers:
The total pressure cell readings were found to be reasonably consistent and in close
agreement with the pressures calculated based on thickness and unit weight of the fill,
which signifies that stresses beneath the embankment can be calculated by the
conventional formulas. There is not any need to modify these formulas.
Dissipation of excess pore pressure has been reported during the early stages of
construction for the Sackville embankment. Literature also governs a similar kind of relation.
Therefore, various ground improvement techniques like stage construction, pre- loading can
be very helpful in dissipating excess pore pressure in the deposit in early stages of
construction.
The results of all three inclinometers indicated very similar, small (less than 0.06 m),
horizontal displacement responses up to 3.4 m thickness. This reflects an essentially elastic
response of the foundation soil up to at least 3.4 m fill thickness. The horizontal
displacement profiles indicate the initiation of a failure zone at a depth of about 3.5 m and
horizontal displacement of .24 m occurs, when net thickness of embankment became 5 m.
The results of settlement plates also confirmed that the settlement were less than 0.25 m
and elastic in nature up to 3.4 m. Therefore, the maximum net height of embankment, that
can be constructed on organic clayey deposits is up to 5 m and smaller than the height as
governed by the literature.
The failure of embankment occurs quite gradually. Therefore, the failure type for this kind of
sol is visco-plastic type, as no classical-type abrupt failure was encountered during the
construction of this embankment.
The height to which the embankment could be constructed is substantially less than what
would be expected based on a conventional 2D limit equilibrium calculation using
conventional vane strength data.
Question 2:
0.025
SETTLEMENT, Y(X)
0
0 5 10 15 20 25
BEAM LENGTH, X
-0.025
Numerical model is developed in the Geostudio with the help of Slope W function. As slope of
embankment provided as 4:1 and unit weight of fill is assumed as 22 KN/ m3 .
Figure 1: figure showing the embankment slope and FOS after analysis in Geostudio