File - Ch08, Chapter 8 - Scheduling Multiple Choice
File - Ch08, Chapter 8 - Scheduling Multiple Choice
Main page
File: ch08, Chapter 8: Scheduling Multiple Choice time required
0 0 0 0 critical path
early start
0 0 0
find similar
Multiple Choice
Ans: c
Level: easy
a) Construction
b) Manufacturing
c) Industrial
Ans: d
Level: easy
3. The critical activities in real-world projects typically constitute no more than ________% of the
total activities in the project.
a) 5 percent
b) 10 percent
c) 20 percent
d) 50 percent
Ans: b
Level: easy
http://essaydocs.org/file-ch08-chapter-8-scheduling-multiple-choice.html 1/8
4/11/2018 File: ch08, Chapter 8: Scheduling Multiple Choice
4. In a network, an activity can be shown in one of three conditions. Identify the statement that does
not correctly describe one of the three possible conditions.
Ans: d
Response: Refer to section 8.2, terminology. If neither a successor nor a predecessor is present, the
activity is referred to as a hanging task.
Level: easy
5. In an AON diagram, when there are multiple activities without predecessors and there are multiple
activities having no successors, ________ are used to eliminate the potential for hanging tasks in the
network.
b) Dummy activities
d) Loopbacks
Ans: a
Level: intermediate
a) Activities
b) Events
c) Logical dependencies
d) Dummy activities
Ans: b
Level: easy
7. Most commercially available project management software applications use the ________ type of
network.
a) GERT
b) PERT
c) AOA
d) AON
Ans: d
Level: easy
8. The Gantt chart is intended to monitor the detailed progress of work, whereas the master schedule
contains only major tasks and is oriented toward ________.
http://essaydocs.org/file-ch08-chapter-8-scheduling-multiple-choice.html 2/8
4/11/2018 File: ch08, Chapter 8: Scheduling Multiple Choice
b) Overall project management rather than precise control of detailed work
Ans: b
Response: Refer to section 8.2, Gantt charts and Microsoft Project 2002.
Level:
9. The calculation of the standard deviation for the beta distribution is based on the assumption that
________.
a) The range is divided by a count of the values used to compute the mean
Ans: b
Level: intermediate
10. Task F has duration of 10 days and an early start date of 20 days. Based on the given data,
determine the early finish date for task F.
a) 10 days
b) 20 days
c) 30 days
d) 5 days
Ans: c
Level: easy
11. The shortest time in which the entire network can be completed is referred to as ________.
Ans: a
Response: Refer to section 8.2, critical path and time. The critical path denotes activities that, if
delayed, will affect the project’s completion time. The critical time can be changed without changing
the critical path. This is a fine but important distinction.
Level: advanced
12. While performing a forward pass calculation to determine the critical path of a network, when
multiple paths converge into a successor activity, the value carried forward to the early start of the
successor activity is ________.
http://essaydocs.org/file-ch08-chapter-8-scheduling-multiple-choice.html 3/8
4/11/2018 File: ch08, Chapter 8: Scheduling Multiple Choice
Ans: d
Level: easy
13. While performing a backward pass calculation for a network, when multiple paths converge into a
predecessor activity, the value carried backward to the late finish of the predecessor activity is
Ans: a
Level: easy
14. In a statistical distribution, when an observation’s value moves closer to the distribution’s mean,
the z-score value will ________.
a) Increase
c) Decrease
Ans: c
Level: intermediate
15. When using the beta distribution, the denominator of the formula for standard deviation should
________.
a) Always equal 6
Ans: c
Level: advanced
Short Answer
16. A ________ is the conversion of the project action plan into an operating timetable.
Ans: schedule
Level: easy
17. The authors, when discussing networks, describe ________ as a specific task or set of tasks that
are required by the project, use up resources, and take time to complete.
Ans: activity
http://essaydocs.org/file-ch08-chapter-8-scheduling-multiple-choice.html 4/8
4/11/2018 File: ch08, Chapter 8: Scheduling Multiple Choice
Response: Refer to section 8.2, terminology.
Level: easy
18. The authors, when discussing networks, describe an ________ as the result of completing one or
more activities. It is an identifiable end state occurring at a particular time. It does not use resources.
Ans: event
Level: easy
19. The arrangement of all activities (and, in some cases, events) in a project arrayed in their logical
sequence and represented by arcs and nodes, is called a ________.
Ans: network
Level: easy
20. In a network, a ________ is a series of connected activities (or intermediate events) between any
two events in a network.
Ans: path
Level: easy
21. In a network, if the delay of an activity will delay completion of the project, the activity is called
________.
Ans: critical
Level: easy
Level: easy
23. The ________ chart shows planned and actual progress for a number of tasks displayed against a
horizontal timescale.
Ans: Gantt
Response: Refer to section 8.2, Gantt charts and Microsoft Project 2002.
Level: easy
24. Given project task E and estimates of 10 days for the optimistic time, 20 days for the pessimistic
time, and 12 days for the most likely time, the expected time using the beta statistical distribution is
________ days.
Ans: 13
Response: Refer to section 8.2, calculating activity times. 13 days = (10 days + [4 * 12 days] + 20
days) / 6.
Level: easy
25. ________ law suggests that work expands to fill the allotted time.
Ans: Parkinson's
http://essaydocs.org/file-ch08-chapter-8-scheduling-multiple-choice.html 5/8
4/11/2018 File: ch08, Chapter 8: Scheduling Multiple Choice
Response: Refer to section 8.2, calculating activity times.
Level: easy
26. Given project task E and estimates of 10 days for the optimistic time, 20 days for the pessimistic
time, and 12 days for the most likely time, the standard deviation for time using the beta statistical
distribution is ________ days.
Ans: 1.67
Response: Refer to section 8.2, calculating activity times. 1.67 days = (20 days -10 days) / 6.
Level: easy
27. Task H has duration of 5 days, an early start of 25 days, an early finish of 30 days, a late start of 20
days, and a late finish of 30 days. There are ________ days of slack for task H.
Ans: 0 days
Response: Refer to section 8.2, slack. The slack = (late finish - early finish) = (late start -early start).
Level:
28. Any time two or more paths of a network come together, the probability of both paths being on
time is the product of the probabilities for the individual paths. This scenario is referred to as
________.
Level: intermediate
29. Assume that task J has a most likely duration of 20 days, an optimistic duration of 13 days, and a
pessimistic duration of 30 days. If the optimistic and pessimistic durations are 95 percent estimates,
the standard deviation for task J is ________ days.
Ans: 5.15
Level: intermediate
30. Using precedence diagramming methods, activity B must not start until after activity A has been
completed. Moreover, the outcome of activity A cannot be used until 3 days after its completion. The
type of relationship that exists between activities A and B is correctly labeled as ________.
Ans: FS + 3d or FS + 3ed
Response: Refer to section 8.4, precedence diagramming. The amount of lag could be indicated as +3d
to reference work periods or as +3ed to reference calendar time that includes both work periods and
nonwork periods.
Level: advanced
31. In CPM, an activity can be conducted at a normal pace or an expedited pace, known as ________,
at a greater cost.
Ans: crashing
Level: easy
32. An activity or event that, if delayed, will delay project completion is ________.
Ans: critical
Level: easy
http://essaydocs.org/file-ch08-chapter-8-scheduling-multiple-choice.html 6/8
4/11/2018 File: ch08, Chapter 8: Scheduling Multiple Choice
33. A clearly identifiable point in a project or set of activities that commonly denotes a reporting
requirement or completion of a large or important set of activities is called a ________.
Ans: milestone
Level: easy
34. A ________ is a combination of interrelated activities and events depicted with arcs and nodes.
Ans: network
Level: easy
35. A ________ is an intersection of two or more lines or arrows, commonly used for depicting an
event or activity.
Ans: node
Level: easy
Essay
36. Describe the benefits of forming a network of activity and event relationships that graphically
portrays sequential relations between tasks in a project.
Ans: The benefits of such a network include: the interdependence of all tasks, work package, and
network elements is documented, it can be used to determine the expected project completion date, it
identifies the critical activities that if delayed will delay the project completion time, it identifies
activities with slack that can be used should schedule compression become necessary on the critical
path, and it can be used to schedule resources.
Response: Refer to section 8.1. Any benefit listed in section 8.1 is acceptable.
Level: easy
37. Explain why it is important to evaluate noncritical paths that possess large variances and/or path
times that are close to critical in duration.
Ans: Assuming that the project is stable and under control, random uncertainty present in the network
will exhibit cumulative interactions reflecting the inherent randomness of independent activities within
the network. Therefore, an activity having only a relatively small amount of slack could potentially
exceed the critical time calculated from the expected critical path. Moreover, as statistical variances
rise in relation to expected duration, the range of uncertainty in near critical paths will exhibit wider
dispersion. When interdependencies are present in the network, simulation is an effective technique for
modeling the random interactions on critical and near critical paths.
Response: Refer to section 8.2, uncertainty of project completion time, and merge bias.
Level: advanced
38. Describe the differences between GERT and PERT/CPM network models.
Ans: In GERT, branching from a node is probabilistic whereas in PERT/CPM branching from a node
is deterministic. GERT provides flexibility in node realization while the PERT/CPM method does not.
GERT allows loopback to earlier events but PERT/CPM does not. The arrows in GERT can represent
time, costs, reliability, and other relevant variables. In PERT/CPM, the arrows can only represent time.
PERT/CPM is comparatively easy to use as a control tool during execution of a project. GERT is
difficult to use as a control tool during project execution.
Level: intermediate
Ans: Slack is synonymous with float. Slack is the amount of time that an activity can be delayed
without delaying completion of the project. In order to have slack, the activity will not be located on
http://essaydocs.org/file-ch08-chapter-8-scheduling-multiple-choice.html 7/8
4/11/2018 File: ch08, Chapter 8: Scheduling Multiple Choice
the critical path of the network. An activity with slack can be classified as a near critical activity
because the amount of slack is small in relation to the time required to complete the path it is in.
Should it become necessary to crash a project, it may be possible to borrow resources from activities
that have slack.
Level: intermediate
40. Describe the process for determining the critical path in a network.
Ans: Draw the network and determine the logical relationships between the activities in it. Determine
the duration for each activity. Perform the forward pass calculation to determine the critical time for
the network. Perform the backward pass calculation to establish the slack for each activity in the
network. If an activity has 0 slack, then it is a critical activity. The critical path is composed of the
critical activities identified in this manner. It is possible to have more than one critical path in a
network.
Level: easy
http://essaydocs.org/file-ch08-chapter-8-scheduling-multiple-choice.html 8/8