Requirements for SAMM Approved Signatory

TABLE OF CONTENTS
Page

1 Introduction 1
2 Requirements of MS ISO/IEC 17025 1
3 SAMM policy on approved signatory 1

4 Requirements for signatory approval 3


5 Liabilities 4

SAMM Policy 6, Issue 4, 30 August 2008 i


Requirements for SAMM Approved Signatory

1 INTRODUCTION

1.1 This document specifies the policy and requirements for SAMM
signatory approval for use by SAMM laboratories, assessors and other
interested parties.

1.2 The approved signatory under SAMM is as defined in SAMM Policy 1


(SP 1) – Terms and conditions governing the laboratory accreditation
scheme of Malaysia.

1.3 This policy document is applicable to testing and calibration


laboratories under MS ISO/IEC 17025.

1.4 The presence of SAMM symbol or reference to SAMM accreditation in


the test reports or calibration certificates is a formal recognition of the
technical competence of the laboratory and the evidence of its
compliance with MS ISO/IEC 17025 and SAMM requirements.

2 REQUIREMENTS OF MS ISO/IEC 17025

2.1 Clause 5.2.5 of MS ISO/IEC 17025 requires,


“The management shall authorise specific personnel … to issue test
reports and calibration certificates…”

Note: Such personnel shall be SAMM approved signatory for SAMM


endorsed test reports or calibration certificates.

“The laboratory shall maintain records of the relevant authorisation(s),


competence, educational and professional qualifications, training, skills
and experience of all technical personnel,…”

Note: Records for all technical personnel including approved


signatory(ies) shall be maintained.

2.2 Clause 5.10.2(j) of MS ISO/IEC 17025 requires that each test report or
calibration certificate shall bear the name(s), function(s), signature(s)
or equivalent identification of person(s) authorising the test report or
calibration certificate.

3 SAMM POLICY ON APPROVED SIGNATORY

3.1 Test report or calibration certificate issued by SAMM accredited


laboratories for accredited test shall be signed by the personnel
authorised by the laboratory, to whom signatory approval has been
granted by STANDARDS MALAYSIA. The approved signatory is
responsible for the technical validity and accuracy of all information
contained in the test report or calibration certificate.

SAMM Policy 6, Issue 4, 30 August 2008 Page 1 of 6


Requirements for SAMM Approved Signatory

3.2 The nominated signatory shall be assessed on-site by the assessment


team for compliance with clause 4 of this SP document.

3.3 The signatory shall hold a position within the organisation, which
provides authority over the testing or calibration activities and to reject
results when he/she considers them to be inadequate.

3.4 Signatory approval by STANDARDS MALAYSIA is granted to


personnel for specific scopes for which he/she has been assessed to
be technically qualified and competent.

3.5 Signatory approval under STANDARDS MALAYSIA is not a personal


qualification and is not transferable from one laboratory to another.
The approved signatory status is deemed to be terminated when the
personnel leaves the organisation.

3.6 Signatory approval by STANDARDS MALAYSIA may also be granted


to personnel registered under the regulatory authorities/organisations
providing recognition. Such personnel may be employed or contracted
full-time or part-time, provided that the requirements of clause 4 of this
SP document are met.

NOTE 1 Resident signatory means a signatory working full-time in the


accredited laboratory or in another section/department within the
same organisation at the same site.

NOTE 2 Non-resident signatory means a signatory who is a part-time


employee of the accredited laboratory or a signatory from another
branch providing covering duties to the accredited laboratory.

Non-resident signatory

3.7 A non-resident signatory can only be approved if the accredited


laboratory has a permanent resident signatory. Should the accredited
laboratory lose the service of the permanent resident signatory the
laboratory shall apply to STANDARDS MALAYSIA to continue its use of
the non-resident signatory. STANDARDS MALAYSIA at its discretion
may grant approval on the continual use of the non-resident signatory
for a specified period.

3.8 A non-resident signatory shall have direct interaction with the


laboratory on-site at least once a month.

3.9 Formal agreement between the laboratory and the non-resident


signatory shall be established. The agreement shall ensure that:

i) the functions, responsibilities and authority in particular those of


an approved signatory shall be clearly defined.

SAMM Policy 6, Issue 4, 30 August 2008 Page 2 of 6


Requirements for SAMM Approved Signatory

ii) records of input including dates and duration of on-site visits,


topics and issues discussed, interaction with on-site staff and
recommendations, advice or instruction given are kept.

iii) the non resident signatory shall attend:

a) the management review meeting and


b) SAMM assessments unless specific exemption is granted by
STANDARDS MALAYSIA.

iv) the non resident signatory shall sign test report or calibration
certificate on site and shall review and initial quality control
records and relevant technical records.

Continual professional development

3.10 The SAMM approved signatory shall maintain his/her technical


competence to ensure his/her ability to evaluate the test or calibration
results.

3.11 The SAMM approved signatory shall participate in continual


professional development through in-house and external activities e.g.:
method development and validation, review and update of test
procedure, training, presentation of papers, attending seminars and
lectures etc.

4 REQUIREMENTS FOR SIGNATORY APPROVAL

Legal requirements

4.1 These requirements shall be read in conjunction with any other legal
requirements relating to the signatory of test report or calibration
certificate. Granting of SAMM signatory does not absolve the signatory
and laboratory from complying with legal requirements relating to the
signatory of test report or calibration certificate. Compliance with legal
requirements shall be the sole responsibility of the signatory and
laboratory.

4.2 SAMM laboratories shall provide necessary information and


documentary evidence to STANDARDS MALAYSIA for compliance
with the necessary legal requirements.

Qualification and experience

4.3 Education qualification and working experience:

a) SPM or equivalent in science or technical stream, with at least 8


years of experience working in the relevant fields; or

SAMM Policy 6, Issue 4, 30 August 2008 Page 3 of 6


Requirements for SAMM Approved Signatory

b) STPM or diploma in science or equivalent discipline, with at


least 3 years working experience in relevant fields; or

c) Degree holders in science or equivalent discipline with at least


six months relevant working experience in relevant fields;

and

d) Other requirements as stipulated in the relevant specific


technical requirements.

Technical and operational requirements

4.4 Knowledge and understanding of the technical and laboratory


operational requirements:

i) Requirements of MS ISO/IEC 17025 and all related SAMM


requirements (eg: SP series, SC and STR) and relevant
regulatory requirements.

ii) The principles of testing, calibration or measurement.

iii) The standards, methods and specifications for accreditation


sought or held.

iv) The estimation of measurement uncertainties for the


accreditation sought or held.

4.5 Working at least three months in the current laboratory and be


knowledgeable of its management system.

Specific Exceptions

4.6 The Director of Accreditation, at his discretion, may grant specific


exceptions to the requirements for approved signatory or impose other
requirements upon consultation with relevant parties.

5 LIABILITIES

5.1 An accredited laboratory shall assume full liability on all test reports
and calibration certificates issued.

SAMM Policy 6, Issue 4, 30 August 2008 Page 4 of 6


Requirements for SAMM Approved Signatory

Abbreviations:

1) SAMM – Skim Akreditasi Makmal Malaysia

2) SC – Specific criteria

3) SP – SAMM policy

4) STR – Specific technical requirements

SAMM Policy 6, Issue 4, 30 August 2008 Page 5 of 6


Requirements for SAMM Approved Signatory

Acknowledgements

1. Mr. Tham Kok Pheng (Chairman) STANDARDS MALAYSIA

2. Ms. Siti Rohaya Omar /


Ms. Siti Norehan Ishak (Secretariat) STANDARDS MALAYSIA

3. Mr. Pua Hiang STANDARDS MALAYSIA

4. Mr. Tan Kim Ho STANDARDS MALAYSIA

5. Dr. Norhayati Moris STANDARDS MALAYSIA

6. Mr. Zulkifli Abd. Rahman PETRONAS

7. Ms. Hasnah Hassan Sime-SIRIM Technologies Sdn. Bhd.

SAMM Policy 6, Issue 4, 30 August 2008

You might also like