50% found this document useful (2 votes)
628 views

Network Diagram Exercises

The document provides instructions and details for four network diagram exercises. Exercise 1 asks to draw a network diagram with activities A through G and their predecessors. Exercise 2 provides activities A through H with durations and predecessors to draw the diagram, determine the critical path, and project duration. Exercise 3 similarly provides activities A through H and Exercise 4 provides activities A through I to draw the diagram, find the critical path, and duration.

Uploaded by

gabboudeh
Copyright
© © All Rights Reserved
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
50% found this document useful (2 votes)
628 views

Network Diagram Exercises

The document provides instructions and details for four network diagram exercises. Exercise 1 asks to draw a network diagram with activities A through G and their predecessors. Exercise 2 provides activities A through H with durations and predecessors to draw the diagram, determine the critical path, and project duration. Exercise 3 similarly provides activities A through H and Exercise 4 provides activities A through I to draw the diagram, find the critical path, and duration.

Uploaded by

gabboudeh
Copyright
© © All Rights Reserved
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
You are on page 1/ 2

NETWORK DIAGRAM EXERCISES:

Exercise 1

Draw the following Network Diagram:

Activity Predecessor(s)
A -
B -
C A
D B
E D
F C
G E,F

Exercise 2

Draw the Network Diagram and determine the Critical Path and duration of
the project (in days).

Activity Details Duration (days) Predecessor(s)


A Dig Holes 3 -
B Buy Wood 2 Dig Holes
C Buy Gate 1 Dig Holes
D Erect Fence 3 Buy Wood
E Buy Paint 1 Buy Gate
F Erect Gate 1 Erect Fence, Buy
Paint
G Paint Fence 2 Erect Gate
H Paint Gate 1 Paint Fence

Exercise 3

Draw the Network Diagram and determine the Critical Path and duration of
the project (in days).

Activity Duration (days) Predecessor(s)


A 2 -
B 2 A
C 4 A

Prepared by: D.Calderwood


D 1 B
E 3 C,D
F 2 C,D
G 4 E
H 5 F,G

Exercise 4

Draw the Network Diagram and determine the Critical Path and duration of
the project (in days).

Activity Duration (days) Predecessor(s)


A 2 -
B 3 -
C 4 A,B
D 5 C
E 2 D
F 3 D
G 4 E
H 2 F
I 2 G,H

Prepared by: D.Calderwood