0% found this document useful (0 votes)
1K views2 pages

Some Important Formula For IE

This document lists various important formulas used in industrial engineering, including formulas to calculate standard pitch time, gross standard minutes, standard minute value, basic time, observed time, rating, efficiency, earn minutes, available minutes, organization efficiency, upper control limit, lower control limit, capacity, cycle time, capacity achievable, daily output, factory capacity, cost per minute, and required number of operators.

Uploaded by

Md. Hasan Sheikh
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
1K views2 pages

Some Important Formula For IE

This document lists various important formulas used in industrial engineering, including formulas to calculate standard pitch time, gross standard minutes, standard minute value, basic time, observed time, rating, efficiency, earn minutes, available minutes, organization efficiency, upper control limit, lower control limit, capacity, cycle time, capacity achievable, daily output, factory capacity, cost per minute, and required number of operators.

Uploaded by

Md. Hasan Sheikh
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 2

Some Important Formula for IE:

1. Standard Pitch Time (S.P.T) = Basic Pitch Time (B.P.T) + Allowances (%)
▪ GSD = (Man power * Work hour) / Target

▪ SMV = Basic time + (Basic time * Allowance)

▪ Basic time = Observed time * Rating

▪ Observed time = Total Cycle time / No of cycle

▪ Rating = (Observed Rating * Standard rating) / Standard rating

▪ Efficiency = (Earn minute * Available minute) * 100

▪ Earn minute = No of Pc’s (Production) * Garments SMV

▪ Available minute = Work hour * Manpower

▪ Organization Efficiency = (Basic pis time / Bottle neck time) * 100

▪ Basic pis time = Total GMT SMV / Total Manpower

▪ UCL = Basic pis time / Organization Efficiency

▪ LCL = 2 * Basic pis time – UCL

▪ Capacity = 60 / Capacity time in minute

▪ Cycle Time = 60 / Team target

▪ Capacity Achievable = Capacity * Balance

▪ Daily output = Work hour / SMV

▪ Factory capacity = (Work hour / SMV) * Total worker * Working day * Efficiency

▪ CPM = (Total over head cost of the month / No of SMV earners * Work minutes) *Efficiency

▪ Required no of operator = Target daily output / Daily output per operator