Adhunik Steel LTD V Orissa Manganese and Mineral PVT LTD (2007-SC)
Adhunik Steel LTD V Orissa Manganese and Mineral PVT LTD (2007-SC)
Adhunik Steel LTD V Orissa Manganese and Mineral PVT LTD (2007-SC)
H.K Sema
P.K Balasubramanyan, JJ.
Relevant Act/Section:
4. We may notice that prior to approaching the District Court at Sundargarh, Adhunik
Steels had moved the Calcutta High Court under Section 9 of the Act seeking
identical reliefs.
OMM Private Limited had raised an objection to jurisdiction in the Calcutta High
Court and the said objection was upheld by the Calcutta High Court and that had led
to Adhunik Steels approaching the District Court at Sundargarh.
We may also notice that it is contended that Adhunik Steels had thereafter moved
the Chief Justice of the High Court of Orissa under Section 11(6) of the Act for
appointment of an arbitrator in terms of the arbitration agreement.
6. Aggrieved by the order of the District Court, Sundargarh, OMM Private Limited
filed an appeal before the High Court of Orissa.
The High Court allowed the appeal filed by OMM Private Limited and set aside the
order of injunction passed by the District Court, Sundargarh.
The dispute may prevent perishable goods from being put to their intended use, or
may impede the proper exploitation of a profit-earning article, such as a ship.
"It is not incompatible with an arbitration agreement for a party to request, before or
during arbitral proceedings, from a court an interim measure of protection and for a
court to grant such measure."
The Court of Appeal thought that it was an appropriate case for an injunction but that
it had no power to grant injunction because of the arbitration.
The Specific Relief Act, 1963 purports to define and amend the law relating to certain
kinds of specific reliefs obtainable in civil courts.
The power to grant injunctions by way of specific relief is covered by the Specific
Relief Act, 1963.
On the whole, we feel that it would not be correct to say that the power under
Section 9 of the Act is totally independent of the well-known principles governing the
grant of an interim injunction that generally govern the courts in this connection.
The District Court and the High Court have prima facie come to the conclusion that
the said Rule has no application.
It appears to be just and proper to direct OMM Private Limited not to enter into a
contract for mining and lifting of mineralswith any other entity until the conclusion of
the arbitral proceedings.
It is not possible to accede to the contention of learned counsel for Adhunik Steels
that in any event OMM Private Limited must be restrained from carrying on any
mining operation in the mines concerned pending the arbitral proceedings.
27. We dismiss the appeal filed by OMM Private Limited leaving open the questions
raised by it for being decided by the arbitrator or Arbitral Tribunal in accordance with
law.
We think that it would be in the interests of justice if we appoint and now a sole
arbitrator to adjudicate on the dispute between the parties.