0% found this document useful (0 votes)
104 views2 pages

NCR Disposition Proposal

Download as docx, pdf, or txt
Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1/ 2

PMC Site NCRs Follow up Update : 17/05/2018

NCR
No. Description Date Issued Disposition Progress
1- Method Statement for slab crack repairs P4045ZOR-MS-CT-CM-033 to be
approved by CPY
Concrete cracks on Unit 85
2- Trial test to be performed
Trestle slabs / slab Cracks repair ongoing on trestle 1; repair method for bottom slab
015 05/11/17 3- Technical note P4045ZOR-0085-19R-5004 to validate the alignment
installation not as per surface to be proposed to CPY
tolerances in line with existing installation
tolerances
4- Notification for inspection to release the trestle 1 Span 1A up to Trestle 2
Span 20
1- Welding Book S-P4045ZOR-SC1008-000-QA-H013-007 to be revised to Welding book S-P4045ZOR-SC1008-01-000-QA-H013-007 rev C was
Welding Carried Out
include new WPQR (with impact test results) approved by CPY. 1 PQR to be performed to cover impact test
018 Without Approved WPS - 30/01/18
2- Welding reports to be submitted-Acceptable, provided all Mechanical tests requirement. Internal test planned on 17th May, Test with CPY on 20th
Wave Shield Structures
passed as per AWS D1.1. May
L&T - GRP 6'' pipe joint with 1- Item 1 PMC Management to agree with NOV Rep in place
excessive adhesive & 2- Items 2 & 3 of NCR are closed: E Mail P. Ramajal on 11/03/18 (11:38)
Manufacturer representative not approved by CPY; HSS JV sent a
019 without support clamping; 30/01/18
letter on 14th May in order to get approval of personnel in place
Supplier representative not
mobilized
021 Sea Island, Damage on 22/04/2018 1- Method Statement for civil & Mechanical repair to be submitted to CPY for Incident Report issued
Tubular Piles and concrete approval
deck (Incident with bad
weather)
022 Sea Island, UV protection 25/04/2018 1- Contractor to issue a waiver-Additionally evidence required to show no
on tubular piles not yet chalking on coatings- as the overcoat period exceed.
applied
Painting System FS2-N 1- Paint procedure S-P4045ZOR-SC0933-93-B01-QA-H003-034 to be revise
applied on internal staircase to include the FS2-N System
not included in the 2- Notification for inspection to be issue to CPY for the stair case-Acceptable
023 26/04/18 RFI drafted
approved painting
procedure (Eversendai)
DNVGL NCR 005
CPY wasn’t notified after 1- MPI reports to be provided for each pipe ends after cut out to length.
completion of hydro test;
024 spools were cut and erected 29/04/18
in pipe rack; MPI/PT on
pipe ends not done (L&T)
Storage of GRP spool not in 1- Evidence of storage improvement to be provided
accordance with project 2- Toll box talks to be organized and attendance sheet to be submitted-
025 requirements; No protection 29/04/18 Evidence required to show for GRP pipes free from chalking and mechanical Evidences requested from Eversendai
against UV, unsafe location damages.
(L&T)
1- Method Statement for GRP erection above ground to be submitted and
GRP pipe spools installed in
approved by CPY
pipe racks are exposed to
026 30/04/18 2- Toll box talks to be organized and attendance sheet to be submitted- Evidences requested from Eversendai
damage by the surrounding
Evidence required to show for GRP pipes free from chalking and mechanical
ongoing activities
damages.
1- Contractor to replace personnel during their rotation leave
2- Notification for inspection approved by CPY & Coating and welding reports
to be submitted
Lack of QC Personnel at
027 01/05/18 Inspection report should be reviewed in the absent period of qualified coating Notifications & NDT reports received for coating
Eversendei
inspector and Random inspection required during the absence period for
Witness and hold involvements of both contractor(HSSJV) and
company(DNV).
1- Individual welders performance and penalty joints records to be
L & T piping repair rate;
028 07/05/18 submitted-Provide weld repairs occurred, welder wise for more than Welding Records internal review ongoing
Individual welder repair rate
5% and Defect wise for more than 2%.
Hi Paulo,

Good morning,

Please see below mail for ‘inspection notification ’ on hydrotest of diffuser, But there is no approved hydro test procedure-HDPE and our involvement should be witness (as per the previous comment on
HDPE-ITP).

We are going to reject this RFI.

Thanks & Regards

Karthik Dhayalan B.Eng.,

Welding Engineer/Inspections-PMC, Package-5(45)

D (+965) 2209 3344 Ext 3908

M (+965) 94080198

[email protected]

www.woodplc.com

You might also like