Progress Report + March
Progress Report + March
Progress Report + March
CONSTRUCTION OF
CONTRACTOR :
RECORD NO: SKSC3/PR/01
PROJECT : PROPOSED ADDITIONS TO SAMPATH CENTRE
REVISION NO: 0
REPORT CONTENTS
ITEM NO DESCRIPTION
PAGE NO
1.0 PROJECT OUTLINE 3
Page 2
RECORD NO: SKSC3/PR/01
PROJECT :PROPOSED ADDITIONS TO SAMPATH CENTRE
REVISION NO: 0
PROJECT OUTLINE
2.0 PROJECT LOCATION No. 100, Sir James Peiris Mawatha, Colombo -02.
4.0 PROJECT MANAGEMENT Project Management & Engineering Consultants Pvt. Ltd
Page 3
RECORD NO: SKSC3/PR/01
PROJECT : PROPOSED ADDITIONS TO SAMPATH CENTRE
REVISION NO: 0
Page 4
RECORD NO: SKSC3/PR/01
PROJECT : PROPOSED ADDITIONS TO SAMPATH CENTRE
REVISION NO: 0
SCOPE OF WORK
01 Prelimineries
02 Demolition and Dismantling
03 Concrete Work
04 Masonry Work
05 Water Proofing Work
06 Aluminum Joinery
07 Timber Joinery
08 Metal Work
09 Structural Steel And Roof
10 Floor, Wall And Ceiling Finishes
11 Painting
12 Electrical Installation
13 Fire Installation
14 Plumbing Installation
15 Passenger Elevators
16 Car Parking System
17 Provisional Sum
17.1 Enhancement to Existing Water Connection
17.2 Enhancement to Existing Electrical Connection
17.3 Services And Coordination of Ac Work (Attendance Fee)
17.3 Gondola System
17.4 Supply Of Light Fittings
Page 5
RECORD NO: SKSC3/PR/01
PROJECT : PROPOSED ADDITIONS TO SAMPATH CENTRE
REVISION NO: 0
SANKEN CONSTRUCTION PVT.LTD QUALITY RECORDS
Page 6
RECORD NO: SKSC3/PR/01
PROJECT : PROPOSED ADDITIONS TO SAMPATH CENTRE
REVISION NO:0
Sanken Record No: 7/R/12
CONSTRUCTION Revision No: 01
Date of Issue: 20/3/2009
Page No: 1OF1
PROJECT: Proposed Additions to Sampath Centre MONTH : March 2018
TOOLS,PLANT & MACHINERIES
Date
CATEGORY 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 Remarks
Roller
Gas cutter set
Water Pump 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Excavator
Generator 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
GI cutter
RBC cutter
Submerged Pressure Pump
Sutter vibrator machine
Rammer
Wacker machine
Lorry 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Van
Porker 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Air Compressor 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Welding Plant 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Light vehicle 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Grinder machine 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3
Theodolite 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
Total Station
Leveling Instrument 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Laser Instrument 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Power Saw 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
Bar Cutter 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Bar Bending Machine 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Hammer Drill 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Hand Drill 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Tower Crane 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Plate compactor 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
High Speed cutter
Tractor
Chipper 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Stationary Pump
Jig saw
Heat Gun
Breaker Machine 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Blow Lamp
Alimak (double)
Putty Mixer
U 60 Pump
Hydraulic Jack
Vacumed cleaner
Total 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25
Page 7
RECORD NO: SKSC3/PR/01
PROJECT : PROPOSED ADDITIONS TO SAMPATH CENTRE
REVISION NO: 0
1 STEEL
T16 Ton
T20 Ton
T25 Ton
4 TIMBER
5 PLYWOOD
Coated 15 mm Nos 45 45
6 MELAMINE SHEET
6mm thk Nos
Page 8
RECORD NO: SKSC3/PR/01
PROJECT : PROPOSED ADDITIONS TO SAMPATH CENTRE
REVISION NO: 0
BASELINE PROGRAMME
Page 9
RECORD NO: SKSC3/PR/01
PROJECT : PROPOSED ADDITIONS TO SAMPATH CENTRE
REVISION NO: 0
PROGRESS OF WORK - PHYSICAL (ACCORDING TO THE BASELINE PROGRAMME)
PROPOSED SAMPATH CENTRE EXTENSION 549 days Aug 29 '17 Feb 28 '19 13% 6%
MILESTONES 549 days Aug 29 '17 Feb 28 '19 0% 0%
LOA 0 days Aug 29 '17 Aug 29 '17 100% 100%
PROJECT START DATE 0 days Oct 1 '17 Oct 1 '17 100% 100%
PARTIAL COMPLETION MILESTONES 304 days Apr 30 '18 Feb 28 '19 0% 0%
PRELIMINARIES 91 days Sep 14 '17 Dec 29 '17 100% 100%
ACCESS 69 days Oct 13 '17 Jan 2 '18 100% 100%
CONCRETE WORK UPTO 9TH FLOOR 286 days Nov 7 '17 Oct 19 '18 59% 44%
Area 2 Part 1 127 days Nov 7 '17 Apr 4 '18 98% 86%
4th Floor 20 days Nov 7 '17 Nov 29 '17 100% 100%
5th Floor 14 days Nov 30 '17 Dec 15 '17 100% 100%
Scaffolding Arrangement Upto 10th Floor 7 days Dec 16 '17 Dec 23 '17 100% 100%
6th Floor 14 days Jan 30 '18 Feb 14 '18 100% 100%
7th Floor 14 days Feb 15 '18 Mar 2 '18 100% 100%
8th Floor 14 days Mar 3 '18 Mar 19 '18 100% 100%
9th Floor 14 days Mar 20 '18 Apr 4 '18 86% 0%
Area 2 Part 2 264 days Dec 1 '17 Oct 19 '18 38% 23%
3rd Floor Temporary Support Arrangement
0 days Dec 1 '17 Dec 1 '17 100% 100%
Details
4th Floor Area 2 - Part 2 Structural Details 0 days Dec 1 '17 Dec 1 '17 100% 100%
4th Floor 15 days Dec 9 '17 Dec 27 '17 100% 100%
Scaffolding Arrangement Upto 10th Floor 7 days Dec 28 '17 Jan 4 '18 100% 100%
5th Floor 15 days Oct 3 '18 Oct 19 '18 0% 0%
6th Floor 15 days Aug 14 '18 Aug 30 '18 0% 0%
7th Floor 15 days Jun 25 '18 Jul 11 '18 0% 0%
8th Floor 15 days May 3 '18 May 22 '18 0% 0%
9th Floor 15 days Mar 3 '18 Mar 20 '18 100% 0%
Area 5 225 days Dec 1 '17 Sep 4 '18 45% 45%
4th Floor Temporary Support Arrangement
0 days Dec 1 '17 Dec 1 '17 100% 100%
Details
5th Floor Area 5 - Structural Details 0 days Dec 1 '17 Dec 1 '17 100% 100%
Handing Over the Area for Conctruction 0 days Dec 8 '17 Dec 8 '17 100% 100%
5th Floor 16 days Dec 8 '17 Dec 27 '17 100% 100%
Scaffolding Arrangement Upto 10th Floor 7 days Dec 28 '17 Jan 4 '18 100% 100%
6th Floor 16 days Aug 17 '18 Sep 4 '18 0% 0%
7th Floor 16 days Jun 27 '18 Jul 14 '18 0% 0%
8th Floor 16 days May 4 '18 May 24 '18 0% 0%
9th Floor 16 days Mar 3 '18 Mar 21 '18 100% 100%
RCC Roof Slabs 236.86 days Jan 3 '18 Oct 18 '18 50% 0%
8th FLOOR Area 4 25 days Jan 3 '18 Jan 31 '18 100% 0%
AHU Room Roof Slab 25 days Sep 19 '18 Oct 18 '18 0% 0%
STEEL ROOF 48.86 days Jun 14 '18 Aug 9 '18 0% 0%
Completion of Concrete Work Upto 9th Floor 0 days Oct 19 '18 Oct 19 '18 0% 0%
CONCRETE WORK ABOVE 9TH FLOOR 257 days Dec 5 '17 Oct 15 '18 43% 3%
10th Floor Structural & Lift Core Details 0 days Dec 5 '17 Dec 5 '17 100% 100%
10th FLOOR 21 days Jan 5 '18 Jan 29 '18 100% 25%
11th FLOOR 21 days Jan 30 '18 Feb 22 '18 100% 0%
12th FLOOR 21 days Feb 23 '18 Mar 19 '18 100% 0%
13th FLOOR 21 days Mar 20 '18 Apr 12 '18 57% 0%
14th FLOOR 21 days Apr 23 '18 May 17 '18 0% 0%
ROOF TERRACE 21 days May 21 '18 Jun 13 '18 0% 0%
MACHINE ROOM 14 days Jun 14 '18 Jun 29 '18 0% 0%
WATER TANK LEVEL 14 days Jun 30 '18 Jul 16 '18 0% 0%
WATER TANK ROOF LEVEL 13 days Jul 17 '18 Jul 31 '18 0% 0%
10th Floor Slab Cooling Tower Area 7 days Oct 8 '18 Oct 15 '18 0% 0%
CIVIL, MEP & FINISHING UPTO 9TH FLOOR 294 days Jan 30 '18 Jan 21 '19 10% 0%
CIVIL, MEP & FINISHING ABOVE 9TH FLOOR 232.5 days Mar 12 '18 Dec 20 '18 1% 0%
General MEP & Other Work 308 days Jan 30 '18 Feb 6 '19 6% 0%
Dismantling of Scaffoldings 30 days Dec 24 '18 Jan 28 '19 0% 0%
Dismantling of Tower Crane 20 days Jan 5 '19 Jan 28 '19 0% 0%
Demobilization & Handover 19 days Feb 7 '19 Feb 28 '19 0% 0%
Page 10
RECORD NO: SKSC3/PR/01
PROJECT : PROPOSED ADDITIONS TO SAMPATH CENTRE
REVISION NO: 0
PROGRESS OF WORK - PHYSICAL (ACCORDING TO THE REVISED PROGRAMME SUBMITTED FOR APPROVAl)
PROPOSED SAMPATH CENTRE EXTENSION 665 days Aug 29 '17 Jun 24 '19 8% 8%
MILESTONES 665 days Aug 29 '17 Jun 24 '19 0% 0%
LOA 0 days Aug 29 '17 Aug 29 '17 100% 100%
PROJECT START DATE 0 days Oct 1 '17 Oct 1 '17 100% 100%
PARTIAL COMPLETION MILESTONES 279 days Sep 18 '18 Jun 24 '19 0% 0%
PRELIMINARIES 91 days Sep 14 '17 Dec 30 '17 100% 100%
ACCESS 69 days Oct 13 '17 Jan 3 '18 100% 100%
CONCRETE WORK UPTO 9TH FLOOR 418 days Nov 7 '17 Mar 30 '19 36% 36%
Area 2 Part 1 Slab Concreting 210 days Nov 7 '17 Jul 31 '18 86% 86%
4th Floor 20 days Nov 7 '17 Nov 29 '17 100% 100%
5th Floor 14 days Nov 30 '17 Dec 15 '17 100% 100%
6th Floor 14 days Dec 16 '17 Jan 3 '18 100% 100%
7th Floor 14 days Jan 4 '18 Jan 19 '18 100% 100%
8th Floor 14 days Jan 20 '18 Feb 5 '18 100% 100%
Scaffolding Arrangement Upto 10th Floor 7 days Feb 6 '18 Feb 13 '18 100% 100%
9th Floor 14 days Jul 16 '18 Jul 31 '18 0% 0%
Area 2 Part 2 Slab Concreting 396 days Dec 1 '17 Mar 30 '19 23% 23%
3rd Floor Temporary Support Arrangement
0 days Dec 1 '17 Dec 1 '17 100% 100%
Details
4th Floor Area 2 - Part 2 Structural Details 0 days Dec 1 '17 Dec 1 '17 100% 100%
4th Floor 15 days Dec 9 '17 Dec 28 '17 100% 100%
Scaffolding Arrangement Upto 10th Floor 7 days Dec 29 '17 Jan 5 '18 100% 100%
9th Floor 15 days Aug 25 '18 Sep 11 '18 0% 0%
8th Floor 15 days Oct 15 '18 Oct 31 '18 0% 0%
7th Floor 15 days Dec 4 '18 Dec 20 '18 0% 0%
6th Floor 15 days Jan 23 '19 Feb 8 '19 0% 0%
5th Floor 15 days Mar 14 '19 Mar 30 '19 0% 0%
Area 5 Slab Concreting 357 days Dec 1 '17 Feb 13 '19 26% 26%
4th Floor Temporary Support Arrangement
0 days Dec 1 '17 Dec 1 '17 100% 100%
Details
5th Floor Area 5 - Structural Details 0 days Dec 1 '17 Dec 1 '17 100% 100%
Handing Over the Area for Conctruction 0 days Dec 8 '17 Dec 8 '17 100% 100%
5th Floor 16 days Dec 8 '17 Dec 28 '17 100% 100%
Scaffolding Arrangement Upto 10th Floor 7 days Dec 29 '17 Jan 5 '18 100% 100%
9th Floor 16 days Aug 25 '18 Sep 12 '18 0% 0%
8th Floor 16 days Oct 16 '18 Nov 2 '18 0% 0%
7th Floor 16 days Dec 6 '18 Dec 24 '18 0% 0%
6th Floor 16 days Jan 26 '19 Feb 13 '19 0% 0%
RCC Roof Slab Concreting 57 days Jun 19 '18 Aug 23 '18 0% 0%
STEEL ROOF 72.86 days May 15 '18 Aug 7 '18 0% 0%
Completion of Concrete Work Upto 9th Floor 0 days Mar 30 '19 Mar 30 '19 0% 0%
CONCRETE WORK ABOVE 9TH FLOOR 371 days Dec 5 '17 Mar 5 '19 22% 18%
10th Floor Structural & Lift Core Details 0 days Dec 5 '17 Dec 5 '17 100% 100%
10th Floor Concreting 85 days Mar 2 '18 Jun 28 '18 32% 25%
Rectification work on 8th Floor 68 days Mar 2 '18 Jun 8 '18 24% 24%
Zone 1 Column ( 2 out of 10 Columns) 9 days Mar 2 '18 Mar 12 '18 100% 100%
Zone 1 Column ( 2 out of 8 Columns) 9 days Mar 7 '18 Mar 16 '18 100% 100%
Zone 1 Column ( 2 out of 6 Columns) 13 days Mar 21 '18 Apr 5 '18 82% 82%
Zone 1 Column ( 3 out of 4 Columns) 9 days Apr 6 '18 May 4 '18 0% 0%
Zone 1 Column ( 1 out of 1 Column) 9 days Apr 27 '18 May 9 '18 0% 0%
Zone 2 Column ( 2 out of 6 Columns ) 9 days Apr 27 '18 May 9 '18 0% 0%
Zone 2 Column ( 3 out of 4 Columns ) 9 days May 4 '18 May 14 '18 0% 0%
Zone 2 Column ( 1 out of 1 Column ) 9 days May 9 '18 May 18 '18 0% 0%
Office Area Shifting to Zone 1 1 day May 13 '18 May 13 '18 0% 0%
Support Arrangement under beams 5 days May 14 '18 May 18 '18 0% 0%
Page 11
RECORD NO: SKSC3/PR/01
PROJECT : PROPOSED ADDITIONS TO SAMPATH CENTRE
REVISION NO: 0
PROGRESS OF WORK - PHYSICAL (ACCORDING TO THE REVISED PROGRAMME SUBMITTED FOR APPROVAl)
Page 12
RECORD NO : SKSC3/PR/01
PROJECT : PROPOSED ADDITIONS TO SAMPATH CENTRE
REVISION NO: 0
FINANCIAL STATEMENT UP TO 31st OF MARCH 2018
(Without VAT & NBT)
Bill No. 01 29,151,194.51 03- 01- 2018 24,507,106.41 26 - 01- 2018 24,507,106.41 15-02-2018 -
Page 13
RECORD NO: SKSC3/PR/01
PROJECT : PROPOSED ADDITIONS TO SAMPATH CENTRE
REVISION NO:0
WEATHER REPORT
PERIOD 01st MARCH 2018 - 31th MARCH 2018
Page 14
RECORD NO: SKSC3/PR/01
PROJECT : PROPOSED ADDITIONS TO SAMPATH CENTRE
REVISION NO: 0
PROGRESS PHOTOS
Page 15
RECORD NO: SKSC3/PR/01
PROJECT : PROPOSED ADDITIONS TO SAMPATH CENTRE
REVISION NO: 0
PROGRESS PHOTOS
Page 16
RECORD NO: SKSC3/PR/01
PROJECT : PROPOSED ADDITIONS TO SAMPATH CENTRE
REVISION NO: 0
PROGRESS PHOTOS
Page 17