Project Management & Insurance Costs: Cable Lengths
Project Management & Insurance Costs: Cable Lengths
This worksheet shows the breakdown of capital costs for 4 AR1500 devices installed at the Meygen si
locations shown in Figure 1 of the coursework brief. For the purposes of the coursework project, you c
assume that all of the costs stated are accurate.
Electrical Costs
Cable Lengths m
Length of 6.6kV Cable 10000 Assumes 4 turbines with a si
£k
Turbine/Generator 2000 30 % of total project cost values
Foundation and Support Structure 500 8
Device Installation (Turbine & Foundation) 1600 24
Device Total 4100 62
No of Turbines 4
Total Device Cost (£k) 16400
Page 1
Capital Costs
Assumes 4 turbines with a single 2.5Km cable from each turbine to the onshore substation.
% of total project cost values (without contingency) in cells D31 to D34 account for the number of turbines.
The total project cost, including the contingeny, is the value transferred to the cash flow analysis worksheet.
Page 2
Cash Flow Analysis
This worksheet performs a cash flow analysis and calculates an Internal Rate of Return (IRR), NPV an
separate 'Tidal Turbine Performance and Energy Yield' spreadsheet and 'Capital Costs' worksheet. On
requested in the Conclusions & Recommendations section of the group coursework project.
PROJECT DETAILS
Turbine AR1500
Rated capacity 1.5 MW
Number of turbines 4 Number of turbines in farm (a single row of 4 devices is
Installed capacity 6 MW
Ideal annual output per turbine 4.29 GWh Calculated using turbine power curve and annual tidal fl
Ideal tidal farm output 17.16 GWh Ideal annual output per turbine * No. of turbines
Wake Losses 0% Assumed as 0%
Electrical Losses 2% Assumed as 2%
Availability Losses 5% Assumed as 5%
Total annual output 15.96 GWh Ideal Output * Total Losses
Capacity factor 0.30
Capex 29.04 £m Capex value obtained from Capital Costs Spreadsheet.
Opex 0.15 £m/MW/yr A default value of £0.15m/MW/yr has been assumed (ap
Energy Strike Price (Year 1) 305 £/MWh This is no longer accurate (refer to finance lecture) but s
Wholesale Energy Price (Year 1) 40 £/MWh
Inflation rate 2.00% per year Inflation rate assumed to be 2% throughout project lifeti
CASHFLOW 1 2 3 4 5
Cash in
Energy Strike Price £/MWh 305 311 317 324 330
Wholesale Energy Price £/MWh 40 41 42 42 43
Production (GWh) 0 16.0 16.0 16.0 16.0
Cash income (£m) 0.0 5.0 5.1 5.2 5.3
Cash out
Capex (£m) 29.0
Opex (£m) 0.0 0.9 0.9 1.0 1.0
Cash flow (£m) -29.0 4.0 4.1 4.2 4.3
Cumulative cash (£m) -29.0 -25.0 -20.9 -16.7 -12.4
FINANCIAL PERFORMANCE
IRR 12.76%
Discount Rate 0.10
20 yr NPV 4.91 £m
NPV Cost of Capital 29.0 £m
NPV O&M 8.9 £m
NPV Energy 135.9 GWh
LCOE 279.5 £/MWh
Page 1
Cash Flow Analysis
of Return (IRR), NPV and LCOE using data generated from the
tal Costs' worksheet. Only the LCOE is required for the chart
ework project.
ower curve and annual tidal flow data from Turbine Energy Yield worksheet.
bine * No. of turbines
Page 2
Cash Flow Analysis
14 15 16 17 18 19 20 21
Page 3
5.93 -2.9
8.895 3.2 20
11.86 7.8
14.825 11.8
17.79 15.5
15
10
IRR (%)
5
0
4 6 8 10 12 14 16
-5
Annual Energy Yield (GWh)
Figure 1: Change in IRR for a +/-50% variation in ene
10 12 14 16 18 20