Quiz Oil & Gas Engineering
Quiz Oil & Gas Engineering
BARON
Good luck!
The Heat & Material Balance (HMB) shows the flowrate, conditions and
composition of process and utility streams.
Right or Wrong?
The Heat & Material Balance (HMB) shows the flowrate, conditions and
composition of process and utility streams.
Right or Wrong?
Wrong, only the process streams. Utility streams, such as cooling water
flowrate etc., are defined later on, once equipment is sized.
INPUT flow rate (kg/hr) = OUTPUT flow rate (kg/hr) – True (mass
balance)
INPUT flow rate (kg/hr) = OUTPUT flow rate (kg/hr) – True (mass
balance)
IFC issuance curves, e.g. m3 of IFC concrete, tons of IFC steel, tons of
IFC piping isometrics
Utilities conditions: Fuel gas composition, pressure, electric power: voltage etc.
Regulatory requirements: Emission limits etc.
HERVE The Oil & Gas Engineering Quiz
BARON
HAZOP
HAZOP
ESD logic
Equipment spacing
Overflow of equipment
PLANT location
Overpressure hazard
P&IDs
PFDs
Plot Plan
H&MB
P&IDs - HAZOP
PFDs - HAZID
H&MB - HAZID
Process
Safety
Plant layout
Process - HAZOP
Safety - HAZID
The Inspection and Test Plan specifies the extent of Non Destructive
Examination and tests.
Right or wrong?
The Inspection and Test Plan specifies the extent of Non Destructive
Examination and tests.
Right or wrong?
Right or wrong?
Right or wrong?
Right
Table of Contents
Discipline presentation:
activities and deliverables
http://www.editionstechnip.com/en/catalogue
-detail/1111/oil-gas-engineering-guide-the.html
Process
Not endorsed data and rely-upon data mean the same thing.
Right or Wrong?
Not endorsed data and rely-upon data mean the same thing.
Right or Wrong?
Right. It means the Engineer is not responsible for this data. If it changes,
the Engineer is entitled to a change order.
On an typical large EPC Project of 3 year duration, the IFC P&IDs are
usually issued at which month of the Project?
Month 6
Month 9
Month 12
Month 15
Month 18
On an typical large EPC Project of 3 year duration, the IFC P&IDs are
usually issued at which month of the Project?
Month 6
Month 9
Month 12
Month 15
Month 18
Piping
As per the piping code for oil & gas plants (ASME/ANSI B31.3), the wall
thickness of a line
As per the piping code for oil & gas plants (ASME/ANSI B31.3), the wall
thickness of a line
Safety
Electrical
Process
Safety
Electrical
The designer performs the calculations and the Engineer checks them.
Right or wrong?
The designer performs the calculations and the Engineer checks them.
-46°C
-29°C
-20°C
0°C
-46°C
-29°C
-20°C
0°C
Heat exchangers
Rotating equipment
Packages
Pressure Vessels
Boilers
Fired Equipment
Packages - specifies
Boilers - specifies
Wind
What is the governing factor for the sizing of steel members of pipe-
racks/structures?
Structure deflection
What is the governing factor for the sizing of steel members of pipe-
racks/structures?
Structure deflection
Settings of controllers
Settings of alarms
Setting of trips
Settings of controllers
Settings of alarms
Setting of trips
16” and 2500 lbs, above that hubs (see picture) have to be used
Field instrumentation
Systems
Installation
Right or Wrong?
Field instrumentation
Systems
Installation
Right
thick lines
thick lines
The code
The code
the P&ID
the P&ID
the piping class specification – not for large diameters for which the
w.t. is calculated with the line design pressure!
Right or Wrong?
Wrong
Right or Wrong?
Right or Wrong?
Right, but for main process lines only. This is where the money is.
Remember that the purpose of q FEED is to estimate the cost – and allow
EPC contractors to bid.
Engineering is a
Linear
Iterative
Process?
Engineering is a
Linear
Process?
Heat & Material Balance and Process Data Sheet: flowrate, operating
conditions
The design and construction code applied in the Oil & Gas industry for
pressure vessels is
ASME VIII
API 5L
ANSI B31.3
ASME I
The design and construction code applied in the Oil & Gas industry for
pressure vessels is
ASME VIII
API 5L
ANSI B31.3
ASME I
Temperature
Pressure
Wall thickness
Post Weld Heat treatment is specified by Piping and Pressure Vessel codes
above a certain
Temperature
Pressure
Wall thickness: above 19.7mm for piping (ANSI B31.3) and above 38mm
for pressure vessels ordinary carbon steel plates (ASME VIII div. 1)
Table of Contents
Discipline presentation:
activities and deliverables
Table of Contents
Discipline presentation:
activities and deliverables
Difference between
Engineering and Shop
drawings
Table of Contents
Table of Contents
Implement powerful
procedures
http://www.editionstechnip.com/en/catalogue
-detail/1111/oil-gas-engineering-guide-the.html